Escolar Documentos
Profissional Documentos
Cultura Documentos
1. Introduction
This note elaborates the construction sequence for the excavation of bored tunnels using Tunnel Boring
Machine for Bangalore Metro Phase II underground works project. This project comprises of 13.92km of
underground activity divided into four packages (3.67km in package 1, 3.62km in package 2, 3.32km in
package 3 and 3.31km in package 4). Combing all four packages, the project includes 12 UG Stations,10.51km
of TBM excavation for Twin Bored Tunnels, 1 NATM Tunnel, 0.5km of Cut and Cover tunnel works, 5
Launching/Retrieval/Intermediate Shafts and 15 Cross Passages between Bored Tunnels.
Figure 1 BMRCL
Tunnels will be constructed by pressurized face TBMs to optimise the force form the surrounding ground and
reduce the settlement. Also, the tunnel lining can be installed concurrently and without lowering the ground
water levels.
Project 1
Technical note
Project 2
Technical note
2.3. TBM Tunnel Excavation
The TBM require a launching area to start each tunnelling operation. It will continuously drill that excavate
circular tunnels. As the machine advances, both the ground in front of the machine and the horizontal hole it
creates are continuously supported by TBM shield.
TBMs are normally manufactured in drum shaped steel shield equipped inside with excavation and segment
erection facilities. The fully functional operation of the machine includes the following steps:
1. The rotating cutter head excavates the ground in-front of the machine with the help of hydraulic jacks.
2. The slurry mix provides the face support at TBM face.
3. When certain amount of cutting is done, the TBM cutting operation stops and the erector installed in
the machine place the precast lining segments in their respective location in the ring, provide the
necessary grouting.
4. The TBM advances forward again by applying the hydraulic thrust to previously built tunnel lining.
Sometime, highly plastic and dense additive is added to the slurry mix in the cutter chamber to increase the
fluidity and reduce the permeability of the soil.
Project 3
Technical note
The tunnel depth, tunnel size, proximity of adjacent tunnels, ground conditions, TBM characteristics and
excavation techniques can affect the amount ground settlement. Moreover, the requirement for precast tunnel
lining segment, grouted as TBM advances, can also reduce the settlement.
Permeation Grouting - adding chemical or cement based grouts into the ground to fill the voids
between soil particles
Compaction Grouting of ground prior to tunnel excavation
Compensation Grouting Grout is injected, thickens the soil above the tunnel and replaces some of
the ground that may be lost during the tunnelling
Project 4