Presented by
The Energy Systems Laboratory
Texas Engineering Experiment Station
Texas A&M University System
ASHRAE Standard 90.1-2010 Update & Overview Workshop
Energy Systems Laboratory, TEES, Texas A&M University System 1
Acknowledgments
Thanks to:
Department of Energy
(U.S.DOE)
9:00 am Part I: Workshop introduction & Energy code status in Texas. (16) *
9:20 am Part II: Overview of the 90.1-2010 document & climate zones (24)
9:40 am Part III: Highlights of 90.1-2010 changes since the 2007 version. (17)
10:00 am Part IV: Alterations and exemption conditions. (6)
10:10 am Part V (1st half): Opaque Elements of the Envelope Criteria (22)
10:30 am 15-Minute Break
10:45 am Part V (2nd half): Fenestration Elements of the Envelope Criteria (15)
11:15 am Part VI (1st half): Mandatory portions of HVAC Criteria (37)
12:00 noon Lunch Break
1:00 pm Part VI (2nd half): Prescriptive portions of HVAC Criteria (23)
1:30 pm Part VII: Details of the SWH, Power and Equipment Criteria (14)
1:50 pm Part VIII: Details of the Lighting Criteria (28)
2:30 pm 15-Minute Break
2:45 pm Part IX: ECB Methodology and Appendix G, Perf. Rating Method (29)
Part X: New ASHRAE Standards Activity, Green Building Standard 189.1,
3:20 pm
AEDG, tax incentives and software (31)
3:45 pm Q&A wrap-up and workshop evaluation forms (8). Adjourn at 4:00 pm
DOEs energy
efficiency standards
cover the rest. (e.g.,
Energy Star ratings.)
State Website(s):
State Energy Conservation Office (SECO): http://www.seco.cpa.state.tx.us
SECO Bldg. Codes & Standards: http://www.txbuildingenergycode.com
Energy Systems Laboratory: http://www-esl.tamu.edu
Conditioned space:
cooled by a cooling system with a sensible output capacity >5
Btu/h-ft2
heated by a heating system with an output capacity Table 3.1
indirectly conditioned space adjacent to conditioned space
but neither heated nor cooled
6. HVAC
Mandatory Trade Off
7. SWH Provisions Option Energy Code
(required for Compliance
8. Power most compliance
options) Energy Cost
9. Lighting Budget
Section Contents
5 Building envelope
6 HVAC
7 SWH
8 Power
9 Lighting
10 Other equipment
11 Energy Cost Budget (ECB)
12 Normative References
Appendices A G
NORMATIVE INFORMATIVE
A. Assembly U-, C-, and F-Factor E. Informative References
Determination F. Addenda Description
B. Climate Zones Designations Information
C. Envelope Trade-Off
Methodology
D. Climatic Data
Addenda to 90.1-2007
Addendum by changes:
For most building types, the
LPDs are reduced.
Average LPDs:
90.1-2007 ave=1.09
90.1-2010... ave=0.906
Difference .. -16.9%
2007 2010
ASHRAE Standard 90.1-2010 Update & Overview Workshop
Energy Systems Laboratory, TEES, Texas A&M University System 50
Part III. ASHRAE Standard 90.1-2010 Updates (from 2007)
Changes: Reduced Lighting Allowances in
Merchandising Areas
Addendum bq reduces the allowance for specifically designed and
directed lighting to highlight merchandise.
Mandatory Provision:
Addendum cy introduced an
updated Table 6.3.2 that exempts the
requirement for economizers thru
the use of higher efficiency HVAC
equipment. The table reflects the
new ASHRAE benchmark building
models and has been expanded to
allow use for any type of HVAC
system and not just for unitary air
cooled equipment in the current
table.
Lighting changes:
The LPD limitations are more stringent than both the 2004 and 2007 versions, and will
save around 16% over the 2007 version and more than from 25% over 2004 version.
A new exterior lighting section includes specific lighting power limits for a variety of
exterior applications.
Internally illuminated Exit Signs now shall not exceed 5W per face.
LED lamps okay, but most incandescent lamps will not be acceptable.
Power limits added for exterior lighting categories (e.g. walkways, parking lots, ATMs).
Exception:
Compliance w/ sections 5-10, except National Registry of
Historic Places or total energy consumption equivalent
design that complies with sections 5 through 10.
