Você está na página 1de 16

Energy Service

TB Maintenance Concept
A lifetime of support for your investment.
2
Protecting your What do we provide?

Investment Operational Maintenance 4-5


- Typical operational tasks
Siemens are committed to helping maintain - Parts Kit
your operations in the field.
The combination of our accurate build Scheduled Maintenance 6 - 11
information, component history and - Typical maintenance work scopes
- Parts Kits
component lifing data allows us to schedule
the correct maintenance, optimizing Maintenance Planning 12 - 13
operation, reducing downtime and reduces - Maintenance scheduling
the risk of component failure. - General Parts Kits

Remote Diagnostic Services 14 - 15

3
Current design philosophy
accommodates a six year
maintenance cycle before major
overhaul, with Gas Generator
overhaul at year three.

This information describes the


maintenance required for 48,000
running hours, approximately 6
years of operation; however should
annual running hours be less than
this then the calendar periods
between maintenance activities
may be extended.

Typical Operational Tasks Electrolyte levels of the battery may be checked.


A running check of the operation of the DC Lube oil
Daily checks
pump may be performed.
System pipework and components are checked for VDU/HMI screens are cleaned to remove dust from the
signs of leaks. control panel. They might also be examined for any
All gauges and lubricating oil levels in the tank are signs of overheating.
assessed as a guide to component condition. All connections on the actuator stepper motor may be
Engine and package are checked for oil leaks. assessed for security.
All vents and drain lines are checked to ensure they
Monthly checks
are clear of obstruction.
A visual assessment of the oil cooler is made and may Oil levels on oil filled type couplings are examined and
be cleaned if necessary. replenished.
All differential filter indicators (if fitted) are checked Flame failure head and combustion chamber glass are
and elements replaced as required. checked and cleaned.
The fuel supply pressure is checked. All solenoids are examined for signs of leakage.
The battery charger output is assessed, along with D.C. Operation of the fuel changeover system.
and A.C. supply levels. Electrical connections on the starter motor are
Control panel annunciation lights are checked to checked and gas/air starter system piping may be
ensure that they are fully functional and replaced as assessed for signs of leaks.
required. In addition, couplings are checked for security, along
The flame-on indication system will be checked to with an examination of the starter motor hold down
ensure it is functioning. bolts.
A general check of the igniter gas bottle should also be The control cabinet filter pad is checked (if fitted), and
done on a daily basis. cleaned as required.
Batteries should be boost charged.
Weekly checks
Auto drain valves are checked during start up and run
The gas starter motor may be lubricated (if fitted) and down.
the oil fog lubricator will be replenished.
The Gas Turbine
requires regular
attention in order to
replenish / replace
consumables, detect
trends and to determine
abnormalities at an
early stage.

Operational Maintenance
Operational maintenance activities are typically performed on a daily, weekly,
and monthly basis. Less frequent checks could be opportunity based
according to operational running regimes.

Quarterly checks On condition


A simulated check of the over speed safety device to Using the installed system, the compressor may be
be performed. cleaned and its recovery monitored to enable
Generator holding down bolts and visible fixings are adjustment of the period between cleaning. (The
checked to be secure in accordance with the combustion drain to be inspected for particles.)
manufacturers recommendations. For Hot wash or cold crank wash on fluid based
Vibration levels are reviewed. systems, the correct operation of all automatic drain
valves on systems with fluid wash systems may be
Lube oil pumps are checked for noisy operation and
checked.
output pressures are examined.
An inspection of the under base is made to check for
Six monthly checks signs of corrosion. If necessary, corrosion will be
removed and protective treatment applied.
Bearings on all motors will be greased.
An external check of system protective devices to be
made.
Parts Kit
Door seals, hinges, pivot pins and fasteners are
examined and lubricated as required. All spare parts used during these checks would come from
A thorough cleaning of the flame trap to be performed. an operational consumables kit. This kit would contain
easily replaceable items such as fuses, bulbs and filter
elements etc. These activities would normally be carried
out by suitably trained site personnel.
Components maintained
at calendar intervals are
done so on the basis of
safety, regulatory or as a
consequence of
application conditions.

Scheduled Maintenance
Scheduled maintenance is carried out based on either calendar intervals
or running hours, depending on the components under consideration.

