DATE: JUNE 24, 2015 SCHEDULE COST PROGRESS REPORT January Februrary March April May June ITEM DURATION START FINISH ITEM COST WT% ACCOMPLISHED ACTUAL WT% W1 Wk2 Wk3 Wk4 Wk5 Wk6 Wk7 Wk8 Wk9 Wk10 Wk11 Wk12 Wk13 Wk14 Wk15 Wk16 Wk17 Wk18 Wk19 Wk20 Wk21 Wk22 Wk23 Wk24 Wk25 Wk26 W27
Division 1 - General Requirements
Administrative Requirements Quality Requirements Product Requirements Execution Requirements Division 2 - Site Construction Basic Site Materials and Methods Site Remediation Site Preparation Earthwork Foundation and Load-Bearing Elements Utility Services Drainage and Containment Bases, Ballasts, Pavements and Appurtenances Division 3 - Concrete Concrete Reinforcement Cast-In-Place Concrete Division 4 - Masonry Masonry Units Stone Division 5 - Metals Structural Metal Framing Ornamental Metal Division 6 - Wood and Plastics Wood Treatment Architectural Woodwork Division 7 - Thermal and Moisture Protection Damproofing and Waterproofing Thermal Protection Shingles, Roof Tiles, and Roof Coverings Division 8 - Doors and Windows Wood and Plastic Doors Windows Division 9 - Finishes Plaster and Gypsum Board Tile Ceilings Flooring Wall Finishes Paints and Coatings Division 10 - Specialties Storage Shelving Telephone Specialties Toilet, Bath, and Laundry Specialties Wardrobe and Closet Specialties Division 11 - Equipment Maintenance Equipment Water Supply and Treatment Equipment Division 12 - Furnishings Fabrics Furnishings and Accessories Furniture Division 13 - Special Construction Building Modules Security Access and Surveillance Detection and Alarm Division 14 - Conveying Systems Scaffolding Division 15 - Mechanical Plumbing Fixtures and Equipment Division 16 - Electrical Wiring Methods Electrical Power Lighting Wiring Methods Contingencies Total Target % of the week Actual % of the Week Target % Accomplishment Commulative % Accomplishment Status
Prepared By: CARLO S. MARASIGAN BONESSA IONY P. CACPAL ROMAN ANTONIO T. SANTIAGO B.S. Architecture 5 - B B.S. Architecture 5 - B B.S. Architecture 5 - B