Você está na página 1de 27

Disclosure to Promote the Right To Information

Whereas the Parliament of India has set out to provide a practical regime of right to
information for citizens to secure access to information under the control of public authorities,
in order to promote transparency and accountability in the working of every public authority,
and whereas the attached publication of the Bureau of Indian Standards is of particular interest
to the public, particularly disadvantaged communities and those engaged in the pursuit of
education and knowledge, the attached public safety standard is made available to promote the
timely dissemination of this information in an accurate manner to the public.

1 +, 1 + 01 ' 5
Mazdoor Kisan Shakti Sangathan Jawaharlal Nehru
The Right to Information, The Right to Live Step Out From the Old to the New

IS 5613-3-2 (1989): Code of Practice for Design,


Installation and Maintenance of Overhead Power Lines, Part
3: 400 kV Lines, Section 2: Installation and Maintenance
[ETD 37: Conductors and Accessories for Overhead Lines]

! $ ' +-
Satyanarayan Gangaram Pitroda
Invent a New India Using Knowledge

! > 0 B


BharthariNtiatakam
Knowledge is such a treasure which cannot be stolen
IS 5613 ( Part 3/Set 2 ) : 1988

Indian Standard
I
.-
--*
t CODE OF PRACTICE FOR DESIGN,
INSTALLATION AND MAINTENANCE OF
OVERHEAD POWER LINES
PART 3 400 kV LINES
Section 2 Installation and Maintenance

UDC 62131517

@ BIS 1990

BUREAU OF INDIAN STANDARDS


MANAK BHAVAN, 9 BAHADUR SHAH ZAFAR MARO
NEW DELHI 110002

Janwy 1990 Price Group 8

I
*--
Conductors and Accessories for Overhead Lines Sectional Committee, ETDC 60

FOREWORD
This Indian Standard ( Part 3/Set 2 ) was adopted by the Bureau of Indian Standards on 23 March
1989, after the draft finalized by the Conductors and Accessories for Overhead Lines Sectional
Committee hed been approved by the Electrotechnical Division Council.
The present strategy for development of power has necessitated a rapid development of extensive EHV
network covering the whole country. After successful introduction of 220 kV system in the country, F
400 fV has been adopted as the next higher system voltage after detailed techno-economic studies.
For development of 400 kV network, this code provides, in addition to specifying the good practices
for EHV lines, gives the detailed requirements with respect to 400 kV lines in particular.
IS 5613 _(Part 3/Z&c 2 ) : 1989

Indian Standard
CODE OF PRACTICE FOR DESIGN,
INSTALLATION AND MAINTENANCE OF
OVERHEAD POWER LINES
PART 3 400 k V LIN E S
S e c tion 2 I n s t a ll a t i o n a n d M a i n t e n a n c e

1 SCOPE should be obtained along with a true assessment of


problems facing procurement of right-of-way
1.1 This code ( Part S/Set 2 ) covers installation and way leaves for access, and compensation
and maintenance of 400 kV transmission lines. required to be paid.
2 REFERENCES 4.4.1 Compensation to the Owners
2.1 The Indian Standards listed in Annex A are Compensations to the owners for damage of crops,
necessary adjuncts to this standard. fruit trees and other vegetation, if required, should
be evaluated with the help of the Revenue
3 TERMINOLOGY Authorities and paid accordingly.
3.1 For the purpose of this code, the definitions 4.5 Local Laws
given in IS 1885 ( Part 30 ) : 1971 and the Indian
Electricity Rules, 1956 shall apply. The~information about the local laws should be
obtained in advance in order that there is no
4 EXCHANGE OF INFORMATION infringement of prevailing local laws and to ensure
smooth installation, operation and maintenance
4.1 General work.
A proper design of transmission line and its 5 GENERAL REQUIREMENTS
supporting structures, insulators, conductors, etc,
should be finalized on the basis of relavant Indian 5.1 Materials and Equipment
Standards. Detailed specifications shall be prepared
All materials, fittings, etc, used in the installation
for individual items before~ordering the materials.
and also the construction tools and equipment
4.2 Transport Limitations shall conform to the relevant Indian Standards
wherever they exist. In cases where there is no
Information about transport limitation particularly Indian Standard available, the items shall conform
for line materials should be obtained from rail to the specifications mutually agreed between the
road or navigation authorities where required. purchaser and the manufacturer.
This may involve procurement of special trailers
or alternatively restricts the size and weight of the 5.2 Compliance with Indian Electricity Rules and
package in uneven terrain where head-loading is Other Authorities Regulations
more often resorted to. All overhead lines shall comply with the require-
ments of the Indian Electricity Act and Rules made
4.3 Terrain and Weather Conditions
thereunder and the regulations or specifications
Information on this is necessary in order to as laid down by Railway Authorities, Post and
procure right type of installation tools and material Telegraphs Department, Roadway, Navigation or
handling equipments. Aviation Authorities, Local Governing Bodies,
Defence Authorities, Power and Telecommunica-
4.4 Right-of-Way (ROW ) and Access Requirments tions Co-ordination Committee, Forest Authorities
and Oil & Gas Authorities, wherever applicable.
Having decided on the choice of route ( see 4 of Ralevant matters requiring attention of such
Section 1 of this standard ), it is necessary to authorities should be referred to them before
inspect right-of-way before starting any construc- planning the layout, installation and during con-
tion work on the line. Information on vegetation struction work. Such refenences, however, be

1
IS 5613 ( Part 3/Set 2 ) : 1989

made by the owner of the installations and within lines, rivers, canaIs and important roads, power
appropriate time so as to ensure smooth progress. and telecommunication lines, oil and gas pipe
lines, etc, up to 8 kms on either side of the-route of
5.3 The transmission line installation shall be the line shall be drawn to the scale with longitude
carried out by trained and experienced personnel and latitude properly marked. Route near the
and supervised by technically qualified persons
towers or for railway line crossings or for certain
competent to undertake such work. stretches where the proposed lint route runs
5.4 Scope of Work parallel to existing power/telephone lines, shall be
drawn to the scale of I : 20 000, if required by the
Installation of overhead line includes waIk-over concerned authorities for containing necessary
survey laying out the line ( route alignment ); clearances. Jf considered necessary, a key map to
detailed and check survey; clearing the work site a scale of I : 200 000 may be prepared showing the
and line route; making access roads; civil con- main sections of the line in addition to the above.
struction work of foundations, etc, erection of
line; all connected material transport and handling 6.2.1 For convenient handling in the field, the
till the line is ready for use; testing and com- maps should be made on sheets of ~3OOxI 190 mm,
missioning or taking over. with 3~cm overlap shown on the subsequent sheets.
6.3 Clearing Right-of-Way ( ROW ) and Access
6 SURVEY
Roads
6.1 Walk-Over Survey The trees essentially required to be removed for
Before starting the detailed survey a walk-over carrying out detailed survey be cleared, followed
survey of the line shall be made. The various by complete clearing of ROW based on the actuaI
feasible routes shall be ascertained and marked on route adopted. The clearing should be carried out
the toposheet. both in the legal and physical sense. If any com-
pensation has to be made on crops, it shall be
6.2 Route-Aligpment Map accounted for the period till the installation work
On completion of walk-over survey, a route-align- is to be over according to programme.
ment map shall be prepared to a scale of 1: 50 000. 6.3.1 Clearing may be done in accordance with
All the topographical details including all railway Fig. 1.

MAXIM&i SWING
MINIMUM ELECTRICAL
CLEARANCE 3

NOTE - Portion of tree falling within clearance zone to be lopped or trimmed.