Equipment modification or
repair only (no increase in
energy)
Where compliance requires
extensive revision to other
systems
Refrigerant change only
Relocation of existing
equipment
Ductwork, and Piping where
there is insufficient space to
access.
Mandatory
Provisions (5.4)
Prescriptive Trade-Off
Option (5.5) Option (5.6)
Compliance
Exceptions:
Field-fabricated fenestration and doors
Metal garage roller doors semiheated
spaces in climate zones 1 through 6.
Categories of
Construction
Requirements:
a. Three-yr-aged roof solar reflectance 0.55 and emittance 0.75, (certified by
ASTM C1549/ E1918/ C1371/ E408), or
b. Three-yr-aged SRI (solar reflectance index) 64*, (certified by ASTM E1980), or
c. Increased insulation from Table 5.5.3.1.2
---------------------------------------------
* SRI 100 x (R + 0.12E) approx.
Strip Mall
Retail Sales
Medical Offices
** SHGCs have a major change from 90.1-2004: These now apply to all orientations, including North
Observation:
There are no SHGC requirements for
semiheated spaces in any climate zone
nor for residential buildings in climate
zones 7 and 8.
Specification requirements:
Daylight area under skylights the floor area and either:
a. Skylight area-to-daylit area ratio 3% w/ VT 0.40, or
b. Skylight effective aperture area 1%
________________
Effective aperature area = 0.85 x skylight area x VT x WF / daylit area
VT = Visible Transmittance
WF = Well Factor = 0.9 for well depth < 2 or 0.7 for well depth 2
ASHRAE Standard 90.1-2010 Update & Overview Workshop
Energy Systems Laboratory, TEES, Texas A&M University System 99
Part V. Section 5 - Building Envelope
Skylight Exemptions
to 5.5.4.2.3
a. In spaces in climate zones 6 through 8.
b. In spaces with general LPD < 0.5 W/ft2.
c. In spaces that are blocked from receiving direct beam
sunlight on 50% of roof area for > 1500 daylight hrs/yr.
a. In spaces where the daylight area under roof-top monitors is > 50% of the
floor area.
b. In spaces where 90% of the skylight area is shaded on June 21 in Northern
Hemisphere.
The required daylight area under skylights may be reduced by the amount of:
a. primary sidelighted area with a sidelighting aperture > 15%, given
appropriate general lighting control, or
b. secondary sidelighted area with a sidelighting aperture > 30% and with
general lighting controlled by continuous daylight dimmers.
Mandatory
Provisions (6.4)
proposed
HVAC design Prescriptive Energy Cost
Path (6.5) Budget (11)
Simplified
Approach (6.3)
90.1-compliant
HVAC system
ASHRAE Standard 90.1-2010 Update & Overview Workshop
Energy Systems Laboratory, TEES, Texas A&M University System 106
Part VI. Mechanical Systems
Simplified Approach Option for HVAC Systems
Section 6.3
Simplified
Limited to
Approach
Buildings with 1 or 2 stories and with < 25,000ft2, and that meet 17 criteria:
a. Single-zone systems.
b. VAV controls to of design cfm.
c. Air-cooled or evaporatively-cooled unitary/
split per Tables 6.8.1A, B, D.
d. Economizer required per Table 6.5.1
But, economizer requirement can be
exempted by conditions in Table 6.3.2
e. Heating required per Tables 6.8.1B, D, E, F.
f. Meet exhaust energy recovery reqmts of Section 6.5.6.1, at 50% efficiency.
g. Manual changeover or dual set-point thermostat.
Fans with motors > h.p. (0.5 kW) shall have automatic
controls complying with section 6.4.3.3.1 that are capable
of shutting off fans when not required *.
Exception: HVAC systems that operate continuously.
Exceptions:
a. Garages <30,000 ft2 with ventilation systems that do not utilize
mechanical heating or cooling.
b. Garages that have an area-to-horsepower ratio that is > 1500 ft2/hp
and do not utilize mechanical heating or cooling.
c. Where not permitted by the authority having jurisdiction.
Exceptions:
a. Zones served by desiccant systems, used with direct evaporative
cooling in series.
b. Systems serving zones where specific humidity levels are required,
such as museums and hospitals, and others approved by the
authority having jurisdiction.
