Você está na página 1de 8

Understanding the Role of Production

Drilling and Drilled Stocks in Efficient


Operation of a Sublevel Cave Mine
C Beal1

ABSTRACT
Proper understanding and management of production drilling in sublevel cave (SLC) mines
is essential for meeting production targets and for avoiding inefficiencies that could lead to
costly bottlenecks. In many SLC mine management models drilling is considered a derivative
activity of firing and bogging. Its scheduling is considered to be implied in a firing schedule
and given an arbitrary target completion, several weeks or a month, ahead of production
firing. Like development, drilling activities are most efficient when conducted separately from
other production activities. Unlike development, however, it is not apparent during planning
and feasibility how far in advance of firing drilling activities ought to be conducted. This paper
presents a method of defining a minimum threshold of drilled stocks above which drilling, firing
and bogging operations occur most efficiently. As an example, the drilling activities, procedures,
and maintenance at Glencore Xstratas Ernest Henry Mine are presented, and the larger scale
consequences of improvements to these areas are presented to illustrate their importance in the
operation of an SLC mine.

INTRODUCTION
In most stoping methods production drilling can be thought So how many rings in front, or how large a buffer, is
of as distinctly individual jobs, with each job being made up enough? Is there a maximum amount of drilled stocks that
of a single stope or sublevel. To complete the job a drill plan shouldnt be exceeded? This paper addresses and attempts to
is issued for the entire stope, the drilling pattern is marked up answer these questions, as well as describing the experiences
and the drilling is conducted. Once all of the drilling for each of Glencore Xstratas Ernest Henry Mining (EHM) in
stope location is complete the job is finished and the drill can ramping up its production drilling. Over a 12-month period
move onto another job. By completing the drilling for the site at EHM, following the identification of production drilling
in a single pass, interactions between the drill rig, charge-up, as a bottleneck, the longhole production drilling rate per rig
doubled from around half the industry benchmark of 10000m
bogging, and backfilling activities can be minimised and the
per drill per month to rates exceeding the benchmark. This
stope is mined most efficiently. Where available, down hole
improvement was the result of operational, mechanical and
drilling can also be used to further separate activities into
paradigm changes affected over that time; an account of these
charging and bogging levels.
changes is included.
By contrast, sublevel cave (SLC) mines must continually
alternate drilling, charging/firing and bogging activities in The Ernest Henry underground mine
all ore drives. Ore is produced as consistently and evenly as The EHM underground mine is a copper and gold mining and
possible from all draw points. At SLC mines, drilling of an processing operation located 38 km north-east of Cloncurry
ore drive is usually only partly complete with drilling being in north-west Queensland, Australia. Commercial production
a number of production rings ahead of charging or bogging first began in March 1998 with an open pit mining operation
fronts. This quantity of drilled stocks or buffer of drilled that transitioned to underground production in December
rings has a substantial effect on the rate of ore extraction 2011, extending the life of the mine to 2025.
from a draw point: when drilled stocks are too low, drills EHM aims to hoist approximately 6 Mt/a of ore from the
fall into a downward spiral where their daily drill metres are SLC following shaft completion and subsequent ramp-up in
reduced further and further by having to move the machine 2014. During the expansionary development, construction
to new locations as often as several times per day. Continuing and commissioning phase, ore is extracted concurrently
along that route can eventually result in drilling becoming by traditional haulage methods at a rate of 33.5 Mt/a and
the bottleneck of the operation. However, when there are utilises a fleet of Atlas Copco MT 6020 underground haul
enough drilled stocks, drills can remain at a single location trucks operated by Barminco.
for days at a time without being interrupted, allowing them The orebody at EHM dips south at 45 and occurs in a pipe-
to continually achieve high drill metres. like geometry that has east-west footwall drives of 250m

1. MAusIMM, Underground Scheduling Engineer, Ernest Henry Mining Pty Ltd (Glencore Xstrata), PO Box 527, Cloncurry Qld 4824. Email: chris@beal.net