FIG. 1 LINE CLEARANCE ( RIGHT-OF-WAY ) REQUIREMENTS

2
IS :5613 ( Part. 3/Set, 2 ) : 1989

6.3.2 Taking into considera.tion the theoretical All topographical details, permanent features such
requirement of right-of-way .and transport require- as road buildings, etc, w.ithin the rightof-way shall
ments of maintenance, the following right-of-way be marked on the profile plane.
width for 400 kV lines are recommended:
6.4.1 From the field book entries, the ruute. plan
For single circuit line 50 m ( under and level profile, commonly referred to as survey
For double circuit line 3 consideration ) chart shall be plotted and prepared to the scales
of 1 = 2 000 horizontal and 1 = 200 vertical on
6.3.3 While routing the transmission line, care 1 mm/5 mm/l cm square papers or formed tracing
shall be taken to avoid restricted areas such as graph papers made for the purpose. The entire
civil and military airfields, coal bearing areas on survey work shall be cross-checked with respect to
quarry sites, tea, tobacco, saffron field and any the Standard Bench Marks.
other tmportant plantation scheme, etc. Special
care shall be taken to avoid routing the line 6.4.2 If the difference in level is very ,high, the
through protected/reserved forest areas. If chart may be broken up according to requirments.
avoidance~of the forest stretches is not possible, A 1 cm overlap shall be shown on each following
the proposals, in the prescribed format as required section and on each following sheet. The chart
by state/central forest authority, for obtaining the shall progress from left to right. For convenience
requisite clearance from the forest authority, shall in handling the sheet size may be limited to
be submitted by the owner of the installation. 420 x 1 190 mm or 590 x 1 190 mm depending
on whether profile is for plains or hills respectively.
Each section shall be started on a new sheet.
6.4 Detailed Survey
6.4.3 Bearing strength, density and angle of repose
Detailed survey shall be conducted on the approved of the soil shall also be determined in accordance
alignment. The choice of the method of survey, with the standard test methods at the time of
namely: theodolite or aerial survey considered, detailed survey for different type of terrain through
convement, shall be left to the surveying party. In which line traverses,
hilly region, level of ground at a suitable distance
below the outer conductor on either side from the 6.5 Sag Template and Tower Spotting
centre line is also to be noted and marked in pro-
file so as to ensure required ground clearance A typical sag template is-shown in Fig. 2 and the
underneath conductor and side clearances in swung method of its preparation and application for
conditions of conductor. tower spotting is given in Annex B.

1 represents cold template or uplift curve


2 represents hot template or maximum sag curve
3 represents ground clearance curve
4 represents support foot curve
IMRT Central Line represents Right Offset Level
IMLT Central Line represents Left Offset Level

FIG. 2 SAG TEMPLATE

3
IS 5613 ( Part 3/Set 2 ) : 1989

6.5.1 While locating the towers on survey charts, the same voltage or Iower voltage, suspension/
the following shall be borne in mind: tension tower with suitable extensions shall be
used ( Refer Table 1 );
-a) Maximum length of a section shall not exceed
5 km. Telecommunication Iine crossing

b) The intermediate spans shall be as near as The angle of crossing shall preferably be 90.
possible the normal design span. In case an However, deviation to the extent of 30 may
individual span becomes too short on account be permitted under exceptionally difficult situa-
of undulations in ground profile, one or more tions. When the angle of crossing is below -6O,
line supports of the section may be extended the matter shall be referred to the authority
by inserting standard body extension designed inchage of the telecommunication system. Also,
for the purpose according to technical specifica- in the crossing span, power line supports shall
tions to bring the intermediate span as near as be as near the telecommunication line as
possible to the design span; possible, to obtain increased vertical clearance
between the wires; and
d There shall not be any upward force on
suspension tower under normal working con- Requisite clearance to foreign objects shall be
dition, and the suspension towers shall support maintained.
the minimum weight span as provided in the
designs. In case uplift is unavoidable, it will be 6.6 Chesk Survey
examined if the same may be overcome by
adding standard body extensions to the towers, This will be conducted to make a check on detailed
failing which tension towers designed for the survey and to locate and peg marks the tower
purpose shall be employed at such positions; positions on ground conforming to the survey
charts. In the-process it is necessary to have the
d) Tower spotting shall be tfurther checked by pit centres marked according to the excavation
means of tower capacity charts approved by marking charts. The levels, up or down, of each
the purchaser; pit centre with respect to the centre of the tower
location shall be noted and recorded for determin-
4 Road crossing.
ing the amount of benching or earthwork required
At all important crossings, the towers shall be to meet design requirements of the~foundation.
fitted with normal suspension or tension insu-
lator strings depending on the type of towers 6.6.1 If the levels of the pit centres be in sharp
but the ground clearance at the roads under contrast with the level of the tower centre ( say
maximum temperature and in still air shall be beyond a slope of 1 : 4 ), suitable leg extensions
such that even with conductor bundle broken may be deployed as required.
in adjacent span, the ground clearance of the 6.6.2 For the sake of reference,the pits of a tower
conductor from the road surface shall not be shall be designated as shown in Fig. 3.
less than 884 metres. At all national highways
tension towers shall be used. The crossing 6.7 Tower Schedule
span, however, shall not exceed 25 metres in
any case; A tower schedule shall be prepared for planning of
materials. The proforma shall be made on a
Railway crossings convenient sheet size of 280 x 508 mm. Tower
schedule shall further be checked by means of the
For railway crossings, towers shall be of tower capacity charts approved by the purchaser.
tension type and railway crossings construction If the limits are exceeded anywhere, the spotting ,
shall conform to the regulations laid down by should be relocated by trials.
Railway Authorities;
6.7.1 Along with the tower schedules, a line
g) River crossing
schedule should also be prepared which should
In case of major river crossings in planes, tower cover in detail the total quantity of all line
shall be of suspension type using double materials required and the quantity in which these
suspension strings and the anchor towers on are required at various points on the line.
either side of the main river crossing shall be
dead end type. Clearance required by navigad 7 MATERIAL TRANSPORT
tion authority shall be provided. For non- 7.1 All material transport shall be undertaken in
navigable rivers clearance shall be reckoned vehicles suitable_for the purpose and free from the
with respect to highest flood level (HFL); effects of any chemica1 substances. Tower members
h) Power line crossings shall be loaded and transported in such a manner
that these are not bent intransit and sharp-hent
Where a line is to cross over another line of members are not opened up or damaged.

4
IS 5613 ( Part 3/Set 2 ) : 1989

REdEILING...END
t NAME OF SUBSTATION )

4
LL

SENDING (FEEDING) END


(NAME OF SUBSTATION)

1 represents leg or pit No. 1 A represents near side (NS) transverse face
2 represents leg or pit No. 2 B represents near side (NS) longitudinal face
3 represents leg or pit No. 3 C represents far side (FS) transverse face
4 represents leg or pit No. 4 D represents far side (FS) longitudinal face
NOTES
1 Danger and number plates are located on face A
2 Leg 1 represents the leg with step bolts and anti-climb device gate, if any.
If two legs with step bolts are required, the next is No. 3 leg.
FIG. 3 DESIGNATION OF TOWER LEGS, FOOTINGSAND FACES

Conductor and earthwire drums shall be handled necessary inthe case of undercut foundations. The
carefully, so that the drums-and their contents are depth of the excavation at the pit centre shall be
not damaged. measured with reference to the tower centre level.

8 FOUNDATION 8.1.2 Shoring and Struttinp


8.1 The construction of tower foundations shall
be in accordance with IS 4091 : 1979. Shoring and strutting shall be done keeping in
view the requirements given in IS 3764 : 1966. In
8.1.1 Pit Marking pits excavated in sandy soil or water bearing strata
Pit marking shall be carried out according to tower and where there is every likelihood of pits collaps-
schedule chart. The pit size in the case of open ing, shoring and strutting shall be made out of
cut foundation shall be determined after allowing timber planks or steel frames of adequate strength
a margin of 150 mm all round. No margin is to suit the requirements.

