1-Rbi may include methodologies to assess the effectiveness of the management systems
in
maintaining
A. Mechanical integrity
C. Plant integrity
Answer: A
A. FMEA
C. OSHA 1910.110
Blast-resistant construction may provide personnel protection from the effects of an explosion, It may
also be useful for which of the following?
D. Management
Blast-resistant construction may provide personnel protection from the effects of explosion. It may also
be useful for:
C. Emergency isolation
1-In some cases, damage by one mechanism may progress to a point at which a different mechanism
takes over and begins to dominate the rate of
Damage
RBI could be expanded to include failures other than loss of containment. Examples of other failures and
failure modes are:
D. Machinery Components
Terms of reference by which the significance of risk is assessed. This may include associated cost and
benefits, legal and statutory requirements, socio-economic and environmental aspects and other inputs
to the assessment:
A. Risk Avoidance
B. Risk Criteria
C. Risk Identification
D. Quantitative Risk
This is described as a model depicting the progression of accidents, transport of a hazardous material to
the environment.
A. Risk model
B. Logic model
C. Concentric model
D. Physical model
Application of RBI can provide evidence of complete risk management and integrity monitoring
programs that can be used as a basis for which of the following?
A. Fitness-for-service evaluation
B. Risk analysis
By dividing a process unit into systems, the equipment can be screened together saving time, compared
to treating each piece of equipment separately. Selection of the systems may be based on:
A. Volume of systems
D. Age of systems
Process unit screening may assign priorities based on each of the following except which one?
D. Turnaround schedule
When determining the deterioration susceptibility and rate, the best data will be derived from which of
the following?
D. Published Data
Flammable events - Most of the damage from a flammable event is caused by:
A. Blast overpressure
B. Thermal Radiation
D. Thermal overpressure
B. Must be added to the deterioration mechanism and then factored into the probability of the specific
consequences occurring
C. Should be discounted since they were previously assessed during the RBI
A. The environment
B. Property
C. Toxic release
D. People
RBI is a Team Approach. Who on the team is responsible for providing recommendations on methods of
mitigating the POF (such as coatings/linings, etc.)?
A. Corrosion Specialist
C. Team Leader
D. Process Specialist
Emergency isolation capability can reduce all except which of the following?
B. Toxic release
C. Explosion consequence