Você está na página 1de 127

ODISHA POWER TRANSMISSION CORPORATION LTD

(A Govt. of Odisha Undertaking)


Regd. Office, Jan path,
Bhubaneswar - 751022

ODISHA DISTRIBUTION SYSTEM STRENGTHING PROJECT


(ODSSP)

PROJECT MANAGEMENT UNIT

VOL II
Technical Specification
For
Engineering, Supply, Erection & Commissioning of
33/11kV Sub-stations With associated lines

FOR PHASE II (R)


TECHNICAL SPECIFICATION
CONTENT
CHAPTER NO SUB DESCRIPTION PAGE NO
E1 SCOPE OF WORK 1-9
E2 GENERAL TECHNICAL CLAUSES & DESIGN 1-39
E3 SYSTEM AND CLIMATIC CONDITION 1-3
INDOOR SWITCHGEAR GIS/AIS
E4 (VCB, CT, DISCONNECTOR, IVT, PROTECTION RELAY, MULTI 1-72
FUNCTION METER)
E5 OUT DOOR EQUIPMENT
1 POWER TRANSFORMER 1-55
2 STATION TRANSFORMER 1-23
3 33KV VCB 1-9
4 33KV & 11kV CT 1-14
5 33 kV & 11kV IVT 1-11
6 11kV & 33KV SURGE ARRESTOR 1-11
7 11kV & 33KV ISOLATOR 1-13
8 33kV AB SWITCH 1-6
9 SUB STATION STRUCTURE 1-6
10 CT CONSOLE BOX & BMK 1-3
E6 BATTERY AND BATTERY CHARGER 1-16
E7 AC DISTRIBUTION BOARD & DC DISTRIBUTION BOARD 1-19
CONTROL AND PROTECTION PANEL WITH MULTIFUNCTION
E8 1-36
METER & ENERGY METER
E9 1 CONTOL CABLE , XLPE CABLES & LT POWER CABLE 1-49
2 CABLE LAYING 1-18
3 CABLE TERMINATIN AND JOINTING KIT 1-12
E10 LINE MATERIALS
1 NBLS TOWER & ERECTION 1-18
2 JOIST POLE & PSC POLE 1-13
3 V CROSS ARM, BACK CLAMP AND F CLAMP 1-5
4 HT STAY SET & STAY WIRE 1-9
E11 RTU FOR SCADA COMPATIBILITY 1-16
E12 COMMON MATERIALS FOR SUBSTATION AND LINE
1 AAA CONDUCTOR 1-11
2 ACSR- ZEBRA CONDUCTOR 1-10
3 INSULATOR (DISC TYPE) 1-16
4 POST INSULATOR (PIN TYPE) 1-5
5 INSULATOR (POLYMER TYPE) 1-20
6 HARD WARE FITTINGS 1-10
7 HG FUSE 1-4
8 CLAMP AND CONNECTOR 1-7
9 LT DISTRIBUTION BOX 1-8
E13 EARTHING AND EARTHING COIL 1-12
E14 33KV & 11KV LINE AND ERECTION 1-21
E15 CIVIL WORKS 1-32
E16 FIRE FIGHTING AND FIRE DETECTION SYSTEM 1-9
E17 SUBSTATION AND CONTROL ROOM LIGHTING 1-23
E18 AIR CONDITIONING SYSTEM 1-3
TESTING EQUIPMENTS , MAINTENANCE TOOLS, T&P, OFFICE
E19 1-10
EQUIPMENT AND FURNITURES
E20 MANDATORY SPARES (PROVIDED IN THE PRICE SCHEDULE) 1-5
SINGLE LINE DIAGRAM, SCHEMATIC LAYOUT OF SUBSTATION
E21
AND OTHER DRAWINGS
SINGLE LINE DIAGRAM & SCHEMATIC LAYOUT FOR 33kV OUT
1 ENCLOSED
DOOR , 33kV INDOOR GIS & 11kV INDOOR AIS
2 SUBSTATION AND LINE EQUIPMENT DRAWINGS ENCLOSED
3 CIVIL DRAWINGS ENCLOSED
E22 TOPO GRAPH ENCLOSED
E23 VENDOR LIST ENCLOSED
E24 GTP ENCLOSED
E25 WORK COMPLETION SCHEDULE ENCLOSED
CHAPTER - E1

SCOPE OF WORK

VOL-II(TS) E1-SCOPE OF WORK PAGE 1/10


1.0 SCOPE OF WORK:
1.1 Scope of Work for Sub-station & Line

Bidders are requested to visit the site before participating in the Tender.
Scope of work of the Contractor includes Design, Engineering, Supply, Erection,
Testing and Commissioning of all materials & equipment such as

Sub-station:
a) 33/11kV, 3.15MVA /5MVA /8MVA outdoor Power Transformer
b) 33/0.433kV,100 kVA Station Transformer
c) 33kV out door switchyard without door equipment containing Bus bar,
VCB, CT, PT, Surge arrestors and isolator with supporting structures.
d) Substation structures.
e) 33kV GIS indoor Switchgear containing Bus bar, VCB, CT, Bus IVT,
Relays, multifunction meters, energy meters.
f) 11kV AIS indoor Switchgear containing Bus bar, VCB, CT, Bus IVT,
Relays, multifunction meters, energy meters.
g) Distribution Board for both AC & DC
h) Conductors, Insulators, Hardware fitting and Clamps & Connector.
i) 33kV Control and Relay panels with multifunction meter and energy
meter in outdoor Substations and Source Substations.
j) Battery & Battery charger
k) RTU for SCADA
l) AB Switches (for 33 and 11 kV), HG fuses (for 33 and 11 kV) for station
Transformer.
m) XLPE HT cable, LT Power Cables & their jointing kits, Control Cables &
their termination.
n) Earthing.
o) Control Room cum Customer Care Centre Building.
p) Air Conditioner for the building.
q) Fire Fighting equipment.
r) Furniture and PC.
s) Fencing.
t) Boundary wall.
u) Retaining wall.
v) Road.
w) Fire fighting wall.
x) Site surfacing including antiweed treatment.
y) Switchyard illumination.
z) Concrete Cable trench.
aa) Fixing of Danger plate, Bay marking & colour coding.
bb) Excavation of soil for foundation works.
cc) Open cast foundation/Pile foundation.
dd) Leveling of Sub-station area including borrowed earth.

VOL-II(TS) E1-SCOPE OF WORK PAGE 2/10


ee) Bay extension in the source Substation with feeder protection.

Line:-
a) Survey of 33kV & 11kV lines.
b) Profile plotting for 33kV lines and important crossings of 11kV lines such
as river crossing, road crossing, power line/telecommunication line
crossing etc.
c) Preparation of pole schedule.
d) Erection of Galvanised GI H pole/ GI Joist Pole/PSC poles Galvanised
lattice towers (for river crossing, road crossing) including civil works.
e) Open foundation for H poles/Joist Poles/PSC poles.
f) Open foundation and pile foundation of lattice towers.
g) Stringing of conductors
h) Erection of insulators & other hardware fittings.
i) Erection of stay wires with insulator.
j) Earthing of towers/poles.
k) Fixing of number plates, Phase plates. Danger Boards etc.
l) Underground cable with jointing kits and terminations, cable jointing
chambers, in lines associated with GIS substations in Package-5.

1.2 Wherever the source is from an existing 33/11kV S/s of Discom or 132/33 kV or
220/33 kV Grid sub-station of OPTCL , care is to be taken for construction of
bays at the existing Substation end for matching with the existing system. The
dismantling works if any involved shall also be done as per the direction of the
Engineer- in-Charge. Dismantling shall be done by the contractor at his own
cost.

1.3 The scope is on the basis of a single/JV Bidders responsibility, completely


covering supply and erection of all the equipment specified under the
Specifications including other services. It will include the following:

a) Providing Engineering drawings related to foundation details, structural


details of both line & Sub-station work.
b) Providing Equipment data, Operational manual.
c) Preparation of Cable Schedule (in shape of a booklet) etc for the Owners
approval.
d) Packing and transportation from the manufacturers works to the site.
e) Loading, unloading and transportation as required.
f) Receipt, storage, preservation and conservation of equipment at the site
including insurance.
g) Erection, testing and commissioning of all the equipment.
h) Performance and Guarantee tests on completion of commissioning.

The scope of work shall also include all work incidentals for successful
operation and commissioning and handing over of works whether specifically

VOL-II(TS) E1-SCOPE OF WORK PAGE 3/10


mentioned or not. In general, works are to be carried out by the Contractor in
accordance with the stipulations in Conditions of Contract.

1.4 The following items of work are specifically excluded from the Contractors
scope of work unless otherwise specifically brought out.
a) Sub-station site selection
b) Land acquisition for sub-station

1.5 The Chapter E10-1 (NBLS tower and Erection) is not applicable for this
tender. However, the erection practices mention in this chapter shall be
followed for PC+6 tower and UR+6 tower.

2.0 Names of Sub-stations under different packages wind velocity considered in that
area are tabulated below: The design/engineering philosophy of lines in different
wind zones is described in chapter-E2.

PACKAGE-1(CESU - AIS)
Sl.No District Proposed S/s Tapping point Wind
velocity
1 Gopapur Gagana Pokhari
Near Khuntukanta Tarini 200
2 Saranda
Chhaka km /hr
Near Bindanmia By Pass
3 Bandalo
Chhaka
Cuttack
4 Asureswar 33/11kV Danpur S/s
5 Japkuda Balia Grid 300
Raghunathpur 33kV km /hr
6 Somapur
feeder at - Sompur
7 Kula Kapasi Niali 33/11kV S/s
Fategarh 33/11KV
8 Bijipur
Structure
9 Banigochha 33/11kv Daspalla S/s 200
Nayagarh
km /hr
10 Barakoli Khalisahi
11 Lathipada Rajpatna Grid
12 Alagum SAKHIGOPAL S/S
33KV tapping near 300
13 Puri Kalayanpur
KALYANPUR VILLAGE km /hr
14 Sutan 33/11kV S/s Konark
15 Bangurigaon 33/11kV S/s Kakatpur
16 Basantamal 33/11kV S/s Nimapara
Near Sarua Industrial
300
17 Khurda Sarua Estate (33KV Banki
km /hr
Feeder)
18 Trahiachutanagar 33/11kV S/s Pipili

VOL-II(TS) E1-SCOPE OF WORK PAGE 4/10


19 Saranga 4 Pole Structure, Saranga
Mahulpal
20 33/11KV Bhuban S/s
(Bhuban)
33/11kV S/s
21 Jiral 160
Mathakaragola
Dhenkanal
33/11KV Gundichapada km/hr
22 Muktapasi
S/s
33/11KV Hindol Road
23 Babandha
Structure
24 Jiridamali Mathakargola 33KV line
25 Nakchi 33/11KV Bamur S/s
160
26 Anugul Kulad 132/33 KV Chainpal Grid
km/hr
27 Hanumanpur Near Hanumanpur Village
28 Jahara Barimula Danpur S/S
300
29 Kendrapara Chokada 33kV Luna Feeder
km /hr
30 Ayatan 33/11kV S/s Rajkaniaka
31 Duvalo (Borikina) 33/11kV Sova S/s
Baisimouja 33kV feeder at
32 Balia (Adhanga)
- Basantapur
300
33 Jagatsinghpur Bhatapada Taleswar Temple
km /hr
34 Krishnandapur 33/11kV Paruna S/s
From 33/11kV Paradeep
35 Kothi
S/s
300
36 Jajpur Kundala Chandikhol Grid
km /hr
TOTAL 36

Package- 2 (SOUTHO - AIS)

SL. Name of The Project Wind


District Tapping Point
NO. 33/11kV velocity
1 AMBAJHARI GUMMA
2 RAMAGIRI R. UDAYAGIRI GRID 200
Gajapati
MOHANA via km/hr
3 CHANDRAGIRI
LUHAGUDI
BALIPADAR- 200
4 HATITOTA
BUGUDA km/hr
GANJAM 4 POLE STR AT
5 KHANDADEULI 300
HUMA
km/hr
6 M.J. PUR TAKARADA

VOL-II(TS) E1-SCOPE OF WORK PAGE 5/10


DIGAPAHANDI-
7 NUAPADA
CHIKITI
RAJPUR
8 P.S.PUR
(DASIAMARPALLI)
9 TABHAPALLI BUGUDA
10 BANKA BELAGUNTHA
200
11 GAYAGANGDA TILISINGI S/S
km/hr
12 DAHA LALSING
DIGAPAHANDI- 300
13 PALASPUR
ADAPADA km/hr
14 GOJALBADI SORODA S/S 200
15 GALLARY TILISINGI S/S km/hr

16 BARAKHAMA BALLIGUDA
160
KANDHAMAL
km/hr
17 NUAPADAR PHIRINGIA

18 BAGDERI KUNDRA

19 S.B.NUAGAON KUSUMI
HARADULI
20 RANDAPALLI S/S 160
KORAPUT /JAMMUNDA
km/hr
21 BALIA RANDAPALLI S/S
22 NILABADI BANDHUGAON S/S

23 RAMAGIRI BOIPARIGUDA

24 KEUTAGUDA/ANTAMUDA EMALIGUDA
25 KENDUGUDA AKHUSINGI GRID
160
26 JALTARA GUNUPUR
km/hr
Rayagada MUNIGUDA-
27 HATADAHIKHAL AMBADOLA
FEEDER
RAYAGADA-
28 PITAMAHAL
JIMILIPETA FEEDER
160
29 BOUDH RAMBHIKUTA HAREKRUSHNAPUR
km/hr
30 KODINGA KOSAGUMUDA
NABARANGPUR-
31 CHUTIGUDA SANAMASIGAON 160
NABARANGPUR
FEEDER km/hr
32 ANTASORA DANGERBHEJA

VOL-II(TS) E1-SCOPE OF WORK PAGE 6/10


TENTULIKHUNTI
33 ANCHALAGUMA
GRID
160
34 MALKANGIRI BADILI MALKANGIRI
km/hr
Total 34

Package- 3 (NESCO AIS)


SL DISTRICT Wind
Name of The 33/11kV s/s Tapping point
No NAME velocity
1 Durgadevi (Baliapal) Bijipur 33/11kV S/s
2 Manudiha 33kV Basta feeder
3 Kacheripada (Dahipur) 33kV Bahanaga feeder
4 Ajodhya Mitrapur 33/11kV S/s 300
BALASORE
5 Khantapada Bahanagar 33/11kV S/s km / hr
6 Bishnupur 33kV feeder
7 Ada Barahapur 33/11kV S/s
8 Astia(Bati) (Jamujhadi) Markona 33/11kV S/s
33kV Chandaballi
9 Kundibag(Ichhapur)
feeder
10 Asura(AdibasiSahi) Rahanja 33/11kV S/s
11 Bilana Asuralli 33/11kV S/s
300
BHADRAK 33kV Chandaballi
12 Matto km / hr
feeder
13 Manjuri Road Dahala 33/11kV S/s
Dhamanagar 33/11kV
14 Malda
S/s
15 Salabanisahi(Nahadasole) 33kV Betnoti feeder
16 Manda(Jamila,Adisahi) Bisoi 33/11kV S/s
Dhangidisole 33/11kV
17 Sirsa
S/s
160
MAYURBHANJ Shyamakhunta 33/11kV
18 Sapanichua km/hr
S/s
19 Amarda Rajghat 33/11kV S/s
33kV Baripada-Udala
20 Ambadalli
feeder
i) 33 kv Dhenkikote
21 Keonjhar feeder &
ii) Judia 33/11 kv s/s
22 Jagamohanpur Telkoi 33/1 kv S/s
Harichandanpur 33/11 kv
23 Bhagamunda 160
KEONJHAR S/s
km/hr
24 Musakhori Patna 33/11 kv S/s
25 Jyotipur 33 kv Turumunga feeder
26 Kendiposi 33 kv Patna feeder
27 Basudevpur Remuli 33/11 kv S/s
28 Karanjia Champua 33/11 kv S/s

VOL-II(TS) E1-SCOPE OF WORK PAGE 7/10


29 Pipilia Dhenkikote 33/11 kv S/s
Ramachandrapur 33 kv
30 Sainkul
feeder
31 Rekutia Ghasipura 33kV feeder
32 Salabani Anandpur 33/11 kv S/s
33 Salania Orali 33/11 kv s/s
34 Janghira Naranpur 33/11 kv s/s
Harichandanpur 33/11 kv
35 Sunapentha
S/s
36 Dhakotha Ghasipura 33/11 kv S/s
37 Machhagarh Saharpada 33kV feeder
38 Basantpur Jurudi 33/11 kv S/s
39 Damodarpur Sukinda 33/11 kv S/s 300
JAJPUR
40 Narasinghpur Jarka 33kV feeder km/hr
TOTAL 40 nos

Package- 4 (WESCO AIS) (All projects are in 160 km/hr zone)


