Escolar Documentos
Profissional Documentos
Cultura Documentos
Basement
long walls 1 x 2 6.55 0.23 0.60 1.81
short walls room 1 x 2 4.72 0.23 0.60 1.30
Columns Hall 1 x 6 0.30 0.23 0.60 -0.25
TOTAL 2.86 4439.88 1m3 12698.00
Brick Masonry with CM (1:8) prop: using second class bricks crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials and
9 labour charges such as scaffolding charges, lift charges, curing, etc.,
complete for finished item of work for Super Structure
MT MT
29 Provision for Name Board 1.00 3000.00 LS 3000.00
Authority:
Provisions:
The Detailed Estimates are prepared with the following common provisions:
2 P.C.C (1:5:10) prop: nominal mix for levelling course in foundations and as bed con
flooring.
3 Reinforced Cement Concrete M 20 Nominal Mix Nominal Mix using 20mm size HBG
crushed metal, including cost and conveyance of all materials to site and machine mixin
concrete, lift charges, curing etc., complete but excluding cost of steel and its fabrication
for finished item of worok for Coloums footings, Pedastals, Columns, GL beam, Lint
beams and Roof slab.
4 Brick Masonry with CM (1:6) prop: using second class bricks crushing strength of 40 Kg/Sqcm. inc
and conveyance of all materials and labour charges such as scaffolding charges, lift charges, cu
complete for finished item of work for Basement
5 Brick Masonry with CM (1:8) prop: using second class bricks crushing strength of 40 Kg/Sqcm. inc
and conveyance of all materials and labour charges such as scaffolding charges, lift charges, cu
complete for finished item of work for Superstructure.
6 Filling with gravel in basement with initial lead in layers not exceeding 15cm thick, consolidating each
layer by watering and ramming including cost and conveyence of water to work site and all o
incidental, labour charges, hire charges of T & P etc., complete.
7 Weather Proof Course over RCC roof slab to required slopes with CM (1:3) prop. 20 mm thick
mixed with water proofing compound laid over roof slab finished smooth with a floating coat of nea
including cost and conveyance of all materials etc., to site,and labour charges complete for finished item
8 Ceiling Plastering with CM (1:3) 12mm thick sponge finish including cost and conveyance of all ma
cement, sand, water etc., to site and labour charges such as mixing mortar, scaffolding charges, li
including curing, etc., complete for Even Surfaces for finished item of work.
9 Plastering 12 mm thick in two coats, base coat 8mm thick in CM(1:6) and top coat 4mm
CM(1:4) for even face of walls.
10 Plastering 20 mm thick in two coats, base coat 16mm thick in CM(1:6) and top coat 4mm
CM(1:4) for uneven face of walls.
11 Flooring with Rough shabad / Tandur Stone slabs of minimum 40 mm thick (0.457 x 4
over a base coat of CM (1:8), 12mm thick over already laid C.C. bed or R.C.C. roof slabs.
12 Providing Green Chalk Board of size 3.00 x 1.2 mm including border with palstering in
12 mm thick as base coat and 3 mm thick top coat with cement green oxide powder in (1
13 Whiting to new walls and ceiling in two coats with Birla white or equavalent quality fo
walls.
14 Colour painting to new walls with 2 coats of Emulsion paint of superior quality of over base coa
coat making three coats of including cost and conveyance of all materials and labour charge
scaffolding charges, lift charges, curing etc., complete for finished item of work in all floors for Externa
All Floors
15 Painting two coats with synthetic enamel paint 1st grade to new iron work.
16 Supply and Fixing of MS Double leaf Door of Size 1.20Mx2.10M using with Outer MS Angle
35x35x6MM Thick ,Inner MS Angle Frame of 25x25x5MM Thick using with 18 Guage MS Sheet incl
of fixtures such as M.S.P.C.Tower Bolts, aldrops, butt hinges, hold fasts including cost and conveny
materials to site all Labour charges etc., complete for finsihed item of work.
17 Supply and fixing of MS iron Window of size 1.50m X 1.35m using MS angles of 40x40x6 mm siz
frame and 35x35x6 mm size for shutter frame using 18 guage MS sheet and 12 mm MS square ro
fixing horizontally, wind appliance of MS flat of 20x4 mm size - 3 No. inclding cost & conveyance of all
fabrication, welding and placing in position etc., complete for 1 Kg of finished item of work
18 Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-
8mm to 40mm diameters, cutting, bending, to required sizes and shapes placing in pos
cover blocks of approved size and binding wire of 20SWG, forming grills for reinforcemen
per approved designs and drawings including cost and conveyance of bars from approved
to site of work, including cost and conveyance of binding wire, cover blocks, chairs,
spacers, dowels, wastage etc., and all operational, incidental, and labour charges such a
bending, placing in position, tying etc., and sales & other taxes,on cost of all materials
for finished item of work (APSS No.126) in all floors.
