Escolar Documentos
Profissional Documentos
Cultura Documentos
CM Assingment 3
CM Assingment 3
ASSIGNMENT NO.3
Before submitting the tender, contractor should go inspect the site to satisfy himself regarding these
matters:
a) Nature of the ground and subsoil
b) Form and nature of the site
c) The extent and nature of the works, materials and goods necessary for the completion of
the works
d) Means of communication with and access to the site
e) Accommodation he may require
f) Contractor responsible for all the information that affects the tender
Any information or document forwarded by the government to the contractor shall not relieve the
contractor of his obligations under the provisions of this clause
Date of possession
Degree of possession
The extent of possession that must be given to the contractor is not necessarily to be the
whole site.
R v the walter cabott (1979) - the contractor must be given a reasonable degree of
possession to enable him to commence the work in accordance to programme unless there
is agreement to the contrary; execute the work unimpeded by others; and to perform the
work in a satisfactory manner based on construction methods desired by him.
Employer is not deemed to guarantee possession due to events outside his control. For
example, employer is not liable if contractor is prevented from gaining access by third party
such as unlawful picket.
Thorn v london corp (1876) - employer is not deemed to guarantee that the site is fit for the
work or the contractor will be able to construct the building on site.
Nobody else has the right to access the site except for:
S.O or his representative who have the rights to access the site at any time (clause 46.1(a)),
Other contractors engaged by government and their workers executing works on or near the
site (clause 46.2),
Employer and any authorized persons to investigate causes of accident, failure or other
events connected with the works (clause 45).
Restricted possession
Any restrictions on the giving of possession of site must be stipulated in the contract.
It includes:
I. Giving possession for some parts of the works on different dates. For example,
works to be done in phases.
II. Also, any conditions obtaining which amount to some obstruction or restriction of
possession. For example, proximity of electric power line, existence of squatters,
and other structures on site
The contractor is entitled to assume a degree of possession of the site to enable him to
plan his work accordingly. The contractor is also entitled to claim damages if he is put
to extra cost.
-Clause 38.1
No work under this contract shall commence unless and until the performance bondinsurances
policyhave been deposited with the government.
However, there is the condition precedent that requires the contractor to provide the following
documents to employer before he can start the work:
- Cover notes and receipts for premium paid of all insurance policies
- Performance bond (is the contractor choose bank guarantee sum as performance
Bond & does not choose performance guarantee sum as performance bond )
- Registration numbers for socso schemes (for workers earning less than
RM 3,000/month)
The contractor needs to furnish the above documents first to employer, then only he is allowed to
enter the site
Insurance Involved
When it comes to the planning and organizing of a new construction project, insurance doesnt
always get the priority it requires. Very often it is left to the last minute or even after the work has
commenced.
All standard forms of construction contract require a Contract Works Policy to be in place with
minimum requirements that must be met. The contract conditions will stipulate who is to arrange
the insurance i.e. the contractor or the principal, and who is to be named as Insured under the
Contract Works policy.
The bank will want an insurance certificate before it will release any funds. Arranging
insurance after work has begun can delay your project while this is sorted out.
Your contractor may have insurance already in place but check that the cover he has
is sufficient.
The project must be insured for the full replacement value including any materials or
goods that you are supplying, for example kitchen appliances or any electronic
equipment. These are most vulnerable when they have just been installed and the
house is not secured.
It is important to be aware of what is not covered by the Policy. Not all eventualities are covered:
Contract Document
Construction Contract Documents are the written documents that define the roles,
responsibilities, and Work under the construction Contract, and are legally-binding on the parties
(Owner and Contractor).
Manager of the project implementation unit is the manager of the process of the project
management and owner supervision of the construction projects. He appoints the project manager
or the person responsible for the implementation of the contract agreement to each project.
The basis and input of the project management and provision of the owner supervision is
the contract agreement for the supply of services concluded with the client.
Within the scope of this service, our site supervision team does the following activities:
Site meetings are an important part of the successful management of construction projects.
Regular site meetings between the different stakeholders on a project can help facilitate better
communication and a shared sense of purpose making it more likely that the project is completed
successfully. Project failures are often attributed to inadequate management, with a key factor being
a lack of proper communication.
Meetings should be regular and formerly scheduled, perhaps on a weekly or monthly basis
depending on the parties involved, although the size and complexity of the project may necessitate a
more regular schedule. They are used as a means of reporting progress, enabling discussion of any
problems or issues, and allowing the proposal of solutions. They provide a good opportunity for two-
way discussions of any issues that have arisen or that are anticipated.
Holding meetings on site enables the stakeholders to see progress for themselves (rather
than relying on a report for another party) and to look at problem areas, discuss quality issues,
assess mock-ups and so on.
Construction progress meetings are a specific sort of site meeting during which the contract
administrator receives progress reports from the contractor and consultant team, cost reports from
the cost consultant and other more specific information such as sub-contractor reports, progress
photos and so on.
In order to be able to provide the correct information at construction progress meetings, the
contractor may previously hold a progress meeting with sub-contractors sometimes called a
production meeting.
Meeting minutes should be prepared, with a requirement that any disagreement with the
items recorded in the minutes is raised within a pre-defined period (perhaps one week). Progress
meetings may also result in the preparation of a construction progress report for the client.
Construction progress reports are prepared regularly (often monthly) by the contract
administrator during the construction phase and issued to the client. They will generally be a
summary of the reports received and discussions held at construction progress meetings.
1. Units Completed
-The Units Completed lends itself well to tracking tasks that are done repeatedly, where each
iteration can easily measure. Usually a task that is done repeatedly tends to take about the same
amount of time, resources and effort, so tracking the units completed works well here.
2. Incremental Milestones
-Also known as the steps method, the incremental milestones method is predominantly used for
cost accounts that involve subtasks that need to be completed in an orderly fashion. An example of
this technique is the forming and placing of a concrete foundation wall. Laying the foundation wall
on footings, erecting inside wall panels and brace, setting horizontal and vertical rebar in formwork
and so forth needs to be done in sequence to complete the task appropriately.
3. Start/Finish
-This method is only focused on capturing the starting point and the finishing point of the task and
nothing in between. This method is best for tasks that are short in duration. You would implement
this method if the tasks work estimations are not available or if the percent complete progress data
is too difficult to collect.
-Using the Start/Finish technique, we earn a percentage of progress when the task starts and the
other half is earned once the task is complete. These percentages are determined by the owner and
contractor of the project.
4. Cost Ratio
-The Cost Ratio method is usually implemented on a project that has tasks that tend occur over a
long phase or the entire project. Often used for Overhead costs, this technique is measured based
on the budgeted allocation of dollars vs. the labour hours of production. This method gives the
contractor the ability to earn value that is equal to the overall percent of project completion.
5. Experience/Opinion
-Unlike the methods above that rely on definitive data, this method is relies on the experience and
subjectivity of the project manager. This technique is used for tasks such as dewatering or frost
removal/protection. Its not usually recommended and tends to be seen as the last resort because
each individuals experiences and opinions vary from one another and can cause conflict between
owners, contractors and architect.
-This method was highlighted as the best technique in the text and is the one that requires more
effort, but also extends to a wider data range. The tasks that are being calculated tend to occur over
a longer duration time and includes multiple subtasks, where subtasks can have different units of
measurements.