12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014 235
C BEAL

length and ore drives penetrating 250 m south. The current types of drilling. Initiation of caving was conducted via mass
scope of the project has sublevels spaced 25 m vertically blast as described by McGrath, Campbell and Tucker (2014);
between RL 1650 (RL 2000 is sea level) and RL 1200 for a total underground water storage capacity was achieved through
of 19 production levels. Ore drives are spaced on 15 m centres stoping (open stopes are used for storm water storage);
with current ore drive dimension of 6 m width by 4.5m longhole rises were fired for ventilation and ore passes; and,
height. A standard level is made up of around 14 ore drives, throughout it all, sublevel caving was conducted to produce
depending on ore boundaries. an ore product. Each of these methods or activities, as well as
Production drilling uses 102 mm diameter drill holes to other service or drain hole jobs, demanded longhole drilling
define a silo-shaped ring with a 2.6 m burden. Charging and capacity. As a result of drills being sent intermittently to work
firing is conducted by Dyno Nobel, using inhibited emulsion on other projects, the cave was operated with a variety of
explosives with both non-electronic and electronic detonators. different quantities of drilled stocks. This section will describe
Typically, a minimum of four rings are drilled in advance in the experiences at EHM with regard to different levels of
any ore drive, two of which are precharged. Figure 1 shows a drilled stocks.
typical ring at EHM.
With SLC mining the ore tonnes recovered per metre drilled Minimum drilled stocks just-in-time drilling
is quite low when establishing the cave. Typically only 40per At EHM, several isolated occurrences of just-in-time drilling
cent of fired ore is recovered in the top level, followed by were undertaken where ground conditions raised concerns of
60per cent in the second, 90 per cent in the third, and full hole deterioration. This type of just-in-time drilling effectively
draw of 120 per cent or greater in the subsequent levels. With describes the extreme minimum end of the drilled stocks
the dip of the EHM orebody, each level steps out by around scenarios. By looking at these isolated occurrences, several
25m then progressively retreats under the step-outs above obvious problems associated with just-in-time drilling are
and therefore starts the cave on every level requiring low highlighted.
draw factors (refer to Figure 2). The overall result is a high
demand for production drilling per ore tonne during early The minimum number of rings drilled in advance of firing
production where production ramps up through 12 Mt/a, to activities at EHM is dictated by the safety management plan,
medium demand when the cave is established as a trucking which includes the following:
mine, to lower demand per tonne under full production. In Blast holes within 5 m of an active brow are not practically
essence, the mine requires around the same annual drilling accessible for charge-up due to the rill angle of the cave
targets from the first year until the last year of production. material. Therefore, with 2.6 m ring spacing, two rings are
to be charged in advance at any given time.
APPROPRIATE DRILLED STOCKS Attended drilling (operator in cab) within 6 m of explosives
The transition to full-scale underground production at EHM is prohibited. Therefore, two additional drilled rings must
undertaken between 2011 and 2014 required a variety of be maintained.

FIG 1 Section view of a typical drilled ring.

236 12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014
UNDERSTANDING THE ROLE OF PRODUCTION DRILLING AND DRILLED STOCKS IN EFFICIENT OPERATION OF A SUBLEVEL CAVE MINE

FIG 2 Section view of cave looking west showing draw variation with depth and northing.

Where an ore drive is first being fired into a slot, a five-ring no flexibility to change daily firing plans as a result of
stand-up sequence is used and so a practical minimum of unplanned disruptions, inevitably leading to reduced
nine drilled rings is required. production rates.
As shown in Figure 3, the minimum safe drilled stock This situation is often referred to as hand to mouth and
is four rings per heading, with a fifth drilled ring required is not uncommon in mining where one process bottlenecks
before firing the front ring. When this scenario is used as others. As seen at EHM, the most likely reason for intentionally
operating at minimum drilled stocks is persistent drill hole
the operating drilled stock, the production rate is effectively
deterioration due to high stresses and fracture ground, which
dictated by the drilling rate. Because drilling of the fifth ring in
renders drilled stocks useless. When significant amounts of
each drive is required before firing the front ring, the number time are spent on hole clean-outs and re-drilling then the
of rings available to fire per day is exactly equal to the number system is unreliable and will not be cost effective.
of rings drilled that day. Any occasion of reduced drilling
It is also possible that just-in-time drilling happens as a
rates, whether it is the result of an interaction, mechanical result of the second point listed above, where tramming time
downtime or idle time will force a proportionate reduction in is especially high relative to operating time. It has been found
tonnes produced from the drive. at EHM that even with adequate levels of drilled stocks, if rig
Further complicating the situation is the scheduling of moves occur too frequently then lower and lower drill metres
charging and firing activities to immediately follow drilling, will be achieved until the situation reverts to the minimum
which forces a state of perpetual interaction. Nearly all the drilled stocks cycle.
traffic on a production level will be concentrated in the same
area, which could result in:
Performance above the minimum drilled
stocks
equipment and people left idle, waiting for their turn
From the perspective of a feasibility study, the relationship
as a result of different activities inherently operating at
between drilled stocks and a drills ability to perform
different speeds effectively may be intriguing; but from the operators and
more time tramming and less time operating when only managers perspectives who conducted the drilling it was
one or two rings are drilled at a time, potentially to the abundantly clear: to achieve their targets, building drilled
point where extra wear is introduced to the equipment stocks must be considered a priority.