AMENITIES:
1) Sub-Estimate is prepared for Internal Electrification as per the requirements based on
plan. Excluding Supply and Fixing of Street Lights and Ceiling Fan fittings in view of in
sanction amount.
The Data of all the items are adopted as per the Revised Standard Data Part-III (B
and the rates are worked out based on current SSR i.e Building SSR 2015-2016. Cement a
rates are adopted as approved by the Committee of the Chief Engineers for Sl. No.
SPECIFICATIONS:
The Standard specifications as per APSS are adopted and the work will be carried ou
the relevant standard specification of APSS and as per the agreement conditions.
lakhs
m thick sponge finish including cost and conveyance of all materials like
abour charges such as mixing mortar, scaffolding charges, lift charges,
Surfaces for finished item of work.
s, base coat 8mm thick in CM(1:6) and top coat 4mm thick in
s, base coat 16mm thick in CM(1:6) and top coat 4mm thick in
per APSS are adopted and the work will be carried out true to
SS and as per the agreement conditions.
LEAD STATEMENT
Name of the work: Construction
RATES AS PER COMMON SSR OF 2015-2016
BALAYAPALLI GUDUR-II Est. Cost. Rs. 5.00 Lakh
Add
Add Machine
Sl.No
1 Certified that the above leads are true and correct to the best of my knowledge
2 Certified that the quarry requries blasting for RR, CRS, 20mm & 40mm Metal
3 Certified that the 20mm, 40 mm Metal requires Machine Crushing
Hafhizullaa
D STATEMENT
Un Loading
Total Cost Unit
Charges
10 11
224.38 Cum.
294.38 Cum.
224.38 Cum.
232.38 Cum.
6600.00 M.T.
1832.31 Cum.
2482.31 Cum.
51994.00 1 Cum
10sqm.
1823.89
77.00 KL
34500.00 1MT
Hafhizullaa
DATA SHEET S S R (2015-16)
Name of the work: Construction
Filling with Sand in basement with initial lead in layers not exceeding 15cm thick, consolidating each
2 deposited layer by watering and ramming including cost and conveyence of water to work site and all
operational, incidental, labour charges, hire charges of T & P etc., complete.
material
Metal 40mm 0.90 cu.m. 1832.31 1.00 cu.m.
Sand 0.45 cu.m. 224.38 1.00 cu.m.
Cement 129.60 Kgs. 6600.00 1000.00 Kgs.
Water 1.20 KL 77.00 1.00 KL
Concrete mixer(300/200(diesel) 1.00 hour 352.50 1.00 hour
Mason 1st Class 0.10 day 445.00 1.00 day
Mazdoor 1.39 day 350.00 1.00 day
add
Rate per Cu.m. Total
Vibrated Reinforced Cement Concrete M 20 Design Mix using 20MM HBG machine crushed metal,
7 including cost and conveyance of all materials to site and machine mixing, laying concrete, lift charges,
curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work
Material
Graded Metal 20mm 0.80 cu.m. 2482.31 1.00 cu.m.
Sand 0.4 cu.m. 224.38 1.00 cu.m.
Cement 350 kgs 6600.00 1000.00 kgs
Water 1.20 KL 77.00 1.00 KL
Concrete mixer 1.00 hour 352.50 1.00 hour
Cost of Disel for Miller 0.13 Litres 57.70 1.00 hour
Cost of Petrol for Vibrator 0.67 hour 68.45 1.00 hour
40mm needle vibrator 1.00 hour 184.60 1.00 hour
1st Class Mason 0.133 nos 445.00 1.00 nos
11nd Class Mason 0.267 nos 400.00 1.00 nos
Man and woman mazdoor 4.600 nos 350.00 1.00 nos
Basic rate per Cum
Vibrated Reinforced Cement Concrete M 20 Design Mix using 20mm size HBG machine crushed metal,
including cost and conveyance of all materials to site and machine mixing, laying concrete, lift charges,
8
curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work for
Coloums footings,pedastals, plinth beams
a) RCC M20 grade nominal mix for footings
Basic Rate per Cum. 1.00 cu.m. 6844.42 1.00 cu.m.
Centering Charges per Cum. 1.00 cu.m. 750.00 1.00 cu.m.
