EPC OF WELL PAD D FOR SORIK MARAPI GEOTHERMAL PROJECT RE - Baseline

ID Task Name Duration Start Finish Baseline1 Start Baseline1 Finish Predecessors May 21, '17 May 28, '17 Jun 4, '17 Jun 11, '17 Jun 18, '17 Jun 25, '17 Jul 2, '17 Jul 9, '17 Jul 16, '17 Jul 23, '17 Jul 30, '17 Aug 6, '17 Aug 13, '17 Aug 20, '17
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
1 EPC OF WELL PAD D FOR SORIK MARAPI 162 days Mon Mon Mon 3/13/17 Mon 8/21/17 0%
GEOTHERMAL PROJECT 3/13/17 8/21/17

2 Kick of Meeting 0 days Mon 3/13/17Mon 3/13/17Mon 3/13/17 Mon 3/13/17


3 SM-D Well Pad Completion 0 days Mon 8/14/17Mon 8/14/17Mon 8/14/17 Mon 8/14/17 32 8/14

4 Access Road to SM-D Completion 0 days Fri 7/7/17 Fri 7/7/17 Fri 7/7/17 Fri 7/7/17 7 7/7

5 Completion of Water Drilling system 0 days Wed 6/21/17Wed 6/21/17Wed 6/21/17 Wed 6/21/17 61 6/21

6 Estimated Slope Protection Finish 0 days Mon 7/17/17Mon 7/17/17Mon 7/17/17 Mon 7/17/17 59,60 7/17

7 ACCESS ROAD (from Public Road to SM-D Well 49 days Sat 5/20/17 Fri 7/7/17 Sat 5/20/17 Fri 7/7/17 0%
Pad)

8 Earthworks and subgrade preparation 11 days Sat 5/20/17 Tue 5/30/17 Sat 5/20/17 Tue 5/30/17 0%

9 Hauling Mud 5 days Sat 5/20/17 Wed 5/24/17Sat 5/20/17 Wed 5/24/17 0%

10 Cutting Soil of Access Road 7 days Wed 5/24/17Tue 5/30/17 Wed 5/24/17 Tue 5/30/17 9FS-1 day 0%

11 Surfacing: geotex, subbase and base course 21 days Tue 5/30/17 Mon 6/19/17Tue 5/30/17 Mon 6/19/17 0%

12 Fabricate & Installation Geotextile 12 days Tue 5/30/17 Sat 6/10/17 Tue 5/30/17 Sat 6/10/17 10FS-1 day 0%

13 Install & Compaction Base Course A 12 days Thu 6/1/17 Mon 6/12/17Thu 6/1/17 Mon 6/12/17 12SS+2 days 0%

14 Install & Compaction Agregate A 7 days Tue 6/13/17 Mon 6/19/17Tue 6/13/17 Mon 6/19/17 13 0%

15 Drainage Works, Lined channel 23 days Sun 6/11/17 Mon 7/3/17 Sun 6/11/17 Mon 7/3/17 0%

16 General Excavation 10 days Sun 6/11/17 Tue 6/20/17 Sun 6/11/17 Tue 6/20/17 12 0%

17 Material Arrival 3 days Sun 6/11/17 Tue 6/13/17 Sun 6/11/17 Tue 6/13/17 12 0%

18 Instalation 20 days Wed 6/14/17Mon 7/3/17 Wed 6/14/17 Mon 7/3/17 17 0%

19 Concrete box/Manhole 37 days Fri 5/26/17 Sat 7/1/17 Fri 5/26/17 Sat 7/1/17 0%

20 Fabricate Formwork 3 days Fri 5/26/17 Sun 5/28/17 Fri 5/26/17 Sun 5/28/17 0%

21 Fabricate Reinforcement Steel Bar (Tulangan) 7 days Mon 5/29/17Sun 6/4/17 Mon 5/29/17 Sun 6/4/17 20 0%

