Você está na página 1de 7

Excabacion

A B h V A
1.45 1.45 2.2 26 120.263 54.665
0.7 0.7 2.2 9 9.702 4.41
1 1 2.2 5 11 5
5.4 4.2 5.32 1 120.6576 22.68
2.73 2.1 6.63 1 38.00979 5.733
2 14.01 2.25 1 63.045 28.02
0.3 7.4 0.5 1 1.11 2.22
0.3 5.19 0.5 1 0.7785 1.557
0.3 4.14 0.5 1 0.621 1.242
0.3 5.5 0.5 1 0.825 1.65
366.01189 127.177

Muros de contencion
A B h t
1 5.4 4.2 5.23 0.2 24.6192 123.096
2 14.02 2 2.25 0.2 20.026 100.13
3 2.73 2 6.63 0.2 13.63596 68.1798
0.3 7.4 0.5 0.15 1.488 9.92
0.3 5.19 0.5 0.15 1.05705 7.047
0.3 4.14 0.5 0.15 0.8523 5.682
0.3 5.5 0.5 0.15 1.1175 7.45
62.79601 321.5048

Cimentaciones

A B h cantidad
1 1.45 1.45 0.7 26 38.2655
2 0.7 0.7 0.4 9 1.764
3 1 1 0.45 5 2.25
42.2795
Columnas
A B h cantidad
1 0.45 0.45 2.2 26 11.583
2 0.45 0.45 2.2 9 4.0095
3 0.45 0.45 2.2 5 2.2275
17.82

Losas
A B t
20.8 17.81 0.2 74.0896 370.448
Columna W8x24 13.074 27 35.72 12609.0886
Viga W6x9 2.6 102 17.87 4739.124
Viga W12x22 2.6 10 38.69 1005.94
Viga W8x18 2.6 68 26.79 4736.472
23090.6246

Columnas HSS75x75x3mm 13.074 7 6.6 604.0188


Vigas HSS75x75x3mm 2.6 49 6.6 840.84
Vigas HSS75x75x3mm 2.1 9 6.6 124.74
Vigas HSS50x50x2.5mm 2.1 14 3.6 105.84
Escaleras HSS150x150x3mm 5.4 10 8.96 483.84
Columnas HSS150x150x4 13.74 2 18.01 494.9148
2654.1936

Columnas HSS150x150x4 7.93 5 18.01 714.0965


Vigas W10x12 5.76 10 25.3 1457.28
C Superio HSS150x50x2.5mm 20.83 8 7.73 1288.1272
C Lateral HSS150x150x3mm 20.83 3 13.67 854.2383
4313.742

A h t
SILO 01 2.4 4.8 0.003 1317.58953
SILO 02 2.4 4.8 0.003 1317.58953
SILO 03 2.4 4.8 0.003 1317.58953
SILO 04 2.4 4.8 0.003 1317.58953
SILO 05 2.4 4.8 0.003 1317.58953
SILO 06 2.4 4.8 0.003 1317.58953
SILO 07 2.4 4.8 0.003 1317.58953
SILO 08 2.4 4.8 0.003 1317.58953
SILO 09 2.4 4.8 0.003 1317.58953
SILO 10 2.4 4.8 0.003 1317.58953
SILO 11 2.4 2.4 0.003 774.99753
SILO 12 2.4 2.4 0.003 774.99753
SILO 13 2.4 6 0.003 1588.88553
SILO 14 2.4 6 0.003 1588.88553

Plancha estriada

A B t
20.82 7.75 0.002 2533.2735
5.3 5.3 0.002 441.013
2.2 18.29 0.002 631.7366
5.3 5.3 0.002 441.013
2.2 18.29 0.002 631.7366
15.84 5.3 0.002 1318.0464
2.2 18.29 0.002 631.7366
20.82 7.75 0.002 2533.2735

9161.8292

A B t
0.32 0.32 0.022225 27 482.364288
0.25 0.25 0.012 9 52.9875
0.25 0.25 0.012 5 29.4375
0.1 0.15 0.009 204 216.189
0.133 0.207 0.009 136 264.52886
0.165 0.31 0.009 20 72.27495

1117.7821
24 16
18 12
24 16
36 24
102 68
Presupuesto
Proyecto
Sub Presupuesto
Cliente
Ubicacion Costo a : Jan-17
Item Descripcin UnidadMetrado Precio Parcial Subtotal Total