Vibrated Reinforced Cement Concrete M 20 Design Mix using 20mm size HBG machine crushed metal,
including cost and conveyance of all materials to site and machine mixing, laying concrete, lift charges,
9
curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work for
Coloums
Material
Graded Metal 20mm 0.80 cu.m. 2482.31 1.00 cu.m.
Sand 0.4 cu.m. 224.38 1.00 cu.m.
Cement 350.00 kgs 6600.00 1000.00 kgs
Water 1.20 KL 77.00 1.00 KL
Concrete mixer(300/200 (diesel) 1.00 hour 352.50 1.00 hour
Cost of Disel for Miller 0.13 Litres 57.70 1.00 hour
Cost of Petrol for Vibrator 0.67 hour 68.45 1.00 hour
40mm Needle vibrator 1.00 hour 184.60 1.00 hour
1st Class Mason 0.167 nos 445.00 1.00 nos
11nd Class Mason 0.167 nos 400.00 1.00 nos
Man and woman mazdoor 5.600 nos 350.00 1.00 nos
Basic rate per Cum. Total
a) For COLUMNS
Vibrated Reinforced Cement Concrete M 20 Design Mix using 20mm size HBG machine crushed metal,
including cost and conveyance of all materials to site and machine mixing, laying concrete, lift charges,
10
curing etc., complete but excluding cost of steel and its fabrication charges for finished item of work for
Slabs, beams, Lintels
Material
Graded Metal 20mm 0.80 cu.m. 2482.31 1.00 cu.m.
Sand 0.4 cu.m. 224.38 1.00 cu.m.
Cement 350.00 kgs 6600.00 1000.00 kgs
Water 1.20 KL 77.00 1.00 KL
Concrete mixer 0.27 hour 352.50 1.00 hour
Cost of Disel for Miller 0.13 Litres 57.70 1.00 hour
Cost of Petrol for Vibrator 0.67 hour 68.45 1.00 hour
40mm Needle Vibrator 0.27 hour 184.60 1.00 hour
1st Class Mason 0.067 nos 445.00 1.00 nos
11nd Class Mason 0.133 nos 400.00 1.00 nos
Man and woman mazdoor 3.077 nos 350.00 1.00 nos
Description Quanti Rate (Rs.) Per Unit
Basic rate per Cum. ty Total
a) For roof beams
Rate for other Floors GF FF SF TF
Rate as worked out above per Cum. 5835.26 5835.26 5835.26 5835.26
Labour charges for centering 2464.00 2464.00 2576.00 2688.00
Lift charges @ 10% extra on each floor 0.00 87.80 175.60 263.40
add 0.04 0.04 0.04 0.04
Rate per cu.m. Total 8299.30 8387.10 8586.90 8786.70
c) RCC M20 nominal mix for Slabs of 115mm
thick
Cost of RCC for 115 mm thick slab 0.115 cu.m. 5835.26 1.00 cu.m.
f) Chajja / Sunshade
Cost of RCC for 62.5 mm thick sunshade 0.0625 cu.m. 5835.26 1.00 cu.m.
Brick Masonry with CM (1:6) prop: using second class bricks crushing strength of 40 Kg/Sqcm.
11 including cost and conveyance of all materials and labour charges such as scaffolding charges, lift
charges, curing, etc., complete for finished item of work for Basement
wall thickness 0.225
Material
Cement 48 Kgs 6600.00 1000
Second class Bricks 512 Nos 5945.27 1000.00 Nos
sand for mortor 0.20 cu.m. 224.38 1.00 cu.m.
1st Class Mason 0.240 nos 445.00 1.00 nos
11nd Class Mason 0.560 nos 400.00 1.00 nos
Man and woman mazdoor 1.890 nos 350.00 1.00 nos
Add Water Charges@ 1% on Cost of Material& 4190.630 0.00 0.01 0.00 0.00
Labour
Description Quanti Rate (Rs.) Per Unit
ty
Basic Rate per Cum.
Brick Masonry with CM (1:8) prop: using second class bricks crushing strength of 40 Kg/Sqcm.
12 including cost and conveyance of all materials and labour charges such as scaffolding charges, lift
charges, curing, etc., complete for finished item of work for Superstructure.
wall thickness 0.225
Material
Cement 36.00 kgs 6600.00 1000.00 kgs
Second class Bricks 512 Nos 5945.27 1000.00 Nos
sand for mortor 0.20 cu.m. 224.38 1.00 cu.m.