FIG 3 Section view of an active ore drive showing the minimum number of predrilled and precharged rings required to support operation at a sublevel cave.

12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014 237
C BEAL

The requirement to build enough drilled stocks was Improvements to drilling supply at EHM are discussed
identified early in production and changes were explored below in the categories of:
and implemented throughout the continuing operation. A contract drilling
successful outcome was realised sometime between April and operator improvement
May, 2013 when a barrier appeared to have been overcome.
improved utilisation and availability.
The quantity of drilled stocks had gone over some critical
amount and rather than it inhibiting the performance of the Contract drilling
drills it began to enhance drill performance. Figure 4 shows During the feasibility study the drilling requirements,
the average drill rate per rig between May 2012 and October including ten per cent re-drilling, were assessed as needing
2013. Separate trend lines have been fitted prior to and between two and three drills. In 2009 as a result of the global
following April 2013 to show the marked difference in drill financial crisis the projects capital costs were reviewed and
performance. Figure 5 shows the total drilled stock over the the decision was made to drop one drill in favour of regular
same period, which has an equally notable change in slope. periods of contract drilling to supplement the EHM drills.
This is not intended to imply a direct relationship between Drilling would begin by using contract mining services and
quantity of drilled stocks and monthly drill rate per rig. Rather, move to owner-operator following commissioning of the
below a certain quantity of drilled stocks drill performance is shaft; however, early in 2012 the decision was made to bring
actively depressed by the required behaviour of the drill. The the transition to owner-operator forward.
specifics of this relationship will be explored more in the final Contract drilling was initially provided by Barminco with
section of this paper, where a method is proposed to calculate a single Byrnecut drill added in 2012. All contract drilling
this critical level of drilled stock. was conducted using Sandvik Solo drills. The decision by
EHM to use Atlas Copco L6C Simba model drills contributed
OPERATIONAL CHANGES AND THEIR EFFECTS to a degree of complexity as these drills progressively
The previous section of this paper focused on what might be supplemented the Solos through 2012. Figure 6 shows the
called the drilling demand of an SLC or the level of drilled timeline of drilling equipment used at EHM.
stocks that allows a production cycle to operate without At the monthly benchmark drilling rate of 10 000 m per rig,
unnecessary drilling bottlenecks. The other half of the story three drills were forecast to be sufficient for the mines needs.
is drilling supply. Drilling supply is the rate of drilling that However, when actual drilling rates performed poorly, it was
a drill and operator are capable of delivering on a daily or decided to utilise four drills on-site through 2012 and early
weekly basis. The papers focus now shifts from the variability 2013.
of drill duration operating at a single location to a number The periods of contract drilling were primarily directed
of other factors that directly influence drilling rates. Whilst at large drilling projects such as the transition blast that
drilling demand is essentially addressed during feasibility initiated caving and the underground storm water storage
and planning stages with periodic reviews throughout the system. The drilling of these two projects marked a peak
mine life, efforts to improve the drilling supply are addressed of drilling requirements with the transition blast taking
continuously throughout the operational phase. approximately 63 000 m of drilling and the water storage

FIG 4 Per rig drilling rates at Ernest Henry Mining.

FIG 5 Total sublevel cave drilled stocks.

238 12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014
UNDERSTANDING THE ROLE OF PRODUCTION DRILLING AND DRILLED STOCKS IN EFFICIENT OPERATION OF A SUBLEVEL CAVE MINE

FIG 6 Ernest Henry Mining drilling equipment and drilling project timelines.