5
IS 5613f Part 3jSec 2 ) : 1989

8.1.3 Dewatering centre punch or chisel markings on the ffanges


and heel at the centre line positions of standard
The guidelines for dewatering during construction height towers as well as heights extended with
specified in IS 9759 : 1981 shall be kept in view. standard body extensions. The plumb bob shall
Dewatering shall be carried out manually by be dropped from these reference points which shall
mechanical pumps or power driven pumps to be pre marked at the shops. The same template
facilitate excavation and casting of foundation. shall preferably be suitable for setting stub posi-
The pums shall be suitable for handling mud tions for various tower heights. In case of hill
water. The pits shall also be kept dewatered till side extension, a section of tower body may be
24 hours of concreting-the foundations. Dewatering used as template. For maintaining accuracy of
is not necessary in case-of bored foundations below setting, squaring and the slope, the plan diagonals
water table. These are stabilized by drilling muds and bracket pieces shall be fitted withthe template.
and concreted by displacing the drilling mud.
10.2 Assembly and Check
8.1.4 Excavations in Rock
Assembly shall be made on adjustable screw jacks
The provisions given in IS 4081 : 1986 shall be resting over compact ground. Initial levels shall
followed. For excavations in hard rock, blasting Abemade with an accurate long bubble spirit level
can be resorted to. Reference shall be made to and template shall be centred properly bringing
statutory rules for blasting and use of explosives the side and diagonal measurements equal accord-
for this purpose. No blasting is permitted near ing to design drawing. Levels and alignment
permanent work or dwellings. Blasting shall be shall once again be checked after pouring slab/
so made that pits are as near to the designed pyramid concrete and before pouring chimney
dimensions as practicable. Jack hammers can also concrete and adjusted for differences, if any.
be used in the excavation work.
10.2.1 The allowable tolerances on template setting
8.1.5 All excavated material shall be dumped shall be as given in Annex C.
at least 1 to 2 metre away from the pits, preferably
10.2.2 In case due to collapsed pits the template
in diagonal directions, keeping the space along the
may not be fitted on jacks, the same shall be
centre lines free for foundation work. Care shall
assembled with stubs resting over 1 : 2 : 4 plain
be taken that no moving vehicles or heavy equip
cement concrete blocks in comparatively green
ment are drawn too near the excavated pits.
condition cast at the site with a 300 or 450 mm
9 CLASSIFICATION OF SOIL square base and a depth equal to the designed
concrete cover under stab.
9.1 CJassification of soil shall be made according
to IS 1498 : 1970 for footings cast in open pits. The sides of the blocks shall be rough cast while
It shall, however, be noted that for all the classi- the top shall be smooth for this purpose these
fications Iisted therein the soil may be dry or wet. may be cast in wetted pits made in ground. These
blocks shall remain in position and shall form
9.2 Dry soil shall be that wliere subsoil water is integral part of the foundation concrete. The
met below the foundation base. In the wet templates should remain in position far not less
category, classifications shall be as under: than 24 hours and it should not be removed before
back-filling is done.
a) Wet
Where sub-soil water rises in the pit up to 11 CONCRETE
15 m below ground level; or where there is
water over the ground for long periods but 11.1 Type
does not penetrate beyond 1 m below
ground such as paidy fields; For reasons of-economy and progress it is normal
practice to use coarse and fine agreegates available
b) Partially submerged along with line route and/or nearest locations to
Where water rises in the pit within 075 m the route. A such, it is not practicable to design
below ground level; and the concrete mix and use controlled concrete.
Moreover, since the quantity of concrete involved
C) Fully submerged is rather small, ordinary plain or reinforced
Where sub-soil water rises in the pit below cement concrete given in IS 456 : 1978 shall be
ground level. used in overhead line foundations.
1D STUB-SETTING ( OR TOWER FOOTING ) 11.2 Mixes
10.1 For the purpose of stub-setting, the top For main foundation, M 150 or 1 : 2 : 4 mix
chord pieces of the adjustable frames shall have cement concrete shall be used. For lean concrete

6
IS 5613 ( Part 3/&c 2_) : 1989

sub-bases or pads, M 100 or f : 3 : 6 mix cement


concrete may be used. The properties of concrete
and mix proportions shall be as given in
IS 456 : 1978.
It shall be permissible to proportionate the con-
crete as follows:
a) Prepare a wooden measuring box of ~35
litres capacity ( that is, equal to 1 bag or
50 kg of cement ) with inside dimensions of
( not exceeding 30 x 30 x 30 cm ) alternati-
vely 34 cm diameter and 39 cm height.

The mix quantities according to the measuring


box shall be as follows:
M 150 M 100
Cement 1 bag 1 bag
Sand 2 boxes 3 boxes FIG. 4 FORM WORK FOR SLABS/PYRAMIDS
Stone 4 boxes 6 boxes
Water 1 box less 1 box less removed from the interior of the forms before
3 litres 1 litre the concrete is placed. The surface in contact
with the concrete shall be wetted and sprayed
b) Measurement of water may be made with with fine sand, or treated with an approved com-
separate water-tight drums of the above size position before use, every time. Concreting to be
or with l- or 2-litre mugs. done for cold weather shall be as per IS 7861
NOTE - For concreting the bored foundations by ( Part 2 ) : 1981.
displacing the drilling muds, 10 percent extra
cement in the mix is required. 11.3.4 Stripping Time
112.1 One bag of cement is taken to contain 50 Under fair weather conditions ( generally where
kg or 35 litres of ordinary portland cement. average daily temperature is 20C or above ), and
where ordinary cement is used, forms may be
11.3 Form Work struck after 24 to 48 hours of the placing of
11.3.1 General concrete. In dull weather such as rainy periods
very cold temperature, the forms shall be struck
The form work shall conform to the shape, lines after 48 hours of the placing of concrete.
and dimensions as shown on the design drawings,
and be so constructed as to be rigid during the 11.3.5 Procedure When Removing Form Work
placing and compacting of concrete, and shall be
sufficiently tight $0 prevent loss of liquidfrom All form work shall be removed without such
concrete. It shall be of light design easily remo- shock or vibration as would damage the concrete
vable without distortions and shall be of steel or the forms..
hardwood or framed plywood. The inner surface 11.4 Back Filling
coming in contact with concrete shall be smooth
and free from projections, Window on one face Following opening of form work and removal of
L
shall be provided for pyramid forms to facilitate shoring and strutting, if any, back filling shall be
I
concreting in the lower parts which shall %e fixed started after repair, if any, to the foundation
after concrete in the bottom part is placed. In concrete. Back filling shall normally be done
bored footings form work may be needed only with the excavated soil, unless it consists of large
towards the top for the portion above ground boulders/stones, in which case the boulders shall
level. be broken to a maximum size of 80 mm. The back
filling materials should be clean and free from
11.3.2 The form work for slabs and pyramids
organic or other foreign materials. The earth
shall be made symmetrical about the base of the
chimney to ensure interchangeable. faces as shall be deposited in maximum 200 mm layers,
levelled and wetted and tamped properly before
illustrated in Fig. 4. another layer is deposited. Care shall be taken
11.3+3 Clearing and Treatment of Forms that the back filling is started from the foundation
ends of the pits, towards the outer ends. After
All rubbish, particularly chippings, shavings and pits have been back filled to full depth, the stub
sawdust and traces of concrete, if any, shall be template may be re,moved.

