Você está na página 1de 2

Target Price Request (TPR)

Electrical Installation, Testing and Commissioning Contract

Cost Centre/Cost Code No (Essential) Contract Title TPR No


D.50011598.874 / D.50011793.874 Electrical Installation
Site Location Site Contact
Castleton Primary T12 transformer Name: George Andreakos Tel: 7825453675

Ashwood Dale T11 transformer Date Target Price to be Returned ASAP


Site Visit Date & Time
Overall Project Start Date 6/8/2017
Substation Number Electrical Installation Start Date
Project In Use Date
Major or Minor Project Practical Completion Date
Minor Notional Outage Dates

Description of Work Instruction


Scope of Works: Site Constraints:
As previously discussed,
No. of Documents groundworks to be undertaken at
Attached No. of Documents Attached
each site before the 26/04/2017 to provide:
o 230V power, 6A protection
o Cable trays installed (as necessary) from the installation
location to the tap changer, transformer and control kiosk

CDM Issues: Associated Drawings:


No. of Documents Attached No. of Documents Attached

Direct Supplies/Subcontractors: As Built Information Requried:


No. of Documents Attached No. of Documents Attached

All work to be completed in accordance with the Conditions of Contract. This Work Instruction does not guarantee
payment for the works. Payment will be in accordance with the Terms and Conditions of Contract.
Name/Signature Date issued
Cc: to Mike Richardson
Chartered Quantity Surveyors
Doc 1000-01a EITC Contract

Você também pode gostar