Sl No. District Name of The Project Tapping point
Name 33/11kV
New 33 KV khariar-Muribhal
1. BAGBAHAL (Belpada)
Feeder
2. GUDIGHAT 33/11 KV substation Muribhal
Kholan-Sindekela33 KV
3. Pandripani
Feeder
4. Balangir BUDHABHAL 33/11 KV substation Deogaon
5. KARAMTALA 33/11 KV substation Saintala
6. Bhadra(Kandakhajuri) 33KV Bolangir- Barpali feeder
7. JURIA (Luhasingha) Patnagarh-Padampur 33 KV
Feeder
8. Atanguda 33/11 KV substation Naktiguda
9. DASPUR 132/33 kv s/s Junagarh
10. Kalahandi JURA DUBRA 33/11 kv substation M. Rampur
11. TULAPADA Narla-Rampur 33 kv line
12. LADUGAON 33/11kV Substation Gadramal
33/11 substation Boden under
13. LESUNPALLI (Rokal)
Nuapada construction
14. CHALNA 33 kv feeder khariar - Sinapali
Sonepur Hedkitikira (Kalapathara) 33KV Line sonpur-Binka
15.
16. RAXA CHOWK 33KV Line Sonpur-Ullunda
17. KANDAPALA 33/11kV Substation Bhukta
18. UDEYPALI 33/11 KV Bhatli
19. Dasmaile 33 KV Turunga -Sohela feeder
Bargarh
20. Gandturum (Mahulpali) 33/11KV substation Khuntlipali
21. BALITIKRA 132/33 KV Substation Barpali
22. Sarandapali 33 KV Bijpur Feeder

VOL-II(TS) E1-SCOPE OF WORK PAGE 8/10


33 KV Agalpur-Melchamunda
23. KUNDAKHAI
feeder
24. LAKHAMARA 33/11 substation Padampur
25. FASIMAL 33/11KV Jamankira Substation
132/33 kv grid substation
26. KUSUMI
Sambalpur kuchinda
27. KADALIGARH 132/33 kv Substation Rairkhol
28. Katarbaga 33KV Loida Feeder
29. Deogarh REAMAL 33/11kV Rengalbeda
30. Jharsuguda LAKHANPUR 132/33 KV substation Remja
31. BALISANKARA 33/11 KV Substation Subdega
33-KV Joda-Tensa NBLS tower
32. Malda (Oraghat)
line
33. JAREIKELA 33/11 KV substation Bisra
34. DALPOSH 33/11 KV substation REC
Sundargarh 33 KV Chhend-koel Nagar
35. Hamirpur (Municipality)
feeder
132/33 KV Kalunga Grid under
36. BIRKERA
construction
37. BILEIMUNDA 33/11 substation Garjhanbhal
38. Tumbapali 33 KV Sagarpali- Lefripada line
Total 38 nos

PACKAGE - 5 (CESU, SOUTHCO, WESCO) - GIS


Sl.No District Proposed S/s Tapping point Wind
velocity
160
Anugul Town Near Telephone Exchange
1 km/hr
2 Pradhan Sahi Ranasinghpur Grid
Dumduma 4P Near Alu gadi flyover
3 300
Khurda
Chakeisiani km/hr
(Rajdhani College Rajdhani College road
4 road)
220/132/33 kV Theruvali
Amlabhata 160
5 Rayagada Grid
km/hr
6 Seriguda Gudari Feeder
Sakiri Khalikote-Rambha Line 300
7 Ganjam km/hr
8 Adava Mohona S/S 200
9 Gajapati K.Sitapur Paralakhemundi Grid km/hr

VOL-II(TS) E1-SCOPE OF WORK PAGE 9/10


New 33 KV Bolangir- 160
Bolangir Madiapali
10 Dungripali Feeder km/hr
132/33 KV substation
Gandhi Chowk
11 Remja 160
Jharsuguda
Tapping from 33-KV km/hr
Durlaga
12 Feeder
13 Sambalpur Kainsar 132/33KV Ganesh Nagar
14 Remad 33/11KV Ainthapali S/s 160
132/33 KV Chhend Grid km/hr
Sundargarh Kalingavihar
15
Total 15nos

VOL-II(TS) E1-SCOPE OF WORK PAGE 10/10


CHAPTER - E2

GENERAL TECHNICAL CLAUSES &


DESIGN

VOL-II(TS) GENERAL TECHNICAL CLAUSES & DESIGN PAGE 1/ 39


TABLE OF CONTENTS
OF
GENERAL TECHNICAL CLAUSES

NO DESCRIPTION PAGENO.
PART-A (GENERAL TECHNICAL CLAUSES)

1.0 General particulars of system 4


2.0 Layout arrangement: 7
3.0 Soil data 7
4.0 Completeness and accuracy of information 8
5.0 Drawings attached with tender document 8
6.0 Compliance with specification 8
7.0 Test and maintenance equipment 8
8.0 Spares 8
9.0 Training 9
10.0 Erection at site and accommodation 10
11.0 Compliance with regulations 10
12.0 Insurance 12

PART B (GENERAL TECHNICAL CLAUSES FOR DESIGN)

1.0 Design & standardisation 14


2.0 Quality assurance 15
3.0 Health, safety & environment (HSE) 16
4.0 Progress reporting 16
5.0 Standards 17
6.0 Language & system of units 18
7.0 Correspondence, drawing, approval procedure and sample 18
8.0 General requirements 21
9.0 Production progress requirements 29
10.0 Wiring, cabling & cable installation 29
11.0 Construction management 36
12.0 Code requirements 36
13.0 Owners supervision 36
14.0 Testing & inspection 37
15.0 Fire precaution 38
16.0 Spanners & special tools 38
17.0 Runway beams, eyebolts & lifting tackle 38

VOL-II(TS) GENERAL TECHNICAL CLAUSES & DESIGN PAGE 2/ 39


PART - A

GENERAL TECHNICAL CLAUSES

VOL-II(TS) GENERAL TECHNICAL CLAUSES & DESIGN PAGE 3/ 39


1. 0 GENERAL PARTICULARS OF SYSTEM

1.1 Substation Philosophy:

1.1.1. There will be two types of Substations.

i. GIS Indoor Substation (Package-5): 33kV side will be with GIS Indoor
Switch gear Panel and 11kV side will be with AIS Indoor Switch gear
Panel. In 33kV GIS Switchgear Panel, bus bar, VCB and Disconnector
will be inside SF6 Gas chamber. Others may be kept as per
manufacturers type tested design.
ii. 33kV outdoor substation (Package 1, Package -2, Package -3 and
Package- 4) 33 kV side will be with outdoor equipment and 11 kV side
will be with AIS Indoor switch gear panel with bus bar, breaker, CTs etc.
1.1.2. The substation sites with SBC up to and including 10 tonne per square metre
will have pile foundation for control room and compound wall. In other areas
there will columns by open cast method.

1.1.3 Normally the Switchyard will be 0.6 mtr above the road level and control
room 0.6 mtr above the Switchyard level except in the following
Substations in flood prone area where the control room will be 1.0 mtr
above the highest flood level. The drawings and BoQ for Substations in
flood prone are have been prepared considering the control room 2.0 mtr
above the road (ground) level. The contractor will redesign the buildings taking
into considearation the HFL of the area and revise the BoQ after approval of
redesigned buildings. Payments will be made as per the revised BoQ on
prorata basis.

Name of Sub stations in flood prone area

Sl no Name of Discom Name of district


Name of substation
1. CUTTACK KULAKAPASI
2. PURI KALYANAPUR
3. BANGURIGAON
4. CESU JAGATASINGHPUR DUVALO
5. BALIA
6. KRISHNANANDAPUR
7. JAJPUR KUNDALA
8. SOUTHCO GANJAM NUAPADA
9. TABHAPALI
10. BALASORE MANUDIHA
11. DURGADEVI
12. BHADRAK BILANA
13. KUNDIBAG(ICHHAPUR)
14. NESCO MATTO
15. MALDA
16. JAJPUR NARASINGHPUR
17. KEONJHAR SALABANI
18. SALANIA

VOL-II(TS) GENERAL TECHNICAL CLAUSES & DESIGN PAGE 4/ 39


1.1.4 11kV XLPE cables from power transformer to indoor switchgear panel in
sub stations will be of three core aluminium, armoured, earthed type
400 sq mm (in AIS substation) and 630 sq mm (in GIS substation).
LT cables shall be of 3 and half core aluminium, XLPE, unarmoured,
Control cables shall be of copper conductor, PVC insulated,
unarmoured type

1.2 Line Philosophy:


i. Lines associated with GIS substation (Package 5)

a) In area with wind velocity 300 km/hr (detailed in clause no. 2.0 of Chapter
1- Scope of work):

33 kV incoming lines will be single core, 400 sq mm aluminium,


metallic sheathed, unarmoured Underground cables and 11 kV out
going lines will be 3 core, 300 sq mm aluminium, armoured
Underground cables. 33 kV incoming lines will be with four nos.
single core cables (one spare Cable) & 11 kV out going lines will
have no spare Cables.

b) In area with wind velocity 200 km/hr and 160 km/hr (detailed in clause
no. 2.0 of Chapter 1- Scope of work):
33kV incoming lines and 11kV out going line to GIS substations will
be with 11mtr GI Joist single poles up to 100 deviation, Single Pole
GI Joist pole with guy wire for more than 10 0 but up to 600 deviation
and DP structure using 11 Mtr GI RS Joist for deviation of more than
600 up to 900.
Normal Span length shall be 50 mtr for 33 kV lines and 60 mtr for 11
kV lines.

ii. Lines associated with AIS Substations (Package -1, 2, 3 and 4)

a) In area with wind velocity 300 km/hr (detailed in clause no. 2.0 of
Chapter 1- Scope of work):

33 kV incoming lines will be with GI 11 mtr height single H pole


(drawings uploaded) up to 100 deviation, Single GI H pole with guy
wire for more than 100 but up to 600 deviation, DP structure using 11
Mtr GI RS Joist for deviation of more than 600 up to 900.

11 kV out going lines will with 11mtr height GI RS Joist single pole up
to 100 deviation, GI RS Joist single pole with guy wire for more than
100 but up to 600 deviation, DP structure using 11 Mtr GI RS Joist for
deviation of more than 600 up to 900.
Normal Span length shall be 50 mtr for both 33 kV lines and 11 kV
lines.
b) In area with wind velocity 200 km/hr (detailed in clause no. 2.0 of
Chapter 1- Scope of work):

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 5/39


33kV incoming lines and 11kV out going lines will be with 11mtr GI
Joist single poles up to 100 deviation, Single Pole GI Joist pole with
guy wire for more than 100 but up to 600 deviation and DP structure
using 11 Mtr GI RS Joist for deviation of more than 600 up to 900.

Normal Span length shall be 50 mtr for 33 kV lines and 60 mtr for 11
kV lines.

c) In area with wind velocity 160 km/hr (detailed in clause no. 2.0 of
Chapter 1- Scope of work):

33kV incoming lines will be with 11mtr GI Joist single poles up to


100 deviation, GI Joist single pole with guy wire for more than 100
but up to 600 deviation and DP structure using 11 Mtr GI RS Joist for
deviation of more than 600 up to 900.

11kV out going lines will be with 10mtr PSC single poles up to 100
deviation, 10 mtr PSC pole with guy wire for more than 10 0 but up to
600 deviation and DP structure using 11 Mtr GI RS Joist for deviation
of more than 600 up to 900.

Normal Span length shall be 60 mtr for 33 kV lines and 70 mtr for 11
kV lines.

iii. Road crossings will be with DP structure with 13 mtr long GI Joist
pole. Where clearance will not be sufficient, it will be with PC or
PC+6 mtr lattice GI tower (drawing uploaded).

iv. For river crossing of 33kV & 11kV Line,


For Span Length from 100mtr 450mtr shall be with PC+6 Tower &
11 Mtr H Pole DP as anchoring and for more than 450mtr shall be
with UR+6 Tower & 11 Mtr H Pole DP as anchoring.
For Span Length from 70mtr to100mtr, it shall be with 14mtr H Pole
DP & 11 Mtr H Pole DP as anchoring.
v. All 33 kV over head lines will be with 148 sq mm All Aluminium Alloy
Conductor (AAAC) and 11 kV lines with 100 sq mm AAAC.

1.3 Transformer Capacity:


In GIS sub stations, the transformers will be of 2X5 MVA or 2X8MVA
capacity. In AIS substations, the transformers will have 2X3.15 or
2X5 MVA or 2X8 MVA capacity.

1.4 RTU for SCADA compatibility:


There is a plan to have SCADA system in future. However RTUs will
be installed now, and will be connected to a local PC for Local Data
Monitoring System (LDMS)

1.5 Qualifying requirement of vendors;


The material offered shall be procured from short listed vendor at
Chapter E-23 and shall have been successfully Type Tested during last five
years on the date of bid opening.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 6/39


For other items which are not in the vendor list, the material offered shall be
in accordance with the REC specifications and procured from a vendor who
must have at least three years experience in manufacturing of the same. In
case of non availability of REC standard for any of these materials, they shall
be as per the IS.

The materials shall have been successfully type tested during last five years
on the date of bid opening. The front page of type test report showing the
evidence of successful type test of the items asked for in our Tender
Specification can be uploaded with the signature of bidder. The full text of the
type test report is to be submitted at the time of signing the agreement or
within one month of LOA.

If OPTCL desires, will ask for another type test, even though type test has
been conducted during last five years from bid submission date. In such
cases OPTCL shall bear the transportation charges of the equipment to
testing laboratory and type test charges. But if there is difference in
design/manufacture/raw material having offered and now tested, all cost for
the type test will be to contractors account.
All items except GIS equipment shall be manufactured in India.

For GIS Equipment, the following criteria are to be fulfilled:


I. The SF6 Gas Insulated Switchgear (GIS) equipment (33 kV or higher
voltage class) should have been manufactured from its manufacturing
base in INDIA.
II. The manufacturer must have been installed at least Two (02) nos. of
GIS substations (33 kV or higher voltage class SF6 Gas Insulated
switchgear with minimum 3 bays in each substation) in India and the
same must be in satisfactory operation for a minimum period of one
(01) year, reckoned from the date of bid opening.
III. The Manufacturer shall have to furnish type test report of SF6 gas
insulated sub-station equipment duly Designed, Manufactured, Tested
(as per IEC standard) which, shall not be older than Ten (10) years, as
on date of bid opening.
Type Test should have been conducted at any of the following
internationally reputed testing laboratories,
(a) KEMA (Holland)
(b) CESI (Italy)
(c) CERDA (France)
(d) PHELA (Germany)
(e) KERI (S.Korea).
(f) CPRI, India
IV. A manufacturer who does not meet the requirement as specified in
serial (II & III) above , but has established production line in India for
manufacturing of SF6 Gas Insulated Switchgear (GIS) based on
technological support of its parent company (Holding Company) can
also be considered provided that they (Parent company) have
manufactured, type tested (as per IEC standard) of such equipment &
with the following stipulation :-

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 7/39


(a) The manufacturers parent company (Holding Company) has
manufactured, type tested (as per IEC standard).
(b) The parent company (Holding Company) meets qualifying
requirements stipulated under serial II and III above.

(c) The manufacturer shall furnish followings:

(1) An undertaking (jointly with the parent company (Holding company) to


Guarantee quality, timely supply, performance and warranty obligations
for a period of five (05) years as specified for the equipment(s) in the
parent companys (Holding Company) letter head, which is required to be
submitted at the time of signing/execution of the contract agreement.

(2) Such manufacturer should submit valid collaboration agreement for


technology transfer / license to design, manufacture, test and supply GIS
equipment(s) in India at the time of bidding.

V. The manufacturer shall submit a list of its past supply experience or of the
parent company (Holding company) for last Five (05) years & Owners
certificate regarding the satisfactory operation/performance for at least one
year for the number of substations and bays at Sl II as mentioned above of
33 kV or above voltage class GIS equipment in India.

2.0 Layout arrangement:


Single line diagram and lay out drawings have been furnished in the bid in
Chapter E21. The work shall be done as per the single line diagram and layout
arrangements. The bay lay out in the source sub-stations shall be prepared by
the contractor in line with the existing arrangement and approved by the
Engineer-in-Charge.

3.0 Soil data


Soil investigations in sub-stations and lines have not been made. The Contractor
shall investigate the soil properties and soil bearing capacity as part of the scope
of work. Bidder can do the soil investigation at its cost for bidding purpose.

4.0 Completeness and accuracy of information


The Contractor shall note that the information provided in the bidding document
and relevant schedules/Annexures may not be complete or fully accurate. For his
own interest the Contractor is advised to make site visits and fully satisfy himself
regarding site conditions in all respects, and shall be fully responsible for the
complete design and engineering of the Sub-stations.