7
IS 5613 ( Part 3/Set 2 ) : 1989

The back filling and grading shall be carried to eonerete chimney for curing and ensuring that the
an elevation of about 75 mm above the finished bags are kept wet by the frequent pouring of water
ground level to drain out water. After back filling on them.
50 mm high earthen embankment ( bandh ) will
be made along the sides of excavated pits and 11.9 Measurement of Conerete
sufficient water ~111 be poured in the back filled
earth for at least 24 hours. Except where actual pit size concrete is required
( such as in a rock foundation ), the volume of
11.5 Reinforcement concrete shall be calculated from the design
drawings. All volumes shall be expressed to the
All reinforcement shall be properly placed a&ord-
nearest cubic metre. The heights used for calcu-
ing to design drawing with a minimum concrete
lating concrete volumes shall be the projected
cover of 50 mm. The bars shall, however, be placed
clear of stubs and cleats where interfering. For heights used and not those following the tower
slope; the top of the pyramid concrete shall be
binding, iron wire of not less than 09 mm shall
be employed, and the bars may be bound at considered to be same as the chimney cross section
alternate crossing points. The work shall conform for purpose of calculating the volumes, even
though it is greater on account of the chimney
to IS 2502 : 1963 wherever applicable. For bored
slope.
footings, stub angle shall be used as reinforcement.
11.9.1 The method of measurement of concrete
In case of the foundation having steel reinforce- for pile foundations is given as below.
ment in pyramid on base slab, at least 50 mm
thick pad of lean concrete of 1 : 3 : 6 nominal mix 11.9.1.1 Approximate volume of short bored
shall be provided to avoid the possibility of rein- under-reamed piles is calculated by the following
forcement rod being exposed due to unevenness of formula:
the bottom of the excavated pit.
Volume in cubic metre
11.6 Sizes of Aggregates
=-[LLa+04n(d,--)(~--k)l
The coarse aggregates ( stone ) to be used shall be
single size aggregates of 40 mm nominal size for ( see Fig. 5 )
slab/pyramid concrete and 20 mm nominal size
for chimney concrete conforming to IS 383 : 1970. -where
These sizes are applicable to ordinary plain cement L = total length of pik in metres;
concrete for RCC the aggregates shall preferably
be of 20 mm nominal size. The fine aggregate d = diameter of pile shaft in metres;
( sand ) shall be of Zone I Grade to tS 383 : 1970
du = diameter of under-ream in metres ( 2 or
which i$ the coarse variety with maximum particle
3 times d ), normally 25 d; and
size of 475 mm. Zone II Grade of fine aggregates
may also be used. n = number of under-reams.
11.7 Gravel Sub-base Distance between two under-reams - lS5 to
In case the foundation happens to be over fine 15 du ;
sand, 80 mm thick gravel sub-base may be Spacing between piles = 20 d, ; or 15 du with
provided, if considered necessary, under the foun- 10 percent reduction in capacity.
dation. The maximum size of gravel or stone to be
used shall be 80 mm. 11.10 Mixing, Placing and Compacting of Concrete
11.8 Curing This shall be carried out according to the
procedure laid down in Annex D.
The concrete after setting for 24 hours old shall
be cured by keeping the concrete wet continuously 12 PROTECTION OF TOWER FOOTING
for a period of 10 days after laying. The pit may
be back filled with selected earth sprinkled with 12.1 The work shall include a11 necessary stone
necessary amount of water and well consolidated revetment, concreting and earth filling above
in layers not exceeding 200 mm of consolidated ground level and the clearance from stacking on
thickness after a minimum period of 24 hours the side of all surplus excavated soil, specia1
and thereafter both the aback filled earth and measures for protection of foundations close to
exposed chimney top shall be kept wet for the or in nallahas, river ~beds, etc. by providing suita-
remainder of the prescribed time of 10 days. The hle revetment or galvanized wire netting and
uncovered concrete chimney above the back filled meshing packed with boulders. The contractors
earth shall be kept wet by providing empty cement shall furnish recommendations for providing proteo
bags dipped in water fully wrapped around the tion at such locations.

8
IS 5613 CPart 3/Set 2 ) : 1989

a lug for connection to the tower leg at one end.


The wires are connected to each of the legs and
taken radially away from the tower and embedded
horizontally 1 m below ground level. The length
of each wire is normally limited to 25 m, but may
be increased if the resistance requirements are not
met. The size of the galvanized steel stranded
wire may be taken equal to the sizes of the earth
conductor. A typical example of counterpoise
type earthing of tower is given in Fig. 7.
14 TOWER ERECTION
14.1 General
Towers shall be erected after the concrete is at least
14 days old, but a gap ~of 28 days shall be
preferred.
14.2 Inspection and Sorting Out
The members shall be examined for defects in
protective surface finish, if any. If any defects
are found in case of hot dip galvanized members,
the damage shall be repaired by applying two
coats of zinc-rich paint having at least 90 percent
zinc content conforming to relevant Indian Stand-
ard after cleaning the surface and ensuring that
FIG.5 TYPICALDETAILS OF UNDER- the surface is ~dry before the application of the
REAMED PILES paint. Members bent in transit shall be straight-
ened such that the protective surface finish is not
13 EARTHING damaged.
13.1 Each tower shall be earthed after the founda- All the members shall be sorted out properly
tion has been cast. For this purpose, earth strips at the erection ~site to check that all items are
shall be fixed to the stub during concreting of the available; and shall be placed in a manner such
chimney and taken out horizontally below the that they are easily located during erection.
ground level. In normal circumstances, the earth
strip shall be provided on No. 1 stub leg as given 14.3 Treatment of Joints
in Fig. 3, that is, the leg with step bolts.
Before starting assembly, specially for the lines in
13.2 The resistance of tower to earth shall not coastal or highly polluted areas, the surfaces at
exceed 10 ohm after earthing and tower erection connection points shall be applied a coat of
but before stringing of the overhead ground wire. aluminium or zinc-rich paint in case of galvanized
In case, the resistance exceeds the specified values, members, and red oxide or zinc chromate paint in
multiple pipe earthing or counterpoise earthing case of painted members.
shall be-adopted in accordance with the following
procedure, but without interfering with the founda- 14.4 Assembly
tion concrete even though the earth strip/counter-
poise lead remains exposed at the tower end. The Irrespective of the method followed for the erection
connections in such case shall be made with the of towers, the points mentioned below shall be
existing lattice member holes on the leg just above observed: /
the chimney top. a>Straining of the members shall not be per-
13.3 Pipe Earth mitted for bringing them into position. It
may, however, be necessary to match hold
The installation of the pipe earth shall be in accor- positions at joints and to facilitate this,
dance with IS 3043 : 1987. A typical example tommy bars not more than 450 mm long
of earth in equipment ( pipe type ) is given in may be used.
Fig. 6.
13.4 Counterpoise Earth
b) Before starting erection of an upper section
the lower section shall be completely braced
Counterpoise earth consists of four lengths of and all bolts fitted in accordance with
galvanized steel stranded wires, each fitted with approved drawings.

9
IS 5613(Part 3/!&c2):1989

2 BOL

Sx-6-OmmlMK:Kx5m LO

-6 mm c# OPEN HO

MATERIAL LIST

Quantity Description Length Weight


(mm) (kg)
1 25 mm bore GI pipe 3 000 1188
1 45 x 6mmMSffat 5 oao 1550
2 16 mm dia bolts with nuts 38
2 16 mm dia bolts with nuts To Suit stub -
4 Plain washer for 16 mm dia bolts 0.16
NOTES
1 All ferrous parts are hot-dip galvanized
2 In case of difficult location, horizontal Or slant laying of pipe aad iaying, within the tower base
or fundation pit shall be permissible.

All dimensions in millimetres.

FIG. 6 A TYPICALEXAMPLE OF EARTHING EQUIPMENT

10
IS 5413 ( Part 3/See 2 ) : 1989

been inserted under each nut. In case of step


bolts, spring washer shall be placed under the
outer nut. The tightening shall progressively be
carried out from the top downwards, care being
taken that all bolts are at every level are tightened
simultaneously. It may be better to employ four
persons, each covering one leg and the face to his
left.
14.5.1 The threads of bolts projecting outside nuts
shall be punched at three positions on the diameter
to ensure that the nuts are not in loosened course
of time. If during tightening a nut is found to be
d
LABLE
slipping or running over the bolt threads, the bolt
together with the nuts shall be changed out-right.
14.5.2 The threads of all the bolts projected out-
TERMINALS 6mm THICK side the nuts~shall be welded at two diametrically
I- opposite places. The length of each welding shall
JOINT SOLOERED be at least 10 mm. The welding shall be provided
OR COMPRESSED
1from ground level to waist level for single circuit
towers and to bottom cross-arm level for double
circuit towers. After welding cold galvanizing
i paint with at least 90 percent zinc content shall be
1applied to the welded portion.
713-O STEEL CONDUCTOR
OR AS AVAILABLE .
14.6 Replacement
If any replacements are to be efYe&d after string-
All dimensions in millimetres. ing and tensioning or during maintenance, leg
members and main bracings shall not be taken out
FIG. 7 TYPICAL EXAMPLEOF COUNTERPOISE without reducing the tension of the tower with
TYPE OF EARTHING OF TOWER proper guying or releasing the conductor. If the
replacement of cross-arms becomes necessary after
All plan diagonals relevant to a section of stringing the conductor shall be suitably tied to
tower shall be placed in position before the tower at tension points or transferred to
assembly of upper section is taken up. suitable roller pullies at suspension points.
All bolts shall have theirnuts facing out- 15 INSULATOR HOISTING
side of the tower for horizontal or nearly
horizontal bolt connections and downwards 15.1 Suspension insulator strings shall be used on
for vertical bolt connections. suspension towers and tension insulator strings on
angle~and dead end towers. The strings shall be
4 The cross-arms may be assembled on ground fixed on the tower just prior to the stringing of
and the top cross-arm shall be lifted first,
followed by the middle and bottom cross- conductors. Damaged insulators and fittings, if
arms. The tips shall be fully tightened any, shall not be employed in the assemblies.
before lifting them into position. Such Before, hoisting, all insulators shall be-cleaned in
bolts which are not assessible for tightening a manner that will not spoil, injure or scratch the
by ordinary tommy spanners, may be surface of the insulator, but in no case shall any
tightened with the help of box or ratchet oil be used for the purpose. Corona control
ring spanners. rings shall be fitted in an approved manner. The
yoke arrangements shall be horizontal for tension
f) All the blank holes, if any left, after com- and longitudinal for suspension strings.
plete erection of tower, are to be filled up
by bolts and nuts of correct size. 16 HAPTFLING OF CONDUCTOR AND
EARTHWIRE
14.5 Tightening and Punching of Bolts and Nuts 16.1 While running out the conductors care shall
All nuts shall be tightened properly using correct be taken such that the conductors do not touch
size spanners. Before tightening it will be seen and rub against the ground or objects which could
that filler washers and plates are placed in relevant cause scratches or damage to the strands. The
gaps -between members, bolts of proper size and conductors shall be run out of the drums from the
length dare inserted, and one spring washer has top in order to avoid ~damage due to chafing.