1st Class Mason 0.240 nos 445.00 1.00 nos
11nd Class Mason 0.560 nos 400.00 1.00 nos
Man and woman mazdoor 1.890 nos 350.00 1.00 nos
Add Water Charges@ 1% on Cost of Material& 4111.430 0.00 0.01 0.00 0.00
Labour
Ceiling Plastering with CM (1:3) 12mm thick sponge finish including cost and conveyance of all
materials like cement, sand, water etc., to site and labour charges such as mixing mortar, scaffolding
13 charges, lift charges, including curing, etc., complete for Even Surfaces for finished item of work.
Material
Cement mortor (1:3) 0.15 cu.m 3547.10 1.00 cu.m
1st Class Mason 0.600 nos 445.00 1.00 nos
Man mazdoor 0.960 nos 350.00 1.00 nos
Add Water Charges@ 1% on Cost of Material& 1187.470 0.00 0.01 0.00 0.00
Labour
Basic rate per 1 Sqmt.
Rate for other Floors GF FF SF TF
Basic rate per 1 Sqmt. 1146.93 1146.93 1146.93 1146.93
Labour charges for stage scaffolding per sqm 149.20 149.20 239.10 287.00
Lift charges @ 10% extra on each floor 0.00 55.92 111.84 167.76
add 0.02 0.07 0.08 0.04
Rate per 1 Sqmt. Total 1296.20 1352.10 1497.90 1601.70
Plastering for 12mm thick with base coat in CM(1:5) 12 mm thick sponge finish including cost and
conveyance of all materials like cement, sand, water etc., to site and labour charges such as mixing
14 mortar, scaffolding charges, lift charges, including curing, etc., complete for Even Surfaces of Brick
walls for finished item of work.
Description Quanti Rate (Rs.) Per Unit
Material ty
Cement mortor (1:5) 0.15 cu.m 2279.90 1.00 cu.m
1st Class Mason 0.600 nos 445.00 1.00 nos
Man mazdoor 0.960 nos 350.00 1.00 nos
Add Water Charges@ 1% on Cost of Material& 997.390 0.00 0.01 0.00 0.00
Labour
Basic rate per 1 Sqmt.
Rate for other Floors GF FF SF TF
Basic rate per 1 Sqmt. 954.95 954.95 954.95 954.95
Labour charges for stage scaffolding per sqm 71.70 93.00 117.30 141.70
Lift charges @ 10% extra on each floor 0.00 55.92 111.84 167.76
add 0.00 0.00 0.10 0.07
Rate per 1 Sqmt. Total 1026.70 1103.90 1184.10 1264.50
Plastering with CM (1:5) 20 mm thick with base coat in sponge finish including cost and conveyance of all
15 materials like cement, sand, water etc., to site and labour charges such as mixing mortar, scaffolding charges, lift
charges, including curing, etc., complete for Even Surfaces of Brick walls forf finished item of work.
Material
Cement mortor (1:5) 0.21 cu.m 2279.90 1.00 cu.m
1st Class Mason 0.940 nos 445.00 1.00 nos
Man mazdoor 1.600 nos 350.00 1.00 nos
Add Water Charges@ 1% on Cost of Material& 1530.440 0.00 0.01 0.00 0.00
Labour
Basic rate per 1 Sqmt.
Rate for other Floors GF FF SF TF
Basic rate per 1 Sqmt. 1472.38 1472.38 1472.38 1472.38
Labour charges for access scaffolding per sqm 71.70 71.70 117.30 141.70
Lift charges @ 10% extra on each floor 0.00 90.68 181.36 272.04
0.00 0.06 0.06 0.06
Rate per 1 Sqmt. Total 1544.10 1634.80 1771.10 1886.20
Weather Proof Course over RCC roof slab to required slopes with CM (1:3) prop. 20 mm thick
(average) mixed with water proofing compound laid over roof slab finished smooth with a floating coat of
16
neat cement including cost and conveyance of all materials etc., to site,and labour charges complete for
finished item of work
Cement Mortar (1:3) 0.21 cu.m. 3547.10 1.00 cu.m.
Water proof compound 2.00 Kgs 75.00 1.00 Kgs
1st Class Mason 0.660 nos 445.00 1.00 nos
2nd Class Mason 1.540 nos 400.00 1.00 nos
Man mazdoor 3.700 nos 350.00 1.00 nos
Add Water Charges@ 1% on Cost of Material& 3172.950 0.00 0.01 0.00 0.00
Labour
Basic rate per 1 Sqmt.