5.0 DRAWINGS ATTACHED WITH TENDER DOCUMENT


Drawings and Technical Particulars provided in Chapter E21 in Chapter E24
respectively are a part of the specification. Bids shall be prepared by the Bidder
based on information provided in the drawings and Technical Particulars/
Schedules. The bidder shall fill up his offered values in the column provided.
However, these values shall not be inferior to the values which the OWNER has
specified in the specification in different chapters.
The bidder shall furnish the drawings and Guaranteed Technical Particulars for
those items which have not been provided in Chapter E21 & E-24 along with the

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 8/39


bid. However the contractor will get these drawings and the GTP approved
before supply/erection of the materials. Contractor shall supply the materials and
execute the works as per these drawings and GTP.

6.0 COMPLIANCE WITH SPECIFICATION


In the event of there being any inconsistency between the provisions of the
General conditions of contract (GCC and the provisions in Technical
Specification, the provisions of the General conditions of contract shall take
precedence for commercial matters and the provisions of Technical Specification
shall take precedence in respect of technical matters.
In case of inconsistency between Technical specification & Price Schedule/Bid
proposal Sheet, quantities of various items as specified in the bid proposal sheet
shall be considered for quoting however the work shall be executed as specified
in the Technical specification and payment will be made as per the work
executed.

7.0 TEST AND MAINTENANCE EQUIPMENT

The Contractor shall supply the test and maintenance equipment specified in the
Chapter E19 of the TS as part of the contract works, and quote price in the Price
Schedule.

8.0 SPARES

a) General
The Contractor shall provide the mandatory spares detailed in the price schedule
with their price. Mandatory spares shall be supplied as part of the Works under
this specification.

The spares shall include consumable items sufficient for an operational period of
5 (five) years after commissioning, as well as essential replacement parts to
cover the event of a break-down which would affect the availability or safety of
the equipment. Spares shall be available during the life of the equipment.

The Contractor shall ensure that sufficient spare parts and consumable items are
available for his own use during commissioning of the plant. Spares ordered by
the Owner shall not be used by the Contractor without the written consent of the
Engg In charge and any spares so used by the Contractor during the
commissioning of the plant shall be replaced by the Contractor at the
Contractors expense.

Any spare Equipment, parts and tools shall be subject to the same specification,
tests and conditions as similar material supplied under the Scope of Works of the
Contract. They shall be interchangeable and suitable for use in place of the
corresponding parts supplied with the plant and must be suitably marked and
numbered for identification and prepared for storage by greasing or painting to
prevent deterioration.

All spare Equipment or materials containing electrical insulation shall be packed


and delivered in cases suitable for storing such parts or material over a period of
years without deterioration. Such cases shall have affixed to both the underside

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 9/39


and topside of the lid a list detailing its contents. The case will remain the
property of the Owner.

9.0 TRAINING

9.1 In accordance with GCC, three categories of training shall be imparted as follows:

a) Indoor /out door major equipment maintenance


b) Operator familiarization
c) Installation and commissioning techniques
d) Use and maintenance of testing equipment and T&P materials
One person for each Sub-station will be trained for a period of 7 days, on Indoor
/out door major equipment maintenance, Operator familiarization, Installation and
commissioning techniques. For testing equipment, the training period shall be
fixed as per the requirement.

9.1.1 Indoor/out door equipment maintenance: Training to be imparted on


operation and maintenance of transformers, switchgear, VCB, CT, IVT,
isolators, battery charger, relays, meters, cable jointing, RTU etc.

9.1.2 Operator familiarization:


This course shall familiarise the Engineers/operators with the system and its
use in operating and controlling. The course shall ensure that the control room
staffs are completely familiar with all operational aspects of the equipment
including software management. The means of obtaining special data, report
logs and all other facilities which would enable the operators to be fully
conversant with the system, shall also be incorporated.

9.1.3 Installation and commissioning techniques:


The Owner's staff or its authorised representative will be present during the
installation and commissioning period and it is essential that they be fully
involved in any on-site corrections or modifications to hardware and software
equipment.

9.1.4 Testing Equipment:


The equipment manufacturer shall demonstrate the testing procedure along
with calibration technique on site.

9.2 Proposals for training and manning


For each course recommended the following information shall be provided:
a) Course name and identification
b) Short description of the curriculum
c) Level of competency required for each course, this can be mutually
decided between the contractor and the owner.
d) Date and duration
e) Maximum number of staff that can attend
f) Location

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 10/39


g) Other important information

The times at which the various training courses will take place shall be stated,
and fully documented notes shall be available to the Owner not later than two
months before the commencement of the course.

All training course notes and documentation shall be in the English language.

10.0 ERECTION AT SITE AND ACCOMMODATION


The Contractor shall provide, at his own cost and expense, all labour, plant and
material necessary for unloading and erection at the Site and shall be entirely
responsible for its efficient and correct operation.

The Contractor shall be responsible for arranging and providing all living
accommodation services and amenities required by his employees.

10.1 SUPERVISION AND CHECKING OF WORK ON SITE


All work on site included in the Contract scope of works shall be supervised by
a sufficient number of qualified representatives of the Contractor.

Before putting any plant or Equipment into operation the Contractor shall satisfy
himself as to the correctness of all connections between the plant and
Equipment supplied under this and other contracts. The Contractor shall advise
the Engg In charge in writing, giving seven days, when the plant or Equipment
is ready for inspection or energisation.

11.0 COMPLIANCE WITH REGULATIONS


All Equipment and material supplied, and all work carried out shall comply in all
respects with such of the requirements of all Regulations and Acts in force in
India as are applicable to the Contract Works and with any other applicable
regulations to which the Owner is subject.
The Contractor shall fully inform himself of the requirements of the local Laws,
Regulations and rules in-force in the State of Orissa, especially with respect to
local employment laws, licensing requirements, electrical safety rules and
regulations, building regulations and planning procedures.
The Contractor shall be responsible for applying for all necessary licenses;
including Electrical Contractors License, Workmans Permits and Certificates of
Competency for Supervisors, and local Government approvals required for the
contract works and for the payment of all necessary fees associated with such
licenses and approvals.
Correspondence with the Electrical Inspector shall be conducted through the
Engg In charge, but the Contractor shall provide all necessary information,
regarding the contract works, as may be required by the Electrical Inspector.

Additionally the Contractor shall also follow the minimum regulations on safety,
employees welfare, industrial relation etc. as stipulated under the relevant Acts
and Rules.

12.0 INSURANCE

12.1 General

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 11/39


In accordance to the clause 69 of the General Conditions of Contract
(Erection), the following provisions will apply towards insurance.
12.2 Workmen's Compensation Insurance
This insurance shall protect the Contractor against all claims applicable under
the Workmens Compensation Act, 1948 (Government of India). This policy shall
also cover the Contractor against the claims for injury, disability, disease or
death of his or his sub-contractor's employees, which for any reason are not
covered under the Workmans Compensation Act, 1948.
12.3 Comprehensive auto mobile insurance
This insurance shall be in a such a form to protect the Contractor against all
claims for injuries, disability, disease and death to members of public including
the OWNER's men and damage to the property of others arising from the use of
motor vehicles during on or off the Site operations, irrespective of the ownership
of such vehicles. The minimum liability covered shall be as herein indicated:
1) Fatal Injury : Rs. 100,000/- each person
2) Property : Rs. 200,000/- each occurrence
3) Damage : Rs. 100,000/- each occurrence

* As per latest prevailing Govt. rules.


12.4 Comprehensive General Liability Insurance
This insurance shall protect the Contractor against all claims arising from
injuries, disabilities, disease or death of members or public or damage to
property of others, due to any act or omission on the part of the Contractor, its
agents, its employees, its representatives and sub-contractors or from riots,
strikes and civil commotion.
The hazards to be covered will pertain to all works and areas where the
Contractor, its sub-contractors, agents and employees have to perform work
pursuant to the Contracts.
The above are only an illustrative list of insurance covers normally required and
it will be the responsibility of the Contractor to maintain all necessary insurance
coverage to the extent both in time and amount to take care of all its liabilities
either direct or indirect, in pursuance of the Contract.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 12/39


PART B

GENERAL TECHNICAL CLAUSES


FOR DESIGN

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 13/39


1.0 DESIGN AND STANDARDISATION

All Equipment shall be designed to ensure satisfactory operation in all atmospheric


conditions prevailing at the Site(s) and during such sudden variation of load and
voltage as may be met with under working conditions on the system, including those
due to faulty synchronising and short circuit.

The design shall incorporate all reasonable precautions and provisions for the safety
of those concerned in the operation and maintenance of the Contract Works and of
associated works supplied under other contracts.

Where the Specification does not contain characteristics with reference to


workmanship, equipment, materials and components of the covered equipment, it is
understood that the same must be new, of highest grade of the best quality of their
kind, conforming to best engineering practice and suitable for the purpose for which
they are intended.

In case where the equipment, materials or components are indicated in the


specification as 'similar' to any special standard, the Engg.-In-charge shall decide
upon the question of similarity. When required by the Specification; or when required
by Engg.-In-charge the Contractor shall submit, for approval, all the information
concerning materials or components to be used in manufacture. Machinery,
equipment, materials and components supplied, installed or used without such
approval shall run the risk of subsequent rejection, it being understood that the cost
as well as the time delay associated with the rejection shall be borne by the
Contractor.

The design of the Works shall be such that installation, future expansions,
replacements and general maintenance may be undertaken with a minimum of time
and expense. Each component shall be designed to be consistent with its duty and
suitable factors of safety, subject to mutual agreements and shall be used throughout
the design. All joints and fastenings shall be so devised, constructed and
documented that the component parts shall be accurately positioned and restrained
to fulfill their required function.

All outdoor Equipment and fittings shall be designed so that water cannot collect at
any point. Grease lubricators shall be fitted with nipples and where necessary for
accessibility, the nipples shall be placed at the end of extension piping.

All water and oil pipe flanges shall be to IS 6392/BS 4504 or other equivalent
standard, as regards both dimensions and drilling, unless otherwise approved.

Cast iron shall not be used for chambers of oil filled Equipment or for any part of the
equipment which is in tension or subject to impact stresses.

Kiosks, cubicles and similar enclosed compartments shall be adequately ventilated to


restrict condensation. All contactor or relay coils and other parts shall be suitably
protected against corrosion.

All Equipment shall be designed to obviate the risk of accidental short circuit due to
animals, birds, insects, mites, rodents or micro-organisms.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 14/39


Corresponding parts shall be interchangeable. Where required by the Engg. In
charge the Contractor shall demonstrate this quality.

2.0 QUALITY ASSURANCE

The quality assurance arrangements shall conform to the relevant requirements of


ISO 9001 or ISO 9002 as appropriate.

The systems and procedures which the Contractor will use to ensure that the Works
comply with the Contract requirements shall be defined in the Contractors Quality
Plan for the Works.

The Contractor shall operate systems which implement the following:


Hold Point A stage in the material procurement or workmanship process beyond
which work shall not proceed without the documented approval of designated
individuals or organisations.
The Engg. In charge written approval is required to authorise work to progress
beyond the Hold Points indicated in approved Quality Plans.
Notification Point A stage in material procurement or workmanship process for
which advance notice of the activity is required to facilitate witness.
If the Engg. In charge / his authorised person does not attend after receiving
documented notification in accordance with the agreed procedures and with the
correct period of notice then work may proceed.

The following will be the hold points in the contract

i) Sub-structure (Foundation concreting in substation and line)


ii) Roof casting
iii) Stringing of conductor
iv) Acceptance Tests of materials to be supplied in Manufactures premises
v) Stage inspection of transformers
vi) Testing and Commissioning

2.1 Quality plans


The Contractor shall draw up for each section of the work Manufacturing Quality
Plans (MQP) and Field Quality Plan (FQP), which shall be submitted to the Engg. In
charge for approval at least two weeks prior to commencement of the particular
section. Each Quality Plan shall set out the activities in a logical sequence and,
unless advised otherwise, shall include the following:
a) An outline of the proposed work and program sequence
b) The duties and responsibilities assigned to staff ensuring quality of work for
Contract
c) Hold and Notification points
d) The inspection of materials and components on receipt
e) Reference to the Contractors work procedures appropriate to each activity
f) Inspection during fabrication/construction
g) Final inspection and test

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 15/39


Non-conforming product
The Contractor shall retain responsibility for the disposition of non-conforming items.

2.2 Monitoring of quality arrangements


During the course of the Contract the Engg. In charge will monitor the implementation
of the Quality Assurance arrangements. Monitoring will be by surveillance of the
activities at work locations and/or by formal audits of the adherence of the Contractor
to the systems and procedures which constitute his Quality Assurance arrangements.
Corrective actions shall be agreed and implemented in respect of any deficiencies

The Contractor shall provide any facilities, including access, which may be required
by the Engg. In charge for monitoring activities.

3.0 HEALTH, SAFETY AND ENVIRONMENT (HSE) PLAN

3.1 General

Within one month of award of contract the Contractor shall produce an HSE Plan for
the contract and submit for the approval of the Engg. In charge. The HSE Plan is
described in the following sections.

The primary objective of the HSE Plan is for the contractor to demonstrate that he
has the capability to carry out the contract work in a cost effective manner, giving due
consideration to the Health, Safety and Environmental management of both his own
employees, those of the Owner and anyone who may be affected by his activities.

3.2 General structure of HSE Plan

The HSE Plan shall conform to the following general structure:

i. Statutory obligations are complied with


ii. Safety training, both general induction and trade specific, is given to
all site employees.
iii. Appropriate personal safety equipment regulations are developed
and enforced.
iv. Regular Safety meetings are held with all Site contract employees.
v. Safety inspections are carried out and reported.
vi. Accident statistics are prepared and issued monthly and are
displayed at site.
vii. All Lost Time or serious incidents are reported to OPTCL within 8
hours.
viii. Adequate first aid and medical facilities are provided and maintained
at Site(s) to handle routine medical examinations, illness, and
accidents.
ix. Appropriate emergency services and procedures are in place at the
Site(s) including evacuation to the nearest hospitals.
x. Entrance to Site(s) is controlled, monitored and recorded.
xi. Appropriate security measures are enforced.

4.0 PROGRESS REPORTING


The Contractor shall submit for approval, the detailed project schedule for
engineering, material procurement, site mobilisation, man and machine deployment,
delivery, erection, testing, commissioning, and handing over programme etc. in line

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 16/39


with the outline project schedule furnished by the owner in corrigendum. The
Contractor shall submit periodical progress reports (weekly, fortnightly, monthly and
quarterly) whose details will be in accordance with GCC and will be decided at the
time of signing the contract agreement. The reports shall show clearly and accurately
the position of all activities associated with engineering, material procurement, works
tests, shipping, site erection, testing and commissioning with regard to the agreed
contract programme.

In addition to the routine monthly progress report the Contractor shall also submit to
the Engg. In charge by the 25th day of every month, a man hour schedule for the
following month, detailing the man hours scheduled for that month, skill-wise and
area-wise.

The preferred format for presentation of programmes is the latest version of


MS Project. The programmes and monthly updates shall be submitted on CD.

The position on material procurement shall give the date and details of orders placed
and indicate the delivery date quoted by the manufacturer. If any delivery date has an
adverse affect on the contract programme the Contractor shall state the remedial
action taken to ensure that delays do not occur.

The position on manufacture shall indicate the arrival of material, the progress of
manufacture and date at which the equipment will be ready for transport. Any events
that may adversely affect completion in the manufacturers works shall also be
reported.

All works tests executed shall be listed and the test-results shall be remarked upon.
Any test failures shall be highlighted and the Contractor shall detail the necessary
steps taken in order to avoid any adverse affect on the contract completion dates.

The despatch of each order shall be monitored on the progress report giving the date
by which the equipment will be available for transport, the estimated time of arrival on
site and the dates actually achieved.

The site works shall be segregated into foundation, super structure erection,
equipment installation, control room building construction, testing & commissioning
etc for reporting purposes and each section of the site works shall be monitored
giving the percentage completion and the estimated completion date in accordance
with the contract programme. The number of men working on site, both labour and
supervisory staff, shall be reported together with any incidents or events that may
affect the progress of site works.

Any delays which may affect any milestone or final completion dates shall be detailed
by the Contractor who shall state the action taken to effect contract completion in
accordance with the contract programme.

The contractor shall provide two copies of the progress report to the Engg. In charge.

5.0 STANDARDS
Except where otherwise specified or implied, the Contract Works shall comply with
the latest edition of the relevant Indian Standards, International Electro technical
Commission (IEC) standards and any other standards mentioned in this
Specification. The Contractor may submit for approval, equipment or materials

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 17/39


conforming to these specifications. In case of conflict the order of precedence shall
be (1) IS, (2) IEC.

Reference to a particular standard or recommendation in this Specification does not


relieve the Contractor of the necessity of providing the Contract Works complying
with other relevant standards or recommendations.

The contractor shall furnish a copy of all standards (IEC/IS) within one month
of LOA

6.0 LANGUAGE AND SYSTEM OF UNITS


The English language shall be used in all written communications between the
Owner and the Contractor with respect to the services to be rendered and with
respect to all documents and drawings procured or prepared by the Contractor
pertaining to the work, unless otherwise agreed by the Owner.