Four exceptions:
(a) Factory-installed plenums, casings, or
ductwork furnished as part of HVAC
equipment
(b) Ducts or plenums located in heated,
semi-heated, or cooled spaces
(c) For runouts < 10 ft in length to air
terminals or air outlets, the R-value
need not exceed R-3.5
(d) Backs of air outlets and outlet plenums
exposed to unconditioned or indirectly
conditioned spaces with face areas > 5
ft2 need not exceed R-2; those 5 ft2
need not be insulated
Exceptions:
a. Factory-installed piping within HVAC equipment.
b. Piping conveying fluids between 600F and 1050F
c. Piping conveying fluids not heated or cooled with purchased energy
(such as roof & condensate drains, nat. gas piping, etc.)
d. Where heat gains or losses will not increase energy use (such as the
case with liquid refrigerant piping.)
e. Strainers, control & balancing valves in pipes 1 diameter.
Longitudinal Joint
Appendix E.
Duct tape or other pressure-sensitive tape
shall not be used as the primary sealant
unless certified to comply with UL-181A or
UL-181B by an independent testing
laboratory.
For ductwork designed > 3 in. w.c. and all ductwork located
outside:
Leak tested per standards in Appendix E.
Representative sections 25% of the total installed duct
area shall be tested.
Duct ratings that are > 3 in. w.c. to be identified on
drawings.
Maximum permitted duct leakage shall be calculated and
specified, per next slide --
Lmax CL P 0.65
where,
Lmax = maximum permitted leakage in cfm/100 ft2 duct
surface area
CL = leakage class, cfm/100 ft2 @ 1 w.c.
( = 4 for rectangular or round duct.)
P = Test (design) pressure, in w.c.
Prescriptive
Path (6.5)
1b,2b,3b,3c,4b,4c,
Differential DB TOA > TRA OA temp exceeds return air temp
5b,5c,6a,6b,7,8
Fixed enthalpy 2a,3a,4a,5a,6a hOA > 28 Btu/lb OA enthalpy exceeds 28 Btu/lb.
Electronic OA temp/RH exceeds the A set
All (Toa, RHoa) >A
enthalpy point curve.
Differential Outdoor enthalpy exceeds return air
All HOA > HRA
enthalpy enthalpy
DP and DPOA > 55F or Outdoor DP exceeds 55F (65
All
DB temp. TOA > 75F gr/lb.) or outdoor DB > 75F
Zones for which volume of air that is reheated, recooled, or mixed is no greater than
the larger of the following:
1. 30% of zone design peak supply.
2. Volume of outside air to meet Section 6.2 of ASHRAE 62.1 for the zone.
3. Any higher rate that will reduce the overall system annual energy usage by
offsetting the reheat/recool energy losses by a reduction in OA.
4. The air flow rate required to comply with applicable codes or accreditation
standards.
Zones that comply with all the following:
1. Air flow in the dead band 20% of peak supply rate, or OA rate ASHRAE 62.1
requirements, or can be modulated.
2. Mixed air flow rate < 50% of zone peak supply rate.
Lab exhaust systems that comply with Section 6.5.7.2, regarding preconditioning of
makeup air from lab exhaust air.
Zones where at least 75% of the energy for reheating or for providing warm air in
mixing systems is provided from a site-recovered or site- solar energy source.
Thats a NO-NO!
No common return
system for both hot and
chilled water.
Footnote: This methodology was first introduced in Standard 90.1-2007, though with
different adjustment values.
Record drawings
Operating and maintenance manuals
System balancing
System commissioning
Mandatory
Provisions (7.4)
Compliance
Note: Q = nameplate input rating (Btu/h); V = tank volume (gallons); Et = thermal efficiency
Voltage drop
Completion requirements
9.6 Space-by-space
9.5 Building area method
method
Compliance
Example:
Calculate the total lighting Wattage of a room
containing the following fixtures:
A. Eight 2x 4 Fluorescent Fixtures
Three 4 fluorescent T8 lamps per fixture, 32 Watts
1 three-lamp electronic ballast
Ballast Input Wattage - 90 watts
B. 6 Incandescent Downlights
Specified Lamps - 60 Watt, A-line, Medium Screw Base
Maximum labeled wattage of fixture - 75 Watts
C. 16 Feet of Line Voltage Track
Specified - 5 Track Heads
90 Watt Halogen PAR38 lamps
Wrong Way!