Rate for other Floors GF FF SF TF
Basic rate per 1 Sqmt. 3131.32 3131.32 3131.32 3131.32
Scaffolding charges 131.90 131.90 176.80 176.80
Lift charges @ 10% extra on each floor 0.00 203.87 407.74 611.61
add 0.00 0.08 0.02 176.87
Rate per 1 Sqmt. Say 3263.30 3467.10 3715.90 3919.80
Description Quanti Rate (Rs.) Per Unit
ty
Flooring with Polished kadapa/shabad stone 15 to 18mm thick set over a base coat of CM (1:8),
12mm thick over C.C. bed already laid or R.C.C. roof slab, where necessary treated with neat grey
17 cement slurry of honey like consistency spred at 3.3 kgs of cement for 1 sqm. and jointed with neat
cement paste to full depth, including cost and conveyance of all materials and labour charges etc.,
complete for finished item of work.(APSS No.701 & 703)
Material
Cost of Polished kadapa Slabas 15 to 18 mm 10.10 Sqmt. 1823.89 10.00 Sqmt.
thick (0.457M
jointing x 0.457M)
compound BMT-M.22 0.00 Kgs 6600.00 1000.00 Kgs
Cement for (1:8) proportion for base coat 54.60 kgs 6600.00 1000.00 kgs
Cement for Morter and slurry 33.00 Kgs 6600.00 1000.00 Kgs
Coarse sand for mortor 0.12 cum 224.38 1.00 cum
1st Class Mason 3.100 nos 445.00 1.00 nos
2nd Class Mason 1.100 nos 400.00 1.00 nos
Man mazdoor 0.860 nos 350.00 1.00 nos
Add Water Charges@1% on Labour 2120.500 0.00 0.01 1.00 0.00
Add
Basic rate per 10 Sqmt.
Rate for other Floors GF FF SF TF
Basic rate per 10 Sqmt. 4635.55 4635.55 4635.55 4635.55
Lift charges @ 10% extra on each floor 0.00 198.97 397.94 596.91
0.05 0.08 0.01 0.04
Rate per 10 Sqmt. Total 4635.60 4834.60 5033.50 5232.50
Skirting with Polished kadapa Slab 15 to 18 mm thick set over a base coat of CM (1:8), 12mm thick
over C.C. bed already laid or R.C.C. roof slab, where necessary treated with neat grey cement slurry of
18 honey like consistency spred at 3.3 kgs of cement for 1 sqm. and jointed with neat cement paste to full
depth, including cost and conveyance of all materials and labour charges etc., complete for finished item
of work(BLD CSTN -7-20)
Material
Cost of Polished Shabad/Kadapa Slabas 15 to 10.10 Sqmt. 1823.89 1.00 Sqmt.
18 mm thick (0.457M x 0.457M)
sand for Cement Mortar (1:3) 0.12 cu.m. 224.38 1.00 cu.m.
cement for Cement Mortar (1:3) base coat 54.6 Kgs 6600.00 1000 Kgs
Cement for slurry 33.00 Kgs 6600.00 1000 Kgs
1st Class Mason 0.960 nos 445.00 1.00 nos
2nd Class Mason 2.240 nos 400.00 1.00 nos
Man mazdoor 3.100 nos 350.00 1.00 nos
Add Water Charges@1% on Labour 2408.200 0.00 0.01 1.00 0.00
Basic rate per 1 Sqmt.
Rate for other Floors GF FF SF TF
Basic rate per 1 Sqmt. 4879.70 4879.70 4879.70 4879.70
Lift charges @ 10% extra on each floor 0.00 223.52 447.04 670.56
0.00 0.08 0.06 0.04
Rate per 1 Sqmt. Total 4879.70 5103.30 5326.80 5550.30
Description Quanti Rate (Rs.) Per Unit
ty
Painting to new walls with 2 coats of ready mixed oil bound wahsable distemper of approved brand and
shade over a base coat of appropriate primer of approved brand, making 3 coats in all to give an even
19 shade after thourughly brushing the surface to remove all dirt and remains of loose powdered materials,
including cost and conveyance of all materials to work site and all operational, incidental, labour charges
etc. complete for finished item of work as per SS 911 for internal walls
PRIMARY COAT
Cost of Primer(BMT J.01) 0.50 Lit 165.00 1.00 Lit
Painter 1st class 0.08 nos 510.00 nos
Painter 2nd class 0.19 nos 400.00 nos
Cost of Washable Oil Bound Distemper(BMT J.21) 1.70 Lit 90.00 Lit
Painter 1st class 0.36 nos 510.00 nos
Painter 2nd class 0.84 nos 400.00 nos
sundries including brushes,ladders, etc.,
add
Rater per 1 Sqmt. for all floors Total
painting to New walls with 2 coats of Snowcem Cement paint of superior quality over base coat of
primer coat making three coats in all to give an including cost and conveyance of all materials and
20
labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in
all floors for External Walls. in All Floors
Material
Snowcem Cement Paint 3 sqm., per kg 3.50 Kgs 55.00 1.00 Kgs
Painter 1st class 0.50 nos 510.00 nos
Man Mazdoor 1.50 nos 350.00 nos
sundries including brushes,ladders, etc.,
add
Rater per 10Sqmt. for all floors Total
Colour painting to New walls with 2 coats of Emulsion paint of superior quality over base coat of
primer coat making three coats in all to give an including cost and conveyance of all materials and