It is required that danger plates, equipment designation labels or plates, instruction


notices on plant and general substation notices be written in English, Hindi and Odia.
Control switch and lamp labels, indicator lamp and annunciator inscriptions shall be
in English only.

The Contractor must furnish a schedule giving the English, Hindi and Oriya version of
all labels, notices, etc., for approval.

The design features of all equipment shall be based on the SI system of units.

7.0 CORRESPONDENCE, DRAWINGS, APPROVAL PROCEDURE AND SAMPLES

7.1 Correspondence
All correspondence shall be addressed to the Project Manager, Project Management
Unit-33/11kV, OPTCL or the Engineer-In-charge.

7.2 Drawings and samples

Within 15 days of contract commencement the Contractor shall submit, for approval
by the Engg. In charge a schedule of the drawings to be produced detailing which are
to be submitted for Approval and which are to be submitted For Information Only.
The schedule shall also provide a programme of drawing submission, for approval by
the Engg. In charge that ensures that all drawings and calculations are submitted
within two months.

All drawings submitted by the Contractor shall be in sufficient detail to indicate the
type, size, arrangement, material description, Bill of Materials, weight of each
component, break-up for packing and shipment, the external connections, fixing
arrangement, and the dimensions, required for installation and interconnections with
other equipment and materials, clearances and spaces required for installation and
interconnections between various portions of equipment and any other information
specifically requested in the specification.

All dimensions marked on drawings shall be considered correct although


measurement by scale may differ from general arrangement drawings. Detailed
drawings shall be worked to where they differ from general arrangement drawings.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 18/39


All detail drawings submitted for approval shall be to scale not less than 1: 20. All
important dimensions shall be given and the material of which each part is to be
constructed shall be indicated on the drawings.

All documents, drawings and samples shall be submitted in accordance with the
provisions of this Specification and shall become the property of the Owner.

All drawings and calculations, submitted to the Engg. In charge shall be on


international standard size paper, A0, A1, A2, A3 or A4. All such drawings and
calculations shall be provided with a contract title block and shall be assigned a
unique project drawing number; the contact title block and project numbering system
shall be agreed with the Engg. In charge.

All drawings for approval shall have the OPTCL-LOGO.

Technical drawings must be shown, in such a form that the information necessary to
construct an installation or part of an installation must be understandable by the
technicians/skilled workmen responsible for construction and supervision. The
drawings must therefore conform to following standards.

For presentation of design drawings and circuit documents IEC Publication 617 or
equivalent standards for graphical symbols are to be followed.

Script sizes and thickness of scripts and lines be selected so that if reduced by two
stages the alphanumeric characters and lines are still perfectly legible so as to
microfilm them.
7.3 Approval procedure
The Contractor shall submit all drawings and samples for approval in sufficient time
to permit modifications to be made if such are deemed necessary, and the drawings
and samples to be re-submitted without delaying the initial deliveries or completion of
the Contract Works. The following schedule shall be adhered for submission,
approval, re-submission and final distribution drawings/ documents.

Initial submission: All drawings, designs and documents


requiring approval of Engg. In charge - not
later than 30 days from award of contract.
Approval /comments of 1st Within 15 days of receipt.
submission:
Re-submission where required: Within 7 days of receipt including postal
time both ways.
Approval/comments of re- Within 7 days of receipt.
submission:
Submission of distribution copies: Within 15 days of approval.

Three copies of all drawings shall be submitted for approval and three copies for any
subsequent revision. The Engg. In charge reserves the rights to request any
additional information that may be considered necessary in order to fully review the
drawings. Drawings for approval shall be submitted as paper prints and shall bear the
approved contract references. Submittal should where possible be staggered to
facilitate maintenance of the above schedule.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 19/39


If the Engg. In charge is satisfied with the drawing, one copy will be returned to the
Contractor marked with Approved stamp. If the Engg. In charge is not totally
satisfied with the drawing, then Approved subject to comment status will be given
to it and a comment sheet will be sent to the Contractor. If the drawing does not
comply with the requirements of the specification then it will be given Not
Approved status and a comment sheet will be sent to the Contractor. In both the
latter cases the Contractor will have to modify the drawing, update the revision
column and resubmit for final approval.

Following approval copies of final drawings will be required as given below.

a) Hard Copies on paper (Blue print or Xerox) : Equal to the number s/s in
the package
b) Computer CD ROM : 1 copy

Any drawing or document submitted for information only should be indicated as such
by the Contractor. Drawings submitted for information only will not be returned to the
Contractor unless the Engg-In-charge considers that such drawings do need to be
approved, in which case they will be returned suitably stamped with comments.

Drawings, samples and models submitted by the Contractor and approved by the
Engg-In-charge shall not be departed from without the instruction in writing of the
Engg-In-charge.

The Contractor shall be responsible for any discrepancies or errors in or omissions


from the drawings, whether such drawings have been approved or not by the Engg-
In-charge. Approval given by the Engg-In-charge to any drawing or sample shall
neither relieve the Contractor from his liability to complete the Contract Works in
accordance with this Specification and the conditions of contract nor exonerate him
from any of his guarantees.

7.4 Final as-built drawings


After completion of work on site all drawings shall be revised where necessary to
show the equipment as installed and three copies submitted duly signed by site-in-
charge. Following approval, twenty prints shall then be provided as required by the
Engg-In-charge and shall be of sufficient detail to enable all parts to be identified.
The contractor shall also submit, where possible, digitally stored copies of all as-built
drawings on disc or CD-ROM (02nos. CD-ROM i.e. one is readable and other is
editable) in a format compatible with the Owners drawing system.

7.5 Operation and Maintenance Manuals


Three months prior to the contractual completion date for each substation site the
Contractor shall forward to the Engg-In-charge through PMC, two copies of the
Operation and Maintenance Manual unique to the substation site being handed over.

After approval by the Engg-In-charge the Contractor shall deliver ten (10) copies of
the complete manual.

The Taking over Certificate will not be issued until the required numbers of approved
copies of the manuals have been provided by the Contractor.

The manuals shall be as complete and as specific as possible and shall incorporate
documentation that is specific to the materials and equipment used on the contract.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 20/39


Because the nature of the work varies from site to site the manuals will have to be
tailored to the specific needs of each site.

All precautions and warnings relative to the safety of life and equipment shall be
included in the manuals.

The manuals should also show exploded views wherever required. Mass and size of
parts and quantities of oil

Each item shall be labeled to indicate its mass, quantity of oil (if any) and any special
handling instructions.

8.0 GENERAL REQUIREMENTS

8.1 Bolts and nuts


All bolts, studs, screw threads, threads, bolt heads and nuts shall comply with the
Indian Standard.

Except for small wiring, current carrying terminal bolts or studs, for mechanical
reasons, shall not be less than 6 mm in diameter.

All nuts and pins shall be adequately locked.

Wherever possible bolts shall be fitted in such a manner that in the event of failure of
locking resulting in the nuts working loose and falling off, the bolt will remain in
position.

All bolts, nuts and washers placed in outdoor positions shall be treated to prevent
corrosion, by hot dip galvanising or electro galvanising to service condition.
Appropriate precautions shall be taken to prevent electrolytic action between
dissimilar metals.

Where bolts are used on external horizontal surfaces where water can collect,
methods of preventing the ingress of moisture to the threads shall be provided.

Each bolt or stud shall project at least one thread but not more than three threads
through its nut, except when otherwise approved for terminal board studs or relay
stems. If bolts and nuts are placed so that they are inaccessible by means of ordinary
spanners, special spanners shall be provided.

The length of the screwed portion of the bolts shall be such that no screw thread may
form part of a shear plane between members.

Taper washers shall be provided where necessary.

Protective washers of suitable material shall be provided front and back on the
securing screws.

In the Price Schedule , the price quoted for each item shall be inclusive of Nuts,
Bolts, Washers and other petti materials require for completion of the
structures, Towers etc irrespective of their mention.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 21/39


8.2 Galvanising.

8.2.1 General
All machining, drilling, welding, engraving, scribing or other manufacturing activities
which would damage the final surface treatment shall be completed before the
specified surface treatment is carried out.

8.2.2 Galvanising
All metal surfaces shall be subjected to treatment for anti-corrosion protection. All
ferrous surfaces for external use shall be hot dip galvanised. High tensile steel nuts,
bolts and spring washers shall be electro galvanised to service condition. All steel
conductors including those used for earthing and grounding (above ground level)
shall also be galvanised according to IS 2629.

All galvanising shall be applied by the hot dip process and shall comply with IS 2629,
IS 2633, IS 4759, IS 1367 or IS 6745.

All welds shall be de-scaled, all machining carried out and all parts shall be
adequately cleaned prior to galvanising. The preparation for galvanising and the
galvanising itself shall not adversely affect the mechanical properties of the coated
material.

The threads of all galvanised bolts and screwed rods shall be cleared of spelter by
spinning or brushing. All nuts shall be galvanised with the exception of the threads
which shall be oiled. Surfaces which are in contact with oil shall not be galvanised or
cadmium plated.

Partial immersion of the work will not be permitted and the galvanising tank must
therefore be sufficiently large to permit galvanising to be carried out by one
immersion.
Galvanising of wires shall be applied by the hot dip process and shall meet the
requirements of IS 2141.
The minimum weight of the zinc coating shall be 610 gm/sq.m and minimum
thickness of coating shall be 86 microns for all items thicker than 5 mm. For items of
less than 5 mm thickness requirement of coating thickness shall be as per BS 729.
For surface which shall be embedded in concrete, the zinc coating shall be a
minimum of 800 gm/sq.m.

The galvanised surfaces shall consist of a continuous and uniform thick coating of
zinc, firmly adhering to the surface of steel. The finished surface shall be clean and
smooth and shall be free from defects such as discoloured patches, bare spots,
unevenness of coating, spelter which is loosely attached to the steel globules, spiky
deposits, blistered surface, flaking or peeling off, etc. The presence of any of these
defects noticed on visual or microscopic inspection shall render the material liable to
rejection.
After galvanising no drilling or welding shall be performed on the galvanised parts of
the equipment excepting that nuts may be threaded after galvanising. Sodium
dichromate treatment shall be provided to avoid formation of white rust after hot dip
galvanisation.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 22/39


The galvanised steel shall be subjected to six one minute dips in copper sulphate
solution as per IS 2633.

Sharp edges with radii less than 2.5 mm shall be able to withstand four immersions of
the Standard Preece test. All other coatings shall withstand six immersions. The
following galvanising tests should essentially be performed as per relevant Indian
Standards:
a) Coating thickness
b) Uniformity of zinc
c) Adhesion test
d) Mass of zinc coating

Galvanised material must be transported properly to ensure that galvanised surfaces


are not damaged during transit. Application of zinc rich paint at site shall not be
allowed.

8.3 Cleaning, painting and tropicalisation


8.3.1 General
All paints shall be applied in strict accordance with the paint manufacturers
instructions.
All painting shall be carried out on dry and clean surfaces and under suitable
atmospheric and other conditions in accordance with the paint manufacturers
recommendations.
An alternative method of coating equipment such as with epoxy resin cast-based
coating powders will be permitted, subject to the approval of the Engg-In-charge and
such powders shall comply with the requirements of IEC 455. The Contractor shall
provide full details of the coating process to the Engg-In-charge for approval.
It is the responsibility of the Contractor to ensure that the quality of paints used shall
withstand the tropical heat and extremes of weather conditions specified in the
schedules. The paint shall not peel off, wrinkle, be removed by wind, storm and
handling on site and the surface finish shall neither rust nor fade during the service
life of the equipment.
The colours of paints for external and internal surfaces shall be in accordance with
the approved colour schemes.

8.3.2 Works painting processes


All steelworks, plant supporting steelworks and metalwork, except galvanised
surfaces or where otherwise specified, ISO standards. All sheet steel work shall be
degreased, pickled, phosphated in accordance with the IS 6005 Code of Practice for
phosphating iron and sheet steel. All surfaces shall then be painted with one coat of
epoxy zinc rich primer, two pack type, to a film thickness of 50 microns. This primer
shall be applied preferably by airless spray and within twenty minutes but not
exceeding one hour of shot blasting.

All rough surfaces of coatings shall be filled with an approved two pack filler and
rubbed down to a smooth surface.

The interior surfaces of all steel tanks and oil filled chambers shall be shot blasted in
accordance ISO, and painted within a period of preferably twenty minutes, but not

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 23/39


exceeding one hour with an oil resisting coating of a type and make to the approval
of the Engg-In-charge.

The interior surfaces of mechanism chambers, boxes and kiosks, after preparation,
cleaning and priming as required above, shall be painted with one coat zinc chromate
primer, one coat phenolic based undercoating, followed by one coat phenolic based
finishing paint to a light or white colour. For equipment for outdoor use this shall be
followed by a final coat of anti-condensation paint of a type and make to the approval
of the Engg. In charge to a light or white colour. A minimum overall paint film
thickness of 150 microns shall be maintained throughout.

All steelworks and metalwork, except where otherwise specified, after preparation
and priming as required above shall be painted with one coat metallic zinc primer and
two coats of micaceous iron oxide paint followed by two coats of either phenolic
based or enamel hard gloss finished coloured paint to the approval to an overall
minimum paint film thickness of 150 microns.

Galvanised surfaces shall not be painted in the works.

All nuts, bolts, washers etc., which may be fitted after fabrication of the plant shall be
painted as described above after fabrication.

The painted metal works shall be subjected to paint qualification test as per IEEE-Std
37.21 -1985 clause 5.2.5.

8.3.3 Site Painting

After erection at site, the interior surfaces of mechanism chambers and kiosks shall
be thoroughly examined, and any deteriorated or mechanically damaged surfaces of
such shall be made good to the full Specification described above.
After installation/erection at site all surfaces of steel works and metal work shall be
thoroughly washed down. Any deteriorated or otherwise faulty paint-work removed
down to bare metal and made good to the full Specification described above, then
painted one further coat of phenolic based undercoating and one coat phenolic
based hard gloss finishing paint to provide an overall minimum paint film thickness of
200 microns.
Any nuts, bolts, washers, etc., which have been removed during site erection, or
which may be required to be removed for maintenance purposes shall be restored to
their original condition.
All paint work shall be left clean and perfect on completion of the works.
8.3.4 Colour Schemes
The Contractor shall propose a colour scheme for the Sub-station for the approval of
Engg-In-charge. The decision of Engg-In-charge shall be final. The scheme shall
include:
a) Finishing colour of indoor equipment
b) Finishing colour of outdoor equipment
c) Finish colour of all cubicles
d) Finishing colour of various auxiliary system equipment including piping.
e) Finishing colour of various building items.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 24/39


All steel structures, plates etc. shall be painted with non-corrosive paint on a suitable
primer. It may be noted that normally all electrical equipment of the Owners
switchyard are painted with shade 631 of IS:5 and Owner will prefer to follow the
same for this project also. All indoor cubicles shall be of same colour scheme. For
other miscellaneous items colour scheme will be subject to the approval of the Engg.
In charge.
Table for Recommended colour schemes

Sl. Equipment Application Environment


No.
Indoor Outdoor
Colour Code Colour Code
IS:5 IS:5
33/11 kV Class Equipment
1 Transformers - - Light grey 631

2 Marshalling boxes, CTs, Light 697 Light 697


PTs, CVTs, Surge counter Admiralty Admiralty
casings, junction boxes etc. grey grey
3 Control and Relay Panels, Smoke grey 692 - -
PLCC cabinets, RTU panel
etc.
4 Porcelain parts i.e. Dark brown 412 Dark brown 412
insulators
5 All structures/ metallic parts Hot dip galvanised
exposed to atmosphere

33kV Class equipment


6 Switchgear cubicles Smoke grey 692 Light grey 631

7 Control and relay panels Smoke grey 692 - -

LT switchgear
8 LT switchgear exterior Smoke grey 692 Light grey 631
9 ACDB/ MCC Smoke grey 692 Light grey 631
10 DCDB Smoke grey 692
11 LT bus duct in side Matt Paint
enclosure
12 LT bus duct outside Smoke grey 692
enclosure
13 Motors Smoke grey 692 Light grey 631

14 Diesel generator engine Smoke grey 692

15 Diesel generator Smoke grey 692


16 LT transformers Smoke grey 692 Light grey 631

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 25/39


17 Battery charger Smoke grey 692
18 Mimic diagram
33kV Sky blue 101
11kV Signal red 537
Canary 309 - -
415V yellow - -
Middle 411
brown - -
Miscellaneous
19 Control modules and Smoke grey 692 Light grey 631
console inserts
20 Lighting package Light grey 631 Light grey 631
equipment outside
21 Lighting package Glossy white Glossy
equipment inside white
22 Water pipes sea green 217 sea green 217
23 Air pipes Sky blue 101 Sky blue 101
24 Transformer oil pipes Light brown 410 Light 410
brown
25 Fire Installations Fire red 536 Fire red 536
26 Insulating oil/ gas treatment Gulf red 473 Gulf red 473
plant

8.4 Provision for exposure to hot and humid climate


Outdoor equipment supplied under the Specification shall be suitable for service and
storage under tropical conditions of high temperature, high humidity, heavy rainfall
and environment favourable to the growth of fungi and mildew. The indoor
equipments located in non air-conditioned areas shall also be of same type.
8.4.1 Anti-condensation Provisions:
Space heaters where provided shall be suitable for continuous operation at 240V
supply voltage. On-off switch and fuse shall be provided.