stopes taking approximately 25 000 m. As shown with the drill mine as a whole began to improve, the encouragement and
equipment timeline in Figure 6, these two projects occurred positive feedback provided continued to assist in improving
simultaneously and required drilling in addition to regular daily drilling rates.
production ramp up.
The period between June and November 2012 was Reduction of lost time
characterised by non-standard drilling and frequent trams A great deal of collaboration between management, mine
to different sites. During this time drills achieved an average planning and maintenance led to substantial reduction in non-
monthly drill rate of 5900 m each. utilisation, tramming and downtime over several months,
The decisions to retain the last contract solo until August which in turn gave the operators increased time to drill.
2013 and to purchase a third EHM Simba were driven directly
by the identification of low drilled stocks as a main contributor Use of automation
to drilling inefficiencies. The use of this additional drilling Atlas Copcos ABC Total drilling option was selected during
capacity was pivotal in pushing stocks through to efficient the original equipment selection process to allow full ring
operating levels. automated drilling to be conducted over shift change. EHM
The final contract drill left site in August 2013, having aimed to use automated drilling over shift changes where up
accomplished the goal of bolstering stocks. By September 2013 to two hours are lost per shift, and during crib times. What
the final fleet of three L6C Simbas achieved 30390 m, or an the mine has found is that the use and acceptance of this
average of 10130 m each. Between three efficiently operating technology hasnt been as straight forward to implement as
drills, more metres were realised in one month than had been first thought. Following a learning curve automated drilling
realised by four drills in the same month of the previous year. now contributes up to 3100 m each month, or nearly ten per
cent of metres drilled. As operators adapt to this technology
Operator improvement this figure is expected to continue to grow. While automated
The first lines of efficiency in an operation are the operators drilling has increased in effectiveness, manual drilling is still
and their skills in using the equipment. With EHMs new preferred where possible.
drills and new operators there was a learning curve to be
navigated in operation and maintenance of the drills. The Mechanical improvements
mine attempted to minimise the early, inefficient stages Despite the new drilling units, mechanical availability was
of the learning curve at the operator level by employing initially lower than expected. The maintenance departments
experienced drill operators. Experience using Simba-model early experiences identified a number of low-expense/high-
drills was especially sought after. Out of the 12 operators who reward areas for improvement of drill rig availability.
were recruited, all were experienced longhole drillers, with
The most effective change was to conduct more of the
nine having extensive experience with Simba-model drills.
scheduled maintenance directly on-site or at a temporary
As the production operation expanded and drilling underground workshop, rather than at the main surface
conditions improved in 2013, the questions of culture and workshop, eliminating a 15 km or two hour round trip plus
motivation were addressed. After operating at a reduced associated delays and interactions. The result was that drills
rate for many months the potential for attitudinal or cultural
were not forced to leave their sites more than once a week,
barriers to reaching higher rates were identified and addressed.
potentially allowing for up to a weeks continuous drilling at
In April 2013, expectations for drilling performance were
a single location. When required to tram to the workshop for
made clear to the operators by including an ultimate goal
weekly services the travel time was also significantly reduced
of 250m of production drilling per shift as their target rate
to less than 2 km.
within their job description. Operators and their cross-shifts
were acknowledged for holding 24-hour record drilling rates, Power faults associated with cable lead connections were
and an effort was made to relay performance data back to the found to be a source of delays. The installation of cable leads
operators so that they could gauge their own performance. fitted with Atlas Copcos rig control system (RCS) provided
Initially, the drilling target, which was over twice the rate an interface that allowed the root causes of these faults to
being achieved at the time, caused some friction with the be more easily identified. Eventually the problematic power
operators. However, as the operators and the production faults were brought back to an acceptable level.