21
labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in
all floors for External Walls. in All Floors
Material
cement primer water based SDR 353 page 27 1.00 Lts 165.00 1.00 Lts
Painter 1st class 0.21 nos 510.00 nos
Painter 2nd class 0.49 nos 400.00 nos
Emulsion paint SDR 374 page 27 0.90 Lts 261.00 1.00 Lts
Painter 1st class 0.36 nos 510.00 nos
Painter 1st class 0.84 nos 510.00 nos
sundries including brushes,ladders, etc.,
add
Rater per 10 Sqmt. for all floors Total
painting to New walls with 2 coats of Snowcem Cement paint of superior quality over base coat of
primer coat making three coats in all to give an including cost and conveyance of all materials and
22
labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in
all floors for External Walls. in First Floor
Material
Snowcem Cement Paint 3 sqm., per kg 3.50 Kgs 55.00 1.00 Kgs
Painter 1st class 0.50 nos 480.00 nos
Man Mazdoor 1.50 nos 320.00 nos
sundries including brushes,ladders, etc.,
Description Quanti Rate (Rs.) Per Unit
Lift Charges @10% on labour charges ty
add
Rater per 10Sqmt. for all floors Total
Colour painting to New walls with 2 coats of Emulsion paint of superior quality over base coat of
primer coat making three coats in all to give an including cost and conveyance of all materials and
23
labour charges such as scaffolding charges, lift charges, curing etc., complete for finished item of work in
all floors for External Walls. in First Floor
Material
Water Based Cement primer Interior Grafe-1 (BMT.J-01) 1.00 Lts 165.00 1.00 Lts
Painter 1st class 0.21 nos 480.00 nos
Painter 2nd class 0.49 nos 375.00 nos
Emulsion paint SDR 374 page 27 0.90 Lts 261.00 1.00 Lts
Painter 1st class 0.36 nos 480.00 nos
Painter 1st class 0.84 nos 480.00 nos
sundries including brushes,ladders, etc.,
Lift Charges @10% on labour charges
add
Rater per 10 Sqmt. for all floors Total
Painting to New wood work with two coats of ready mixed synthetic enamel paint first quality all
22 shades including cost and conveyance of all materials labour charges etc., complete for finished item of
work..in All Floors
Synthetic enamel paint (BMT J.30) 1.20 lit 276.00 1.00 lit
Painter 1st class 1.20 nos 510.00 nos
sundries including brushes,ladders, etc.,
add
add
Rate per 1 Sqmt. for all Floors Total
Supply and fixing of MS iron Door of size 1.20M x2.13M using MS angles of 35x35x6 mm size for outer
frame and 25x25x5 mm for Inner frame size for shutter frame using 18 guage MS sheet wind appliance of
23
MS flat of 25x6 mm size - 3 Nos. inclding cost & conveyance of all materials, fabrication, welding and
placing in position etc., complete for 1 Kg of finished item of work
ABSTRACT
a)MATERIAL
DOOR SIZE: 1.20Mx2.13M, Area 2.56sqm
1) Outer angle frames:
MS Angle ISA 3535 of 35x35x6 mm size
Horizontal (Top& Bottom) 4.00 1.20
Verticals (2Nos external) 2.00 2.13
Add
Supply and fixing of MS iron Window of size 1.50m X 1.35m using MS angles of 40x40x6 mm size for
outer frame and 35x35x6 mm size for shutter frame using 18 guage MS sheet and 16 mm MS square rods
24
- 9 No. fixing horizontally, wind appliance of MS flat of 20x4 mm size - 3 No. inclding cost & conveyance
of all materials, fabrication, welding and placing in position etc., complete for 1 Kg of finished item of work
ABSTRACT
a)MATERIAL
WINDOW SIZE: 1.50x1.35M, Area 2.025sqm
1) Outer angle frames:
MS Angle ISA 4040 of 40x40x6 mm size
Horizontal (Top& Bottom) 2.00 1.50
Verticals (2Nos external) 2.00 1.35
Add
Supply and fixing of MS iron Ventilator size 1.50m X 0.45&1.20Mx0.45M m inclding cost & conveyance of
25
all materials, fabrication, welding and placing in position etc., complete for 1 Kg of finished item of work
ABSTRACT
a)MATERIAL
Cost of MS angle Structural Steels 1.0000 Kgs 37500.00 1.00 MT
Labour charges for fabricating iron
windows&Ventilators(BMM-V.14)
Labour Charges for fixing Iron Doors,Iron 1.00 Kgs 24.00 1.00 Kgs
Windows,window Grills fixing position(BMM-V-
15) 1.00 Kgs 4.00 1.00 Kgs
Rate per / KG
Supply and Fitting and placing HYSD bar reinforcement in foundation complete as per drawings and
26 technical specifications for bars below 36 mm dia including over laps and wastage, where they are not
welded
ABSTRACT
a)MATERIAL
HYSD bars including 5% for over laps and 1.05 mt 34500.00 1.00 Cu.m.
