LNG Regasification Terminal - Tanjung Priok (Indonesia Power)

No. Equipment Quantity Unit Cost


1 Installed Ship (FSU) 1 $ 47,352,822.42
2 Buffer tank 1 $ 7,500,000.00
3 Submerge pump 2 $ 23,686.95
4 BOG compressor dual stage 2 $ 472,275.18
5 LNG HP pump 2 $ 61,844.26
6 Sea water pump 2 $ 129,039.92
7 BOG recondenser 1 $ 1,837,835.96
8 Vaporizer 2

Engineering & Construction cost (30%)


(no. 3-8)
Electrical & Instrumentation cost (10%)
Total Cost

harus cari dimensi kapal


belum ada data
ung Priok (Indonesia Power)
Cost Source
$ 47,352,822.42 SER & Lampung FSRU
$ 7,500,000.00 IGU
$ 47,373.89 Nikkiso Cryo/ Bolivian LNG
$ 944,550.35 Nikkiso Cryo/ Bolivian LNG
$ 123,688.53 Nikkiso Cryo/ Bolivian LNG
$ 258,079.83 SEIDER
$ 1,837,835.96 IGU/SEIDER
$ -
$ 58,064,350.99
$ 963,458.57 Western LNG Terminal Associate

$ 5,806,435.10 Western LNG Terminal Associate


$ 64,834,244.66
volume price
Tank 5000 m3 1,500 USD/m3
recondenser 500 m3 7,500,000 USD
67.06 m3 1,837,836
HP LNG pump 11500 m3/h 1,100,000 USD
188.3 m3/h 61,844
SW pump 893.4256 m3/h 96,500 USD
1353.13 m3/h 129,040
BOG compressor 609.7 lbmol/hr 2,000,000 USD
77.56 472,275
LP LNG Pump 11500 m3/h 425,000 USD
185.9691 23,687
Installed ship 25000 m3 29,994,043 USD
48000 m3 47,352,822 USD
IGU
IGU/Seider

Nikkiso Cryo/ Bolivian LNG

seider

Nikkiso Cryo/ Bolivian LNG

SER & Lampung FSRU