01.01 OBRAS PROVISIONALES S/. 28,250.00


01.01.01 CAMPAMENTO PROVISIONAL DE LA OBRA GLB 1.00 ### 15,000.00
01.01.02 GUARDIANIA MES 5.00 1,250.00 6,250.00
01.01.03 AGUA PARA LA CONSTRUCCION GLB 1.00 2,000.00 2,000.00
01.01.04 SERVICIOS HIGIENICOS GLB 1.00 5,000.00 5,000.00
-
01.02 TRABAJOS PRELIMINARES - S/. 3,041.50
01.02.01 TRAZO Y REPLANTEO PRELIMINAR M2 550.00 5.53 3,041.50
-
01.03 FLETE TERRESTRE - S/. 60,000.00
01.03.01 FLETE TERRESTRE ALMACEN CENTRAL A ALMACEN DE OBRA GLB 1.00 ### 40,000.00
01.03.02 MOVILIZACION Y DESMOVILIZACION DE MAQUINARIA Y EQUIPO GLB 1.00 ### 20,000.00

01.04 ESTRUCTURAS DE CONCRETO S/. 182,334.91


01.04.01 ESTRUCTURAS DE CIMENTACION 131,703.97
01.04.01.01 MOVIMIENTO DE TIERRAS 16,409.64
01.04.01.01.02 EXCAVACION PARA CIMIENTOS Y ZAPATAS M3 367.00 34.89 12,804.63
01.04.01.01.03 ACARREO INTERNO, MATERIAL PROCEDENTE DE EX M3 91.22 20.35 1,856.33
01.04.01.01.04 ELIMINACION MATERIAL EXCEDENTE C/MAQUINA M3 91.22 19.17 1,748.69
01.04.01.02 OBRAS DE CONCRETO SIMPLE 59,974.91
01.04.01.02.01 SOLADOS 2,576.64
04.01.02.01.01. SOLADO PARA ESTRUCTURAS DE CONCRETO M2 128.00 20.13 2,576.64
01.04.01.02.02 MUROS DE CONTENCION - 57,398.27
01.04.01.02.02. CONCRETO EN MURO DE CONTENCION M3 62.79 422.58 26,533.80
01.04.01.02.02. ENCOFRADO Y DESENCOFRADO PARA M2 322.00 42.36 13,639.92
04.01.02.02.01. ACERO CORRUGADO fy=4200 kg/cm2 kg 4,520.88 3.81 17,224.55
01.04.01.03 OBRAS DE CONCRETO ARMADO - 36,470.65
01.04.01.03.01 ZAPATAS - 17,621.88
01.04.01.03.01. ZAPATAS, CONCRETO F'C=175 KG/CM2 M3 42.28 280.79 11,871.80
01.04.01.03.01. ZAPATAS, ACERO fy=4200 kg/cm2 KG 1,352.96 4.25 5,750.08
01.04.01.03.02 COLUMNAS Y PLACAS - 18,848.76
01.04.01.03.02. COLUMNAS, CONCRETO 210 KG/CM2 M3 17.28 417.91 7,221.48
01.04.01.03.02. COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 72.00 57.45 4,136.40
01.04.01.03.02. COLUMNAS, ACERO fy=4200 kg/cm2 KG 1,762.56 4.25 7,490.88
01.04.02 PAVIMENTO RIGIDO - 50,630.95
01.04.02.01 MOVIMIENTO DE TIERRAS -
01.04.02.01.01 PERFILADO Y COMPACTACION DE SUB RASANTE - 1,713.10
01.04.02.01.01. PERFILADO Y COMPACTADO DE SUB-RASANTE M2 370.00 4.63 1,713.10
01.04.02.02 PAVIMENTO RIGIDO - 48,917.85
01.04.02.02.01 TIPO I - 48,917.85
01.04.02.02.01. CONCRETO F'C= 280 kg/cm2 PARA PA M3 74.08 436.58 32,341.85
01.04.02.02.01. PAVIMENTO RIGIDO: ENCOFRADO Y D M2 370.00 43.23 15,995.10
01.04.02.02.01. CURADO LOSA DE CONCRETO M2 370.00 1.57 580.90