Service exchange Gas Generators and Power Turbine Typical Maintenance Activity Work Scopes
assemblies are recommended as an alternative to the B (not exhaustive).
Type (24,000 hours) inspection on the Gas Generator, and
Maintenance activities are classed into A, B or C levels,
on C Type (48,000 hours) inspection(s) on both the Gas
depending on the scope of work required:
Generator and Power Turbine, where on-site internal
inspection of the complete gas generator and power
turbine assemblies are normally carried out, based on the A Service Inspection
expected design life of the hot path components. This is recommended annually and consists of calibration
It is therefore recommended that any resulting overhaul and system/ operational/ safety checks, filters and
(strip/rebuild) of the Gas Generator and Power Turbine consumables are changed and lubricant levels checked
sections is carried out at a Siemens SGT approved and replenished. The condition of the combustion system
workshop. This ensures that the correct processes and and first stage stators are checked by removal of the
tooling are utilized, including replacement of CT bladed combustor end covers.
discs and the subsequent balancing of the Gas Generator The workscope of a typical A service for the TB gas turbine
and Power Turbine rotor assembly is performed to the is detailed below. The estimated time to complete the
correct specification. workscope at site using two men (one Siemens personnel
and one customer assistant at a total of twenty man hours
Maintenance based on the running hours of the gas turbine may be per day) is approximately 7 days.
related to predictable events such as bearing and blade life.
Further opportunities for
maintenance are present during a
scheduled shutdown of your engine.
Gas or dual fuel burners can be
inspected for deposits and cleaned.

In addition, there is an opportunity


to perform maintenance of the Fire
and Gas & Extinguishant systems in
accordance with manufacturers
recommendations for system
installed.

(Training courses are available


through your Siemens
representative.)