11 *
IS 5613 ( Part 3/Set 2 ) : 1989

Immediately after running out, .the conductor 16.6 Derricks shall be used where roads, rivers,
shall be raised at the supports to the levels of the channels, telecommunication or overhead power
clamp and placed into the running blocks. The lines, railway lines, fences or walls have to be
groove of the running blocks shall be of such a crossed during stringing operations. It shall be
design that the seat is semi-circular and larger seen that normal services are not interrupted or
than the diameter of the conductor earthwire and damage caused to property. Shut down shall~be
it does not slip over or rub against the sides. obtained when working at crossing of overhead
The grooves shall be lined with hard rubber or power lines.
neoprene to avoid damage to conductor and shall
be mounted on properly lubricated bearings. 16.7 The sequence of running out shall be from
top to downwards, that is, the earthwire shall be
16.2 The running blocks shall be suspended in a run out first, followed by the conductors in
manner to suit the design of the cross-arm. All succession. Unbalances of loads on towers shall
running blocks especially those eat the tensioning be avoided as far as possible. Outer phases of
and, will be fitted on the cross-arms with jute line conductor-shall be strung before the stringing
cloth wrapped over the steel work and under the of the middle phase is taken up.
slings to avoid damage to the slings as well as to
the protective surface finish of the steel work. In 16.8 The proposed 400 kV transmission line may
case suspension or section towers are used even run parallel for certain distance with the existing
for temporary terminations, if this be unavoidable, 220 kV, 132 kV lines which may remain energized
they shall be well guyed and steps shall be taken during the stringing period. As a result there is
to avoid damage. The drums shall be provided a possibility of dangerous voltage build up due to
with a suitable breaking device to avoid damages, electromagnetic and electrostatic coupling in the
loose running out and kinking of the conductor. pulling wire conductors and earthwires, which
The conductor shall be continuously observed for although comparatively small ~during normal
loose or broken strands or any other damage. operations can be severe during switching.
When approaching end of a drum length at least Adequate safety precautions are to be taken to
three coils shall be left when the stringing opera- protect workmen and others working on line from
tions are to be stopped. These coils are to be this potential danger by way of providing travel-
removed carefully, and, if another length is ling ground.
required to be run out, a joint shall be made as
per the recommendations of the conductor manu- 17 STRINGING OF CONDUCTOR AND
facturers. EARTHWIRE

16.3 Repairs to conductors, if necessary, shall be 17.1 The stringing of the conductors shall be done
carried out during the running out operations, by control tension method, with the help of tension
with repair sleeves. Repairing of conductor stringing equipment. The equipment shall be
surface shall be done only in case of minor capable of maintaining a continuous tension. The
damage, scuff marks, etc, keeping in view both maximum tension imposed on a conductor during
electrical and mechanical safe requirements. stringing operations shall not exceed than that
Number of damaged strands shall not exceed 1/6th necessary to clear obstructions on the ground. In
of the total strands in the outer layer. The final general stringing tension of about one-half of
conductor surface shall be clean, smooth and shall sagging tension is a good criterion.
be without any projection, sharp points, cuts,
abrasions, etc. 17.1.1 Controlled stringing method suitable for
simultaneous stringing of the sub-conductor shall
16.4 Adequate steps shall be taken to prevent be used. Both the conductors making one phase
clashing of sub-conductors from paying out to bundle shall be pulled in and-paid off simtiltane-
the installations of the spacers/spacer dampers. ously. Both the conductors of the bundle shall be
Care shall be taken that both sub-conductors of of matched length. After being pulled the con-
a bundle are from the same conductor supplier ductor/earthwire shall not be allowed to hang in
and-preferably from the same batch SO that creep the stringing blocks for more than 96 hours
behaviour ofthe sub-conductor remains identical. before being pulled to the specified sag.
During sagging care shall be taken to eliminate
differential sags in the sub-conductor. as far as 17.2 Stringing of Earthwire
possible. However, in no case the sag mismatching
of more than 40 mm shall be allowed. Stringing of earthwire shall be carried out by con-
ventional stringing method.
16.5 Conductor splices shall be so made that they
do not crack or get damaged in the stringing 17.3 The contractor shall give complete details _of
operation. The contractor shall use only such the stringing methods which he proposes to follow.
equipment/methods during conduc!or .stringing Before the commencement of stringing the contrac-
which ensures complete compliance In this regard. tor shall submit the stringing charts. for the

12
IS 5613 ( Part 3/Set 2 ) : 1989

conductors and earthwire showing the initial and normally assume vertical positions when the
final sags and tension for various temperatures conductor is clamped.
and spans, along with equivalant spans in the lines
for the dpproval of the owner. 19.5 Tensioning and sagging operations shall be
carried out in calm weather when rapid changes
18 JOINTS in temperatures are not likely to occur.

18.1All the joints on the conductor and earthwire 20 TENSIONING AND SAGGING OF
shall be of compression type, in accordance with CONDUCTORS AND EARTHWIRE
the recommendations of the manufacturer for
20.1 The tensioning and sagging shall be done in
which all necessary tools and equipment like
accordance with the approved stringing charts
compressors, dies process, etc, shall have to be
before the conductors and earthwire are -finally
arranged by the contractor. Each part of the joint
attached to the towers through the earthwire
shall be cleaned by wire brush to make it free of
clamps for the earthwire and insulator strings for
rust or dirt, etc. and properly greased with anti- the conductor. The initial stringing chart shall
corrosive compound before the final compression
be used for the conductor and final stringing
is done with the compressors.
chart for earthwire should be employed for this
18.2 All!joints or splices shall be made at least 30 purpose. Dynamometers shall be -employed for
metres away from the structures. No joints or measuring tension in the conductor and earthwire.
splices shall be made in spans crossing over main The dynamometers employed shall be periodically
roads, railways, small rivers in tension spans. Not checked and calibrated with the standard dynamo-
more than one joint per sub-conductor shall be meter.
allowed in one span. The compression type fitting
used shall be of self-centring type or care shall be 21 CLIPPING IN
taken to mark the conductors to indicate when 21.1 Clipping of the conductors in position shall
the fitting is centred properly. During compres- be done in accordance with the recommendations
sion or splicing operation, the conductor shall be of the manufacturer. Conductor shall be fitted
handled in such a manner as to prevent lateral or with armour rods where it is made to pass through
vertical bearing against the dies. After pressing suspension clamps.
the joint the aluminium sleeve shall have all
corners rounded, burrs and sharp edges removed 21.2 The jumpers at the section and angle towers
and smoothened shall be formed to parabolic shape to ensure
19 SAGGING-IN-OPERATION maximum clearance requirements. Pilot suspension
insulator string shall be used, if found necessary,
19.1 The conductors shall be pulled up to the to restrict the jumper swings to the design values.
desired dag and left in running blocks for at least
one hour after which the sag shall be rechecked 21.3 Fasteners in all fittings and accessories shall
and adjusted. if necessary, before transferrmg the be secured in position. The security clip shall be
cbnductors from the running blocks to be suspen- properly opened and sprung into position.
sion clamps. The conductors shall be clamped
within 56 hours of sagging in. 22 FIXING OF CONDUCTOR AND
EARTHWIRE ACCESSORIES
19.2 The sag will be checked in the first and the
last span of the section in case of sections up to 22.1 Spacers, spacer dampers, vibration dampers
eight spens and in one intermediate span also for and other conductor and earthwire accessories
sections with more than eight spans. The sag shall be installed by the contractor as per the
shall also be checked when the conductors have design requirements and respective manufacturers
been drawn up and transferred from running instructions. Spacers shall be fitted within 24
blocks to the insulator clamps. hours of the conductor clamping. While installing
the conductor and earthwire accessories proper
19.3 The running blocks, when suspended from care shall be taken to ensure that the surfaces are
the transmission structure for sagging shall be so clean and smooth~and no damage shall occur to
adjusted that the conductors on running blocks any part ~of the accessories. Spacing bicycle/
will be at the same height as the suspension clamp trolley may also be used for fixing conductor
to which it is to be secured. accessories.
19.4 At sharp vertical angles, the sags and tensions 23 TESTING AND COMMISSIONING
shall be checked on both sides of the angle, the
conductor and earthwire shall be checked on the 23.1 General
running blocks for equality of tension on both
sides. The suspenrion insulator assemblies will 23.1.1 Before the line is energized, visual

