Prequalification Test of a 245 kV Cable System with

Reduced Insulation Wall Thickness

Pierre Argaut

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Spring ICC 2008, TNL St Pete Beach, March 11th , 2008
Background
Silec Cable entered General Cable Group in
Dec 2005,22nd
Immediately after acquisition, decision was
made to carry out Prequalification Test as per
IEC 62067 in KEMA Laboratories on a 245 kV
cable sytem comprising General Cable Iberia
cable and Silec Cable Accessories
Installation started January 2006
PQ Test was successfully completed in 2007

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Equipment under test
2000mm Aluminum 245 kV cable with 17mm
insulation wall thickness
One porcelain outdoor termination
One composite outdoor termination
Two GIS terminations according to IEC 60859
Two one piece premolded joints directly
buried
Two one piece premolded joints installed in
tunnel/manhole configuration

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Cable System Layout

2 Joints
Porcelain T

Composite T

2 Joints 2 GIS

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Cable Construction
1 Conductor
Cross-section : 2000 mm
Material : Aluminum
Nominal diameter :56.5 mm
2 - Inner semi-conductive layer
Nominal thickness : 2 mm
3 - XLPE Insulation
Nominal average thickness : 17 mm
4 - Smooth outer semi-conductive layer
Nominal thickness : 2.0 mm
5 Screen Wires
60 copper wires totalling 150 mm
5 Water Barrier
Aluminum Foil:0.25 mm
Indicative external diameter : 110.8 mm 6 - Smooth HDPE outer sheath with graphite
Indicative weight : 14.43 kg/m Minimum average thickness : 4 mm *
Electrical Stress:
On the conductor: 9.36 kV/mm
Over insulation: 6.00 kV/mm

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Open Air
InstallationInstallation
in open air:

Two One
Installation in open air
piece
premolded
joints

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Heat cycling
HEATING CYCLE CHECK
May 31 - June 1, 2006

100 2500

90 2250

80 2000

Current [A] / Voltage [kV]


70 1750
temperature [C]

60 Stars fans on transformers


1500

50 1250

40 1000

30 750

20 500

10 250

0 0
08h00 12h00 16h00 20h00 00h00 04h00 08h00

time

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Outdoor and GIS Terminations

Composite outdoor
Porcelain outdoor termination
termination
Spring ICC 2008, TNL St Pete Beach, March 11th , 2008
Dismantling after Long Term Test

GIS Joint

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Dismantling after Long Term Test

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Conclusion after Long Term Test
All accessories and cable are in perfect
shape after Long Term Test
Full compatibility of Silec Cable
accessories and General Cable Iberia
insulated cable is demonstrated
Cable System with reduced wall thickness
can be offered:
Increased shipping lengths
Optimized cost for cable system

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008


Thank you for your attention!

Questions?

Spring ICC 2008, TNL St Pete Beach, March 11th , 2008