22 Fabricate Box Culvert 16 days Mon 6/5/17 Tue 6/20/17 Mon 6/5/17 Tue 6/20/17 21 0%

23 Curing 3 days Wed 6/21/17Fri 6/23/17 Wed 6/21/17 Fri 6/23/17 22 0%

24 Moving & Laydown Culvert 3 days Sat 6/24/17 Mon 6/26/17Sat 6/24/17 Mon 6/26/17 23 0%

25 Installation 3 days Tue 6/27/17 Thu 6/29/17 Tue 6/27/17 Thu 6/29/17 24 0%

26 Structural Backfilling Compacted 1 day Fri 6/30/17 Fri 6/30/17 Fri 6/30/17 Fri 6/30/17 25 0%

27 Place Base Course 1 day Sat 7/1/17 Sat 7/1/17 Sat 7/1/17 Sat 7/1/17 26 0%

28 Installed retaining wall at access road, stone 27 days Sun 6/11/17 Fri 7/7/17 Sun 6/11/17 Fri 7/7/17 0%
masonry

29 General Excavation 5 days Sun 6/11/17 Thu 6/15/17 Sun 6/11/17 Thu 6/15/17 12 0%

30 Fabricate basket for gabion 7 days Fri 6/16/17 Thu 6/22/17 Fri 6/16/17 Thu 6/22/17 29 0%

31 Installation Gabion Wall 15 days Fri 6/23/17 Fri 7/7/17 Fri 6/23/17 Fri 7/7/17 30 0%

32 SM-D WELL PAD WORKS 86 days Sun 5/21/17 Mon 8/14/17Sun 5/21/17 Mon 8/14/17 0%

33 Earthworks 68 days Sun 5/21/17 Thu 7/27/17 Sun 5/21/17 Thu 7/27/17 0%

34 Excavation, Backfilling and Disposing (50.500 33 days Sun 5/21/17 Thu 6/22/17 Sun 5/21/17 Thu 6/22/17 0%
m3 remaining)

35 Pad Surfacing to include sub-base and base 14 days Tue 7/4/17 Mon Tue 7/4/17 Mon 7/17/17 34FS-4 days,11,15,19 0%
course 7/17/17

36 Geotextile fabric (50.000 m2 remaining) 33 days Sun 5/21/17 Thu 6/22/17 Sun 5/21/17 Thu 6/22/17 34FF 0%

37 Rig Foot print foundation, 15 meters x 38 10 days Tue 7/18/17 Thu 7/27/17 Tue 7/18/17 Thu 7/27/17 35,36 0%
meters, consist of geotextile, sub-base, base
course, gravel bed

38 Drainage Works 21 days Tue 7/18/17 Mon 8/7/17 Tue 7/18/17 Mon 8/7/17 0%

39 Sub surface perforated pipe drain works 15 days Tue 7/18/17 Tue 8/1/17 Tue 7/18/17 Tue 8/1/17 35 0%

40 Open canal lined with stone masonry 15 days Tue 7/18/17 Tue 8/1/17 Tue 7/18/17 Tue 8/1/17 39SS 0%

41 Open canal lined with reinforced concrete 15 days Tue 7/18/17 Tue 8/1/17 Tue 7/18/17 Tue 8/1/17 40SS 0%

42 Pipe culverts along potentail slope failure 21 days Tue 7/18/17 Mon 8/7/17 Tue 7/18/17 Mon 8/7/17 41SS 0%

43 Concrete collection/manhole box 14 days Tue 7/18/17 Mon 7/31/17Tue 7/18/17 Mon 7/31/17 42SS 0%

44 Open canal cascading lined with stone 14 days Tue 7/18/17 Mon Tue 7/18/17 Mon 7/31/17 43SS 0%
masonry used for slope steeper than 6H:1V 7/31/17

