Você está na página 1de 2

Bill of Quantities

BILL NO. 12 : Culverts (Box, Slab, Pipe)


MORTH
data book Sl.No Description Unit Quantity Rate Amount
item no.
Dismantling of Structures (Dismantling of existing structures like culverts, bridges, retaining walls
and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P
2.4 5.01 and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable 0.00
material and stacking the serviceable material with all lifts and lead of 1000 metres)

(a) Reinforced Cement Concrete Cum 936.34 1,313.00 12,29,415


(b) Plain Cement Concrete Cum 4031.98 784.00 31,61,075
(c) Stone Masonry Cum 0.00 - -
(d) Rigid Apron Cum 58.05 - -
(e) Flexible Apron Cum 145.13 - -
(f) Railing Lm 0.00 - -
(g) Guard Stones Nos 0.00 - -
(h) Wearing Coat Cum 354.43 1,313.00 4,65,365
(i) Hume pipes of all sizes Lm 2282.52 633.00 14,44,835
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing
and technical specification, including setting out, construction of shoring and bracing, removal of
12.1 5.02 0.00 - -
stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.)
a) In all types of Soil/Clay Cum 8077.51 120.00 9,69,301
b) In Ordinary Rocks Cum 0.00 - -
c) In Hard Rocks Cum 0.00 - -
Providing and laying in position Plain Cement Concrete of Grade M 15 in levelling course below
12.8 5.03 foundations complete as per drawings and Technical Specifications Cum 1602.40 5,994.00 96,04,796

Providing and laying in position Plain Cement Concrete of Grade M20 head walls, wing walls, cut
5.04 off walls and craddle walls etc. complete as per drawings and Technical Specifications Sections Cum 4066.98 6,659.00 2,70,81,989
1500, 1700, 2100 and 2900.

Laying Reinforced cement concrete pipe NP4/prestrssed concrete pipe for culverts on first class
bedding of granular material including fixing collar with cement mortar 1:2 but excluding excavation,
9.2 5.05 protection works, backfilling, concrete and masonry works in head walls and parapets 0.00 - -

a) Internal dia 900 mm Lm 324.60 - -


b) Internal dia 1000 mm Lm 165.60 9,096.00 15,06,298
c) Internal dia 1200 mm Lm 1574.00 11,338.00 1,78,46,012
d) Internal dia 1500 mm Lm 0.00 - -
e) Internal dia 1800 mm Lm 0.00 - -
Providing and laying in position Reinforced Cement Concrete in box cell structures and slab
5.06 culverts, Wing walls, Retaining walls for culverts complete as per drawings and Technical 0.00 - -
Specifications
a) M 20 Grade Cum 44.83 6,295.00 2,82,208
b) M 25 Grade Cum 0.00 - -
c) M 30 Grade Cum 498.75 6,766.00 33,74,567
Supplying, Fitting and Placing un-coated Fe 500 TMT -HYSD bar Reinforcement in Box cells,
5.07 Retaining walls, Wing walls complete as per Drawing and Technical Specifications MT 42.59 71,287.00 30,35,934

Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing wall/return wall
with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V :20H
13.8 5.08 towards drawing foce. Complete as per drawing and Technical specifications Nos. 472.00 186.00 87,792

Back filling behind abutment, wing wall and return wall complete as per drawing and Technical
13.9 5.09 0.00 - -
specification
a) Granular material Cum 82.56 1,351.00 1,11,536
b) Sandy material Cum 0.00 - -
Providing and laying of Filter media with granular materials/stone crushed aggregates satisfying
the requirements laid down in clause 2504.2.2. of MoRTH specifications to a thickness of not less
than 600 mm with smaller size towards the soil and bigger size towards the wall and provided over
13.10 5.10 Cum 47.18 2,236.00 1,05,503
the entire surface behind abutment, wing wall and return wall to the full height compacted to a firm
condition complete as per drawing and technical specification.