wastage
Binding wire 6.00 Kgs 70.00 1.00 Kgs
Black smith/Barbender 10.000 nos 555.00 1.00 nos
mazdoor (Un skilled) 10.000 nos 350.00 1.00 nos
add
Rate per / MT
Supply & Fixing of 50 mm thick Jali including cost and conveyance of all materials to site, sales & other
27
taxes, all operational, incidental and labour charges etc., complete for finished item of work in All Floors
Supply and fixing MS pipe 50mm dia including labour charges for fixing complete including cost and
28
conveyance of all materials to site and labour charges complete for finished item of work.
Description Quanti Rate (Rs.) Per Unit
Cost of MS pipe 50mm dia asper(BMT-F.04) ty
5.10 Kgs 61.00 1.00 Kgs
Fabrication,cutting and fixing charges (BMV-V 5.100 Kgs 24.00 1.00 nos
14)
Transport charges 1.000 LS 200.00 1.00 LS
add
EET S S R (2015-16)
onstruction
(1:8)
235.60
1188.00
70.00
1493.60
Amount
(Rs.)
127.40
95.55
0.04
223.00
224.38
109.20
7.70
7.72
341.30
232.38
109.20
7.70
7.72
349.30
trenches, sides of foundations, basement with initial lead in layers
posited layer by watering and ramming, including cost, seignorage
o work site and all operational, incidental, labour charges, etc.
182.00
9.24
0.06
191.30
Amount
(Rs.)
1649.08
100.97
855.36
92.40
352.50
44.50
486.50
0.04
3581.35
1985.85
89.75
2310.00
92.40
352.50
7.67
45.66
184.60
59.19
106.80
1610.00
6844.42
6844.42
750.00
0.05
7594.47
6844.42
2476.00
0.05
9320.47
6844.42
1068.00
0.05
Amount
(Rs.)
7912.47
1985.85
89.75
2310.00
92.40
352.50
7.67
45.66
184.60
74.32
66.80
1960.00
7169.55
1985.85
89.75
2310.00
92.40
94.12
7.67
45.66
49.84
29.82
53.20
1076.95
Amount
(Rs.)
5835.26
671.05
1021.17
364.70
316.80
3043.98
44.88
106.80
224.00
661.50
41.91
Amount
(Rs.)
0.01
4439.88
237.60
3043.98
44.88
106.80
224.00
661.50
41.11
0.07
4359.94
532.06
267.00
336.00
11.87
1146.93
Amount
(Rs.)
341.98
267.00
336.00
9.97
954.95
478.78
418.30
560.00
15.30
1472.38
744.89
150.00
293.70
616.00
1295.00
31.73
3131.32
Amount
(Rs.)
1842.13
0.00
360.36
217.80
73.54
1379.50
440.00
301.00
21.21
0.01
4635.55
1842.13
26.93
360.36
218.00
427.20
896.00
1085.00
24.08
4879.70
Amount
(Rs.)
82.50
40.80
76.00
153.00
183.60
336.00
0.76
0.04
872.70
192.50
255.00
525.00
6.63
0.07
979.20
165.00
107.10
196.00
234.90
183.60
428.40
4.28
0.02
1319.30
192.50
240.00
480.00
6.63
Amount
(Rs.)
72.00
0.07
991.20
165.00
100.80
183.75
234.90
172.80
403.20
4.03
86.05
0.02
1350.55
331.20
612.00
1.50
944.70
4.80
4.26
9.06
34.97
KGS
KGS
2.28
3.42
8.24
31.37
KGS
2.10
Amount
(Rs.)
