NEPAL ELECTRICITY AUTHORITY

Medium Generation, Operation & Maintenance Department


Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
Civil works
1 Site Preparation of Surface dressing
works.
1 14.37 14.37 206.50
Total: 206.50 Sqm.
2
Excavation for foundation, drain, pipeline
etc. in boulder mixed soils, disposal ( up
to 10m lead and 1.5m lift).
Isolated foundation
Footing (F1) 3 1.50 1.50 1.75 11.81
Footing (F2) 3 1.75 1.75 1.75 16.08
Footing (F3) 3 2.00 2.00 1.75 21.00
Below tie beam(Grid wise)
1&3 4 2.13 0.50 1.13 4.78
Grid 2-2. 2 2.13 0.45 0.50 0.96
2'-2' 1 3.55 0.45 0.50 0.80
A&C 4 2.38 0.50 1.13 5.34

B 2 2.38 0.45 1.13 2.40


A1 1 3.55 0.45 1.13 1.80
Appron Long 2 9.58 0.64 0.20 2.45
Appron Long 2 9.58 0.64 0.20 2.45
Total: 69.87 Cum.

3 Back filling of footing


Trench Footing (F1) 3 1.50 1.50 1.12 7.56
Footing (F2) 3 1.80 1.80 1.12 10.89
Footing (F3) 3 2.00 2.00 1.12 13.44
For Room 4 3.77 3.77 0.32 18.19
Total: 50.08 Cum.

4 Stone soling works in the foundation and


flooring and levelling including haulage
distance up to 30 m.
Below isolated footing
Footing (F1) 3 1.30 1.30 0.25 1.27
Footing (F2) 3 1.60 1.60 0.25 1.92
Footing (F3) 3 1.80 1.80 0.25 2.43
Flooring
2 3.55 3.55 0.25 6.30
2 3.15 3.15 0.25 4.96
Total: 16.88 Cum.
5 Sand filling work below stone soling in
rooms floor
4 3.77 3.77 0.10 5.69
Total: 5.69 Cum.
6 Cement Concrete (P.C.C.) works of
Foundation in (1:4:8 ratio ) of Concrete
including supply of material and haulage
distance up to 30 m.
PCC works below footing
Footing (F1) 3 1.30 1.30 0.10 0.51
Footing (F2) 3 1.60 1.60 0.10 0.77
Footing (F3) 3 1.80 1.80 0.10 0.97
PCC works for Flooring 2 3.55 3.55 0.10 2.52

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
2 3.15 3.15 0.10 1.98
Total: 6.75 Cum.
7 Rubble masonry works including supply
of hard stone blocks, preparing cement
mortar and const. of wall upto 5 m. high
( haulage distance up to 30 m. ) in 1:4
ratio.
Below tie beam
Four wall 8 7.70 0.50 1.10 33.88
Internal wall 4 3.70 0.35 0.50 2.56
3 3.77 0.35 0.50 1.96
1 1.60 0.35 0.50 0.28
Four wall 8 7.70 0.50 0.50 15.40
Internal wall 4 3.70 0.35 0.50 2.56
3 3.77 0.35 0.50 1.96
1 1.60 0.35 0.50 0.28
Appron Long 2 8.94 0.64 0.40 4.58
Appron Short 2 8.30 0.64 0.40 4.25
Steps 1 1.00 0.64 0.18 0.12
1 1.00 0.34 0.18 0.06

Total: 67.89 Cum.


8 Cement Concrete works of super
structures, deck, slab, beams in (1:1.5:3
ratio M20 ) of Concrete including supply
of material and haulage distance up to
30 m.
Isolated footings
Footing (F1) 3 1.30 1.30 0.25 1.27
Footing (F2) 3 1.60 1.60 0.30 2.30
Footing (F3) 3 1.80 1.80 0.33 3.16
Column foundation 9 0.30 0.30 1.85 1.49
Tie beam 12 3.65 0.40 0.30 5.26
2 3.20 0.40 0.30 0.77

