Você está na página 1de 12

Table Of Contents

1995/1997/2000 CON/SPAN Bridge Systems, Inc. The contents of this handbook should be
reviewed by the contractor prior to construction of a CON/SPAN structure. Compliance with the
guidelines in this handbook does not relieve the contractor of the responsibility to adhere to the
projects plans, specifications and contract documents, or for complying with all safety stan-
dards and procedures at the project site. Reproduction of this handbook, in whole or part, with-
out the written consent of CON/SPAN Bridge Systems, Inc. is expressly prohibited.
Clean (sweep) footing, and confirm its When setting the unit have one person
length and layout. When checking the with a heavy spud bar at each side to
length of footing, allow for 1/2'' joint creep position the unit as the crane is lower-
for each joint between units. For exam- ing it. Spud the unit up against the 2x4
ple, if you have six units eight ft. wide, blocks and check it for alignment with
allow for five joints at 1/2 inch for a total the chalked reference line. Check the
length of 48'-2 1/2''. Once you have laid vertical front face of the unit with a level
out the total length on one footing, start- for vertical alignment. If necessary adjust
ing at one end turn a 90 deg. angle to the the shims accordingly to achieve the
opposite footing and lay out the starting required alignment of the front face.
point on the footing (see diagram back Do not use your hands directly
page). Follow the same procedure at under a unit to adjust shims. Use
opposite ends of the footings and chalk a stick or a tool to reach under
a reference line (to the outside of the unit.
the units) for alignment purposes.
When setting successive
Shims are to be set one ft. in units, it is often best to match
from the corner of each unit. a rough face with a smooth
Check the footing for any high face. The joint between units
spots and use the high spot as the should be 1/8 inch minimum
control elevation. Add 1 inch to this and 3/4 inch maximum. A shim can be
high elevation and set all shim pads to placed in the tightest area of the joint to
this elevation. maintain this minimum opening.

When installing units on a sloping grade, When setting successive units you will
shoot elevation control points at approxi- achieve better joints and save time if
mately 50 ft. increments and run a string the unit to be set is hanging such that
line between these elevations to set other the top of the unit is leaning away from
shims. Another method is to use a 6 ft. the previously set unit. Adjust the
level with a spacer taped to one end of length of the lifting cables so that the
the level to match the required cables on the side of the unit away from
vertical elevation change across the previously set unit are slightly longer
a 6 ft. distance. Use this level than the near side cables. This can be
then to set shim pads achieved in two different ways.
from one pad to another. The first is to add a shackle to
the far-side cables to effectively
Select a crew of at least four, lengthen the cables. The second
and assign one as the leader method is to place a large
(decision maker) to provide the signals diameter rod between the shackle and the
to the crane operator. A short safety end of the cable to effectively shorten the
meeting before setting the units is advisable. length of the near-side cable.
Pinched fingers, toes, etc. are avoidable.
Units with spans exceeding 24 ft. will be
You will normally start with setting an end shipped and installed with a horizontal
unit with or without an attached headwall. cable tie between the legs of the units
The alignment of this first unit is critical located normally 2'-0'' above the bottom
to the alignment of the rest of the units. of the leg. It shall be left in place until the
Secure a 2x4 to the top of the footing at the units have been grouted in the foundation
starting line for the units on each footing. keyway, and the grout has set. The foun-
This will act as a stop when setting the units dation elevation relative to the streambed
and will assist in the alignment of the unit. elevation should be reviewed for any
Stay out from underneath the unit until potential conflicts with this cable location.
the unit is set on the footing.
tion when you start to fasten the plates.
To prevent spalling near the connection
plates from localized stresses, a thin
neoprene pad should be inserted between
the wingwall and the end bridge unit. Once
the wall is moved snug against the plates
and all holes are in line, a shorter bolt may
be utilized.

The wingwalls will nor-


mally be leaning for-
ward when hanging by
the top two inserts.
Loosely fasten the
connection plates to
the end bridge unit
before setting the wing-
wall. After setting the
wall down on the footing, the wall will
have to be pushed back to rest against
the bolted plates. Often times it will take
a considerable effort to get the bolts to
line up with the holes in the plates. The
large or slotted holes on the plate
should be placed on the wingwall side. Proper alignment of the wingwall is
indicated by the uniformity of the joint
To help pull the wall back and align the between the wingwall and the end bridge
holes a long bolt or threaded stud can be unit from front to back. Before back-
used. By starting the bolting of the plates filling the wingwalls, install the drainage
with the long bolt, the wall can still be pipe as shown on the plans.
several inches away from its final posi-

Setting Detached
Precast Headwalls
bolts to thread the bolts into
the inserts as far as possible.
Before backfilling, remove the
nuts and grout the sleeve sur-
rounding the bolts (See the
Grouting section). Replace the
nuts and waterproof as outlined
in the Sealing Joints section.

Mound the grout on one side


of the leg and vibrate the
grout until it passes through
to the other side of the leg.
After completing this process on
one side you may find that you
have to repeat this process in
places on the opposite side.

The lift holes in the units shall


be grouted or plugged and then
sealed with mastic and/or a
piece of the joint wrap material.
The backfill of a CON/SPAN structure is base of the unit to two feet above the crown.
an important element of the overall If the final fill height is less than two feet,
structure. Not only is it important to the finished grade shall be the boundary
provide the necessary support for the of the CBZ. For spans less than 24 ft., with
structure, it is also important for the fill heights less than 12 ft., backfill material
roadway approach support. Do not take meeting AASHTO classification A1, A2, A3,
this element lightly. Backfilling shall be or A4 shall be used. For fill heights greater
performed in accordance with the than 12 ft., or for spans greater than 24 ft.,
CON/SPAN SPECIFICATIONS or the with any amount of fill, only material meet-
project specifications, whichever is ing the A1 or A3 classification shall be used.
more severe. For heights of fill over Maximum dry density shall be determined
12 feet, no backfilling may begin until a by AASHTO T-99 or other approved methods.
backfill compaction testing plan has Backfill shall be placed and compacted in
been coordinated with, and approved by layers until the density is not less than
CON/SPAN through the licensee.
95% of the maximum dry density. All
material outside the Critical Backfill Zone
shall be good quality, well compacted
embankment or in situ soil.

No backfill shall be placed against any


structural elements until they have been
approved by the engineer. Do not backfill
behind the wingwalls unless the drainage
pipe has been installed.

A Critical Backfill Zone (CBZ) around Backfill against a waterproofed surface shall
the structure shall be defined as follows. be placed in such a way as to avoid damage
The CBZ extends a minimum of 4 ft. on to the waterproofing material.
either side of the structure, and from the
3100 Research Blvd., P.O. Box 20266
Dayton, Ohio 45420-0266
(937) 254-2233 (800) 526-3999
Fax (937) 254-8365
http://www.con-span.com

Você também pode gostar