02 ESTRUCTURAS METALICAS S/. 824,369.94
02.01 ESTRUCTURAS DE SOPORTE 436,590.00
02.01.01 ESTRUCTURAS DE PLANTA DE PRODUCCION 323,260.00
02.01.01.01 ESTRUCTURAS METALICAS KG ### 14.00 ### -
02.01.02 ESTRUCTURAS DE ESCALERAS Y PASILLOS - 32,634.00
02.01.02.01 ESTRUCTURAS METALICAS KG 2,331.00 14.00 32,634.00 -
02.01.03 ESTRUCTURAS DE TECHO DE RECEPCION - 60,396.00
02.01.03.01 ESTRUCTURAS METALICAS KG 4,314.00 14.00 60,396.00 -
02.01.03 COBERTURA DE TECHO - 12,000.00
02.01.03.01 PLANCHA DE ALUZING TR3 0.3.5mm m2 240.00 50.00 12,000.00 -
02.01.04 COBERTURA LATERAL - 8,300.00
02.01.04.01 PLANCHA DE ALUZING TR4 0.3.5mm m2 166.00 50.00 8,300.00 -
02.02 SILOS - 240,499.94
02.02.01 ESTRUCTURAS METALICAS SILO 01 KG 1,317.59 12.00 15,811.07
02.02.02 ESTRUCTURAS METALICAS SILO 02 KG 1,317.59 12.00 15,811.07
02.02.03 ESTRUCTURAS METALICAS SILO 03 KG 1,317.59 12.00 15,811.07
02.02.04 ESTRUCTURAS METALICAS SILO 04 KG 1,317.59 12.00 15,811.07
02.02.05 ESTRUCTURAS METALICAS SILO 05 KG 1,317.59 12.00 15,811.07
02.02.06 ESTRUCTURAS METALICAS SILO 06 KG 1,317.59 12.00 15,811.07
02.02.07 ESTRUCTURAS METALICAS SILO 07 KG 1,317.59 12.00 15,811.07
02.02.08 ESTRUCTURAS METALICAS SILO 08 KG 1,317.59 12.00 15,811.07
02.02.09 ESTRUCTURAS METALICAS SILO 09 KG 1,317.59 12.00 15,811.07
02.02.10 ESTRUCTURAS METALICAS SILO 10 KG 1,317.59 12.00 15,811.07
02.02.11 ESTRUCTURAS METALICAS SILO 11 KG 775.00 12.00 9,299.97
02.02.12 ESTRUCTURAS METALICAS SILO 12 KG 775.00 12.00 9,299.97
02.02.13 ESTRUCTURAS METALICAS SILO 13 KG 1,588.89 12.00 19,066.63
02.02.14 ESTRUCTURAS METALICAS SILO 14 KG 1,588.89 12.00 19,066.63
02.02.15 ESTRUCTURAS METALICAS TOLVA BASCULA KG 1,354.00 12.00 16,248.00
02.02.16 ESTRUCTURAS METALICAS TOLVA PULMON KG 784.00 12.00 9,408.00
02.03 PARRILLA DE POZA DE DECARGA 15,750.00
02.03.01 ESTRUCTURAS DE PARRILLA KG 1,125.00 14.00 15,750.00
02.04 PLANCHA ESTRIADA USADA EN PISOS 128,254.00
02.04.01 PLANCHA ESTRIADA DE PISOS e=2.5mm KG 9,161.00 14.00 ###
02.05 CARTELAS 3,276.00
02.05.01 ESTRUCTURAS DE PARRILLA KG 117.00 28.00 3,276.00
02.06 BARANDAS -
02.06.01 BARANDAS DE PLATAFORMAS KG - 28.00 -
03 INSTALACIONES ELECTRICAS S/. 46,031.25
03.01 TABLERO DE CONTROL 5,086.00
0.01.01 TABLERO DE FUERZA UNID. 5,086.00 1 5,086.00
03.02 CONDUCTORES -
03.02.01 CABLE ELECTRICO N2XOH 3-1X4MM2 m 993.00 3.87 3,842.91
03.02.02 CABLE ELECTRICO N2XOH 3-1X35MM2 m 32.00 17.07 546.24
03.02.03 CABLE ELECTRICO N2XOH 3-1X50MM2 m 32.00 20.72 663.04