13
IS 5613 ( Part S/SW 2 ) : 1989

examination of the line shall be carried out to The patrollers should write the insuection notes
check that all nuts and bolts are tight and insulators and -pass them on to the maintenance gang for
are in position at each support. The earth and carrying out the necessary repairs. The patrollers
earth connections shall also be checked to verify should be equipped with inspection books, draw-
that these are in order. The insulators of those ings, tape and binoculars. The main points to be
sections of the line which fall in areas of heavy noted while patrolling are as follows:
pollution shall be cleaned and washed before
energization of the line. a) Structures
23.2 Testing Seriously leaning structures; deformed mem-
bers; buckled structures; missing fasteners
23.2.1 Before commissioning of the lines, the and members; accessories removed; protec-
following tests may be carried out: tive coatings, like galvanizing or paints
a) Conductor continuity test disappeared; suspension and strain attach-
ments for insulators damaged.
The Objective of this test is to varify that
b) Foundations
each conductor of the overhead line is
properly connected electrically ( that is, the Signs of external damage; settled and
value of its electrical resistance does not washed out soil below designed ground
vary abnormally form that of a continuous level over. foundations within uplift frustum
conductor of the same size and length ). perimetres; tilted stubs; cracks or breaks
The electrical resistance of the conductor in chimney top; slippage of stubs from
shall be measured with a wheatstone bridge encasing chimney concrete; uneven settle-
or other suitable instrument. ment of footing; disappearance of gravel
blanket protection; backfills embankment
b) Insubtion resistance test and its covers ( rip-rap or revetment );
This test may be carried out with the help damage to retaining walls, abutments and
of 5 000 volts megger preferably power breast walls and disappearance of externa1
driven to ascertain the insulation condition earth backing retaining walls below designed
of line. lines.

23.2.2 The line may be charged at a low value Insulators and$ttings


of power frequerey voltage ~for the purposes of Damage to insulators; surface pollution of
testing. a bad nature; missing locking devices like
23.3 Statutory Requirements nuts, washers and pins; burnt out fittings;
deflected strings; damage to protective
23.3.1 The statutory authorities shall be informed coatings. The cracked insulators, bird
before commissioning the lines and their approval droppmgs, dense spider webs, kites with
obtained in accordance with Indian Electricity Act, cord hanging on the insulators string may
I9IO and Zhdian Electricity Rules 1956 (For also be noted.
details, see Rule 63 to 69 of Indian Electricity
Conductors andjumpers
Rules, 1956 ).
Strands cut and opened up, Ioose jumpers
24 MAINTENANCE OF OVERHAD LINES gone out of shape and causing infringement
24.1 General of clearance of live wire to earthed metal
parts. Dead birds, fallen branches or fallen i
The overhead lines shall be inspected periodically trees on conductors may also be noted. 1
for maintenance purposes to detect any faults
Earthwire and jumper, in aocordance with
which may lead to breakdown of electric suppIy
24.1 of this standard. 1
and necessary repairs should be done immediately
using hot line maintenance techniques, if necessary f) Earthing equipment, damaged, broken or
and feasible. missing earth strip.
24.1.1 Patroiling of Overhead Lines from the g) Right-of-way and clearance
Ground
Shrubs and trees within right-of-way
Patrolling of all overhead lines shall be done causing obstruction, and infringement of
before and after the monsoon. The frequency clearance of bottom conductor to ground;
of patrolling of the overhead lines for the rest of objects within line clearance excavation
the period shall depend on the local conditions. ( see Fig. I ). In no circumstances.

14
IS 5613 ( Part 3/k 2 ) : 1989

however, clearance measurement should be decreas in this interval but it should not be less
taken from live line, till hot line mainte- than once in two years.
nance has been established.
24.4.1 The clearance and shaps of the jumpers
h) Foreign objects should be checked at an interval not exceeding
3 years.
Construction works near lines causing
infringement in line safety or electrical 24.5 Line Repairs Tools
clearance; bird nests on structures; use of The following special tools, apart from tools
structure for applying permanent support required for maintenance of civil works of the
or pull to other objects; huts newly cons- lines, should be kept handy and.in working order:
tructed underneath lines, also embankments/
fencing. a) Conductor jointing tools,
b) Bolted come-alongs.
24.2 Inspection of Overhead Lines from Tower
Tops c) Winches,
Many breakdowns-including slipping of conductor 4 Aerial trolleys,
due to loose clamps, cracks in insulator porcelain, e>Aerial rollers,
defects in insulator fittings, conductor, earthwire
and their accessories and their attachment points
f>Thermometers,
on structures can only be dispersed or seen by g) Dynamometers,
going on top of every structure. This inspection h) Level and theodolite,
should be carried out by taking a shutdown of 3 Measuring tapes,
the line at least once in six years and should be
done in the shortest time possible during seasons
k) Linesmens ratchet,
of comparatively light climate and power loading m> Pull-lift device of adequete capacity,
on the line. Along with such inspection, repairs 4 Wire ropes, and
should also be carried out. Any replacement as
required should also be made.
PI Spanners,
24.51 Drawings
24.3 Special and Emergency Inspection
Sets of tower schedules, structural, foundation,
A special inspection of the overhead lines should insulators and accessories or route profile drawing
be carried out after severe wind/hail storms, including those for special constructions bound in
quakes, sabotages, snowfalls, forest fires, floods or folders should be available with patrollers as well
heavy rains. The purpose of such inspection is to as the maintenance crew.
detect any damage or breakage on line and to
affect necessary repairs. 24.5.2 Replacement
24.3.1 When an overhead line trips on fault often, An inventorv of spare line materials shall be
it should be inspected to ascertain the nature of maintained ii the stores for effecting repairs. Such
fault, such as bridge loose sag, tree branches inventory should be based upon the experience of
touching the line, et!, and to find out the amount repairs required in the earlier periods on similar
of repair involved with a view to avoid recurrence other lines.
of such faults.
24.5.3 Method of Repairs
24.4 Maintenance Tests and Measurements
Damage to aluminium strands of line conductors
Insulation of line should be measured at conve- shall be repaired with repair sleeves provided not
nient interval particularly at the time when the more than one-sixth of the strands in the outer-
line is shutdown for repairs or maintenance. In most layer have been severed. For portions
regard to measurements Of earth resistance of adjacent to armour rod ends affected by vibrations
metal structures, it should normally be carried due to wind, and minor abrasions due to some
out annually, however, local circumstances in the rubbing objects, extra-long preformed armour
light of the experience may justify increase or rods may be used for such repairs.

