1 Earth work excavation in foundation trenches &
column footing including dressing of sides &
ramming of bottoms & side including soils as
directed with in a lead of 50 m etc, with a lift up to
1.5 met in hard soil
1st footing
a)Long wall 1.00 28.17 0.75 0.45 9.51
b)Short wall 1.00 35.25 0.75 0.45 11.90
2nd footing
a)Long wall 1.00 28.17 0.60 0.45 7.61
b)Short wall 1.00 35.25 0.60 0.45 9.52
38.53 1,500.00 57,791.48
4 Providing & construction size stone masonry
hammer dressed in courses edges of stone chisel
dressed & all quoins 2line dressed 5cm wide on
each face C.M.(1:4) for foundation including all
necessary scaffolding & curing etc, & complete
above G.L.
a)Outside area
1 48.80 1 1 48.80
Deduction of item no 4 quantity of above G.L
Stilt floor ,
A)Long wall 1 28.17 0.23 3.00 19.44
B)Short wall 1 35.25 0.23 3.00 24.32
43.76
Deduction
RS 4 3.65 0.23 2.1 1.76
D 3 1.06 0.23 2.1 1.54
WINDOWS
W1 2 1.82 0.23 1.37 1.15
W2 1 1.21 0.23 1.37 0.38
Total deduction quantity 4.83
Parapet wall all round 44.81 0.15 0.75 5.04
43.97 2,000.00 87,947.60
8 Providing & fixing Neem or Nandi wood for
window with frame of 65mmx125mm fixed in the
masonry with 40mmx5mm size &40cm. long M.S.
holes fasts embedded in 15 cm. thick C.C 1:3:6&
providing mullions wherever necessary with fully
paneled Hone wood shutter of 30mm thick & with
paneled of 20mm thick with or without halves &
M.S.rods of 12mm dia at 60mm & 120mm apart
alternately & M.S.falts of 6mmx25mm vertically at
150mm apart with or without ventilators at top of
glazed shuttered as per drawing (excluding the
cost of fittings) with fully glazed shutters (30mm
thick)
WINDOWS
W 2 1.82 1.37 4.99
W1 1 1.21 1.37 1.66
Doors
RS 4 3.65 2.1 30.66
D 1 1.06 2.1 2.23
32.89 1000.00 32886.00
10 Providing & laying cement concert 1:2:4 using
20mm & down size gradient or trap jelly for R.C.C
works laid in 15cm thick layers &well compacted
clouding vibrating. Curing & necessary steel or
plywood or plank centering & form works etc
including smooth finishing in cement mortar 1:3
etc , Complete (exclusive of cost of steel &
fabrication charges) for Lintels
Deduction
D 1 3.04 2.1 6.38
W 2 1.82 1.5 5.46
W1 1 1.21 0.6 0.73
12.57
21 Providing & laying of waterproof course (WPC) over RCC roof slab etc complete L.S 15,000.00
Providing & constructing steps and platform allround the building etc complete 15,000.00
22 Providing , fitting & Fixture Doors, windows, ventilators etc., complete L.S 10,000.00
23 Providing & fixing glazed tiles, ceramic tiles vitrified tiles .etc,. complete L.S 10,000.00
24 Providing & fixing M.S.Grill works and other steel works etc. complete L.S 10,000.00
25 Providing & constructing decorative parpetwall over RCC roof slab L.S 10,000.00
L.S 0.00
26 L.S 0.00
25 Providing Electrification work &water supply etc complete L.S 20,000.00
27 For Miscellaneous & unforeseen charges etc... complete round off L.S 5,000.00