Você está na página 1de 8

7.

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


MEMORIAL STADIUM
Project Features
New Stadium with 5,000 seats New Restroom Facilities
Synthetic Turf Field New Concession Stands
New Team Locker Rooms / Officials Rooms Shell Space for future Community Center
New War Memorial

Department of Engineering and Department of Parks and Recreation

Packet Pg. 12
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


MEMORIAL STADIUM
Project Schedule

Project out to bid August 10, 2017


Contract award early Winter 2017
Construction start Winter 2017
Field Completion Fall 2018
Project Completion late Summer 2019

Department of Engineering and Department of Parks and Recreation

Packet Pg. 13
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


JENNIFER ROSS SOCCER COMPLEX EXPANSION
Project Features
Three multipurpose sports fields with artificial Lake modifications for Stormwater Mitigation
surface Subsurface drainage system for extended use
Utility extensions for water, sewer and lighting Storm drainage and landscaping improvements
Concession/Restroom Facility

Department of Engineering and Department of Parks and Recreation

Packet Pg. 14
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


JENNIFER ROSS SOCCER COMPLEX EXPANSION
Project Schedule

Permitting Completion late Fall 2017


Bid opening early Winter 2017
Contract Award mid Winter 2018
Construction begin late Winter 2018
Field Completion Fall 2018
Project Completion late Fall 2018

Department of Engineering and Department of Parks and Recreation

Packet Pg. 15
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


CHARLIE BROOKS PARK EXPANSION
Project Features

New Baseball/Softball Field Batting Cages


New Multi-Purpose Field New Parking Lot (100+ spaces)

Department of Engineering and Department of Parks and Recreation

Packet Pg. 16
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


CHARLIE BROOKS PARK EXPANSION
Project Schedule

Complete design February 2018


Complete Permitting May 2018
Open Bids July 2018
Award Contract July 2018
Begin Construction August 2018

Department of Engineering and Department of Parks and Recreation

Packet Pg. 17
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


THOMAS AVENUE FOOTBALL FIELDS
Project Features
Five new football fields New Irrigation
Aluminum Bleachers Gravel Drive and Parking Lots
ADA Accessible Site New Parking Lot (100+ spaces)

Department of Engineering and Department of Parks and Recreation

Packet Pg. 18
7.1

SPLOST RECREATIONAL PROJECTS

Communication: Status of County's athletic fields. (Requested by Commissioner Farrell.)


THOMAS AVENUE FOOTBALL FIELDS
Project Schedule

Complete design Winter 2018


Complete Permitting Spring 2018
Open Bids Summer 2018
Award Contract Summer 2018
Begin Construction Late Summer 2018

Department of Engineering and Department of Parks and Recreation

Packet Pg. 19