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
Ground Floor
Column 9 0.30 0.30 2.48 2.01
For sill beam 8 3.77 0.23 0.075 0.52
Lintels for windows
W2 6 1.96 0.23 0.15 0.41
W3 3 1.26 0.23 0.15 0.13
D1 1 1.46 0.23 0.15 0.05
D2 2 1.36 0.23 0.15 0.09
D3 1 1.26 0.23 0.15 0.04
Beams- Grid- A to C 6 3.65 0.23 0.28 1.39
Beams- Gred- 1,2 & 3 6 3.65 0.23 0.28 1.41
Beams- Gred- A' & 2' 2 3.55 0.23 0.28 0.46
Slab 1 8.30 8.30 0.125 8.61
Slab Projection 2 1.21 5.48 0.125 1.66
Stair 1 4.51 1.00 0.10 0.45
Stair steps 16 1.00 0.225 0.18 0.65

1st. Floor
Column 9 0.30 0.30 2.48 2.01
For sill beam 8 3.77 0.23 0.075 0.52
Lintels for windows
W2 6 1.96 0.23 0.15 0.41
W3 3 1.26 0.23 0.15 0.13
D2 3 1.36 0.23 0.15 0.14
D3 2 1.26 0.23 0.15 0.09
Beams- Grid- A to C 6 3.65 0.23 0.28 1.39
Beams- Grid- 1,2 & 3 6 3.65 0.23 0.28 1.41
Beams- Grid- A' & 2' 2 3.55 0.23 0.28 0.46

Slab 1 8.80 8.6 0.125 9.46


Stair 2 4.51 1.00 0.125 1.13
Stair steps 16 1.00 0.25 0.18 0.72
Parapet Column
Column 8 0.30 0.30 1.00 0.72
Kitchen slab 1 2.29 0.60 0.10 0.14
R.C.C. Band 10 4.02 0.125 0.10 0.50
4 3.35 0.125 0.10 0.17
4 3.25 0.125 0.10 0.16
4 2.06 0.125 0.10 0.10
4 1.92 0.125 0.10 0.10
Stair area -4 3.55 2.75 0.13 -4.88
Grand Total: 47.01 Cum.

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
9 Cutting, binding, placing in position as
shown in the drawings and binding wire
of reinforcement steel bars for R.C.C.
works including haulage distance of
30m. 10228.65 Kg.
10 Making wooden forms including
selection of material,
measuring,cutting,fixing,nailing as per
specified drawings and hauling upto
30m. and placing & removal with all
complete works.
Footing
Footing (F1) 12 1.30 0.10 1.56
Footing (F2) 12 1.60 0.10 1.92
Footing (F3) 12 1.80 0.10 2.16
Footing (F1) 12 1.30 0.30 4.68
Footing (F2) 12 1.60 0.30 5.76
Footing (F3) 12 1.80 0.35 7.56

Column below tie beam to uoto Footing


9 1.40 1.62 20.41

Tie beam
12 3.70 0.30 13.32
2 3.70 0.30 2.22

Ground Floor
Column 9 1.20 2.88 31.10
Lintels for windows
For sill beam 16 3.77 0.075 4.52
Lintels for windows
W2 12 1.96 0.15 3.53
6 1.50 0.23 2.07
W3 6 1.26 0.15 1.13
3 0.80 0.23 0.55
D2 6 1.36 0.15 1.22
3 0.90 0.23 0.62
D3 4 1.26 0.15 0.76
2 0.80 0.23 0.37

Beams 24 3.65 0.40 35.04


12 3.65 0.23 10.07

Slab
Internal slabs 4 3.77 3.77 56.85
Slab Projection 1 5.48 1.215 6.66
1 4.265 1.215 5.18
Stair 2 2.305 1.00 4.61
1 2.250 1.405 3.16

Stair steps 16 0.18 2.88

1st. Floor
Column 9 1.40 2.88 36.29
Lintels for windows
For sill beam 16 3.77 0.075 4.52

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
Lintels for windows
W2 12 1.96 0.15 3.53
6 1.50 0.23 2.07
W3 6 1.26 0.15 1.13
3 0.80 0.23 0.55
D2 6 1.36 0.15 1.22
3 0.90 0.23 0.62
D3 4 1.26 0.15 0.76
2 0.80 0.23 0.37

Beams 24 3.65 0.40 35.04


12 3.65 0.23 10.07
Slab
Internal slabs 4 3.77 3.77 56.85
Slab Projectctions 2 9.30 0.50 9.30
2 8.30 0.50 8.30
Stair 2 4.02 1.25 10.05
1 2.250 1.405 3.16
Stair steps 16 0.18 2.88

Kitchen slab 1 3.09 0.60 1.85


Total: 418.47 Sqm.