8 Fixtures x 3 Lamps x 32 Watts per Lamp = 768 Watts
6 Downlights x 60 Watts/A-line lamp = 360 Watts
5 Track Heads x 90 Watts/Halogen Par Lamp = 450 Watts
Total Wattage = 1578 Watts
Right Way!
8 Fixtures x 90 Ballast Input Watts = 720 Watts
6 Downlights x 75 Watt Labeled A-line Fixture = 450 Watts
16 Track x 30 Watts/Foot = 480 Watts
Total Wattage = 1650 Watts
Solution
200 x 350 = 70,000 sq. ft. per floor
6 Floors x 70,000 sq. ft per floor = 420,000 sq. ft.
420,000 sq. ft. x 0.9 watts per sq. ft = 378,000 Watts
Total Lighting Power Allowance = 378 kiloWatts *
* 420,000 W when using 90.1-2007 (42,000 W saved.)
Example:
Calculate Total Lighting Power Allowance
using the Space by Space Method:
Mandatory Provisions
(Sections 5.4, 6.4, 7.4, 8.4, 9.4 & 10.4)
Compliance
Normative Appendix G
Provides specific rules for determining degree of
improvement over 90.1
Responding to demand by LEED designers
Distinct from Energy Cost Budget compliance method
(Section 11)
Purpose:
To provide tools by
2020 that enable the
building community to
produce market viable
NZEBs by 2030.
Mandatory Provisions
Allowable sites
o Brownfields, greyfields
o Greenfield sites where < 800 m ( mi) to
transit or 10 basic services, or residential area
with density > 10 units/acre
Prohibited development activity
o Flood plains, wetlands, fish and wildlife
habitat
Heat island effect
o Site hardscape: to be shaded, paving to be SRI 29, or porous pavers
o Wall: to be shaded up to 20 feet above grade
o Roofs: to be SRI 78 (low-slope) or 29 (steep-slope) or be a cool roof
Site development
o All sites: Min. 40% of area to be
effective pervious surface
(vegetation, green roof, porous
pavers)
o Greenfield sites: Min. 20% of area to
be native or adapted plants
Prescriptive Option:
Daylighting by sidelighting
(offices/classrooms)
o Minimum effective apertures = 10%
in climate zones 1 to 3B and 15% in
climate zones 3C to 8.
o Minimum interior surface visible
light reflectances 80% for ceilings
and 70% for partitions.
o Minimum interior or exterior shading
projection factor (PF) 0.5 for all
facades except north-facing.
Prescriptive Provisions
Reduced Impact Materials
o Recycled Content
o Regionally Extracted, Processed, and
Manufactured Materials
o Biobased Products
Consumer tax credits: Up through Dec 31, 2016, 30% of the cost (up to
$1500 for efficient appliances) and with no upper for renewable energy
systems (geothermal, solar, wind turbines) -- for existing homes & new
construction
Web site:
http://www.energystar.gov/index.cfm?c=tax_credits.tx_index
Source: http://www1.eere.energy.gov/buildings/qualified_software.html
Software name, latest version submitted , and date DOE received latest full documentation
EnergyPlus 6.0 10/29/10
Green Building Studio 3.4 10/16/08
DOE 2.2 47d 9/30/09
DOE 2.1E 119 7/2/07
DOE 2.1E-JJH 130 11/5/07
eQuest 3.63b 9/9/09
EnergyGauge 3.22 1/14/10
Energy Pro 5.1 1/20/10
EnerSim 9.02 12/16/09
Hourly Analysis Program (HAP) 4.41 4/10/09
IES <Virtual Environment> 6.3 3/30/11
Owens Corning (OC-CEC) 1.1 8/14/07
Trace 700 6.2.6 9/9/10
VisualDOE 4.1 build 0002 9/11/06
(404) 636-8400
ASHRAE Standard 90.1-2010 Update & Overview Workshop
Energy Systems Laboratory, TEES, Texas A&M University System 271
ASHRAE Certification Program
Cyndi Lewis
cyndim@tamu.edu
Texas Emissions Reduction Plan (TERP) Manager
Energy Systems Laboratory, TEES