One or more adequately rated permanently or thermostatically connected heaters


shall be supplied to prevent condensation in any compartment. The heaters shall be
installed in the lower portion of the compartment and electrical connections shall be
made from below the heaters to minimise deterioration of supply wire insulation. The
heaters shall be suitable to maintain the compartment temperature at approximately
100C, above the outside air temperature to prevent condensation. This shall be
demonstrated by tests.

8.4.2 Fungi static treatment


Besides the space heaters, special moisture and fungus resistant varnish shall be
applied to parts which may be subjected or predisposed to the formation of fungi due
to the presence or deposit of nutrient substances. The varnish shall not be applied to
any surface or part where the treatment will interfere with the operation or
performance of the equipment. Such surfaces or parts shall be protected against the
application of the varnish.

8.4.3 Ventilating specifications


In order to ensure adequate ventilation, compartments shall have ventilation
openings provided with fine wire mesh of brass or galvanised steel to prevent the

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 26/39


entry of insects and to reduce to a minimum the entry of dirt and dust. Outdoor
compartment openings shall be provided with shutter type blinds.

8.4.4 Labels and plates


All Equipment shall be clearly labeled indicating, where necessary, its purpose and
service positions. Each phase of alternating current and each pole of direct current
equipment and connections shall be coloured in an approved manner to distinguish
phase or polarity.

The material of all labels and the dimensions, legend, and method of printing shall be
to approval. The surface of indoor labels shall have a matt or satin finish to avoid
dazzle from reflected light.

Colours shall be permanent and free from fading. Labels mounted on black surfaces
shall have white lettering. Danger plates shall have red lettering on a white
background. Please refer to drawing no. ODSSP/LINE/15.

All labels and plates for outdoor use shall be of non corroding material. Where the
use of enameled iron plates is approved, the whole surface including the back and
edges shall be properly covered and resistant to corrosion. Protective washers of
suitable material shall be provided front and back on the securing screws.

Labels shall be engraved in Hindi, English and Oriya. Name plates shall be white with
black engraved lettering and shall carry all the applicable information specified in the
applicable items of the Standards.

Any other relevant information which may be required for groups of smaller items for
which this is not possible e.g. switch bays etc. a common name plate in Oriya with
the title and special instructions on it shall be provided.

No scratching, corrections or changes will be allowed on name plates.

All equipment mounted on front and rear sides as well as equipment mounted inside
the panels shall be provided with individual name plates with equipment designation
engraved.

On the top of each panel on front as well as rear sides large name plates with bold
size lettering shall be provided for circuit/ feeder/ cubicle box designation.

All front mounted equipment shall be also provided, at the rear, with individual name
plates engraved with tag numbers corresponding to the one shown in the panel
internal wiring to facilitate tracing of the wiring. The name plates shall be mounted
directly by the side of the respective equipment wiring.

Name plates of cubicles and panels may be made of non rusting metal or 3 ply
lamicoid. These name plates may be black with white engraved lettering.

The name plate inscription and size of name plates and letters shall be submitted to
the Engg-In-charge for approval.
The name plates of the Equipment shall include, at least, the information listed below,
together with any other relevant information specified in the applicable standards:
a) Concise descriptive title of the equipment
b) Rating and circuit diagrams

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 27/39


c) Manufacturer's name, trade-mark, model type, serial number
d) Instruction book number
e) Year of manufacture
f) Special instructions, if any, about storage, transportation, handling etc.

Each measuring instrument and meter shall be prominently marked with the quantity
measured e.g. kV, A, MW etc. All relays and other devices shall be clearly marked
with manufacturers name, type, serial number and electrical rating data.

Danger plates and plates for phase colours shall be provided as per requirement.
The Contractor shall devise a system to designate equipment and sub-systems. The
nameplates/labels displaying these designations shall be installed at appropriate
locations. Whenever motion or flow of fluids is involved, plates showing direction of
motion or flow shall also be provided.

8.5 Padlocks
For each item of plant the Contractor shall provide a pad lockable handle and a non-
ferrous padlock with different key changes in order to prevent access to control
cabinets, cubicles and relay panels. The Contractor shall provide two keys for each
lock and a master key for each substation.

Cabinets for the accommodation of padlocks and keys, whilst not in use, shall be
provided and shall be suitably labeled so that keys will be readily identifiable.

8.6 Earthing
Metal parts of all equipment other than those forming part of an electrical circuit shall
be connected directly to the main earth system via two separate conductors of
adequate capacity at two different points.

All main members of structural steelworks shall be earthed by galvanised iron flat
connections bonded by welding or bolting to the steelworks.

Connections to Equipment and structures shall be made clear of ground level,


preferably to a vertical face and protected as appropriate against electrolytic
corrosion. They shall be made between clean surfaces and of sufficient size and
pressure to carry the rated short circuit current without damage.

Earth bars installed directly into the ground should normally be laid bare and the
trench back-filled with a fine top soil. Where the soil is of a hostile nature, special
precautions must be taken to protect the earth bar, the method used being subject to
the agreement of the Engg. In charge.

Joints in earth bars shall be welded and then coated with a suitable anti-corrosion
protection treatment.

Facilities shall be provided on the earth bar run between equipment and the base of
structures, comprising a looped strip, so as to permit the attachment of portable
earth connections for maintenance purposes.

The cross sectional area of the earth bar and connections shall be such that the
current density is not greater than 100 A/mm2 for a 3 second fault duration.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 28/39


8.7 Lubrication
Bearings which require lubrication either with oil or grease shall be fitted with nipples.

9.0 PRODUCTION PROCESS REQUIREMENTS

9.1 Castings
9.1.1 General
All castings shall be true to pattern, free from defects and of uniform quality and
condition. The surfaces of castings which do not undergo machining, shall be free
from foundry irregularities. The castings shall be subject to NDT, chemical,
mechanical and metallographic tests. Details of the same shall be furnished to
Engg.-In-charge for review/approval. Magnetic particle inspection (MPI) test,
wherever applicable, shall be carried out in longitudinal and transverse direction to
detect radial and axial cracks.
9.2 Welding
All welding shall be in accordance with the corresponding Indian standards.

10.0 WIRING, CABLING AND CABLE INSTALLATION IN SUB STATION


10.1 Cubicle wiring
Panels shall be complete with interconnecting wiring between all electrical devices in
the panels. External connections shall be achieved through terminal blocks. Where
panels are required to be located adjacent to each other all inter panel wiring and
connections between the panels shall be carried out internally. The Contractor shall
furnish a detailed drawing of such inter panel wiring. The Contractor shall ensure the
completeness and correctness of the internal wiring and the proper functioning of the
connected equipment.

All wiring shall be carried out with 1.1 kV grade, PVC insulated, single core, stranded
copper wires. The PVC shall have oxygen index not less than 29 and Temperature
index not less than 250C. The wires shall have annealed copper conductors of
adequate size comprise not less than three strands

The minimum cross sectional area of the stranded copper conductor used for internal
wiring shall be as follows:
a) All circuits excepting CT circuits and energy metering circuit of VT 2.5 sq.mm
b) All CT circuits and metering circuit of VT 2.5 sq. mm
All internal wiring shall be supported, neatly arranged, readily accessible and
connected to equipment terminals and terminal blocks. Wiring gutters and troughs
shall be used for this purpose.
Cubicle connections shall be insulated with PVC to IEC 227. Wires shall not be
jointed or teed between terminal points.
Bus wires shall be fully insulated and run separately from one another. Auxiliary bus
wiring for AC and DC supplies, voltage transformer circuits, annunciation circuits and
other common services shall be provided near the top of the panels running
throughout the entire length of the panel suite. Longitudinal troughs extending
throughout the full length of panel shall be preferred for inter panel wiring.
All inter connecting wires between adjacent panels shall be brought to a separate set
of terminal blocks located near the slots of holes meant for the passage of the inter
connecting wires. Interconnection of adjacent panels on site shall be straightforward

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 29/39


and simple. The bus wires for this purpose shall be bunched properly inside each
panel.
Wire termination shall be made with solder less crimping type and tinned copper lugs
which firmly grip the conductor. Insulated sleeves shall be provided at all the wire
terminations. Engraved core identification plastic ferrules marked to correspond with
panel wiring diagram shall be fitted at both ends of each wire. Ferrules shall fit tightly
on the wire and shall not fall off when the wire is disconnected from terminal blocks.
Numbers 6 and 9 shall not be included for ferrules purposes unless the ferrules have
numbers underscored to enable differentiation. (i.e. 6 and 9).
Fuses and links shall be provided to enable all circuits in a cubicle, except a lighting
circuit, to be isolated from the bus wires.
The DC trip and AC voltage supplies and wiring to main protective gear shall be
segregated from those for back-up protection and also from protective Equipment for
special purposes. Each such group shall be fed through separate fuses from the bus
wires. There shall not be more than one set of supplies to the Equipment comprising
each group. All wires associated with the tripping circuits shall be provided with red
ferrules marked Trip.
It shall be possible to work on small wiring for maintenance or test purposes without
making a switchboard dead.
The insulation material shall be suitably coloured in order to distinguish between the
relevant phases of the circuit.
When connections rated at 380 volt and above are taken through junction boxes
they shall be adequately screened and DANGER notices shall be affixed to the
outsides of junction boxes or marshalling kiosk.
Where connections to other equipment and supervisory equipment are required the
connections shall be grouped together.

10.2 LV power cabling


LVAC cable terminals shall be provided with adequately sized, hot pressed, cast or
crimp type lugs. Where sweating sockets are provided they shall be without
additional clamping or pinch bolts. Where crimp type lugs are provided they shall be
applied with the correct tool and the crimping tool shall be checked regularly for
correct calibration. Bi-metallic joints between the terminals and lugs shall be
provided where necessary.
Terminals shall be marked with the phase colour in a clear and permanent manner.
A removable gland plate shall be provided by the Contractor. The Contractor shall be
responsible for drilling the cable gland plate.
Armoured cables shall be provided with suitable glands for terminating the cable
armour and shall be provided with an earthing ring and lug to facilitate connection of
the gland to the earth bar.

10.3 Multi-core cables and conduit wiring


External multi-core cabling between items of main and ancillary equipment shall form
part of the Contract Works and shall consist of un-armoured multi-core cable with
stranded copper conductors PVC insulated and PVC over sheathed complying with
the requirements of IEC 227 and 228 as applicable.
Multi-core cable for instrumentation and control purposes shall be supplied with
2.5 mm2 stranded copper cores. Multi-core cables for CT and VT circuits shall be
supplied with two by 2.5 mm2 stranded copper cores and the cores shall be identified
by the phase colour.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 30/39


Where conduit is used the runs shall be laid with suitable falls and the lowest parts of
the run shall be external to the equipment. All conduit runs shall be adequately
drained and ventilated. Conduits shall not be run at or below ground level.
Multi-core cable tails shall be so bound that each wire may be traced to its cable
without difficulty. Where cables are terminated in a junction box and the connections
to a relay or control cubicle are continued in conduit, the spare cores shall be taken
through the conduit and terminated in the cubicle. The dc trip and ac voltage circuits
shall be segregated from each other as shall the circuits to main protective gear be
segregated from those for back-up protection.
The screens of screened pairs of multi-core cables shall be earthed at one end of
the cable only. The position of the earthing connections shall be shown clearly on
the diagram.
All wires on panels and all multi-core cable cores shall be crimped with the correct
size of crimp and crimping tool and will have ferrules which bear the same number at
both ends. At those points of interconnection between the wiring carried out by
separate contractors where a change of number cannot be avoided double ferrules
shall be provided on each wire. The change of numbering shall be shown on the
appropriate diagram of the equipment. The same ferrule number shall not be used
on wires in different circuits on the same panels.
The Contractor shall provide a two (2) metre loop of spare cable at both ends of all
multi-core cable runs and shall leave sufficient lengths of tails at each end of the
multi-core cables to connect up to the terminal boards. The Contractor shall also
strip, insulate, ring through and tag the tails and shall also seal the cable boxes. The
Contractor shall be responsible for re-checking the individual cores and for the final
connecting up and fitting of numbered ferrules within all equipment provided on this
contract.
The drilling of gland plates, supply and fitting of compression glands and connecting
up of power cables included in the Contract scope of work shall be carried out under
this contract.

10.4 Laying and installing of cables:


10.4.1 General
For cable laying the following shall apply:
a) Switchyard area - In concrete cable troughs (cable trench having cable racks
with cable trays)
b) Control Room - On cable racks consisting of slotted type and ladder type
cable trays
c) Buildings - Conduits Directly buried cables shall be used wherever
necessary with the approval of Engg. In charge.
10.4.2 Laying of cable
Cables shall be laid in concrete troughs provided under this contract or drawn into
pipes or ducts or on cable racks or directly buried as may be required by the Engg.
In charge. Concrete troughs shall be designed so that the cables are supported on
cable support systems and the supports shall be arranged so as to allow the
segregation of power, control (including CT and VT circuits) and communications
cables onto different layers of cable supports. All cable supports shall be earthed in
accordance with IS 3043. The minimum vertical separation between layers of cable
tray shall be not less than 300 mm.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 31/39


The cable support system shall be designed and constructed to carry the required
cables without undue crowding of the supports and without overloading the supports.
The maximum number of layers of cable that shall be permitted on a single cable
support shall be three. The width of the cable supports shall be selected to ensure
that the supports are not crowded, the cable supports are not overloaded and that
sufficient space is provided in the cable trough to allow for personnel access during
and after cable installation. The width of cable supports should not exceed 750 mm.
Cables shall be laid direct in the ground only at the discretion of the Engg. In charge.
All cables laid direct in the ground outside buildings shall be laid in a trench and
protected by reinforced concrete slabs or cable tiles.
For auxiliary cables the top of the slab or tile shall be at a depth not less than
300 mm below the surface of the ground and there shall be a layer of fine well
packed riddled earth 75 mm thick in between the cable and the bottom of the trench
and between the top of the cable and the underside of the slab.
The Contractor shall be responsible for the proper laying of all cables in the ground.
Where cables in the same trench are laid over each other, they shall be separated
by not less than 75 mm of riddled earth. The riddled earth used for this purpose shall
have been passed through a screen having a 12 mm square mesh. Where cables
pass under roadways they shall be laid in pipes at a depth not less than 800 mm
below the surface.
The Contractor shall be responsible for the excavation of trenches which shall
include all pumping and baling required and the provision of all necessary labour,
plant, tools, water, additional soil, fuel or motor power for such purposes.
Cables in trenches will be inspected by the Engg. In charge before the trenches are
backfilled.
The running of communications and power cables along the same route shall be
avoided as far as possible. Where this is not possible they shall be segregated, the
one group from the other. Power and communication cables shall be laid in separate
tiers. For other than directly buried cables the order of laying of various cables shall
be as follows:
d) Power cables on top tiers.
e) Control/ instrumentation and other service cables in bottom tiers.

10.4.3 Cable tags and markers


Each cable and conduit run shall be tagged with numbers that appear in the cable
and conduit schedule.
The tag shall be of aluminium with the number punched on it and securely attached
to the cable conduit by not less than two turns of 20 SWG GI wire conforming to IS
280. Cable tags shall be of rectangular shape for power cables and of circular shape
for control cables.
Location of cables laid directly in the ground shall be clearly indicated with cable
marker made of galvanised iron plate.
Location of buried cable joints shall be indicated with a cable marker having an
additional inscription "Cable joint".
Cable markers shall project 150 mm above ground and shall be spaced at an
interval of 30 meters and at every change in direction. They shall be located on both
sides of road and drain crossings.
Cable tags shall be provided on all cables at each end (just before entering the
equipment enclosure), on both sides of a wall or floor crossing, on each duct, conduit
entry and at every twenty meters (20 m) in cable tray/trench runs. Cable tags shall

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 32/39


be provided inside switchgear, motor control centers, control and relay panels etc..
and wherever required for cable identification when a number of cables enter
together through a gland plate.
The price of cable tags and markers shall be included in the installation rates for
cables/conduits quoted by the Bidder.
10.4.4 Cable supports and cable tray mounting arrangements in control room
The control room will normally be provided with embedded steel inserts on concrete
floors/walls for the purpose of cabling in the control room. The supports shall be
secured by welding to these inserts or available building steel structures. However,
in cases where no such embedded steel inserts are available, the same shall have
to secure to the supports on walls or floors by suitable anchoring.
10.4.5 Cable support structure in switchyard cable trenches
The contractor shall fabricate and install cable support structures in cable trenches.
These supports shall be provided at 750 mm spacing along the run of cable
trenches.
Cable supports and cable racks shall be fabricated from standard structural steel
members, channels, angles and flats of required size. The fabrication, welding and
erection of these structures shall conform to the relevant clauses of this
Specification, in addition to the specification given herein.