11 Brick ( Chimny Bhatta) masonry works


including supply of Bricks, preparing
cement mortar and const. of wall upto 5
m. high ( haulage distance up to 30 m. )
in 1:4 ratio.
Ground floor
Four wall 11 3.70 0.23 2.48 23.22
Internal wall 1 2.38 0.23 2.48 1.36
1 1.83 0.23 2.48 1.04

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
1st. floor
Four wall 10 3.70 0.23 2.48 21.10
Internal wall 2 2.38 0.23 2.48 2.72
1 3.70 0.115 2.78 1.18
1 3.70 0.115 2.78 1.18
staircase 4 4.30 0.115 1.50 2.97
parapet wall 4 0.23 0.230 1.00 0.21
2 5.48 0.115 1.00 1.26
2 1.22 0.115 1.00 0.28
railing wall 3 8.00 0.115 0.90 2.48
1 3.86 0.115 0.90 0.40

Kitchen slab wall 2 0.600 0.23 0.75 0.21


Sub-Total: 59.61
Deduction Door & window Openings
D1 1 1.00 0.23 2.175 0.50
D2 6 0.90 0.23 2.175 2.70
D3 2 0.80 0.23 2.175 0.80
1 0.80 0.10 2.175 0.17
W2 12 1.50 0.23 1.25 5.18
W3 6 0.80 0.23 0.80 0.88
W4 2 1.50 0.23 0.80 0.55
Sub-Total: 10.78
Total after Deduction: 48.83 Cum.

12 12.5mm thick Cement sand plastreing


works on external wall plastered surface
works in 1:4 ratio.
a External wall face
Side Eevation 2 8.44 6.66 112.42
Front Elevation 1 8.44 6.66 56.21
Back Elevation 1 8.44 6.66 56.21
Parapet wall 4 8.44 1.115 37.64
Balcony parapet wall 4 5.48 1.30 28.50
Stair Reling 4 2.03 1.925 15.62
1 1.20 1.925 2.31
Sub-Total: 308.91
b Internal wall surface.
For Ground Floor
Living 1 15.08 2.78 41.92
Dining 1 15.33 2.78 42.62
Kitchen 1 9.33 2.78 25.94
Store 1 7.25 2.78 20.16
Bath 1 5.78 2.78 16.07
Stair / passes 1 15.58 2.78 43.31
For 1st. Floor
M. Bed room 1 16.15 2.78 44.91
Bath 1 6.58 2.78 18.29
1st. Bed room 1 14.27 2.78 39.66
2nd. Bed room 1 12.38 2.78 34.42

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
Bath 1 6.50 2.78 18.07
Stair / passes 1 15.58 2.78 43.31
Sub-Total: 388.68

Deduction Door & window Openings


D1 -1 1.00 2.175 -2.18
D2 -6 0.90 2.175 -11.75
D3 -4 0.80 2.175 -6.96
W2 -12 1.50 1.25 -22.50
W3 -6 0.80 0.80 -3.84
W4 -2 1.50 0.80 -2.40
Total: -49.63
one tite
Total after Deduction: 647.96 sq.m
deduction
13 12.5mm thick Cement sand plastreing
works of Ceiling plaster works in 1:4
ratio.
3.77mx3.37m size room 6 3.77 3.37 76.23
Slab Projection 1 5.48 1.215 6.66
1 4.265 1.215 5.18
Slab Projectctions 2 9.30 0.50 9.30
2 8.30 0.50 8.30
Stair 4 2.75 1.00 11.00
1 24.40 0.90 21.96
Total : 138.63 sq.m
14 Washable Distemper painting works on
Internal plastered wall surface upto
Refer Item No. 12b & 13 527.31
satisfaction of site Engineer all
complete. sq.m
15 Weather Coat painting on external
Refer Item No. 12a 308.91
building wall surface all complete. sq.m
16 Making and fittings of sal wood frame
Doors (Frame size 100x75mm) all
complete.
D1 ( 1.00 x 2.175 ) 1 6.350 0.100 0.075 0.05
D2 ( 0.90 x 2.175 ) 6 5.250 0.100 0.075 0.24
D3 ( 0.80 x 2.175 ) 3 5.150 0.100 0.075 0.12
Total: 0.41 Cum.
17 Making and fittings of 38mm. thick sal
wood frame Panelled shutter with Hinge,
Tower bolt, locking set, handle and
screw & nail all complete.
D1 ( 1.00 x 2.175 ) 1 1.000 2.150 2.15
D2 ( 0.90 x 2.175 ) 2 0.900 2.150 3.87
Total: 6.02 sq.m.
18 Making and fittings of 12mm. thick
plywood shutter in 38mm. sal wood
frame with Hinge, Tower bolt, locking
set, handle and screw & nail all
complete.
D2 ( 0.90 x 2.175 ) 4 0.900 2.150 7.74
Total: 7.74 Sqm.

