zaki mossallam-lallocation Classic Schedule Layout 23-May-17 14:05

Oct 22 Oct 29 Nov 05 Nov 12 Nov 19 Nov 26 Dec 03 Dec 10 Dec 17 Dec 24 Dec 31 Jan 07 Jan 14 Jan 21 Jan 28 Feb 04 Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25 Apr 01 Apr 08 Apr 15 Apr 22 Apr 29 May 06
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW

30-Oct-17, z-3.1000 START


start, 30-Oct-17
09-Nov-17, z-3.100 Preparation
site cleaning
levelling
survey works

20-Dec-17, z-3.200.001 soil works


excavation
backfilling

formwork for pc footing


casting pc footing
formwork removal pc footing
formwork rc footing
steel fixing rc footing
casting rc footing
formwork removal rc footing

formwork rc columns
steel fixing rc columns
casting rc columns
formwork removal rc columns

formwork rc slabs
steel fixing rc slabs
casting rc slabs
formwork removal rc slabs

formwork rc columns
steel fixing rc columns
casting rc columns
formwork removal rc columns

formwork rc slabs
steel fixing rc slabs
casting rc slabs
formwork removal rc slabs

brickwork
primary electrical work
primary sanitary work
primary carpentry work
plastering
flooring
painting

brickwork
primary electrical work
primary sanitary work
primary carpentry work
plastering
flooring
painting

10 1500

8 1200

6 900

4 600

2 300

M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M TW
Oct 22 Oct 29 Nov 05 Nov 12 Nov 19 Nov 26 Dec 03 Dec 10 Dec 17 Dec 24 Dec 31 Jan 07 Jan 14 Jan 21 Jan 28 Feb 04 Feb 11 Feb 18 Feb 25 Mar 04 Mar 11 Mar 18 Mar 25 Apr 01 Apr 08 Apr 15 Apr 22 Apr 29 May 06

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remaining Work summary Resource Profile Filter:All Resources