10.5 Termination of cables and wires


Where cables leave the Equipment in an upward direction the cable boxes shall be
provided with a barrier joint to prevent leakage of cable oil or compound into the
Equipment. Where cable cores are liable to contact with oil or oil vapour the
insulation shall be unaffected by oil.
PVC sheathed cables shall be terminated by compression glands complying with
BS 6121 (or equivalent).
Auxiliary PVC insulated cables shall be terminated with compression type glands,
clamps or armour clamps complete with all the necessary fittings.

Colours shall be marked on the cable box, cable tail ends and single core cables at
all connecting points and/or any positions the Engg. In charge may determine. Cable
boxes shall be provided with suitable labels indicating the purpose of the supply
where such supply is not obvious or where the Engg. In charge may determine.
All cables shall be identified and shall have phase colours marked at their
termination.

All incoming and outgoing connections shall be terminated at a terminal block. Direct
termination into auxiliary switches will not be accepted.

10.6 DEGREES OF PROTECTION


Degrees of protection shall be provided in accordance with IEC 144 and IEC 529
and be as follows:
f) For outdoor applications, IP 55.
g) For indoor applications where purpose built accommodation is provided, e.g. switch
and control and relay rooms in auxiliary plant buildings, IP 41.
h) Where dust can adversely affect equipment within the enclosure, this equipment
should be separately housed with a degree of protection of IP 51.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 33/39


i) For indoor applications where the equipment is housed in the same building as that
enclosing water and steam operated equipment, the degrees of protection stated in
the previous paragraph shall be up-rated to IP 44 and IP 54 respectively.
Where more severe environments exist, e.g. steam and oil vapour or other
deleterious chemical environments, special measures will be necessary and the
degree of protection required will be specified separately.
The Contractor shall submit a schedule for providing the degree protection to various
control boxes, junction boxes etc. for the Engg. In charges approval.

10.7 SUPPLY VOLTAGE


All incoming supplies of greater than 125 V to earth shall have their termination
shrouded by a suitable insulating material.
The auxiliary supply voltages on site shall be as follows:

Nominal Variation Frequency Hz or Phase Wires Neutral


Voltage V DC Connection

430 10% 50(-5%, +3%) 3 4 Solidly earthed

240 10% 50(-5%, +3%) 1 2 Solidly earthed

220 187V - 242V DC DC 2 Isolated 2 wires

48 43V - 53V DC DC 2 +ve earthed

10.8. ERECTION CONDITIONS

10.8.1 General
The following shall supplement the conditions already contained in the other parts of
these specifications and documents and shall govern that portion of the work on this
Contract to be performed at Site.

10.8.2 Regulation of local authorities and statutes


The Contractor shall comply with all the rules and regulations of local authorities
during the performance of his field activities. He shall also comply with the Minimum
Wages Act, 1948 and the payment of Wages Act (both of the Government of India
and Govt of Orissa ) and the rules made thereunder in respect of any employee or
workman employed or engaged by him or his Sub-Contractor.
All registration and statutory inspection fees, if any, in respect of his work pursuant to
this Contract shall be to the account of the Contractor. However, any registration,
statutory inspection fees lawfully payable under the provisions of the statutory laws
and its amendments from time to time during erection in respect of the substation
ultimately to be owned by the OWNER, shall be to the account of the OWNER.
Should any such inspection or registration need to be re-arranged due to the fault of
the Contractor or his Sub-Contractor, the additional fees to such inspection and/or
registration shall be borne by the Contractor.
The Contractor shall ensure that he obtains, from the Government of Orissa, an
Electrical Contractors Licence and a supervisory certificate of the appropriate grade
to allow him to execute the electrical works included in the Contract. The Contractor
shall ensure that all workmen possess Workman Permits, issued by the Government
of Orissa, for engagement in the Contract Works.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 34/39


10.8.3 Inspection, testing and inspection certificates
The provisions of the General Conditions of Contract shall also be applicable to the
erection portion of the Works. The Engg. In charge shall have the right to re-inspect
any equipment though previously inspected approved by him at the Contractor's
works, before and after the same are erected at Site.

10.9 Contractor's field operation


10.9.1 General
The Contractor shall inform the Engg. In charge in advance of field activity plans and
schedules for carrying-out each part of the works. Any review of such plans or
schedules or methods of work by the Engg. In charge shall not relieve the Contractor
of any of his responsibilities towards the field activities. Such reviews shall not be
considered as an assumption of any risk or liability by the OWNER or any of his
representatives, and no claim of the Contractor will be entertained because of the
failure or inefficiency of any such plan or schedule or method of work reviewed. The
Contractor shall be solely responsible for the safety, adequacy and efficiency of plant
and equipment and his erection methods.
10.9.2 Progress Report
Progress reports shall be provided by the Contractor to the Engg. In charge in
accordance with the relevant parts of this specification. Appropriate photographs
shall accompany the monthly progress reports.

10.10 Facilities to be provided by the contractor


10.10.1 Unloading
Contractor shall make his own arrangement for unloading the equipment at site.
10.10.2 Tools, tackle and scaffoldings
The Contractor shall provide all the construction equipment tools, tackle and
scaffoldings required for offloading, storage, pre-assembly, erection, testing and
commissioning of the equipment covered under the Contract. He shall submit a list
of all such materials to the Engg. In charge before the commencement of pre-
assembly at Site. These tools and tackles shall not be removed from the Site without
the written permission of the Engg. In charge.

10.11 First-Aid and general hygiene


The Contractor shall provide necessary first-aid facilities for all his employees,
representatives and workmen working at the site. At all times at least ten percent of
all Contractors personnel assigned to the worksite shall be shall be trained in
administering first-aid.
The labour colony, offices and residential areas of the Contractors employees and
workmen shall be kept clean and neat to the entire satisfaction of the Engg. In
charge. Proper sanitary arrangements shall be provided by the Contractor in work-
areas, offices and residential areas of the Contractor.
Waste oil shall be disposed of in a manner acceptable to the Engg. In charge. Under
no circumstances shall waste oil be dumped into uncontrolled drains.

10.12 Security
The Contractor shall have total responsibility for all equipment and material in his
custody, stored, loose, semi-assembled and/or erected by him at Site. The
Contractor shall make suitable security arrangements including employment of
security personnel to ensure the protection of all materials, equipment and works
from theft, fire, pilferage and any other damages and loss.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 35/39


10.13 Materials handling and storage
All the equipment furnished under the Contract and arriving at Site shall be promptly
received, unloaded and transported and stored in the stores by the Contractor.
Contractor shall be responsible for examining the complete shipment and notifying
the Engg. In charge immediately of any damage, shortage, discrepancy etc. for the
purpose of Engg. In charges information only. The Contractor shall submit to the
Engg. In charge every week a report detailing all the receipts during the weeks.
However, the Contractor shall be solely responsible for any shortages or damages
during transit, handling, storage and erection of the equipment at Site. Any
demurrage, wharfage and other such charges claimed by the transporters, railways
etc. shall be to the account of the Contractor.
The Contractor shall maintain an accurate and exhaustive record detailing all
equipment received by him for the purpose of erection and keep such record open
for the inspection of the Engg. In charge.
All equipment shall be handled carefully to prevent any damage or loss. All
equipment stored shall be properly protected to prevent damage. Equipment from
the store shall be moved to the actual location at an appropriate time so as to avoid
damage of such equipment at Site.
All the materials stored in the open or dusty location shall be covered with suitable
weather-proof and flameproof covering material.
The Contractor shall be responsible for making suitable indoor facilities for the
storage of all equipment which requires to be kept indoors.

11.0 CONSTRUCTION MANAGEMENT

11.1 General
Time is the essence of the Contract and the Contractor shall be responsible for
performance of his Works in accordance with the specified construction schedule. If
at any time the Contractor is falling behind the schedule, he shall take necessary
action to make good for such delays by increasing his work force or by working
overtime to accelerate the progress of the work and to comply with schedule and
shall communicate such actions in writing to the Engg. In charge, providing evidence
that his action will compensate for the delay. The Contractor shall not be allowed any
extra compensation for such action.

11.2 Field office records


The Contractor shall maintain at his Site office up-to-date copies of all drawings,
specifications and other supplementary data complete with all the latest revisions
thereto. The Contractor shall also maintain in addition the continuous record of all
changes to the above contract documents, drawings, specifications, supplementary
data, etc. effected at the field. On completion of his total assignment under the
Contract, such drawings and engineering data shall be submitted to the Engg. In
charge in the required number of copies.

11.2 Protection of property and Contractor's liability


The Contractor will ensure provision of necessary safety equipment such as barriers,
sign-boards, warning light and alarms, personal protective equipment etc. to provide
adequate protection to persons and property. The Contractor shall be responsible for
giving reasonable notice to the Engg. In charge and the owners of public or private
property and utilities when such property and utilities are likely to be damaged or
injured during the performance of his works, and shall make all necessary
arrangements with such owners, related to removal and/or replacement or protection
of such property and utilities.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 36/39


12.0 CODE REQUIREMENTS
The erection requirements and procedures to be followed during the installation of
the equipment shall be in accordance with the relevant Indian/International
Standards/Regulations, ASME codes, accepted good engineering practice, drawings
and other applicable Indian codes and laws and regulations.

13.0 OWNER'S SUPERVISION


To eliminate delays and avoid disputes and litigation, it is agreed between the
Parties to the Contracts that all matters and questions shall be referred to the
OWNER and without prejudice the Contractor shall proceed to comply with the
OWNER's decision.
The work shall be performed under the direction and supervision of the Engg. In
charge. The scope of the duties of the Engg. In charge, pursuant to the contract, will
include but not be limited to the following:
j) Interpretation of all the terms and conditions of these documents and specifications.
k) Review and interpretation of all the Contractors drawing, engineering data etc.
l) Witness or authorise his representative to witness tests and trials either at the
manufacturer's works or at site, or at any place where work is performed under the
Contract.
m) Inspect, accept or reject any equipment, material and work under Contract.
n) Issue certificate of acceptance and/or progressive payment and final payment
certificates.
o) Review and suggest modification and improvements in completion schedules from
time to time.
p) Supervise the Quality Assurance program implementation at all stages of the Works.

14.0 TESTING AND INSPECTION


The Contractor shall carry out the tests stated in accordance with the General
conditions of Contract, without extra charge as in the opinion of the Engg. In charge
are necessary to determine that the Contract Works comply with this Specification.
The tests shall be carried out generally in accordance with the relevant IECs or IS or
equivalent standards. The specific details of testing and inspection are given in the
appropriate section of this Specification.

All materials used shall be subjected to such routine tests as are customary in the
manufacture of the types of plant included in the Contract Works. These materials
shall withstand satisfactorily all such tests.

All tests shall be carried out to the satisfaction of the Engg. In charge, in his
presence, at such reasonable times as he may require, unless agreed otherwise.
Not less than two weeks notice shall be given to the Engg. In charge in order that he
may be represented if he so desires. As many tests as possible shall be arranged
together. Two hard copies of the Contractors test reports and test sheets shall be
supplied to the Engg. In charge for approval.

The Owner can at any time enter the premises of manufacturer/contractor without
any obstruction to verify the quality of materials under manufacture.

Measuring Equipment shall be approved by the Engg. In charge and if required shall
be calibrated at the expense of the Contractor at an approved laboratory.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 37/39


The Contractor shall be responsible for the proper testing of the work completed or
plant or materials supplied by a sub-contractor to the same extent as if the work,
plant or materials were completed or supplied by the Contractor himself.

All Equipment, instruments and connections required for the above tests shall be
provided by the Contractor, but the Engg. In charge may permit the use for the tests
on site, any instruments and Equipment which may be provided permanently on site
as part of the contract works conditional upon the Contractor accepting liability for
any damage which may be sustained by such equipment during the test.

The contractor shall supply suitable test pieces of all materials as required by the
Engg. In charge. If required by the Engg. In charge, test specimens shall be
prepared for check testing and forwarded at the expense of the Contractor to an
independent testing authority selected by the Engg. In charge.
Any costs incurred by the OWNER in connection with inspection and re-testing as a
result of a failure of the subject under test, or damage during transport, or erection
on site before take-over by the OWNER, shall be to the account of the Contractor.
No inspection or lack of inspection or passing by the Engg. In charge of work, plant
or materials, whether carried out or supplied by the Contractor or sub-contractor,
shall relieve the Contractor from his liability to complete the Contract Works in
accordance with the Contract or exonerate him from any of his guarantees.
The cost of travelling, Lodging and Fooding of the owners personnel during
inspection at Manufacturers premises will be taken care by the owner.

15.0 FIRE PRECAUTIONS


All Equipment, connections and cabling shall be designed and arranged to minimise
the risk of fire and any damage which might be caused in the event of fire. When
cabling is carried out as part of this Contract the Contractor shall be responsible for
sealing all holes in floors, walls, roofs etc. through which the cabling may pass.
The work procedures that are to be used during the erection shall be those which
minimise fire hazards to the maximum extent practicable. Combustible materials,
combustible waste and rubbish shall be collected and removed from the site at least
once each day. Fuels, oils and volatile or flammable materials shall be stored away
from the construction site and equipment and material stores in appropriate safe
containers.
All Contractors supervisory personnel and at least ten percent all of workers shall be
trained for fire-fighting and shall be assigned specific fire protection duties. At least
ten percent of all personnel assigned to site at any one time shall be trained for fire
fighting.
The contractor shall provide sufficient fire protection equipment of the types and
sizes for the ware-houses, office temporary structures, labour colony area etc.
Access to such fire protection equipment shall be easy and kept open at all time.

16.0 SPANNERS AND SPECIAL TOOLS


A complete set of spanners shall be supplied for each station to fit every nut and bolt
head on the Equipment supplied under this Contract, together with all special tools
required for the adjustment and maintenance of the equipment. These tools shall be
mounted in a lockable cabinet at each substation, also to be provided under this
Contract. Eye bolts which have to be removed after use shall be accommodated in
the cabinets.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 38/39


Spanners and other maintenance equipment provided under the Contract shall not
be used for the purpose of erection of the contract Works.
Any special devices, slings or tackle necessary for the complete overhaul of the
plant shall be handed over to the Engg. In charge in working order on completion of
the Contract.
On delivering any or all of these tools to the Engg. In charge, a signature shall be
obtained from the Engg. In charges representative. Any tools not signed for shall be
deemed not to have been delivered.

17.0 RUNWAY BEAMS, EYE BOLTS AND LIFTING TACKLE


Runway beams shall comply with the requirements of BS 2853, or its equivalent, and
shall be tested after erection in accordance with this standard and this Specification.
The Contractor shall be responsible for the provision of the appropriate test
certificates which must be in accordance with Appendix C of BS 2853.
All slings, eye bolts and other lifting tackle provided shall be proof tested to twice the
safe working load and suitably marked with embossed labels to show clearly the
safe working loads.

VOL-II(TS) E2- GENERAL TECHNICAL CLAUSES & DESIGN PAGE 39/39


CHAPTER E3

TECHNICAL SPECIFICATION
FOR
SYSTEM & CLIMATIC CONDITIONS

VOL-II(TS) E3-SYSTEM & CLIMATIC CONDITIONS PAGE 1/3


1.0. SYSTEM PARAMETERS
Sl. Description of Technical
Unit Data
No Parameter
1 Nominal system voltage kVrms 33kV 11kV

2 Maximum system voltage kVrms 36kV 12kV

3 Power frequency with kVrms 70kV 28kV


stand voltage
4 Lightning impulse KV p
withstand voltage (for 1.2 /
1 ) L in e to ea rt h 50s) 170kVp 75 kVp
2 ) Across isolating gap 195kVp 85 kVp
6 System frequency Hz 50
7 Variation in frequency % -5%, +3%
Continuous current rating Amp 1250 1250
(out door equipment)
8 Continuous current rating Amp 630 630
(Indoor Equipment)
Continuous current rating Amp 800 1250
(Indoor Bus Bar)
9 Symmetrical short circuit kA 25kA
current
9.1 Duration of withstand of
short circuit current Second 3
10 Symmetrical Internal Arc kA 25kA
current
10.1 Duration of Arc current Second 1
11 Dynamic short circuit
current rating kAp 62.5kA
13 Conductor spacing for AIS
layouts
Phase to ground meters 3.7 2.8
Phase to phase meters 1.5 0.76
14 Design ambient o
C 50
temperatures
15 Pollution level as per III
IEC- 815 and 71
17 Maximum fault clearing ms not exceeding 1 50ms
time
18 Safety clearances metres
1. Section clearance 4 3
a) Ground clearances metres
(between ground 4 3
and bottom most
part of energised metres
object)
As per I.E. As per I.E.
b) Horizontal clearance metres Rules Rules
between the fence and
energised object As per I.E. As per I.E.
c) Horizontal clearance Rules Rules
between the road
centre line and

VOL-II(TS) E3-SYSTEM & CLIMATIC CONDITIONS Page 2/3


energised part of the
nearby equipment
19 Bay width (out door) metres 5.5 4.0
20 Height of bus equipment metres 4 3.5
interconnection from
ground (out door)
21 Height of strung busbar metres 5.5 4.0
(out door)

2.0 CLIMATIC CONDITIONS

The service conditions shall be as follows:


1 .Maximum altitude above sea level 1 ,000m
2.Maximum ambient air temperature 50C
3. Maximum daily average ambient air temperature 35C
4.Minimum ambient air temperature 0C
5.Maximum relative humidity 95%
6.Average number of thunderstorm days per annum (isokeraunic level) 70

7.Average number of rainy days per annum 120

8.Average annual rainfall 150cm

9. Earthquakes of an intensity in horizontal direction - equivalent to seismic


acceleration of 0.3g

10. Earthquakes of an intensity in vertical direction - equivalent to seismic


acceleration of 0.15g
(g being acceleration due to gravity)

13 .Wind velocity: 300 km/hr, 200 km/hr and 160 km/hr as detailed in chapter 1.

