Escolar Documentos
Profissional Documentos
Cultura Documentos
This paper was prepared for presentation at the SPE Asia Pacific Oil & Gas Conference and Exhibition held in Adelaide, Australia, 14 16 October 2014.
This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents
of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect
any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may
not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright.
Abstract
Optimisation of development well locations is a critical field development objective to ensure maximi-
sation of hydrocarbon production and gas plateau duration. In a large reservoir with relatively sparse well
control, significant inter-well uncertainty can exist, resulting in a high degree of subjectivity in the
selection of production well locations. Following the implementation of a comprehensive workflow to
construct multiple geologic realisations of the Brewster reservoir, a two-step process was developed to:
1) objectively identify optimum production well locations that suited a selected range of geologic models,
and 2) subjectively refine these locations to satisfy practical requirements.
Optimum well locations were initially identified using a systematic approach covering a wide range of
geologic scenarios based on an objective to maximise gas plateau duration. Resulting well locations for
each realisation were then consolidated into a single well pattern using a frequency mapping technique.
Subsequently, a subjective approach was adopted to refine these well locations based on considerations,
including targeting of structurally high points, minimum inter-well spacing, step-out from subsea drill-
centre locations, maximising the value of data acquisition (distance from existing well control) and
reducing well construction complexity (minimising lateral step-out and drilling in non-preferred azimuth).
Concurrently, optimisation of well geometry and total depth was investigated which indicated the
potential for drilling/completion cost savings with negligible impact on predicted production performance.
The integrated, multi-disciplinary nature of this methodology was paramount in effectively commu-
nicating and satisfying well planning/execution objectives between key project disciplines.
Introduction
Following the acquisition of exploration permit WA-285-P by INPEX CORPORATION in 1998, the
Ichthys Field was discovered in 2000 during an initial three-well drilling campaign, and was appraised in
two subsequent campaigns between 2003-2007. The Ichthys LNG Project is expected to produce 8.4
million tons of LNG and 1.6 million tons of LPG per annum, along with approximately 100,000 barrels
of condensate per day at peak. The final investment decision for the Ichthys LNG Project was made in
January 2012, and production licenses WA-50-L and 51-L were subsequently awarded over an area of 1,
077 km2 (Fig. 1).
2 SPE-171469-MS
Figure 5Well-Count vs Field Plateau Duration (left) & Incremental Plateau (right)
Two different initial well patterns were evaluated in Step 1 in order to reduce dependency on initial
well location assignment and impact of local heterogeneity, as shown in Fig. 4. In Step 3, some process
rules were applied: the maximum number of wells eliminated in a single step was set to be less than 10
per cent of the total well-count, and adjacent wells were not eliminated in the same step.
While several criteria could be applied to rank well performance in this process, well gas production
potential, which represents maximum production rate under prevailing production constraints, was
selected as the primary parameter of interest. This process was conducted using an automated, in-house
system which enabled multiple geologic cases to be run simultaneously.
Fig. 5 shows an example of relationships between plateau duration and well-count obtained from this
process.
SPE-171469-MS 5
Reservoir entry points were geographically refined to ensure coincidence with the highest local
structural elevation within the target area. In order to increase confidence in reservoir intersection depth,
all targets were aligned with appropriate seismic lines. A geophysical review was conducted to check
targets located in the vicinity of faults where a secondary faults network can be visible or where volcanic
material may be detected as strong impedance signatures in the main fault plane similar to a volcanic
conduit (see Schematic A in Fig. 9).
Volcanic material can be present as lava flows above the Brewster Reservoir in the Upper Vulcan
Formation (see Schematic B in Fig. 9). Based on previous experience and the expected high inclination
8 SPE-171469-MS
in some development wells, drilling is expected to be challenging in this type of environment. In addition,
due to the vertical resolution of seismic data (and as proven during the appraisal campaign), predicting the
thickness of these seismic features can have a high degree of uncertainty. Some reservoir features were
also observed due to intrusions originating from the underlying Ichthys Formation (see Schematic C in
Fig. 9), which may compromise the Brewster Reservoir interpretation. Following a review of these issues,
some wells were relocated to adjacent, lower-risk areas.
Detailed analyses of each target by the Geology, Petrophysics and Reservoir Engineering Teams
resulted in pragmatic definition of optimum Total Depth (TD) for each of the Brewster development wells.
The Petrophysics and Geology Teams proposed a practical TD based on operational considerations (LWD
string length and sensor locations, survey uncertainties), geological features (depth and thickness of
intra-formational mudstone marker, reservoir quality variation within the Brewster Member) and other
subsurface uncertainties.
Conclusions
Preliminary development well locations were selected using an objective methodology developed in-
house which enabled rapid, automated screening of multiple geologic realisations. Subjective refinement
of these locations was then conducted across multiple disciplines, including assessment of the following
issues:
Optimise reservoir intersection relative to local structural interpretation;
Avoid complex geological features that could cause drilling problems (e.g. large faults, volcanic
rocks);
Refine TD to minimise drilling cost and minimise risk of water production;
Optimise well spacing and offset from existing well control;
Consider drillability (borehole stability, azimuth, etc.), lateral step-out and optimum well incli-
nation; and
Optimise sequence of higher-/lower-risk wells for production assurance and data acquisition.
The well optimisation workflow enabled a comprehensive and logical assessment of multiple well
design variables relating to geoscience, reservoir engineering and well construction, and promoted
discussion/alignment across all disciplines.
Acknowledgements
The authors wish to acknowledge TOTAL, Tokyo Gas, Osaka Gas, Chubu Electric Power and Toho Gas
as Ichthys Joint Venture participants for their permission to publish this paper. INPEX management is also
acknowledged for support provided during the preparation and review of this document.
References
1. The Ichthys Field: Challenges of Geological Modelling for the Field Development, Nakanishi
et alet al., Australian Petroleum Production & Exploration Association (APPEA) 2014 Confer-
ence.
2. Optimal Well Placement for Production Optimisation, Wang C., Li G. & Reynolds A.C.,
SPE-111154, presented at SPE Eastern Regional Meeting, Lexington, Kentucky, 11-14 October
2007.
3. Improved Methods for Multivariate Optimisation of Field Development Scheduling and Well
Placement, SPE-49055, Pan Y. & Horne R.N., presented at SPE Annual Technical Conference
& Exhibition, New Orleans, Louisiana, 27-30 September 1998.
SPE-171469-MS 9
AUTHOR BIOGRAPHIES
Akikazu Kawasaki is Senior Reservoir Engineer at INPEX in Perth. He spent five years working on
reservoir engineering projects in Indonesia, Iraq and Australia. He gained a BS degree in 2003 and MS
degree in 2005 from Kyoto University.
Sebastien Batiot is Senior Development Geology Advisor at INPEX. He gained an M.Sc in Petroleum
Geology in IGAL France in 2000, and worked as a lead geologist with Schlumberger on Venezuela,
Algeria, Angola and Malaysia E&P projects. He joined INPEX Perth in 2012 to manage subsurface well
planning for field developments.
Andy Ion is General Manager, Reservoir Engineering at INPEX in Perth. He gained an M.Eng in
Petroleum Engineering from Heriot-Watt University in 1989 and has worked at INPEX since 2006.