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
19 Making and fittings of Aluminium sheet
both sides in 38mm. sal wood frame with
Hinge, Tower bolt, locking set, handle
and screw & nail all complete.

D3 ( 0.80 x 2.175 ) 3 0.800 2.150 5.16


Total: 5.16 sq.m.
20 Making and fittings of Aluminium double
pannel sliding window with fly mesh
shutter frame section (88x38x1.30)mm
and 5mm thick glass.
W4 2 1.500 0.800 2.40
W2 12 1.500 1.250 22.50
W3 6 0.800 0.800 3.84
Total: 28.74 Sqm.
21 Making and fixing 24 gauge mosquito
proof wire mesh and Diamond wire
mesh door shutter in 38mm thick sal
wood frame. ( shutter size = 1.092 x
D1 ( 1.00 x 2.15 ) 1 1.000 2.150 2.15
D2 ( 0.90 x 2.175 ) 2 0.900 2.150 3.87

Total: 6.02 Sqm.


22 Making 4.5mm x 20mm. Iron grill
(100mmx100mm size) & fixing including
cleaning by sand paper, applying paint
etc. complet.
W2 6 0.800 0.800 3.84
W3 3 0.800 0.800 1.92 2.25 times
Total: 3.84 Sqm. 2 times
23 Readymade enamel or plastic emulsion
painting works upto satisfaction of site
Engineer all complete works.
D1 ( 1.00 x 2.175 ) 1 1.000 2.175 2.18
D2 ( 0.90 x 2.175 ) 6 0.900 2.175 11.75
D3 ( 0.80 x 2.175 ) 3 0.800 2.175 5.22
Total: 19.15
Both side 38.30
Total: 76.60 Sqm.
24 20mm thick Cement sand plastreing
works of Floor plaster works in 1:6 ratio.

Ground floor
4 3.77 3.77 56.85

1st. Floor
4 3.77 3.77 56.85

Open Terrace 1 8.000 8.000 64.00


1 4.010 4.020 16.12
Appron 2 9.580 0.640 12.26
2 8.300 0.640 10.62

Total: 216.70 Sqm.

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
25 3mm thick fine cement punning works. Refer Item No.24 216.70 Sqm.
26 Skirting work in inter wall surface and
external wall surfaces
External wall face
2 8.30 0.54 8.96
2 8.30 0.54 8.96
Internal wall surface.
Living 1 15.08 0.15 2.26
Dining 1 15.33 0.15 2.30
Kitchen 1 9.33 0.15 1.40
Store 1 7.25 0.15 1.09
Bath 1 5.78 0.15 0.87
Stair / passes 1 15.58 0.15 2.34
For 1st. Floor
M. Bed room 1 16.15 0.15 2.42
Bath 1 6.58 0.15 0.99
1st. Bed room 1 14.27 0.15 2.14
2nd. Bed room 1 12.38 0.15 1.86
Bath 1 6.50 0.15 0.98
Stair / passes 1 15.58 0.15 2.34
Total: 38.91 sq.m.
27 Enamel paint on skirting surfaces Refer Item No. 26 38.91 sq.m.
28 Providing & laying porcelain glazed/Non
Glazed tile in (1:4)cement mortar at
Bathrooms with proper line & level as
per specification& site incharge
instruction
Ground Floor
Floor(Non Glazed) 1 1.60 1.290 2.06
Walls(Glazed) 1 5.78 1.20 6.94
1 1.00 1.58 1.58
1st. Floor
Floor(Non Glazed) 2 2.00 1.250 5.00
Walls(Glazed) 2 6.50 1.20 15.60
2 1.00 1.58 3.16
34.34 Sqm.
Sanitary Works
29 Supply and Erection at Kitchen Sink
Complete set with Sink cock
(24"x18"x8") size all complete. 1 1.00 Set.
30 Supply and Erection at One pice
COMODE with low level cistern complet
set and all complet works. 2 2.00 Set.
31 Supply and Erection at 20" size Orissa
Pan with low level cistern complet set
and all complet works. 1 1.00 Set.
32 Supply and Erection at Wash Basin
Complete set (16"x20") ISI mark with
Cock all complete set. 3 3.00 Set.
33 Supply and Erection at Looking mirror
(18"x12" size). 3 3.00 Set.
34 Supply and Erection at4" dia Rose
Shower ,revolving type 3 3.00 Set.
35 Supply and Erection at Soap dish (steel) 4"x6"
3 3.00 Set.
36 Supply and Erection at Tower rod (steel) 16"
3 3.00 Set.