Environmentally, some of the regions, where the work will take place includes
coastal areas, subject to high relative humidity, which can give rise to
condensation. Onshore winds will frequently be salt laden. On occasions, the
combination of salt and condensation may create pollution conditions for outdoor
insulators. Some places are in heavily industrial polluted areas. Therefore,
outdoor material and equipment shall be designed and protected for use in
exposed, heavily polluted, salty, corrosive and humid coastal atmosphere.

VOL-II(TS) E3-SYSTEM & CLIMATIC CONDITIONS PAGE 3/ 3


CHAPTER E4

SWITCHGEAR FOR GIS/AIS

TECHNICAL SPECIFICATION

For

PART A 33 kV Indoor Switchgear Panel for GIS


(Gas Insulated Switchgear)

PART A.1 33 KV Indoor Switchgear Panel for GIS


(Gas Insulated Switchgear) and AIS (AIR
Insulated Switchgear) - General

PART B 11 KV Indoor Switchgear Panel for AIS (AIR


Insulated Switchgear)

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 1 /72


TABLE OF CONTENTS
OF
PAR T A (Technical Specification for 33 KV Indoor Switchgear for
GIS)

NO. DESCRIPTION PAGE NO

1.0 Scope 6
2.0 Standards 6
3.0 Design Criteria 6
4.0 Technical Data 7
5.0 Design Features of Sf 6 Gas Insulated Switchgear 8
6.0 Circuit Breakers 12
7.0 Isolators and Earthing Switches: 13
8.0 Instrument Transformers 14
9.0 Mechanical Safety Interlocking Features 15
10.0 Protection & Control System 16
11.0 Bus IVT 16
12.0 Tests 17

TABLE OF CONTENTS
OF
PAR T A.1 (33 KV Indoor Switchgear panel for GIS and AIS-
General)

NO. DESCRIPTION PAGE NO

1.0 Scope 19
2.0 Standards 19
3.0 Type of Switchgear Panel 21
4.0 Type of Sheet Steel & Cubicle 21
5.0 Circuit Breaker (Vcb): 33 kV 21
6.0 Operating Mechanism 24
7.0 Operation and Controls 25
8.0 Motor 26
9.0 Thermal Rating of Switchgear 26
10.0 Auxiliary Power Supply 27
11.0 Interlocks 27
12.0 Safety Shutters 27
13.0 Fixed Isolating Contacts 28
14.0 Auxiliary Switch and Auxiliary Plug &Socket 28
15.0 Electrical & Mechanical Position Indication 28
16.0 Current Transformer 28
17.0 Tests 30
18.0 General For Ivt 32

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 2 /72


19.0 Test And Inspections 34
20.0 Pressure Discharge Flaps 35
21.0 Busbars 35
22.0 Earth Bus 35
23.0 Buses Cable Earthing 35
24.0 Cable Compartment 35
25.0 Low Voltage Compartment 36
26.0 Control And Power Cable Entry 36
27.0 Protection Relays For Feeder 36
28.0 Protection Relays For Transformer 37
29.0 Detail On Differential Protection 43
30.0 Over Fluxing Relay 47
31.0 Tests 47
32.0 Multifunction Meter 48
33.0 Panel Wiring AndAssessories 50
34.0 Terminal Block 51
35.0 Colour And Numbering 51
36.0 CirucitDigram 51
37.0 Disconnector 51
38.0 Auxiliary Supply 52
39.0 Dimension 52
40.0 Type Test Of The 33 Kv Switch Gear (Vcb) Panel 52
41.0 Qualifying Requirement 53

TABLE OF CONTENTS
OF
PAR T C (Technical Specification for 11 KV Indoor Switchgear panel
for AIS)

NO. DESCRIPTION PAGE NO

1.0 Requirements 55
2.0 Standards 55
3.0 Basic Technical Requirements 56
4.0 System Conditions 57
5.0 11kV VCB 57
6.0 Interrupting Media(Vaccum) 58
7.0 Auxilliary Contacts 58
8.0 Indications 59
9.0 Operation & Control 59
10.0 Current Transformer 60
11.0 Fitting & Accessories of CT 61
12.0 Test 62
13.0 Potential Transformer 63
14.0 Fitting & Accessories of PT 65

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 3 /72


15.0 Fuse Protection 65
16.0 Circuit Diagram 65
17.0 Termination 65
18.0 Earthing Terminal 66
19.0 Test & Inspection 66
20.0 Protective Relay & Control Pannel 67
21.0 Multifunctional Meter 67
22.0 Panel Wiring & Accessories 68
23.0 Terminal Blocks 69
24.0 Colour & Numbering 69
25.0 Circuit Diagram 70
26.0 Operating Mechanism 70
27.0 Tests 72
28.0 Performance Requirement 73
29.0 Earthing 73
30.0 Qualifying Requirement 74

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 4 /72


PART A

Technical Specification
For
33 kV Indoor Switchgear Panel for GIS (Gas Insulated
Switchgear)

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 5 /72


TECHNICAL SPECIFICATION FOR 33kV GAS INSULATED
SWITCHGEAR

1.0 SCOPE:
This specification covers design, manufacture, testing at
manufacturer's works, packing, forwarding & supply of 33kV Gas
Insulated Indoor Switchgear complete with all accessories for
trouble free and efficient performance including installation and
commissioning of SF6 gas-insulated vacuum circuit breaker
switchgear and associated equipment.

2.0 STANDARDS:
Switchgear IEC 62271-200 / EN 62271-200
Switchgear IEC 60694 / EN 60694
Behaviour in the
event of internal faults IEC 62271-200 / EN 62271-200
Three-position disconnector
anddisconnector IEC 62271-102 / EN 62271-102
Busbarearthing switch IEC 62271-102 / EN 62271-102
Circuit-breaker IEC62271-100/EN 62271-100
Current transformer IEC 60044-1 / EN 60044-1
Voltage transformer IEC 60044-2 / EN 60044-2
Voltage detection systems IEC 61243-5
Protection against accidental IEC 60529 / EN 60529
contact, foreign Objects and
water
Installation HD 637 S1

3.0DESIGN CRITERIA:

3.1 OPERATING CONDITIONS:


Operating Conditions according to IEC 60694 / EN 60694
Temperature of ambient air:
Maximum value 50 C

3.2 RATED NORMAL CURRENT:


The rated normal currents of components are stated in the
Technical data and shall be valid for design ambient temperature
of 50 C.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 6 /72


3.3 INTERNAL ARC FAULT:
Classifications to IEC 62271-200 25KA for 1 Sec
Partition class- PM
Internal arc classification - AFL (Authorised person access
permitted from front & lateral side) for the panels with no
rear access required.

3.4 INSULATING GAS:


Insulating gas Type SulphurHexafluoride (SF6)
Design pressureat 20 C for 36 kV Class - 0.05 MPato 0.1 MPa

4.0 TECHNICAL DATA

4.1 BUS RATING:


33 kV GIS, 25 kA 3s, Single Bus Bar 800 A @ max. 50 C

4.2 REQUIRED TECHNICAL PARAMETER:


Busbar System Single busbar
Electrical Data:
Rated voltage 36 kV
Rated operating voltage 33 kV
Rated frequency [Hz] 50
Rated power-frequency withstand voltage 70 kV
Rated lightning impulse withstand voltage 170 kV
Rated short-time withstand current 25 kA
Rated short-circuit duration 3s
Rated Peak current 62.5kA
Rated operating current busbar 800 A

Degree of Protection:
Main circuits IP 65
Drives IP 3X
Cable connection compartment IP 3X
Low voltage cabinet IP 4X
Auxiliary Voltage:
Control 48 V DC

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 7 /72


Motor 48 V DC
Protection system 48 V DC
Remote control 48 V DC
Socket/lighting/heating 230 V AC

IAC Classification acc. to IEC 62271-200


Classification IAC AFL
Internal arc tested minimum 25 kA 1 s
Dimensions:
Cubicle width max. 600mm
Cubicle depth maximum 2000 mm
Cubicle height max. 2500 mm
Properties:
Pressure relief duct Not Required
SF6Pressure control IDIS
Voltage Indication System IVIS
Control Panel mechanical
Mech. Operation Closed door

5.0DESIGN FEATURES OF SF 6 GAS INSULATEDSWITCHGEAR:


GIS Circuit Breaker shall be of fixed type enclosed in the SF 6
gas tank. Withdrawablel facility is not applicable in case of GIS
Switchgear.

5.1 GENERAL DESCRIPTION:


The SF6iinsulated switchgear shall be type-tested and of pre-
fabricated metal construction.
The offered Indoor GIS shall have VCB, Three Position
Disconnecting Switch and Bus Bars shall be enclosed in
SF6 Gas.
Single panels, each built up from a modular range of separate
functional units, can be combined to produce the specified
switchgear configuration. The modular units comprise of:

A) Standard basic module:


Incorporating the vacuum circuit-breaker.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 8 /72


B) Floor-pan module, flange-mounted to the lower part of the basic
module, with:
A wide range of cable connection options, appliance
couplers for outer cone-type cable connection systems.

Current transformers (toroidal type)


Busbar Module - A gas filled, clad compartment, which
is totally segregatedfrom the circuit breaker
compartment with regardto gas handling. The busbar
module incorporates:

Three-position switch.
Three-phase copper busbar system

C) Cable / Instrument Transformer compartment.


A metal-enclosed, air/gas insulated compartment for easy
maintenance, with:

Cable support for single and multiple cable installation


Sufficient space for installation of current transformers

Circuit-breaker and three-position switch drives are to be


designed with mechanical interrogation interlocks and shall
include all necessary auxiliary devices (auxiliary switches,
releases etc.)

The three-position disconnector (ON-OFF-EARTH) is to be


designed with separate manual and/or motorized drives for
the disconnector and earth switch functions.

All switching device drives shall be located outside of the


gas compartments, for easy access. Under normal
operating conditions for indoor switchgear units in
accordance with IEC 50594 and when complying with the
specified number of operations, no maintenance is
required.

5.2 FUNCTIONAL COMPARTMENT:

Circuit-breaker compartment SF6Gas insulated


Busbar compartment SF6Gas insulated

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 9 /72


Cable connection / transformer clad compartment are to
be equipped with individual pressure relief devices - Air
Insulated / SF6Gas insulatedcompartment for easy
access and maintenance.

5.3 SWITCHGEAR OPERATOR INTERFACES REQUIREMENTS:


A standard mechanical user interface, ergonomically
Positioned at a convenient height, must be visible
directly without opening of doors etc.
The user interface comprises all the mechanical, panel-
related interfaces and continuous interrogating
interlocks.
All the basic mechanical ON/OFF of CB,
disconnector& earth switch operation, manual
spring charge of CB must be possible without
opening the door to ensure the operator safety.
Mechanical mimic directly linked to mechanism
should be provided at the panel front door.
The basic switchgear unit is to be designed for suitable
free-standing installation within a switch room.
The Interlocking shall be as per IEC.

5.4 FUNCTIONAL INTUITIVE OPERATOR INTERFACE DESIGN


The SF6 Gas Insulated Switchgear shall be characterized
especially by the following operating features:
Ergonomic operability
Logical operation
Logical function states
Good visual communication of the overall function and
operating states
Optimum operator guidance
All operations can be performed optionally via a motor-
operated mechanism
The mechanical control panel is located at an optimum
height for operation and arranged in a recessed position on
the switchgear front. Thus, the operating area is clearly
visible while no control elements protrude from the
switchgear front. The position of the individual elements

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 10 /72


has been selected according to their function, i.e.
according to their allocation to the corresponding device
functions. The elements which form part of a switching
device, such as position indicators, crank ports or
mechanical push buttons, are visually linked by a specific
pattern and integrated in a mimic diagram. Mechanical
operation is performed the same way as with the habitual
operation with stationary switching devices.Separate
control elements and mechanical switch position indicators
are available for the following functions:

Circuit-breaker ON - OFF
Disconnector ON OFF-EARTH

5.5. BUSBAR / PANEL CONNECTIONS:


The gas-insulated busbar sections of the single panels
shall be connected via single-pole solid-insulated
connection elements which allows for easy exchange of a
cubicle without SF6 works. Busbar connection to be
designed in such a way that no adjacent panels must be
moved or opened for exchange of a Panel.
Busbar couplings between adjacent Panels should be
designed with a minimized quantity of electrical sealing
joints.

5.6 GAS COMPARTMENT TECHNOLOGY:


A Temperature Compensated Gas Monitoring Device shall
be provided on the offered GIS to constantly monitor the
Gas Pressure inside the Gas Tank.
By design there should be no need for gas works
during the whole time on site, not even for exchanging
a centrePanel or extending the switchgear at later
stage, e.g. no gas handling shall be necessary during
the anticipated service life of the switchgear, under
normal operating conditions. (The gas-filled clad
compartments are to be designed to be maintenance-
free and hermetically sealed pressure systems in
accordance with IEC 62271-200).

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 11 /72


The Switchgear Panels shall be filled with gas and checked
for leakage in the factory. For a proper recycling /
emergency replacement, a gas valve in gas compartment
has to be provided. In addition, the standard tools for filling
the SF6 Gas also have to be provided.
The switchgear units shall be divided into several gas-
filled compartments, sealed from each other by gas-
tight partitions including bus bar compartments of two
adjacent panels, so that any leakage may be quickly
localized and limited within enclosure of one panel &
can be indentified immediately.
All the live parts including the VCB, Three position
Disconnector, and main busbar shall be encapsulated
in stainless steel enclosure filled with SF6 gas.

5.7 INSTALLATION FACILITY:


The panels are to be delivered to site as factory assembled and
routine tested units. After linking the panels (or panel
assemblies) by the busbar connection system and connection of
the power and control cables the system should be ready for
operation. No gas filling is required at site during bus bar
connection & installation.
6.0 CIRCUIT BREAKERS:
The three-pole vacuum circuit breaker with its maintenance-free
vacuum interrupters is installed horizontally in the gas
compartment.
The CB shall be spring operated, motor charged, and manually
released spring closing mechanism with three pole simultaneous
operations. The speed of closing operation shall be independent
of the hand-operating lever.The indicating device shall be
mechanical type directly linked to the mechanism & shall
show the OPEN and CLOSE position of breaker visible from
front of the cubicle. The spring charging time of the motor shall
not exceed 20sec in case of Vacuum Circuit Breaker. The
TRIP and CLOSE coils shall be of reliable design and low
consumption.

The Breakers shall be capable of Making & Breaking the


short time current in accordance with the requirement of

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 12 /72


IEC 62271-100 and latest amendment thereof. The
continuous current rating of breaker shall not be less than 630 A
at 50 Deg C design ambient.
Comprehensive interlocking system to prevent any dangerous or
inadvertent operation shall be provided. Two stage gas density,
alarm and lockout system with local and remote indication shall
be provided.

Mechanical trip push button on each CB shall be provided


on Panel front & shall be accessible.
Spring charge indication to be provided.

The vacuum circuit-breakers are to be equipped with


Spring-stored-energy operating mechanism with
motor, auto-reclosing
Mechanical OPEN and CLOSE button
1 closing solenoid
1 shunt release
Operating cycle counter
Auxiliary switch with at least 6NO + 6NC
available
Auxiliary switch for "spring charged" signal

The circuit-breaker has to control at least 10,000 Make-Break


cycles (One operating cycle of making & Breaking)
operations at rated current or 100 breaking operations at
rated short-circuit breaking current without maintenance. The
mechanical life of the vacuum interrupter has to comprise at
least 20,000 operating cycles.
The operating mechanism must be maintenance-free without
time limit up to 10,000 operating cycles.

