Escolar Documentos
Profissional Documentos
Cultura Documentos
This paper was prepared for presentation at the International Petroleum Technology Conference held in Doha, Qatar, 79 December 2009.
This paper was selected for presentation by an IPTC Programme Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the International Petroleum Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily
reflect any position of the International Petroleum Technology Conference, its officers, or members. Papers presented at IPTC are subject to publication review by Sponsor Society Committees
of IPTC. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the International Petroleum Technology Conference is
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of
where and by whom the paper was presented. Write Librarian, IPTC, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax +1-972-952-9435.
Abstract
Gas fields in the Mahakam Delta are the most prolific in Indonesia. TOTAL E&P Indonesia operates Tunu, Tambora, Handil,
Peciko, Bekapai and Sisi Nubi fields. To meet the increased production requirements while enhancing economic development,
the operator is reducing drilling costs as much as possible. Slim hole well is the optimal gas well configuration being applied
in Tunu and Tambora fields. The slim hole design diminishes the size and number of casing strings to produce the low
pressure gas reserves economically.
The latest well design, known as the light slim hole well, reduces the number of casing strings from previously four, to become
three strings: conductor, surface, and production tubingless. In light slim hole well, the 24-in. conductor casing is hammered to
130 m depth, similar to the previous design. The 9 5/8-in. surface casing is set at 1,300 m TVD. The well then is completed
with 4 -in. production tubing, which is set at around 4,000 m TVD.
Like all gas wells, light slimhole requires adequate zonal isolation along the production section. Cement sheath failure will
result in sustained casing pressure and, in the worst case, loss of the well. A long open hole section has to be cemented from
bottom across the production zones to 300 m above surface casing shoe. Placing a nearly 3,000 meters column of cement
slurry along production casing is therefore one of the most challenging operations done on the well.
The long cement column translates into large temperature differences between the bottom hole and the top of cement and high
circulating pressure during slurry placement. In this case, the temperature difference can reach 90 degC [162 degF]. Design
and selection of the cement slurry requires specific and tailored approach to ensure the cement sets uniformly along the long
column, ensuring proper zonal isolation. By using advance software resources, the temperature of the cement particle is
analyzed precisely during the cement placement. This paper outlines cement design approach for this long section hole,
describes the overall cementing process, and shows field results of light slim hole wells in the Mahakam Delta.
Introduction
For several years, TOTAL E&P Indonesia had been optimizing their well architecture by reducing the size of slim hole wells
in order to cut the overall drilling cost. These efforts between 2005 and 2007 led to reducing the drilling time of these slim
wells toabout 22 to 26 days.
The drilling phase has three sections which are shown in Fig.1, while the conductor pipe construction was not included in
drilling time as it was hammered before rig arrival on well site.
The new light well design has two drilling phase as shown in Fig.1and is identified as light slim hole well. The design had
gone through comprehensive study to meet Geology-Geosciences requirement as well as economic value. The main
characteristics of the light slim hole well design are:
Two drilling phases i.e.:
o 12 -in. OH cased by 9 5/8-in. surface casing
o 8 -in. OH cased by 4 -in. production tubingless.
Well profile has J shape.
Maximum well inclination is 30 degree.
2 IPTC 13611
Surface casing cementation for light slim wells are similar from the previous traditional slim hole well architecture but with a
reduced size. Thus the slurry volume is smaller and the circulating pressure higher in these smaller annuli.
The major challenge is for construction the production drilling phase. As the intermediate section is eliminated on the new
Light Slim Hole Well, the drilling phase of production section is extended long enough until reaching the hydrocarbon target.
This is only possible due to a good understanding of the field characteristic, which allows TOTAL E&P Indonesia to drill
deeper while maintaining the trajectory in low pore pressure area. In gas producer wells, TOTAL E&P Indonesia requires
zonal isolation down to the production hole total depth up to 300 meters overlap with the previous casing shoe. The
firstchallenge for cement slurry design in this particular production string is to identify the technical requirements and then
match those with the present and available cementing technology on the location. To narrow down the design boundary, three
conditions are considered as the primary factor:
A long column of cement has to be placed (e.g. up to 3000 meters). In this regard, the top of cement is very critical as
an overlap of 300 m in the previous casing is required to guarantee that no sustained casing pressure will appear
during the well life. That long column of cement will also generate higher hydrostatic pressure. Thus maintaining the
equivalent circulating density (ECD) below the fracture gradient is an important and challenging factor. On the other
hand, minimizing the ECD should be done keeping tailored mechanical properties for the set cement such as high
compressive strength and low permeability.
The second condition is a large temperature difference between the bottom hole and the top of cement, as a 3,000 m
column gives rise to a 90 degC [160 degF] difference. This condition requires the cement slurry system to be able to
build compressive strength within reasonable time while maintaining its fast gel strength development for gas
tightness properties.
Annulus between the 4 -in. tubing inside the 8 -in. open hole is two inches wide. This is a significantly wide
annulus compared to the traditional slim hole well. This third factor requires proper mud removal to ensure good
cement coverage up to the top cement. Special designed centralization is required to fit this wide annulus and
guarantee proper stand-off. Losses, wash-outs and other open hole characteristic are also considered during the job
design.