Pre-shutdown checks Siemens personnel shall be given access to confirm


that all isolations have been carried out and a risk
All data from the Turbine Control Module (TCM) may
assessment will be conducted.
be recorded during the pre-shutdown checks.
The customer is responsible for the isolation of the
The compressor may be cleaned and a post clean data
turbine and driven unit and to ensure that a permit to
comparison performed.
work system is in operation.
Other checks include inlet guide vane operation,
vibration surveys, leak checks, filter checks, noise Mechanical
levels of the pumps, fans, etc, various engine A boroscope inspection may be made.
temperatures and pressures, instrument/gauge checks,
A thorough inspection and clearance check of
liquid fuel piping vibration and a test of fuel
combustion system is done, including; end plates,
changeover, if applicable.
swirlers and cones, flame tubes and extensions and
Shutdown procedure inspection of CT1 stator blades.
Mechanical or Electronic Over speed checks are made Gas and liquid burners are removed and cleaned.
and the annunciation examined. Ignitor bowls are also checked for cleanliness.
The operation of the BOVs and slam shut valves are UV sight glasses are cleaned; UV bulbs will be replaced
checked. and joints renewed where required.
The operation of the auxiliary lub oil and emergency oil The assembly of the combustion air inlet filter and
pumps are checked. ducting are examined; filters will be replaced if
required.
The pumps are also checked to ensure that they stop
at the correct set point. Operation of the pulse clean system or moving screen
filter reservoir are checked. The mechanism greased
The turbine operation is then reviewed in relation to
and checked as applicable.
the controls data and customer report information.
IGV air relay, bellofram cylinder and P2 supply pipe are
Isolation procedure removed, cleaned operation fully examined.
All components are powered-down to ensure safe P2/Stage 10 air supply pipe is checked for blockages.
working conditions. Blow off valves are removed, re-greased, diaphragms
and valve seats lapped as required.
Together, we can effectively
manage your scheduled
maintenance activities to
ensure that appropriately
skilled people and relevant
parts arrive on site at the
right time.
On auto drain valves or overhaul ball type assemblies, The demister filter should be replaced. Condensate
diaphragms are replaced and drain pipes removed and auto drain valve assembly is removed, inspected and
checked for blockages. operation checked.
External vent and drain lines are checked to ensure Fuel shut off valves are checked for stiffness and an
that they are clear with no back pressure present. inspection of the ignitor gas pipe work and non return
Water wash or solid cleaning system components are valves is undertaken.
inspected. The driven unit and starter motor hold down bolts are
Lubricators are topped up. checked for security and alignment; couplings are
regreased and rubber couplings are inspected as
Filters are checked, cleaned and replaced on both
required.
types.
Electric motor and gas starters bearings are greased.
Lub oil breather system is checked for signs of damage
or corrosion, the sand trap vessel is emptied and flame All pipe work, hoses and flexibles are checked and
trap is cleaned. replaced on condition.
The lub oil level is checked and the customer is A visual check is made of the vent dampers and their
assisted in taking oil for analysis as required. operation.
Lub oil sample is checked with the customer and both Electrical
the tank level and quantity added are recorded.
Copies of controls software are taken as required,
Fuel, oil, gas/air start systems and ignitor system filters including package or driven units.
are replaced.
Certified electrical equipment in hazardous areas is
Hale hamilton main and start gas regulator systems inspected, if applicable.
are dismantled and cleaned; throttle actuators are
Fuel actuators are calibrated.
checked for excessive backlash.
Potentiometers are replaced (DC201 star valves only). The remote monitoring system (STA-RMS*) is checked
UV flame viewing head cable insulation and its to be operational (if installed).
operation are checked. Any driven unit or other third party servicing records
T Max or T Op parameters are recorded including are recorded.
governor settings (Mk 1 Rustronic Control System). Pre-Commissioning
The operation of all package devices are calibrated and
Isolated systems are reinstated and a pre-start
operation tested, including solenoids, pressure or
integrity check of all systems is made, including static
temperature monitoring devices, blow in door micro
leak checks.
switches, vent systems, emergency stop circuit,
thermocouples, indicators, watchdog system and any Restart and Running checks
contract specific devices.
The gas generator is rotated up to spin speed.
PPM1 battery on Mk 2 systems is replaced.
The turbine is stopped using the normal stop button
Allen Bradley control system back up battery is and the rundown time is recorded.
replaced.
The fault protection start/running/functions is
TCM monitor or LCD backlight is inspected for signs of checked.
degradation and replaced if required.
The exhaust volute manual shut-off valve is checked to
Checks are made of the battery and charger condition; ensure that it operates on each start-up.
outputs; electrolyte levels and specific gravities. They
IGV operation is examined.
are topped up with distilled water if required and
boost charged when applicable. The turbine system is checked for leaks during running
checks and after four hour test run.
An inspection of the ignitor lead and plug is made,
along with insulation/resistance/function checks and is Vibration checks are carried out at maximum load.
replaced if required.
All motors and A.C. contactors are inspected.
The integrity of vibration monitoring equipment is
*STA-RMS: Siemens Turbomachinery Applications - Remote
checked, either vibraswitch or displacement types.
Monitoring System
The operation of lub oil warning and shutdown are
checked, including auxiliary pump cut out system.

Planned inspection
intervals of 8000 fired
hours, or annually, with
an intermediate
inspection every third
year or 24000 fired hours
and major inspection
every six years or 48000
fired hours, give low cost
maintenance and high
availability.
The design of the gas
turbine provides
operators with the facility
to carry out on-site blade
inspection and servicing
of the unit or, at the
operators choice, at a
Siemens approved
Service Centre.

B Service Inspection
This is recommended at 24,000 hours and is the A type Operation of the IGV blades is checked and blade
service plus a total strip of the gas generator to inspect stems and bushes are strip cleaned as required.
critical components and assess their suitability for a
The compressor turbine (CT) blading is examined for
further three year life cycle.
signs of damage/corrosion/erosion. The 1st and 2nd
The work scope of a typical B service for the TB gas stage CT stator blades undergo dye penetration crack
turbine is detailed below. The B service can be detection. Clearances and all findings are recorded on
performed at site or as a Workshop Overhaul at a Siemens build sheets.
Service Centre.
A sample of the 1st and 2nd stage CT rotor blades is
The estimated time to complete the work scope at site taken, and the blades plus the completed sample
using 2 men (one Siemens personnel and one customer sheet are returned to Siemens metallurgical laboratory
assistant at a total of 20 twenty man hours per day) is for analysis.
approximately 14 fourteen days.
The swirler cones and flame tube extensions are
All A Service activities are included, plus the following: examined for distortion/cracks/fretting. Clearances
and all findings are recorded on build sheets.
Gearbox
The Gas Generator rotor is checked to ensure that it
A visual inspection of the internals is made and
rotates freely, post rebuild.
clearances are recorded on build sheets.
Power Turbine
Package
The first stage power turbine is visually inspected prior
The gas fuel throttle is stripped down, if required.
to replacing the Gas Generator.
Core Engine - Gas Generator (GG) A dye penetration crack detection is undertaken on
Bearings and labyrinth seals are dismantled and the interduct.
inspected.
The compressor rotor and stator blading is cleaned by
hand, as required, with clearances recorded on build sheets.
The TB5000 has been designed for
ease of on-site maintenance
thereby maximizing operating
availability and minimizing
downtime.

