Escolar Documentos
Profissional Documentos
Cultura Documentos
SpectralWave C-Node
STM-4/ STM-1 Compact Multiplexer
RELEASE 3.20
EQUIPMENT
DESCRIPTION/INSTALLATION
NEC Corporation
7-1, Shiba 5-chome, Minato-ku, Tokyo 108-8001, Japan TEL +81-3-3454-1111
Printed in China
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
CONTENTS
1. SUMMARY 1-1
Contents
i
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLTION
Contents
ii
E
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
1. SUMMARY
This manual provides the equipment descriptions for the system, rack layouts and
Subracks used for the C-Node, and their procedures.
Detailed descriptions on subboards and modules, and their installation procedures are
provided in the Subboard/Module Description and Installation manual.
Descriptions and procedures for cable connections are provided in the Cable
Installation manual.
Modules are mounted on the Mainboard or the subboard for additional function.
A Subrack with the Mainboard and subboards composes network element (NE).
Summary
1-1
E
This page is intentionally left blank.
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
2. EQUIPMENT DESCRIPTION
STM-1 system
STM-4 system
Mainboard
Subboard
Power
Fan
Equipment Description
2-1
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
2.2 Subrack
2.2.1 Description
C-Node subracks can be installed into the 19-inch standard type rack (2.6-meter,
2.2-meter or 2.0-meter height) accommodating up to 7 sets of C-Node subracks.
OW EXTCLK
ACO RESET IN OUT PWR
BG
TX RX TX RX
ALM OW f DATA1 DATA2 HKC HKA MON ALM F
1 2 OUT
EXTCLK
(2M Hz)
BAT IN
ON
IN OUT HKA2
DATA1 DATA2
32~25 24~17 16~9 8~1 32~25 24~17 16~9 8~1
OFF
ESD TX RX TX RX
1 2
Mainboard
FAN Board
Equipment Description
2-2
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
482.6 mm
306 mm
88 mm
443 mm
Equipment Description
2-3
E
This page is intentionally left blank.
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
Follow the safety requirements below when installing the C-Node equipment.
After using any power tools or other equipment, they must be cleaned up and put in
storage on a daily basis.
When handling conducting cables, the cable ends must be taped or insulated at all
times.
Do not wear any jewelry or any other kinds of accessories, such as ID around the
neck, while working.
3.3 Admonishment
Installers must also be familiar with and able to employ the following Safety
Requirements:
CAUTION
ESD
4.2 Reference
Procedures for the following tasks are provided in a separate manual:
5 Verify strap settings on Mainboard and Subboards Main/Sub Board Description/Installation manual.
before installing them into the Subrack.
6 Install Mainboard and Subboards into the Main/Sub Board Description/Installation manual.
Subrack.
5. INVENTORY TOOLS
Before starting the equipment installation, confirm that the following tools are
available:
1 Hammer Drill
3 Electric Drill
4 Torque Wrench
11 Jig Saw
12 Hacksaw
16 Heat Gun
17 Wire-Wrap Gun
20 Cable Cutters
22 Extension Cords
25 Chalk Line
Inventory Tools
5-1
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
Inventory Tools
5-2
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
36 Cable Scissors
39 Cable Stripper
41 Cable-Side Cutter
43 Sockets
45 Claw Hammer
47 Adjusted Wrenches
48 Pry Bar
51 Digital Mutlimeter
52 Speed Square
53 Drill iBits
54 Pliers
57 Torpedo Level
58 Center Punch
59 Sponge
60 Flashlight
61 Marking Pens
62 Measuring Tapes
Inventory Tools
5-3
E
This page is intentionally left blank.
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
6. SITE PREPARATION
Site Preparation
6-1
E
This page is intentionally left blank.
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
7. UNPACK EQUIPMENT
3. Locate markings on the box, and position the box with the correct side up according
to the markings.
5. Remove the contents from the carton, and place them on a flat patch.
7. Check the contents (Subracks, modules, cables, etc.) for visible damages.
Unpack Equipment
7-1
E
This page is intentionally left blank.
F2880_F06
EQUIPMENT DESCRIPTION/INSTALLATION
This section describes the mounting method of the C-Node subrack for 19 inch
standard rack.
Since the Subrack is heavy in weight, two or more personnel are required for the
installation.
Since the Subrack is heavy in weight, two or more personnel are required for the
installation.
Subrack mounting kit is necessary to mount the C-Node subrack in the NEC ETS
V-Rack. Before starting the installation work, check supplied components of the
subrack mounting kit shown in Table 8-1 and Figure 8-2.
The following flowchart shows a series of procedures necessary for installing the
subrack. The subrack should be mounted according to these procedures.
START
DONE
Figure 8-3 shows the standard mounting positions for the C-Node subrack. The 1st
subrack requires 300mm space, and after the 2nd , it requires 200mm space.
(2) Attach the angles that are the component of the subrack mounting kit to the
subrack.
Attach the RAC nuts at both sides to the mounting positions shown in Figure 8-6.
(1)Insert the subracksupports into the square holes on the V-Rack rear panel.
(1) Insert the cablesupports into the square holes on the V-Rack rear panel.
8.3 To Wall
This section describes the mounting method of the C-Node subrack for Wall. Since
the Subrack is heavy in weight, two or more personnel are required for the
installation.
Before starting the installation work, check supplied components of the subrack
mounting kit shown in Table 8-3.