In summary, early assessment of well duration and cost saving allows to estimate the following benefits of this light slim hole
well compared to the previous traditional well profile: .
The operation to drill three-phased well shows average five days saving. This is mostly contributed by eliminating the
intermediate drilling phase.
In addition, around 700K USD would be saved due to lower consumption of casing and other accessories.
Finally further reduction of consumables and other expenditures are achieved on those five days saved.
Latest technology for the cement retarder was implemented to give optimum slurry properties on very long column of cement
with huge temperature difference. This objective was achieved and the cement was setting at about the same time all along
column, even though being under influence of higher temperature in the bottom and lower temperature at the top.
Continuing with the laboratory testing, defining the proper cement test schedules was more demanding as the conditions
required testing the slurry properties and behavior both at the bottom and at the top of cement. Extensive software simulations
allowed obtaining the temperature and pressure schedule that the first and last sack of cement would be exposed. Thickening
time was evaluated at bottom hole conditions but also for top of cement. Strength development was evaluated at bottom hole
and confirmed at upper reservoir and top of cement. Specific test schedule was defined taking into consideration the well
geothermic profile and fluid history depending on which fluid was pumped at what rate. The thickening time and strength
development schedules derived from these simulations were more realistic, as the slurry temperatures increased first from
ambient surface temperature to the cementing circulating temperature as the slurry reached bottom hole and later decreased as
it traveled up theannulus and finally remained static until and heating to geothermal temperature until setting. All laboratory
tests were implemented with these specific schedules, which permitted to improve the slurry performance and meet all
technical requirements.
Case History
A case history of the new light well architecture is given in Fig. 2. It was drilled in the Tunu field inn Mahakam Delta.
Temperature and formation are typical for that area. For simulation purposes, the bottom hole static temperature (BHST) is
taken at 145 degC and static temperature at surface casing shoe is 60 degC. The prognosed fracture gradient at bottom hole is
1.86 SG, while the maximum pore pressure is 1.15 SG. The mud weight in the 8 -in. section was 1.25 SG at bottom depth.
Well data and job conditions were input in a cementing simulator, which output the following parameters:
The circulating pressure is maintained between the pore and frac pressure as well as within the casing safety factor.
Temperature simulation is a pre-requisiste to get accurate temperature histories that cement would be exposed to during the
placement. It takes into account fluid thermal properties and heat transfer calculation inside wellbore and casing during the
circulation. This temperature history is used to tailor cement slurry testing in laboratory, rather than using traditional API
schedules or considering geothermal temperature and applying local standards. The objective is to reduce the delay for the
cement to set and develop strength at the shoe and at the top of the cement column.
The slurry design considerations for these operations called for not only realistic thickening time and compressive strength,
but also a proper control of other important parameters like rheology, fluid loss and gas tightness properties.
In terms of well control and mud removal, weighted spacer of 1.4 SG is used with optimized rheology. Spacer volume pumped
was 15 m3 [95 bbl] corresponding to 560 m of annular fill in the 4 1/2-in. x 8 -in. annulus.
The top cement requirement was 300 meter inside the 9 5/8-in. casing. Zonal Isolation was required to cover the pay zone from
bottom hole at 4,087 meters MD up to 1,127 meters MD. The well trajectory had a J- shape with inclination of about 30
degree. The 4 -in. production casing was set at 3,658 meters TVD and the cement column was 2,960 meters in length.
Designing cement properties for such conditions was a big technical and operational challenge. A single slurry system meeting
all the job requirements mentioned previously could be successfully designed.
Acknowledgments
The authors thank the management of TOTAL and Schlumberger for permitting to publish this paper. Also, special thanks to
Schlumberger Support Team and Laboratory Services in developing and introducing the new cement slurry, with additives that
were suitable to meet the light architecture well design requirements.
References
1. Gilmore, T., Harrison J., et al., Effective Slimhole Cementing in a Challenging Environment - A Gulf of Thailand
Case History, paper SPE 68671, presented SPE Asia Pacific Oil and Gas Conference and Exhibition held in Jakarta,
Indonesia, 1719 April 2001.
2. Shanks, F.E., and Willian, K.R.: Slimhole Exploration Requires Proper Technical Preparation, paper SPE 26337,
presented at the 68th Annual Technical Conference and Exhibition of the SPE in Houston, Texas, 3-6 October 1993.
3. Hibberler, J., Seymour R., Rae Phil: Faster, Deeper, Cheaper Slimhole Well Construction in the Gulf of Thailand,
paper SPE 90999, presented at the SPE Annual Technical Conference and Exhibition in Houston, Texas, 26-29 Sep 2004.
4. Pattanapong, K., Keittipong, K., et al., Lightweight cement Slurries Using Multifunctional Liquid Additives: A new
approach to offshore well construction, paper SPE 88018, presented at Asia Pacific Drilling Technology Conference, Kuala
Lumpur, Malaysia 13-15, 2004.
5. International Organization for Standard: ISO 10426-2:2003, Petroleum and natural gas industries Cements and
materials or well cementing Part 2: Testing of well cements
6. Nelson, Erik B. and Guillot, D. eds.: Well Cementing, Second Edition., Elsevier, 2007
Fig. 1 - Comparison between current SLIM HOLE and new Light SLIM Hole