Combustion chambers and fuel


burners are easily accessible when
servicing is required.

C Service Inspection Parts Kit


This is recommended at 48,000 hours and in addition to
Spares for these maintenance intervals consist of various
the B type service, involves a strip of the power turbine.
kits, an inspection replacement parts kit will contain
The work scope of a typical C service for the TB gas those items that are definitely to be replaced during
turbine is detailed below. The C service can be servicing, and an inspection contingency kit will
performed at site or as a Workshop Overhaul at a Siemens contain critical components that may be replaced during
Service Centre. the annual inspection depending on their condition. In
support of these it is recommended that an emergency
The estimated time to complete the work scope using 2
backup spares kit should be held on site to cover other
men (one Siemens personnel and one customer assistant
items that may be found at fault during servicing such as
at a total of twenty man hours per day) is approximately
valves, thermocouples and igniters.
twenty one days.
All A and B Service activities are included plus the following:
Package
Flow tests are carried out (certain configurations).
Power Turbine (PT)
The PT is dismantled and the blading, bearings and
labyrinth seals are inspected. All findings and
clearances are recorded on build sheets
Diffuser welds undergo dye penetration crack
detection and are repaired as required.
Siemens maintenance planning
leaves you to concentrate on your
core business.

The customer may want to consider


items such as the filtration options
available. Highly efficient (HEPA)
filtration may lead to increased
availability due to reduced
requirements for routine
maintenance (water washing) and
less degradation to core
components. This, and other
options, can be discussed in detail
prior to purchase.

Maintenance Planning
Planned maintenance reduces the cost and disruption of unscheduled outages

Maintenance planning should cover at least the following Logistics: How is equipment supplied are export
areas: licences required?
Scope of work: What is required, where it will be Site considerations: Permits to work,
carried out and how long it will take. risk assessments etc.
Spare parts: What parts are required, what is held on OEM specialists: Are specialists available
site, lead times involved. (gearbox etc).
Tools and fixtures: What specialist tooling is required Coordination: Who is coordinating all the above
and available (lifting beams etc). activities?
Inspection and assembly work: Are the correct
personnel and facilities available.
Work plan: What can be performed on site and what Maintenance Scheduling
needs specialist services.
The maintenance schedule of the equipment depends on
Capacity planning: Are the facilities, personnel and annual running hours and the component life consumed,
equipment required? assuming that the gas turbine is running 8,000 - 8,500
hours per year.

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

A A B A A C

Fig 1. A typical TB maintenance schedule, with blade sample at 24000 hours


The compressor features
variable inlet guide vanes to
modulate air flow and assure
fast, easy start-up and
maximum efficiency under
partial loads.

Note: Blade Samples - Turbine section hot path General Parts Kits
component life
Two diametrically opposed blades are removed from each Spares to replace unserviceable items may be held on site.
stage of the Compressor Turbine (CT) rotor and replaced These are generally considered to fall into two types.
with new pairs of match weighed blades. This is initially Emergency backup spares may be held on site and used
conducted at the B type inspection (24,000 hours). to replace a faulty component, thus maintaining gas
Removed blades undergo analysis in the Siemens turbine availability. This could include items such as
metallurgical laboratory. electronic modules, thermocouples and igniters. However
The examination will provide a report of blade condition it is advised that these are only replaced by suitably
and advise the residual operational life of the blades. The trained personnel.
life statement will declare that the blades are either Capital spares may be held on site and are major items or
unacceptable for further operation, or expected to be specially engineered parts such as pumps, motors and
suitable for a further 8,000, 16,000 or 24,000 hours combustion chambers. These cover items where limited
operation, with an expected operational life of 48,000 hours. stock is available or carry a long lead time for delivery;
The expected residual life is based upon the operator utilizing these are only changeable by suitably trained personnel.
the unit in the same conditions (i.e. fuel quality, engine load,
air quality etc).
The TB5000 is well suited
for cogeneration and
combined cycle power
applications.
Using exhaust gas to
generate steam for
process use or
supplementary power
generation significantly
increases the system
efficiency