12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014 239
C BEAL

Delays caused by blown hydraulic hoses were mitigated


by the installation of custom-fabricated and more accessible
centralised hydraulic manifolds. In combination with these,
hydraulic hoses were standardised so that replacements
could be carried on the rig and changed more quickly.
As part of the ABC Total program, fully automated bit
changers were originally installed to eliminate stoppages over
shift change associated with blunt bits and low penetration
rates. These bit changers increasingly became a source of
maintenance as they were subject to contacting walls and
FIG 8 Production cycle progression required to maintain
backs. The reduction in associated maintenance time was
minimum predrilled stocks (first week).
deemed more beneficial than the additional drilling time they
were providing and they were removed. This decision will be and advancing upward. It shows a number of ore drives that
reviewed at a later date as the adoption and performance of extend up the page with the drill ring positions shown as
automated drilling progresses. horizontal lines up each ore drive, giving the appearance of
train tracks. Shown above the flat cave front are ten dark grey
DETERMINATION OF MINIMUM DRILLED shaded rings representing those fired in the week leading
STOCKS up to this snapshot. The next four light grey rings in each
drive represent the minimum level of drilled stocks required
Effectiveness of drilling for safe operation of the cave. The ten outlined rings spread
One of the key aims of this paper is to describe a method to across all the ore drives represent those to be drilled in the
calculate the minimum required drilled stock that will allow coming week. Finally, the asterisks represent the rings to
optimal operational efficiency. The basis for this method is be fired in the coming week, where each of these rings will
to allow a reliably operating machine to drill uninterrupted require the corresponding outlined ring to be drilled before it
in a single location for as long as practical. Any tramming, can be safely fired. This maintains the four ring drilled buffer.
setup, or idle time related to location availability all reduce In this example the drilling will be done just in time.
the portion of the day spent in productive operation. From This scenario would require a drill to move into all eight
a planning and management perspective, the most dramatic drives over the course of the week to stay in advance of
results are achieved by reducing drill moves. Figure 7 shows firing activities. Coordinating eight moves for less than a
daily drilling rates as a function of the number of days a drill day at each drill location every week for every section of the
is left at the same location and demonstrates the variability of producing mine would directly reduce the time spent drilling
daily drilling with regular rig moves. and therefore metres achieved. This is reflected in the left-
hand side of Figure 7, with the drill spending less than a day
The practical upper limit of time spent drilling at a single
in each location. Ore production would subsequently suffer
location is set by the weekly preventative maintenance
proportionately. Production is limited in this scenario to
schedule, which is therefore seven days.
around 40 to 42 rings every four weeks.
The following discussion utilises two examples of drilled An alternative scenario demonstrating the effectiveness
stocks to illustrate how drill effectiveness can be affected by of adequate drilled stocks over four weeks of production is
low drilled stocks. The first example shows how an operating shown in Figure 9. This scenario is optimised for a longhole
level would progress on a weekly basis in an environment of drill to allow it to remain at each location for a full week.
minimum drilled stocks with just-in-time drilling. The numbers indicate the week that the indicated rings were
Figure 8 is a schematic plan view of the SLC production either drilled or fired. The improvement shown is over 30 per
cycle with the cave front of broken ore shown at the bottom cent, or three to four extra rings per week. The number of

FIG 7 Regression of sample average drilling rate and time spent continuously at one location.

240 12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014
UNDERSTANDING THE ROLE OF PRODUCTION DRILLING AND DRILLED STOCKS IN EFFICIENT OPERATION OF A SUBLEVEL CAVE MINE

Minimum drilling = ^m $ a $ nh
minimum drilled rigs per drive $ # of active drives
=e o
$ average drill metres per ring
rings
= e4 $ 8 $ ~165 m o
drive ring
= 5280 m

and:

a- 1
metres per drive interval = > / x $ i c F mH
x R
Sum of
i=1 a -1
FIG 9 Production cycle allowing week-long drilling at each location. m rings fired
8 - 1/1 f 165 ring $ 14 interval p
rings fired has correspondingly increased by over 30per cent, => / 1$i H
i=1 8 - 1 drives
or 56 rings in the month, to match the drilling rate. After week
7
= = / i drive interval ` 330
drive interval jG
four, the drill would progress to each remaining drive and metres
eventually cycle back to the left-most drive on the ninth week. i=1
The minimum buffer of drilled stocks that is required to = 61 $ 330@ + 62 $ 330@ + g + 67 $ 330@
allow this to optimal sequence is indicated by the hatching = 9240 m
and totals 88 rings.
so, therefore:
This example shows rings being drilled and fired in an
orderly left-to-right sequence, while in reality operations often Buffer = Sum of metres per drive interval + Minimum drilling
encounter factors that disrupt the schedule. The principle will
= 9240 m + 5280 m
work just as well with non-sequential drilling provided the 14 520 m 88 rings
drill spends equal time in each drive and encounters all active = 14 520 m , =
165 m
drives evenly. ring
Once enough drilled stocks have been created and the mine
enters a steady-state operational phase, the rate of drilling By using this equation in parallel with mine scheduling
should equal the rate of production. Otherwise, the drilled software (to fill all variable quantities), a minimum threshold
stocks would increase beyond a useful level to the point of predrilled stocks can be determined and clearly referenced
that hole degradation becomes an issue or until they catch for any operating point.
development.
Creating drilling equipment schedules
The theoretical minimum drilled stocks Production drills will be capable of performing optimally
To calculate the theoretical minimum drilled stocks for any and reliably when actual drilled stocks are maintained
given area without having to sequentially plan out each week, above the minimum level calculated using the above
the following formula has been developed by the author: method. Therefore, a drill equipment schedule will forecast
the cumulative drilling throughout the project and subtract
drilling consumed by production firing. An iterative approach
a- 1
B = > / x $ i c F mH + ^m $ a $ nh
x R is required at this stage, as the number of drills is an input to
i=1 a-1 the drilled stocks equation, so the calculated minimum stocks
= Sum of metres per drive interval + Minimum drilling will change with each new equipment schedule. An example
of a final drilling equipment schedule calculated using this
Where an interval is the length of time a drill will spend method is presented in Figure 11. This schedule accounts
at each location, or seven days in the previous example, and: for SLC material only, longhole drilling required for periods
B = minimum buffer of predrilled stock in metres of expansion (eg the transition firings) or non-SLC-based
extraction methods should be managed separately and their
a = number of headings active for firing during each
drilling requirements added to that of the SLC.
interval
The schedule in Figure 11 has been generated from the
x = number of drills
original mine schedule at EHM and follows the actual timeline
RF = rate of firing in metres per interval
of drilling equipment quite accurately. By adding one drill
= average drill metres per ring for the June November 2012 period of non-SLC intensive
m = minimum drilled rings in each ore drive, which is four drilling the schedules become, in fact, quite similar.
at EHM Note the period in Figure 11 between July 2013 and May
The previous examples worked in rings to illustrate the 2014 where the actual drilled metres are forecasted to outpace
concepts, whereas the above equation has been derived the calculated minimum stocks by a wide margin. Drilled
in terms of metres. This more accurately measures the stocks build up until June 2014 and then steadily decline
significance of non-standard rings (ie short rings or slot rings to the minimum level by 2015. This is not the creation of
with fewer metres contribute less than full rings) and allows excessive stocks but the preparation for commissioning of the
for easy tracking of drilled stocks against targets. In the shaft and subsequent hoisting when production rates increase
context of the previous example, the quantities that the two from 3.5 Mt/a to 6 Mt/a. The large quantity of drilled stocks
components of the equation calculate are shown in Figure 10: is a deliberate allowance for the decrease in stocks associated