Miscellaneous 0.00 -
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on top of deck
slab excluding prime coat with paving grade bitumen meeting the requirements given in table 500-
29, prepared by using mastic cooker and laid to required level and slope after cleaning the
surface, including providing antiskid surface with bitumen precoated fine grained hard stone
14.5 5.11 chipping of 9.5 mm nominal size at the rate of 0.005cum per 10 sqm and at an approximate 0.00 - -
spacing of 10 cm center to center in both directions, pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface, all complete as
per clause 515.)
Bituminous Concrete: Providing and laying bituminous concrete 53mm thick with 100-120 TPH
batch type hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bitumen @ 5% by weight of total mixture and filler,
5.8 5.12 transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to 0.00 - -
the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers
to achieve the desired compaction as per MORTH specification clause No. 509 complete in all
respects

a) With 60/70 Bitumen @ 122.5 kg/cum Cum 0.00 - -

b) Alternativly with PMB-40 @ 122.5 kg/cum Cum 0.00 - -

PCC M15 Grade leveling course below approach slab complete as per drawing and Technical
14.10 5.13 specification Cum 0.00 - -

Reinforced cement concrete Grade M30 in approach slab including reinforcement and formwork
14.11 5.14 complete as per drawing and Technical specification Cum 0.00 - -

Providing and fixing Drainage Spouts complete as per drawing and Technical specification.
14.9 5.15 Nos. 6.00 1,314.00 7,884

Page 1 of 2
MORTH
data book Sl.No Description Unit Quantity Rate Amount
item no.
Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches
14.15 5.16 to bridge structures and medians, constructed with M-40 grade concrete with HYSD reinforcement Lm 43.00 - -
@ 36 Kg / Rmt & 0.3 cum of concrete per Rmt conforming to IRC:21
Providing and fixing 80mm NB GI pipe rail on crash barrier complete with fixtures as per drawings
5.17 and Technical Specifications Lm 43.00 - -

Providing and fixing in Position Guard Stones as per Technical Specifications or as directed by the
5.18 Nos. 0.00 - -
engineer incharge.

Providing and fixing in Position Pillar For Inscribing Structure Num.as Technical Specifications or
5.19 Nos. 264.00 450.00 1,18,800
as directed by tie engineer inciarie.

Providing & Painting of structure no., span arrangement and flow directions complete as per
5.20 Nos. 270.00 - -
drawings and Technical Specifications Section 800.
Providing and fixing in position Tar paper bearings true to line and level complete as per drawings
5.21 and Technical Specifications Section 2000. Sqm 16.80 - -

Providing and laying Pitching on slopes laid over prepared filter media including boulder apron
15.4 5.22 laid dry in front of toe of embankment complete as per drawing and Technical specifications. Cum 854.24 2,384.00 20,36,506

Providing and laying Filter material underneath pitching in slopes complete as per drawing and
15.5 5.23 Cum 246.13 2,515.00 6,19,028
Technical specification

15.10 5.24 Curtain wall complete as per drawing and Technical specification 0.00 - -

a) Stone masonry in cement mortar (1:3) Cum 0.00 - -

b) Cement concrete Grade M15 Cum 108.66 5,994.00 6,51,291

Providing and laying Flooring complete as per drawing and Technical specifications laid over
15.8 5.25 0.00 - -
cement concrete bedding.

a) Rubble stone laid in cement mortar 1:3 Cum 0.00 - -

b) Cement Concrete blocks Grade M15 Cum 40.15 8,052.00 3,23,304

Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone boulders
15.11 5.26 Cum 730.25 2,493.00 18,20,516
weighing not less than 40 kg beyond curtain wall.

Providing and fixing in position Expansion joints complete as per drawings and Technical
5.27 Sqm 156.70 - -
Specifications

Providing & fixing Compressible fibre board in expansion joint complete as per drawing &
2.28 Sqm 279.04 346.00 96,548
Technical Specification.

Total Cost in Rs. 7,59,80,504


In crores 7.598
0.089
7,59,80,504

CHECK 0

Page 2 of 2