Introduction
Definitions of Availability
Specific Availability Challenges - revisited
Availability Analyses - updated
Availability Conclusions
Summary
Introduction
Project Staffing
High level of employee turnover for Longer term employment normal
operators - workers market migration of opportunities
20 to 40 turbines per technician crew (2 10 to 20 turbines per technician crew (2
techs) techs)
Relatively few trained expert technicians Larger number of trained technicians
nationwide available
Inexperience = increased time to resolve More experienced crews = faster response
downtime times
Availability Challenges - revisited
US Market European Market
Manufacturer Technical Support
Technical support can be difficult to track Technical support in same time region and
down if foreign based easier to bring to bear
US based support may be dependent upon Technical support is easily referred to main
foreign engineering support = delay in engineering group = same day response
response
Project Construction
1 to 2 weeks for turbine erection and 2 weeks + for turbine erection and
commissioning commissioning
Shorter reliability runs PTC driven Sometimes 250 to 500 hours and
maintenance prior to reliability testing
Miscellaneous
Climate can be extreme high and low Rare for projects to have both high and low
affects performance of crews and turbines extremes
Many projects quite remote Large population centers within nominal
Larger projects 100 + turbines common = distance for most all projects Smaller
difficulty managing issues projects 10 to 40 turbines common =
fewer issues to manage
System Availability Global Market
Annual moving average: Global Annual moving average: N America removed
Count of wind farms (Right axis) Count of wind farms (Right axis)
100% 300
97% 210
96% 180
95% 150
94% 120
93% 90
92% 60
91% 30
90% 0
0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0
Years of wind farm operation
System Availability US Market
Annual moving average Monthly Average
Count of wind farms (2nd y-axis)
100% 100
97%
98%
80
System Availabilty [%]
96%
92%
40
90%
20
88%
86% 0
0 1 2 3 4 5 6
Years of wind farm operation
Turbine and BoP Availability - US
Balance of Plant Turbine Count of wind farms
100% 70
99%
60
98%
97% 50
40
95%
30
94%
93% 20
92%
10
91%
90% 0
0 0.5 1 1.5 2 2.5
Year of operation
Actual Availability - Summary
Years of Operation Annual Turbine BoP Availability
Availability
Year 1 95.0% 98.0%
Year 2 96.0% 98.5%
Year 3 96.0% 99.0%
Year 4 and beyond 96.0% 99.0%
14
12
10
8
Few <95%
6
0
< 80%
82%
83%
85%
86%
88%
89%
91%
92%
93%
94%
95%
97%
98%
99%
81%
84%
87%
90%
96%
100%
Average annual system availability
Downtime Turbine Availability
Parts availability
Major component lead times
Response time to faults
General efficiency
Motivation
Nights / weekends
Troubleshooting / understanding the problem
Expertise of O&M staff
Turbine faults
Major component failures
Vibration
Lightning strike damage
Control / electrical system failures
Downtime BoP Availability
Electrical connections
Collection system splice connections
Collection system terminal connections
Pad Mount transformers
Other terminal connections
Response time to faults
General efficiency
Motivation
Nights / weekends
Troubleshooting / understanding the problem
Expertise of O&M staff
Availability Data Results
Conclusions that can be drawn:
US Market continues to struggle with availability challenges
System availability of wind farm projects may not be achieving
97% long term on average
BoP and Turbine availability must be monitored and addressed
simultaneously
Objective and routine evaluation of the SCADA data of projects is
key to understanding how the project is performing financially
Operating staff motivation is key to improving real performance of
projects as opposed to just meeting numerical goals
Differing definitions of availability, as calculated by projects,
lends some level of uncertainty around results, but trends of
the results appropriately indicate areas for improvement
Questions?