12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014 241
C BEAL

FIG 10 Level view showing calculated regions of drilled stock as per equation.

FIG 11 Sublevel cave drilling equipment schedule with minimum drilled stock requirement and forecast actual drilled stock.

with the initial cave being established and the relatively low performance and stocks fall together and eventually become
draw ratios that are required near the hanging wall as an the bottleneck of production.
extra level must come into production. Over the same period To proactively plan for efficient drilling operations, a firm
of time, the overall draw ratio increases as caving progresses target of drilled stocks should be included in annual and
deeper which yields increasing recovered ore tonnes per fired life of mine scale plans and schedules. The target drill stock
metre. generation and projected consumption, when combined, may
be used to determine the drilling equipment requirements
Maximum drilled stocks throughout the mine life. This technique effectively captures
In a rock mass that closes off holes in a short space of time, the activity of the drills without the requirement for strictly
for example a jointed and stressed ultramafic nickel setting, planned drill movements in broad-scale plans.
the maintenance of actual drilled stock above the minimum
The experience at EHM has been that the development
level may not be possible, or may generate unacceptable
of further understanding and a focused effort from the
levels of re-work. If this is the case, a drilling efficiency closer
management level was effective at improving the core
to 6080 per cent may be the highest practical level and extra
conditions of the drilling process, allowing it to run more
drilling equipment will be required to maintain required drill
efficiently.
hole generation rates. The experience at EHM has shown
such conditions to be present only in rare areas of faulted
ground with high ground stress induced by progressive ore ACKNOWLEDGEMENTS
extraction, although it is expected that a maximum drill hole The author would like to thank colleagues in the development
life exists even in such a competent rock mass. As the cave of the concepts behind this paper, in particular Mr Scott Bell
progresses with depth over the years, the induced stresses (Underground Production Superintendent) and Mr Heath
will increase and hole life may need to be addressed. Tanis (Maintenance Superintendent). The author would also
like to thank Glencore Xstrata Copper for support in the
CONCLUSION publishing of this paper.
Consistent and efficient production drilling is as important
to an SLC mine as trucking, bogging or firing activities. Drill REFERENCES
performance is compounding where periods of increased drill McGrath, A, Campbell, A and Tucker, J, 2014. Transition of the
effectiveness lead to higher drill stocks and in turn allows a Ernest Henry Mine from open pit to underground sublevel
cave, in Proceedings 12th Underground Operators Conference 2014,
drill to perform even more efficiently and vice versa where
pp299310 (The Australasian Institute of Mining and Metallurgy:
Melbourne).

242 12TH AUSIMM UNDERGROUND OPERATORS CONFERENCE / ADELAIDE, SA, 2426 MARCH 2014

Você também pode gostar