Remote Diagnostic Services


Remote data access to provide information and reports, helping to effectively
manage your turbine.

STA-RMS* (suitable control systems only) Technical overview


STA-RMS consists of five components:
Siemens remote monitoring solutions are designed to
maximize your units performance and are tailored to your Data acquisition: this is automatically recorded within
specific machine type. the control system of the equipment.

TB gas turbines can be fitted with our latest remote Data transmission: information is transferred via a
monitoring system, STA-RMS*, which ensures maximum secure internet, VPN/FTP or phone line connection.
machine availability by monitoring and recording various Data storage: all reports are stored centrally within
turbine parameters such as speed, temperature, pressure the Siemens intranet for the whole lifetime of the
and vibration and communicates this information via an machine. This allows for fleet analysis and product
internet connection to Siemens dedicated servers. improvement related to the real operation conditions.
If real time connection is not available due to site location, Data evaluation: a web-based analysis tool is
then data can be stored and downloaded periodically. available to support your TB engine.
Using STA-RMS, Siemens can provide various levels of Expert diagnostic: we provide rotordynamic and
remote services, from basic reporting and support (office thermodynamic tools such as vibration analysis and
hours), to full 24 hour, 7 day service and either diagnostics. Where applicable, this includes polar
comprehensive thermodynamic and/or rotor dynamic plots, waterfall diagrams, bode diagrams, frequency
analysis of your asset. charts and performance calculation.
Whichever service level you choose, all can be tailored to
suit your specific requirements.
* Siemens Turbomachinery
Applications - Remote Monitoring
System (STA-RMS)

STA-RMS utilizes the experience that we as the OEM have Help Desk
accumulated from our operating fleet of over 330
installed RMS units, coupled with the extensive knowledge of 24/7 Hotline Support with duty CSM and technical
both our field and service engineering teams, to advise specialists.
you in all aspects of our product range, tailored to the The 24/7 Hotline Support can ensure help is there when
specific requirements of your TB gas turbine. you really need it, either by telephone or through secure
The key benefits to you are: online connection.

Fast, secure online help and advanced Our help desk is available to assist you with any kind
troubleshooting. of technical issue, as part of an LTP or Service Support
Proactive recommendations. Agreement, whether it is for performance fine tuning or
breakdown assistance.
Increased production through maximum train
performance, availability and reliability.
Outage optimization and reduction of overhaul costs,
through trending and root cause analysis.

STA-RMS is tailor made to improve the remote


functionality of all Siemens units and is the only OEM
approved system commercially available.
STA-RMS can be offered both as part of a Long Term
Programme (LTP) or as a stand alone Service Support
Agreement, which can be arranged through your Siemens
representative.
Energy Service Division
LCN 2013 - F48.1 LN
Printed on elementary chlorine-free
bleached paper.

Published by and copyright 2013: For more information, please contact All rights reserved. Trademarks
mentioned in this document are the
Siemens Plc our Customer Support Centre.
property of Siemens AG, its affiliates, or
Faraday House Phone: +49 180 524 70 00
their respective owners.
Frimley, GU16 6QD (Charges depending on provider)
Subject to change without prior notice.
United Kingdom Email: support.energy@siemens.com
The information in this document
Siemens Industrial Turbomachinery Ltd. contains general descriptions of the
Ruston House, Waterside South technical options available, which may
not apply in all cases. The required
Lincoln LN5 7FD
technical options should therefore be
United Kingdom
specified in the contract.
Siemens Energy, Inc.
4400 Alafaya Trail
Orlando, FL 32826-2399, USA

www.siemens.co.uk/energy

Você também pode gostar