2.35
23.03
Kgs
Amount
264.00
230.00
68.00
75.00
1311.38
1176.38
863.63
2144.88
357.48
363.52
6854.26
0.04
6854.30
3.00
2.70
5.70
19.95
KGS
1.50
2.70
4.20
14.70
KGS
15.00
11.70
Kgs
5.52
7.56
13.08
18.31
1.74
17.05
Amount
(Rs.)
Kgs
Amount
264.00
264.00
150.00
138.00
234.00
748.13
551.25
686.63
438.75
639.38
1961.04
326.84
288.26
6690.27
0.03
6690.30
37.50
24.00
4.00
65.50
36225.00
420.00
5550.00
3500.00
0.00
45695.00
403.00
403.00
Amount
(Rs.)
311.10
122.40
200.00
633.50
DETAILED CUM ABSTRACT ESTIMATE
Name of the work:
Basement
long walls 1 x 2 6.55 0.23 0.60 1.81
short walls room 1 x 2 4.72 0.23 0.60 1.30
Columns Hall 1 x 6 0.23 0.38 0.60 -0.31
TOTAL 2.80 4439.88 1m3
Brick Masonry with CM (1:8) prop: using second class bricks crushing
strength of 40 Kg/Sqcm. including cost and conveyance of all materials and
9 labour charges such as scaffolding charges, lift charges, curing, etc., complete
for finished item of work for Super Structure
No 1 No
Supply and fixing of MS iron Window of size 1.52m X 1.37m using MS angles
of 40x40x6 mm size for outer frame and 35x35x6 mm size for shutter frame
using 18 guage MS sheet and 12 mm MS square rods - 9 No. fixing horizontally,
24 wind appliance of MS flat of 20x4 mm size - 3 No. inclding cost & conveyance of
all materials, fabrication, welding and placing in position etc., complete for 1 Kg
of finished item of work
MT MT
29 Provision for Name Board 1.00 3000.00 LS
Amount
4501.00
6840.00
2994.00
19290.00
5776.00
Amount
16512.00
20319.00
12432.00
69753.00
9143.00
Amount
2114.00
4262.00
24732.00
40417.00
13882.00
Amount
6545.00
6540.00
16400.00
13800.00
6854.00
20071.00
Amount
11181.00
14012.00
2159.00
75397.00
3000.00
3000.00
431926.00
12958.00
6479.00
202.00
451565.00
TOTAL
LENGTH OF LENGTH OF
Sl.no Description MEMBERSDIA SPACING NOS BAR BAR
1 footing-01
a Bottom Main Bar 6 10 7 1.5 10.5
b Bottom Distributor 6 10 7 1.48 10.36
2 Pedestals
vertical Bars 6 10 8 1.39 11.12
rings 6 8 0.15 6 1.32
4 Columns (2 & 6)
Vertical bars 2 16 4 5.54 22.16
Vertical bars 2 12 4 5.54 22.16
striupps 2 8 8 35 1.092
5 Plinth Beam 1
Bottom Main Bar 2 12 4 6.48 25.92
Top Main Bar 2 16 4 6.48 25.92
Top Extra bar 2 16 2 4.74 9.48
Striupps 1 8 43 1.092 47.1744
ROOF BEAM1
Bottom Main Bar 2 12 4 6.48 25.92
Top Main Bar 2 16 4 6.48 25.92
Top Extra bar 2 16 2 4.74 9.48
Striupps 2 8 43 1.092 47.1744
6 Slab
Straight Bra 1 8 0.4 14 6.05 86.06125
Cracked Bars 1 8 0.4 14 6.58 92.12
Extra Bars 1 8 0.4 14 1.63 22.82
Straight Bra 1 8 0.4 14 6.05 86.06125
Cracked Bars 1 8 0.4 14 6.58 92.12
Extra Bars 1 8 0.4 14 1.63 22.82
Top Main Bar 1 8 0.2 27 6.184 166.968
top Extra bar 1 8 0.2 27 1.178 31.806
UNIT T IN Total Wt
kg/m in kgs
0.62 38.84094
0.62 38.32306
77.164 1641.59
0.62 41.1344
0.39 3.125031
44.25943
1.58 279.8007
0.39 1.723502
281.5242
0.89 46.02318
1.58 81.81899 0.474
1.58 29.92454
0.39 18.61382
176.3805
0.89 46.02318
1.58 81.81899 0.474
1.58 29.92454
0.39 37.22764
194.9943
-2.054
0.89 84.05623
1.58 149.4333
1.58 22.4434
0.39 64.12484
320.0578
0.39 33.95758
0.39 36.34821
0.39 9.004192
0.39 33.95758
0.39 36.34821
0.39 9.004192
0.39 65.88133
0.39 12.54984
237.0511