Você está na página 1de 2

Work Item Achieved Planned

UOM Scope Planned Start Actual start Actual finish Remarks


Description Progress finish
SUPPORT
Completed 05/01/2017 (Delay of 15
STRUCTURE UPTO MT 64.8 64.8 18-11-2016 04-12-2016 31-12-2016 30-01-2017
days due to mobalisation )
16.550 M
BEARING SUPPORT MT 0.3 0.3 01-01-2017 01-02-2017 07-01-2017 07-02-2017 Completed on 07.02.2017
Completed on 23.02.2017. Delay
BOTTOM GIRDER MT 38.8 38.8 from 07/02/2017 to 19/02/2017 due to
supply
99% completed on 17.03.2017. Delay
HOPPER MT 50.0 49.5 from 22/02/2017 to 10/03/2017 due to
supply from GEA
HOPPER BOTTOM
PLATFORM AT
EL.+11.625 M , + 30.0 29.5 Hand rail & toe guard required
9.225 M , +7.0M ,
+4.3M & Stair Case MT
(1)From 17/04/2017 to 20/05/2017 there
was no crane to excute the job.
(2)20/05/2017 to till date there is no
SIDE CASING MT 108.0 108.0 29-03-2017 08-06-2017
dedicated crane for job which has
delayed this already delayed activity by 1
month
TOP ROOF BEAM MT 27.7 27.7
COLLECTING
MT 113.0
ELECTRODE
DISCHARGE Frame MT 15.8
Discharge electrode
HOT ROOF MT 7.5 0.0
COLD ROOF MT 3.8 0.0
TR SET MT
TR SET PLATFORM(5
MT 1.2686
NOS)
HV BUS DUCT(5 NOS) MT 1.9405
OIL PAN WITH VALVE(5
MT 0.9163
Nos)
Inlet cone with GD
MT 23.2
Screen
Inlet duct support MT 58.2
Expansion Joint at inlet
MT
cone
Inlet Damper MT
Outlet cone with G.D.
MT 21.1
Screen
Outlet duct supporting
MT 49.3
structure
Expansion Joint at outlet
MT
cone
Outlet Damper MT
CE rapping mechanism MT
DE rapping mechanism MT
GD rapping mechanism MT 0.6113
INTERNAL WALKWAYS
MT 1.172
AT ESP INLET.

INTERNAL INTERIM
MT 6.338
WALKWAYS AT NEW ESP

INTERNAL WALKWAYS
MT 1.194
AT NEW ESP OUTLET
DUST DISPOSAL
MT 35.0
SYSTEM
WEATHER
MT 38.7
ENCLOSER
Total MT 698.6 318.6

Você também pode gostar