15
IS 5613 ( Part 3/&c 2 ) : 1989

ANNEX A
( Clause 2.1 )
LIST OF REFERRED INDIAN STANDARDS

IS No. Title IS No. Title

IS 383 : 1970 Specification for coarse and IS 3043 : 1987 Code of practice for earthing
fine aggregates from natural (j&St revision )
sources for concrete ( second
revision ) IS 3764 : 1966 Safety code for excavation
work
IS 456 : 1978 Code of practice for plain and
reinforced concrete ( third IS 4081 : 1986 Safety code for blasting and
revision ) related drilling operations
( jirst revision )
IS 1199 : 1959 Methods of sampling and
analysis of concrete IS 4091 : 1979 Code of practice for design
IS 1498 : 1970 Classification and identification and construction of founda-
of soils for general engineer- tions for transmission line
ing purposes (Jirst revision ) towers and poles ~(first
revision )
IS 1885 Electrotechnical vocabulary :
(Part30):1971 Part 30 Overhead, transmission IS 7861 Cade of practice for extreme
and distribution of electrical ( Part 2 ) : 1981 weather concreting : Part 2
.energy Recommended practice for
cold weather concreting
IS 2502_: 1963 Code of practice for bending
and fixing of bars for concrete IS 9759 : 1981 Guidelines for dewatering
reinforcement during construction

ANNEX B
( Clause 6.5 )
SAG TEMPLATE AND TOWER SPOTTJNG

B-l SAG TEMPLATE c) Ground clearance curve


B-l.1 The location of structures on the profile Drawn at a distance equal to the minimum
with sag template is essential for both correct specified ground clearance, from and parallel
design and economy. Sag template may be to No. 1 Curve.
prepared on transparent paper, cardboard, hard _d) Support foot curve
plastic sheet or on celluloid.
Drawn at a distance equal to the bottom
B-l.2 Method of Preparation conductor height at tower, from and parallel
B-1.2.1 A typical sag template is shown in Fig. 2. to No. 2 curve. ( If required, additional
It consists of the following curves: Support foot curves may also be drawn
incorporating standard tower body exten-
a) Cold template or zipl$t curve sions to advantage. )
Corresponding to the vertical component of B-1.2.2 Curves No. 1 and 3 are normally drawn
sag at worst load conditions of wind. through the origin 0 at the centre line of the
b) Hot template or maximum sag curve template. The Cold and Hot templates ( curves
1 and 2 j are Dlotted and cut as a Darabola on the
Corresponding to the maximum still air minim& and maximum sag of the ruling span
final sag at maximum temperature ~( or at ( the normal design span is the theoretical ruling
0C with ice load ) including sag tolerance span ) which is extended by computing the sag
to be accounted for, if any. as proportional to square of the span for spans

6
IS 5613 ( Part 3/Set 2 ) : 1989

both shorter and longer than the ruling span. left and right of the centre line up to a distance
Any particular span is considered spread-out by equal to the maximum swing of conductor
half of its value on either side of origin 0. including cross-arm spread on either side.
B-1.2.3 The parabola is accurate to within about B-2.2 The weight span on either side of the
one half of 1 percent for sags up to 5 percent of tower for practical purposes is obtained by mark-
the span which is well within the acceptable limits. ing the low points of the sag in the two adjacent
spans and sealing the same off.
B-l.3 The actual ruling spans for various stringing
sections of a line may differ from the normal B-2.2.1 On steep inclined spans the low point may
design span which forms the basis for the sag fall beyond the lower support; this indicated that
template. It is, therefore, essential that the actual the conductor in the uphill span exerts a negative
ruling spans be as near the normal design spans or upward pull on the lower tower. The amount
as practicable. In case of considerable amount of of this upward pull is equal to the weight of the
difference the following points shall be observed: conductor from the lower tower to the low point
a) The Actual Ruling Span Shorter Than the in the sag. Should the upward pull of the uphill
Normal Design Span span be greater than the downward load of the
next adjacent span, actual uplift would be caused
In this case the maximum working and and the conductor would tend to swing clear of
other tensions are comoarativelv less. and the tower upward.
therefore, the sags, comparatively grkater
than those obtained for the normal design B-2.2.2 For an easy check whether a tower is
span. The sag template, therefore, needs to under uplift or not, the following method may be
be modified. An easier method shall be to adopted. The template is applied horizontally
provide suitably greater ground clearance until the tops of alternate supports coincide with
while carrying out tower spotting. the cold template ( curve I ). If the curve is above
the intermediate support, the support is under
b) The Actual Ruling Span Longer Than the uplift and has to be extended until it touches the
Normal Design Span cold template and so eliminates uplift. If requisite
In this case the maximum working and other standard body extensions are not available for
tensions are comparatively greater, and extending the tower to desired height. a tower
therefore, the sags comparatively less, than designed for uplift shall have to be provided.
those obtained for the same span from the NOTE-The suspension towers shall be checked
volues for the normal design span. for uplift under normal working condition only, that
Obviously, greater tensions cannot be is, both adjacent spans intact. The section and angle
allowed on towers; and therefore, by work- towers shall be checked for uplift under both normal
and broken wire conditions,
ing back with maximum working tension
for normal design span we may get different
sags at the actual ruling spans. This shall B-2.2.3 The analytical method for calculating
be suitably accounted for while carrying weight span is given below:
out tower spotting. Distance of Null point or Low point of con-
B-l.4 The template shall be prepared to the same ductor from centre of span is giv,en by the
scale as the survey chart, that is, 1 : 2 000 for formula ( see Fig. 8 and 9 ):
horizontal distances and 1 : 200 for vertical heights.
The vertical centre line and the horizontal line Th
X=wf
passing through origin 0 shall be drawn promi-
nently. -The curves shall be extended such that
all slopes on the profiles may,be scaled with ease. where

B-2 APPLICATION FOR TOWER SPOTTING X= distance of low point from centre of
span in m,
B-2.1 The method of application of the sag
template is shown in Fig. 2. The template is T= conductor tension in kgf,
applied to the profile by moving the same horizon-
tally as shown while always ensuring that the h = difference between conductor sup-
vertical axis or centre line is held vertical. The port levels in m,
structure positions are marked where the Support
foot cuts the profile, while the Ground clearance w= unit weight of conductor in kg/m,
curve is just clear of and above the profile. The and
ground clearance curve shall not only clear the
route-centre line profile, but also the profile to the I = span length in m.

17
.

IS 5613( Part 3fSec2 ) : 1989

WeigJU span: If the sum of &and b. calculated for a particular


tower is negative, the tower is under uplift.
For tower A, right hand side only:
t It is also evident that maximum weightspans
a=--x are obtained by the worst conditiun of wind load-
2 ing when T is maximum; which means the vertical
Fortower B, left hand side only: component of worst load sag should be taken for
cold curve of sag template m order to assess
b = -_ + X uplift on towers.

Similarly, weight span for the other side of the


towers, ean be calculated and total weight span
obtained.