45 Pond Construction 21 days Fri 6/23/17 Thu 7/13/17 Fri 6/23/17 Thu 7/13/17 0%

46 Capacity= 2,000m3 Drawing No. 21 days Fri 6/23/17 Thu 7/13/17 Fri 6/23/17 Thu 7/13/17 34 0%

47 Capacity= 3,000m3 Drawing No. 21 days Fri 6/23/17 Thu 7/13/17 Fri 6/23/17 Thu 7/13/17 46SS 0%

48 Concrete Works 14 days Wed 7/5/17 Tue 7/18/17 Wed 7/5/17 Tue 7/18/17 0%

49 Well Cellar (3.4mx3.4mx1.2m), 4 cellars @ 7.0 14 days Wed 7/5/17 Tue 7/18/17 Wed 7/5/17 Tue 7/18/17 47FS-9 days,46FS-9 days 0%
meters distance O.C. Drawing No.

50 Cutting Storage (10mx10mx1.2), Drawing No. 14 days Wed 7/5/17 Tue 7/18/17 Wed 7/5/17 Tue 7/18/17 49SS 0%

51 Concrete Pad for cementing area. Drawing No. 14 days Wed 7/5/17 Tue 7/18/17 Wed 7/5/17 Tue 7/18/17 50SS 0%

52 Septic Tank: 2 meters x 6 meters x 1.8 depth 14 days Wed 7/5/17 Tue 7/18/17 Wed 7/5/17 Tue 7/18/17 51SS 0%
and leach field with volume of 30m3

53 Driller Mini-Camp Area 7 days Tue 8/8/17 Mon 8/14/17Tue 8/8/17 Mon 8/14/17 0%

54 Concrete block for containers' base: 250mmx 7 days Tue 8/8/17 Mon Tue 8/8/17 Mon 8/14/17 52FF,39,40,41,42,43,44 0%
300mm x 300mm 8/14/17

55 Concrete walkway, 50mm x 900mm width 7 days Tue 8/8/17 Mon Tue 8/8/17 Mon 8/14/17 54SS 0%
resting on gravel bed 8/14/17

56 SLOPE PROTECTION WORKS 58 days Sun 5/21/17 Mon 7/17/17Sun 5/21/17 Mon 7/17/17 0%

57 Approval design Slope Protection 10 days Sun 5/21/17 Tue 5/30/17 Sun 5/21/17 Tue 5/30/17 0%

58 Geotextile fabric for slope protection 33 days Sun 5/21/17 Thu 6/22/17 Sun 5/21/17 Thu 6/22/17 36SS 0%

59 Gabion walls for slop protection 30 days Thu 6/8/17 Fri 7/7/17 Thu 6/8/17 Fri 7/7/17 58FS-15 days 0%

60 Shotcrete for slope protection (area Cut) 10 days Sat 7/8/17 Mon 7/17/17Sat 7/8/17 Mon 7/17/17 59 0%

61 WATER DRILLING SYSTEM FOR PAD SM-D(WDS-D) 28 days Thu 5/25/17 Wed Thu 5/25/17 Wed 6/21/17 0%
6/21/17

62 Provision for Victaulic Pipe Laying for WDS 28 days Thu 5/25/17 Wed Thu 5/25/17 Wed 6/21/17 0%
including support every 6 meters 6/21/17

63 Pipeline tapping, pressure test and 28 days Thu 5/25/17 Wed Thu 5/25/17 Wed 6/21/17 62SS 0%
commissioning 6/21/17

64 Cleaning Area, Demobilization and As Built 7 days Tue 8/15/17 Mon Tue 8/15/17 Mon 8/21/17 55,51,50,49 0%
Drawing 8/21/17

65 HANDOVER 0 days Mon 8/21/17Mon 8/21/17Mon 8/21/17 Mon 8/21/17 64,62,63,37,28,60,14 8/21

Critical Critical Progress Split Manual Task Finish-only Baseline Baseline Milestone Summary Progress Manual Summary External Tasks Inactive Task Inactive Summary Baseline Summary

Critical Split Task Task Progress Start-only Duration-only Baseline Split Milestone Summary Project Summary External Milestone Inactive Milestone Deadline