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
37 Supply and Erection at Telephonic
shower with 1.5 m flexible tube 2 2.00 Set.
38 15mm,Two way angle cock 2 2.00 Set.
39 Supply and Erection at C.P. Bibcock
15mm dia long neck type with wall
flange 3 3.00 Rm.
40 Supply and Erection at 1000 Lit. PVC
1
Water tank With Tank Nipple /2" & 1"(
NS ISO Premium ) 1 1000 1000.00 Lit.
41 Supply and Erection at 1" . Long G.I.
Pipe Laying With Socket, Elbow,Tee,
Union, Nipple etc. Fitting and fixing
works. 10 10.00 Rm.
42 1
Supply and Erection at / " G.I. Pipe
2
Laying With Socket, Elbow,Tee, Union,
Nipple etc. Fitting and fixing works. 35 35.00 Rm.
43 Supply and Erection at 75mm PVC Pipe
Laying With Socket, Elbow, etc. Fitting
and fixing works. 30 30.00 Set.
44 Supply and Erection at 110mm PVC
Pipe Laying With Socket, Elbow, etc.
Fitting and fixing works. 30 30.00 Rm.

Electricfication works
45 Fixing Didtribution Boards according to
drawings of metal box inclusive or MCB
and connecting to electrical supply of
different capacity. ( Uptp 6 houses
concealed ). 1 1.00 Set.
46 Fixing Wall light,hanging light, spot
disply, ceilling tube, bulb buck
head,electrical bell, wall fan MLL
chandelier upto 6 bulbs.Lighting Fixtures
according to drawing Inclusive of
different main switch (surface or
concealed) and supplying elecricity, all
complete. 16 16.00 Set.
47 Fixing Good quality tubelight pipe or
fixing chain on ceiling chandelier upto 6
bulbs.Lighting Fixtures according to
drawing Inclusive of different main
switch (surface or concealed) and
supplying elecricity, all complete. 6 6.00 Set.
48 Fixing Concealed electrical 6/16
Amp,2/3 pin Power sockets swich,
Indicator & safety shutter according to
drawing connecting to elecricity, all
complete. 12 12.00 Set.
49
Fixing Ceilling Fan according to drawing
and their switch as concealed or surface
and supplying elecricity, all complete. 5 5.00 Set.

.................................... .................................. ............................


Prepared by Checked by Approved by
NEPAL ELECTRICITY AUTHORITY
Medium Generation, Operation & Maintenance Department
Gandak Hydro Power Station
DETAIL QUANTITY ESTIMATE
Job:Civil Construction Works for Building Type - A.

Item No. Description of Works No. Length Breadth Height Quantity Unit Remarks
50
Concealed point Wiring medium Light
Circuit (6m.-10m.) while new house,
According to drawing, placing HDP pipe
while concreting and fixing its switch
board via ceiling rose box; all complete. 15 15.00 Point
51
Concealed point Wiring Long Light
Circuit (11m.-15m.) while new house,
According to drawing, placing HDP pipe
while concreting and fixing its switch
board via ceiling rose box; all complete. 4 4.00 Point
52
Concealed point Wiring medium Power
Circuit (6m.-10m.) while new house,
According to drawing, placing HDP pipe
while concreting and fixing its switch
board via ceiling rose box; all complete. 12 12.00 Point

Miscelleneous
53 Lab Test of Construction Material before
Commencement of Work and Concrete
Compressive Strength test,
Job(P.S.)
Reinforcement Tensile Strength Test
according to codal provision as per
instruction by site Incharge
54 Site Clearing works.(After Completion of
Job(P.S.)
Construction works).

.................................... .................................. ............................


Prepared by Checked by Approved by