LOW OR
NULL POLNT
tow oti
NULL.POW

FIG. 8 DISTANCEOF NULL POINT OR Low FIG. 9 DISTANCE OF NIJLL POINT OR Low
POINTFROM THE CENTRE OF SPAN POINTCENTRE OF SPAN

ANNEX C
(Czause 10.2.1 )
TOLERANCES IN OVERHEAD LINE CONSTRUCTION

Cd SURVEY shall not differ from the computed elevation by


more than l/100 of foundation depth. Stub
C-l.1 The accuracy of~survey work depends upon, angles shall be located horizontally so that each
the accuracy of surveying instruments, the pre- is within 6 mm of its correct position, and the
vailing temperatures, the accuracy of placing batter of the stub angles shall not differ from the
instruments and their reading. It shall be correct batter by more than either l/100 of
ensured, however, that no measurements should erposed stub length, or by the amount of play as
be missed during surveys and check surveys carried offered by the clearance between bolts and holes
out where any doubt arises. of the setting template. To ensure greater accu-
racy, the hole clearance shall not be greater than
C-2 STUB-SETTING ( TOWER FOOTING ) 15 mm of the punched side of the template
C-2.1 All the stub angles for tower legs shall be members.
set accurately to the grade and alignment shown
on the drawings, The difference in elevation C-2.2 If the actual elevation of stubs is beyond
between identical parts of any two stub angles 6 cm as found after casting the foundation
shall not exceed l/l 000 of the horizontal distance is on the plus side ( that is, if the foundation is
between the stubs, allowance being made for the raised ), equivalent depth of earthwork will be
difference, if any, in the lengths of legs -and provided over the top of the foundation as.per
extensions. The actual elevation of any stub angle design requirements with particular reference to

18
IS 5613 ( Part 3/Set 2 ) : 1989

such location. By design requirements is meant shall be f 5 mm. This shall not be accumulative
the earth required to resist uplift forces. on height for various parts of the foundation.
C-4 TOWERS
C-2.3 The following tolarances shall be applicable
in case of position of foundation as a whole with C-4.1 No member of a tower shall be -out ~of
reference to tower position as spotted on the straightness by more than one in 1 000. -Members
survey chart: failing the requirement shall be straightened
before erection in a manner that shall not damage
Type of Out of From Centre From Trans- their properties or the protective finish.
Tower Align- Line of verse Centre
ment Route Line C-4.2 The towers shall not be out of vertical by
more than 1 in 360 before stringing is carried out.
Suspension 025 f25mm & 250 mm C-5 STRINGING
or interme-
diate C-5.1 The maximum toterance in final still air sag
at maximum temparature shall be f4 percent
Section or 025 f25mm * 25mm of such sag, in any span as obtained from the sag
tension tension chart. The sag ~of any conductor in a span
( set at bi- shall not depart from the mean sag of all conduc-
section of tors in the same span by more than 3 percent.
deviation NOTE-In order that the niinimum required
angle ) ground clearance is not interfered with by tolerance
in sag template used for tower sporting shall be
C-3 CONCRETE AND FORM DIMENSIONS based upon a plus tolerance in sag of 4 percent, the
support foot curve being located according~to tower
C-3.1 The maximum tolerance on the dimensions design.

ANNEX D

( Clause 11.10)
MIXING, PLACING AND COMPACTING OF CONCRETE

D-l MIXING D-l.3 For mixing the mechanical mixers, the


same order of placing ingredients in the leader/
D-l.1 Concrete shall preferably be mixed in a drum shall be adopted, that is, coarse aggregates
mechanical mixer, but hand mixing shall be per- shall be put in first followed by sand, cement and
missible. In case of emergency ( when mechanical water.
mixers are in use 1 such as failure of the mixers,
or where it is not practicable to haul the mixers D-l.4 Mixing shall be continued until there is a
up to the location, and also for lean concrete uniform distribution of material and the mass
sub-base, hand mixing may be resorted to. is uniform in colour and consistency but in no
case shall mixing be done for less than 2 minutes.
D-l.2 When hand mixing is adopted, it shall be
carried out on water-tight platforms, such as D-l.5 If the aggregates are wet, the amount of
18 mm glavanized iron plain sheets properly
water shall be reduced suitably.
overlapped and placed upon level ground. The
coarse aggregates shall first be evenly spread out in
required quantity over the sheets. The fine aggre- D-2 TRANSPORTING
gates shall be evenly spread out over coarse
aggregates next. The aggregates shall than be D-2.1 Normally mixing shall be done right at the
thoroughly mixed together and levelled. The foundation. In places where it is not possible,
required amount of cement shall not be spread concrete may be mixed at the nearest convenient
evenly over the mixed aggregates and wet mixing place. The concrete shall be handled from the
shall start from one end with required amount of place of mixing to the place of final deposit as
water suing showels. The whole lot shall not be rapidly as practicable by methods which shall
wetted; instead mixing shall proceed progressively. prevent the sagregation or loss of any of the
If the agreegates are wet nor washed, cement ingredients. If segregation does occur during
shall not be spread out, but shall be put in transport the concrete shall be remixed before
progressively. being placed.

19
IS 5613 ( Part 3/Set 2 ) : 1989

D-2.2 During hot or cold weather, concrete shall bars be worked 100 times in an area of 200 mm
be transported in deep containers; the deep con- square for 300 mm depth. Over-compacting causes
tainers, onaccount of their lower ratio of-surface the liquid to flow out upward causing segregation
area to mass, reduce the rate of loss of water by and should be avoided.
evaporation during hot weather and loss of heat
during cold weather. D-3.3 If, after the form work has been struck, the
concrete surface is found to have defects, all the
D-3 PLACING AND COMPACTING damaged surfaces shall be repaired with mortar
application composed of cement and sand in the
D-3.1 The concrete shall be placed and compact- same proportion as the cement and sand in the
ed before setting commences and should not be concrete mix. Such repairs shall be carried out
subsequently disturbed. The placing should be well before the foundation pits are back filled.
such that no segregation takes place.
D-3.4 For precautions to be taken on concrete
D-3.2 Concrete shall be thoroughly compacted work in extreme weather and under water, the
during the placing operation, and thoroughly provisions of IS 456 : 1978 shall apply.
worked around the reinforcement, around embed-
ded fixtures and into corners of form work by D-3.5 Field tests on workability ~of concrete and
means of 16 mm diameter poking bars pointed at consistency may be carried out in the form of
the ends. As a guide for compacting the poking slump test in accordance with IS 1199 : 1959.

-20
Standard Mark
The use of the Standard Mark is governed by the provisions of the Bureau of Indian
Standards Act, 1986 and the Rules and Regulations made thereunder. The Standard Mark on
products covered by an Indian Standard conveys the assurance that they have been produced
to comply with the requirements of that standard under a well defined system of inspection,
testing and quality control which is devised and supervised by BIS and operated by the
producer. Standard marked products are also continuously checked by BIS for conformity
to that standard as a further safeguard. Details of conditions under which a licence for the
use of the Standard Mark may be granted to manufacturers or producers may be obtained
from the Bureau of Indian Standards.

i
Bureau of Indian Standards
BIS is a statutory institution established under the hreau of Indian Standardr Act, 1986 to promote
harmonious development of the activities of standardization, marking and quality certification of gooda
and attending to connected matters in the country.

Copyright

BIShas the copyright of all its publications. No part of these publications may be reproduced in
any form without the prior permission in writing of BlS. This does not preclude the free use, in the
course of implementing the standard, of necessary details, such as symbols and sizes, type or grade
designations. Enquiries relating to copyright be addressed to the Director ( Publications ), BIS.

Revision 01 Indian Standards


Indian Standards are reviewed periodically and revised, when necessary and amendments, if any, arc
issued from time to time. Users of Indian Standards should ascertain that they are in ~possession of
the latest amendments or edition. Comments on this Indian Standard may be sent to BIS giving tho
foIlowing reference:

Dot : No. ETDC 60 ( 2968 )

Amendments Issued Since Publfcatioe

Amend NO. Date of Issue Text Affected

BUREAU OF INDIA-N STANDARDS


Headquarters :

Manak Bhavan, 9 Bahadur Shah Zafar Marg, New Delhi 110002


Telephones : 331 01 31, 331 13 75 Telegrams : Manaksanstha
( Common to all Offices )
Regional Offices : Telephone

Central : Manak Bhavan, 9 Bahadur Shah Zafar Marg 331 01 31


NEW DELHI 110002 { 331 13 75
Eastern : l/l4 C. I. T. Scheme VII M, V. I. P. Road, Maniktola
CALCUTTA 700054 36 24 99
Northern :-SC0 445-446, Sector 35-C. CHANDIGARH 160036 , 2 1843
1 3 16 41
Southern : C. I. T. Campus, IV Cross Road, MADRAS 600113 41 24 42
41 25 19
{ 41 29 16
Western : Manakalaya, E9 MIDC, Marol, Andheri ( East )
BOMBAY 400093 6 32 92 95
Branches : AHMADABAD. BANGALORE. BHOPAL. BHUBANESHWAR,
GUWAHATI. HYDERABAD. JAIPUR. KANPUR. PATNA.
PIVANDRUM.

Printed at Prlntwoll Printers, Delhi, India

- ^_ ^. a,.,,..-

Você também pode gostar