Você está na página 1de 4

Tender specification

Project Title : Water Treatment Plant expansion for 3.5 Million Project (3.5MP)

Site Location : No.45, No.3 Trunk Road, Pyinmabin Industrial Complex, Mingaladon Township,
Yangon, Myanmar

Contents

1. Scope or work
2. Applicable Law and standard
3. Delivery schedule
4. Conditions of acceptance
5. Conditions for design and engineering
6. Confidentially

1. Scope of work

Item Spec Remark


A.Equipment
Feed pump to Iron New Suitable for
filter iron filter
Iron filter Relocation 33m3/h*2
jurapelre new To increase Depends on supplier
----- m3/h capacity selection based
on water quality.
Acceptable to set bipas
Demin plant new Less than As option
15m3/h
Drain recovery tank new 30m3 100
Attomospheric pressure
Incl. insulation
Carbon filter feed Relocation 17.5m3/h*2
pump
Carbon filter Relocation 17.5m3/h*2
Cartridge Relocation 17.5m3/h*2
Calcium Relocation Tank 0.5m3, 50l/h
hypochlorite dosing pump*2, mixer

B.Service
Civil, building, Foundation,
sturucture
Roof
Modification
Mehanical new and Excl.
Installation relocation 1. Repair work of
softdrink fence
after relocation
2. Air & Steam
pipes are
prepareed by
owner to this
area boundary
line
3. Power cable are
connected by
owner to panel
which supplier
prepared
Electrical Incl. existing
installation integration
as total
Soft integration system
Commissioning

Out of scope
- Pipe bridge ( Ref - Attachment 1,2,3 )
- Repair work after soft drink equipment relocation
- Air and Steam pipe connection to Water Treatment Plant Area boundary line
- Power Cable to panel which supplier prepare for this expansion scope

3 Delivery Schedule

Finish commissioning except for demin plant : End of October 2017

Finish commissioning of demin plant, drain recovery : End of Deceber 2017

4 Conditions of Acceptance
To test run and commission the water treatment plant, suitable capacity quality smell
regeneration time, and prepare all document required below.
To provide training for the factory personels on the operation of the water treatment plant.

4.1 Used Language


All documents, drawings for this Project to be prepared in English.

4.2 The Documents to be submitted after the Contract is made.


4.2.1 Before Site Construction
To be submitted within 30 days after contract date
Detailed Schedule of Switching
Form of Documents for the Site Construction
Pipe Routing Drawings
List of Borrowing Items if necessary (Site Office, Temporary Site, Electricity, Utility,
etc)
Other 4.2.2

Inspection Report (w/I 5 Days)

4-1. Commissioning

To test run and commission the water treatment plant and

Acceptance Test
The Projects hallb e deemedc ompletedb y f,nyiroserveT echnologyo ncet he treated
water capacity reaches the below mentioned capacity and the treated water quality
meets the below mentioned rcquirements:
a) RequiredC apacity
b) Treatedw ater Quality
Turbidity
Colour
Odour
Chlorine
Coliform Count
Total Coutrt
50.0m rnr
Lessth an0 .5N TU
Less than I 5 True Colour Unit
No off-taste
a) I mg,4 after UF
b) None after carbon filter
Zero per I 00 ml
Lessth an2 5p erm l

5 Conditions for Design and Engineering


General 5.1
Based on the following documents
Appendix-1 Piping Service Class
Appendix-2 Painting_and_Insulation_Specification
Appendix-3 Piping Connection List
Appendix-4 Picture for Switching
Appendix-5 Process Flow Diagram or Piping Route Plan for Switching

6 Confidentiality
The content of requisition and drawings cannot be disclosed to any third party without
prior written approval from MBL.
Any information related to the project and other information shall not be disclosed to any
third party without acceptance/approval of MBL.
Strictly obey the regulation of non-disclosure of any personal, customers, technical as
well as any invention information to be shared by MBL and do not disclosed to any third
party.
Prepare and conclude a Confidential Agreement.

- END -