03.02.04 CABLE DESNUDO Cu DE 16mm2 m 10.00 3.29 32.90
03.03 TUBERIA CONDUID - 38,145.25
03.03.01 TUBERIA CONDUID 40 mm m 1,067.00 35.75 ###
03.04 BANDEJAS -
03.04.01 BANDEJAS ELECTRICAS unid. 100.00 68.14 6,814.00
03.04.02 ACCESORIOS unid. 16.00 181.39 2,902.24
0.05 PUESTA A TIERRA - 2,800.00
03.05.01 PUESTA A TIERRA unid. 1.00 2800 2,800.00
04 EQUIPAMIENTO INDUSTRIAL - ###
04.01 MONTAGE - 170,592.03
04.01.01 MONTAJE DE EQUIPOS DE PRODUCCION GLOB 1.00 170592 ###
04.02 EQUIPOS DE PRODUCCION - ###
04.02.01 SILO DE GRANOS 500 TN+ BARREDORA UNID. 1.00 69961.3 ###
04.02.02 ELEVADOR DE CANGILONES 20m UNID. 3.00 58172.4 ###
04.02.03 TORNILLO SINFN 14m UNID. 2.00 28743 ###
04.02.04 COMPUERTA NEUMATICA UNID. 2.00 3946.8 7,893.60
04.02.05 VALVULA REBATIBLE UNID. 4.00 3946.8 ###
04.02.06 INDICADOR DE NIEVEL MOTORIZADO UNID. 12.00 1587.3 ###
04.02.07 INDICADOR DE NIVEL CAPACITIVO UNID. 14.00 1587.3 ###
04.02.08 BASCULA DOSIFICADORA 1000 L UNID. 1.00 36894 ###
04.02.09 TORNILLO SINFN 6m UNID. 10.00 12012 ###
04.02.10 ALIMENTADOR DE MOLINO DE MARTILLOS 1m3 UNID. 1.00 26598 ###
04.02.11 MOLINO DE MARTILLOS 75kW UNID. 1.00 97812 ###
04.02.12 MEZCLADOR HORIZONTAL POR BACTCHES UNID. 1.00 215015 ###
04.02.13 TOLVA DESCARGA DE MEZCLADOR UNID. 1.00 4676.1 4,676.10
04.02.14 PRENZA PELLETS 75kW + ALIMENTADOR UNID. 1.00 337194 ###
04.02.15 ENDRIADORA DE PELLETS UNID. 1.00 81081 ###
04.02.16 CLICLON UNID. 1.00 23595 ###
04.02.17 VENTILADOR CENTRIFUGO UNID. 1.00 26598 ###
04.02.18 DESMENUZADORA + ALIMENTADOR UNID. 1.00 86872.5 ###
04.02.19 TORNILLO SINFN 2m UNID. 2.00 9438 ###
04.02.20 TAMIZ VIBRATORIO UNID. 1.00 45474 ###
04.02.21 VALVULA 2 VIAS UNID. 1.00 3946.8 3,946.80
04.02.22 BALANZA ENSECADORA UNID. 2.00 53625 ###
04.02.23 CORREA DE COSTURA Y COLUMNA UNID. 2.00 39468 ###
04.02.24 MAQUINA DE COSER MOVIL UNID. 2.00 4933.5 9,867.00
04.02.25 COMPRESOR DE 10HP Q 1150L, 7.5bar + INSTALAC UNID. 1.00 18200 ###
04.02.26 CALDERA DE VAPOR 1500KG/H 8 bar UNID. 1.00 0 -
04.03 AUTOMATIZACION DE EQUIPOS - 62,140.00
04.03.01 PANEL DE CONTROL ELECTRICO UNID. 1.00 39200 ###
04.03.02 SISTEMA DE CONTRON BACHING + CABLEADO UNID. 1.00 19040 ###
04.03.03 PLC PARA ALIEMENTADOR DE MOLINO MARTILLOS UNID. 1.00 3900 3,900.00
COSTO DIRECTO ###
GASTOS GENERALES 12 % S/. 369,921.59
UTILIDAD 5% S/. 154,134.00

SUB TOTAL ###


IGV. 18 % S/. 649,212.40

PRESUPUESTO TOTAL ###

Você também pode gostar