7.0 DISCOONECTORS AND EARTHING SWITCHES:


Isolators Disconnectors or Discoonectors combined with
earthing switches (3 position switches) shall be motor operated.
In case of emergency, manual operation or through a separate
switch must be possible.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 13 /72


The earthing position for all 3 phases must be visible via a
mechanical position indicator (MIMIC) directly connected to the
drive shaft on panel front Fascia.
The mechanical operation of isolator / 3 position disconnector
switch must be possible with door closed for operator safety.
8.0 INSTRUMENT TRANSFORMERS:
Only Conventional inductive voltage and current transformers
according to IEC 60044-1 and IEC 60044-2 or electronic current
and voltage transformers to IEC 60044-7 and IEC60044-8 or a
combination of both are acceptable. Current &Voltage Sensors
are not acceptable.
IVT shall be placed in a separate Panel.

8.1 CURRENT TRANSFORMERS:


The Current Transformers shall be toroidal type. The Current
Transformers shall be located outside the Gas Compartment.
The transformer ratio, the accuracy class and the performance
load to be selected to suit the application requirements.
33kV Line CT
Toroidal type Current Transformer
CT Primary Current: 400-200 A
CT Secondary Current: 1-1-1A
Core 1: Cl-0.2S / 15 VA,
Core 2: Cl-PS .
Core3: Cl-PS

33kV Transformer CT
Toroidal type Current Transformer
CT Primary Current: 400-200 A
CT secondary Current: 1-1-1A
Core 1: Cl-0.2 S / 15 VA,
Core 2: Cl-PS
Core 3: Cl-PS
(The Contractor shall calculate the CT burden as per relay
and metering requirement during detail engineering with
CT/ VT Burden calculation)

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 14 /72


Cable Termination:
Cable terminals to be readily accessible from the front and
located at a convenient connection height. System shall be
in accordance with EN 50181 for terminal cross sections
up to 630 mm2, up to incl. 36 kV. For connection of various
cable types via cable screw-type plugs and terminal
adapters Facilities to connect several cables per phase.
With the cables connected, cable testing shall not require
the installation of any supplementary equipment.
Cable testing must be feasible from the panel front and
without disconnecting these cables.
Cable testing shall be possible from the panel front using
DC or AC, with the cables connected.
Cable compartment shall be completely covered by
metal enclosure for operators safety.
"To provide a maximum of personal safety all
operation and maintenance as well as connecting of
cables must be possible from the front of the panels".
"Cable testing must be feasible from the panel front
and without disconnecting these cables".
9.0 MECHANICAL SAFETY INTERLOCKING FEATURES:
Internal mechanical interlocks of the Panel.
With the circuit-breaker closed, the interrogation slide is
locked for the disconnector and the earthing switch.
(Restriction to the insertion of Hand Crank for
Disconnector-Earth Switch when CB is ON)
The interrogation slide always releases one insertion
opening only (disconnector or earthing switch), or both
of them are locked.(To ensure that either Disconnector
or Earth Switch operating at a time)
The crank for the disconnector and earthing switches
can only be removed in its appropriate end position.
When the crank on the disconnector or earthing switch
is still in place, or when the interrogation slide is open,
the following components are locked:
- ON push button of circuit breaker
- ON pulse is interrupted

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 15 /72


10.0 PROTECTION & CONTROL SYSTEM:
Following functions shall be available in the Protection
Relay for Line feeders:
Current protection (Directional & Non-directional feeder
Protection)
* Over current instantaneous (50)
* Over current IDMT (51)
* Earth fault instantaneous (50N)
* Earth fault IDMT (51N)
* Directional Earth fault IDMT (67)
* Directional over Current IDMT (67)
* Auto Reclosure 4 Shots
For Transformers, in addition to the above, the following
protection shall be provided
* Differential protection for transformer (87T)
* Restricted earth-fault for transformer (87N)

11.0 BUS IVT


33kV Bus IVT shall be housed in a separate Panel Panel
with plug in type with a disconnector and it shall be air
insulated / gas insulated.
Voltage protection (Bus VTs shall be Part of Feeder
Protection relay)

* Overvoltage (59)
* Under voltage (27)
* Frequency Relay (81 O/U)

Other protections and related functions (Part of Numerical


Relay)
* Lock-out (86)
* Trip circuit supervision (95)
11.1 COMMUNICATION PROTOCOL:
The protection relay shall have communication protocol
on IEC 61850 Protocol.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 16 /72


12.0 TESTS:
All tests shall be carried out according to relevant IEC
standards.

12.1 TYPE TESTS


The metal-enclosed switchgear is to be type tested at a
recognized and internationally well-reputed test laboratory.
Type test certificates shall be available for verification as
evidence of successful completion of type tests.
The switchgear furnished under this specification shall be fully
tested and documented by certified production test reports in
accordance with IEC 62271-200.

12.2 ROUTINE TESTS


Tests shall be carried out according to IEC requirements.

12.3 FACTORY INSPECTION TESTS


Notification for factory tests along with list of proposed tests
shall be submitted as required.

12.4 SITE TESTS


The site tests shall include the following:
Insulation resistance
Functional test of the fully installed and wired
equipment delivered.

12.5 BASIC Technical Requirements-


The following Basic Technical Requirements at chapter-E24
are required to be furnished by the bidders for 33kV GIS:

Basic Technical Requirement for 33KV Cubicle GIS,


Schedule GTP for 33KV GIS FOR BREAKERS / PANELS,
Schedule GTP for 33KV CURRENT TRANSFORMERS,
Schedule GTP for 33KV INDUCTIVE VOLTAGE
TRANSFORMERS,
Schedule GTP for NUMERICAL RELAYS

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 17 /72


PART A.1

Technical Specification

33 KV Indoor Switcgear Panel


for
GIS and AIS General

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 18 /72


Technical Specification for 33 kV Indoor Switcgear Panel for GIS and AIS

1.0 SCOPE:

This specification covers design, engineering, manufacture, testing, and


inspection of 33 kV indoor Switchgear Panel (provided with Vacuum circuit
Breaker, CT, IVT,Disconnectoretc) for use in the 33/11KV primary
substations under the distribution networks. The 33kV GIS Switchgear
shall be with a Disconnector.

In case of AIS Switchgear there shall not be any Disconnector.


There shall be separate Indoor Panel for IVT.
The equipments must be type tested.

1.1 Description of the Switchgear Panels for GIS & AIS.

Indoor switchgears for GIS/AIS should be provided in a cubicle, which


shall be erected inside a building. Separate switchgear panels for 33kV
GIS &AIS and 11kV AIS system to be considered.

Care should be taken during manufacturing of the same as the


equipment like VCB, Disconnector switches, CT & IVT are to be installed
in the panel individually.

The 33kV GIS Switchgear shall be with a Disconnector and AIS


Switchgear without any Disconnector. There shall be separate Indoor
Panel for IVT.

Vibration is inevitable as mechanical operation for closing the VCB &


disconnectors may cause problem and its performance will be affected.
In 33 KV GIS panel SF6 gas will be filled as insulation at 0.3 bar relative
pressure to ensure insulation and breaking operation. Sealed for life, the
enclosure shall meet the sealed pressure system criterion in
accordance with the IEC 62271-1. The manufacturer shall confirm that
the maximum leakage rate is lower than 0.1% per year.

2.0 STAND ARDS:


Expect where modified by this specification, the circuit breakers and the
accessories shall be designed, manufactured and tested in accordance
with latest editions of the following standards.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 19 /72


IEC/ISO/BS IS Subject
IEC:56 High voltage alternating current Circuit
IEC:62271-100 &200 Breakers general Requirement.

IEC:694 IS : 12729 Common clauses of high voltage switch-gear and


control gear standards (for voltage exceeding
1000V).
IEC:60 IS : 9135 High Voltage testing techniques.
Method of synthetic testing of HV .A.C
IEC:427 IS:13516
circuit breakers.
HV AC Circuit breakers- inductive
IEC: 1233
load switching.
IEC: 17A/CD:474 HV AC Circuit breakers- capacitive switching.
IEC:529 IS: 13947 Degree of protection provided by enclosure.

IEC:137 IS: 2099 Insulating bushing for A.C. voltages above 1000V

Hollow insulators for use in electrical equipment


IEC:233 IS : 5621
& testing.
IEC:273 IS: 5350 Characteristics of indoor and outdoor post
insulators for systems with nominal voltages
greater than 1000V.
Guide for selection of insulators in respect
IEC:815 IS: 13134
of polluted conditions.
IEC: 34 IS : 996 A.C motors

ISO:1460 BS:729 IS:2629 Hot dip galvanizing


Method of testing uniformity of zinc
IS:2633
coated articles.
IS: 5 Colour for ready missed paints and enamels
Code of practice for phosphating or iron
IS: 6005
and steel.
P.V.0 Insulated cables for voltages up to
IEC: 227 IS:1554
and including 1100 Volt.
Low voltage fuses for voltages not
IEC:269 IS:13703
exceeding 1000volt.
ISO:800 IS:1300 Phenolic moulding materials.
IS:13118 Guide for uniform marking and identification of
conductors and apparatus terminals.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 20 /72


IEC: 185 IS: 2705 Current transformers.
IEC: 296 IS: 335 Specification for unused insulating oil
For transformer and switchgear.
IEC:186 IS: 3156 Potential transformers.

CBIP Technical Report No. 88 revised July, 1996 read with


amendment issued (April, 99, September, 99 and also any other
amendment thereafter): Specification for AC Static Electrical Energy
Meter.

3.0 TYPE OF SWITCHGEAR PANEL

The switchgear boards shall be indoor metal clad, single front, single
tier, fully compartmentalized construction comprising of a row of free
standing, floor mounted panels. Each circuit shall have a separate
vertical panel with distinct compartments for circuit breaker, main bus
bars, current transformers cum cable compartment and low voltage
compartment. Each compartment of individual cubicle shall be
segregated by earth metallic sheet. Cubicle should be type tested for
internal arc in all three compartments for 25kA for 1sec as per IEC
62271-200.

4.0 TYPE OF SHEET STEEL &CUBICLE

The cubicle shall be of bolted construction with minimum thickness of


3.0mm for load bearing & cable entry gland plate portion and for other
non-load bearing members such as inter compartment partition etc can
be of 2.0 mm. Sheet steel used for fabrication shall be cold rolled carbon
annealed only and fabrication shall be done through CNC turret punch
press and CNC bending machine. Sheet steel may be of aluzinc material
or CRCA. All covers & doors shall be of folded design type with viewing
window at rear cover (box type) of polycarbonate.

5.0 CIRCUIT BREAKER (VCB): 33 KV


The AIS circuit breaker (VCB) shall be mounted on Withdrawable
Truck, which shall roll out horizontally from service position to isolated
position with ease and it shall also be possible to take out the breaker
truck from cubicle smoothly on to the floor. It is preferred to provide with
guides for withdrawal and insertion of truck into the cubicle with ball
bearing arrangement on the top of the truck. Circuit breaker shall be of

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 21 /72


vacuum only and the truck shall have distinct SERVICE and TEST
position. Special multi point hinged locking arrangement shall be
provided to prevent opening of door in the event of internal arc in
breaker compartment. Isolation shall be horizontal.

The GIS Circuit Breaker shall be of fixed type enclosed in the SF6 gas
tank. Withdrawable facility is not applicable in case of GIS
Switchgear.

All the three interrupters of individual phases shall be fully encapsulated


circuit breaker shall be vacuum type only. No separate fiberglass sheet
barrier to be used.

It shall be operated through a common motor wound spring charged


mechanism with electrical release coil for closing and shunt trip coil for
tripping. Operating mechanism must have manual charging, closing and
tripping facility with the provision locking facility in push to close & push
to trip mechanical push button.

The mechanism shall be such that motor will automatically recharge the
mechanism springs after a closing operation enabling breaker to perform
OCO operation. The charging time of motor shall be less than 15 secs,
making it suitable for rapid auto reclosing duty. Mechanical push to Trip
button shall be provided for manual tripping with front door closed. All
the MS components of circuit breaker mechanism shall be treated
properly with passivation for longer life even in adverse climatic
condition. Yellow passivation shall not be acceptable. The normal
current rating of circuit breaker shall be 630 Ampere, SCC 25 kA for 3
sec with duty cycle of 0-0.3 Sec- CO-3 min-CO &Bus-bar shall be 800
Amp for Indoor Switchgear irrespective of AIS & GIS and the same
shall also be indicated in panel name plate. The mechanism and the
connected interrupters shall satisfy the mechanical endurance requirements
of IEC: 62271-100 & 200and all additional requirements specified herein.

5.1Interrupting media Vacuum:


In AIS vacuum circuit breakers, facilities shall be provided for
monitoring the contract erosion and any change in contact gap. The
vacuum bottles shall be easily replaceable on site and the
mechanism shall be conveniently adjustable to permit resetting the
contact gap. The current rating of the vacuum interrupters shall be
630Amp.

In case of GIS, the VCB is Fixed type and shall be Mounted inside the
stainless tank insulted with SF6 Gas. The Stainless Tank is sealed for
Life time and Vacuum bottles are to be replaced by changing the gas,

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 22 /72


when required. The current rating of the vacuum interrupters shall be
630Amp.

The vacuum circuit breaker poles shall be sealed to prevent


contamination of the spaces surrounding the interrupters. The bidder
shall demonstrate how this is achieved by supplying technical details
with the bid.

The circuit breakers shall be fitted with spring mechanism type. The
inherent design of the circuit breakers shall be such that they shall
satisfactorily perform all test duties and interrupt out-of-phase current
and produce very low over voltage(<2.5p.u)on all switching circuits,
capacitive and inductive to IEC:62271-100 & 200and other associated
standards mentioned in the clause of this specification.

5.2Basic Technical Requirements of 33 KV VCB


SI. No Particulars Requirements
1 Service type Indoor
2 No. of Poles 3
3 Nominal system voltage 33kV
4 Highest system voltage 36kV
5 Rated normal current at 50C
i) For Bus-bar 800A
ii) For Interrupter 630A

iii) For Outgoing Feeders/ For Incomer 630A

6 Rated Internal Arc for Panels for 1 Sec 25kA


7 Rated short circuit making current (peak) 62.5 kA
8 Rated short time current withstand capability 25kA
for 3 sec.
9. Rated insulation level:
i) One minute power frequency withstand 70kV
voltage to earth (wet and dry) rms
ii) Impulse withstand voltage to earth with 170kV
1.2/50sec, wave of +ve and -ve polarity
(Peak)
10 First pole to clear factor 1.5
0-0.3 Sec- CO-3 min-
11 Rated operating sequence (for auto reclosing)
CO

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 23 /72


12 Maximum break time 3 cycles
13 Rated out of phase breaking current 25% of the
symmetrical short
circuit breaking current

14 Maximum pole scatter 10 mili seconds


15 Rated Auxiliary supply for spring charge motor,230V A.C
lamp & heater circuit.
16 Rated supply voltage for trip/close coil 48V D.C
17 No load line/cable breaking current capacity 25A
18 No load transformer breaking current capacity 25A

6.0 OPERATING MECHANISM

General
6.1The operating mechanism of the circuit breaker shall be motor
wound spring charged type. It shall be electrically and
mechanically trip free with anti-pumping device (as per IEC:694
definition). All working parts in the mechanism shall be of corrosion
resistant material. Self-lubricating, wearing resistant bearings
shall be provided in the mechanism.

6.2The mechanism shall fully close the circuit breaker and sustain it in
the closed position against the forces of the rated making
current and shall fully open the circuit breaker without undue
contact bounce at a speed commensurate with that shown by
tests to be necessary to achieve the rated breaking capacity
in accordance with IEC:56 or IS:13118. The mechanism shall be
capable of being locked in either the open or closed position.
The mechanism shall be capable of fully closing and opening
again after the auto-reclose time interval specified as 0.3
second in this specification.

6.3 Spring mechanism (In case of Spring Charged VCB)

6.3.1 The spring operating mechanism shall be with spring charging


motor, opening and closing springs with limit switches and
all accessories necessary for automatic charging. In normal
operation, recharging of the operating springs shall commence
immediately and automatically upon completion of the closing

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 24 /72


operation so that a complete sequence of closing and opening
operation should be possible.

6.3.2 It shall be possible to hand charge the operating spring with the
circuit breaker in either the open or closed position conveniently
from the ground level. Closure whilst a spring charging
operation is in progress shall be prevented and release of the
springs shall not be possible until they are fully charged.

6.3.3The state of charge of the operating springs shall be indicated by a


mechanical device showing 'SPRING CHARGED' when closing
spring is fully charged and operation is permissible and
'SPRING FREE' when closing spring is not fully charged and
the operation is not possible. Provision shall be made for remote
electrical indication of 'Spring Charged' and 'Spring Free'
conditions.

6.3.4The operating mechanism shall be such that the failure of any


auxiliary spring shall not cause tripping or closing the circuit
breaker but shall not prevent tripping against trip command.

6.3.Closing action of the circuit breaker shall charge the opening spring
ready for tripping. From the close position with spring charged,
one open-close-open operation shall be possible without
recharging the spring.

7.0 Operation and controls

The breaker shall normally be operated by electrical control with


electrical trippingby2nos shunt trip coil. Provision shall be made for
local electrical operation and mechanical operation.

The following facilities shall be provided in the circuit breaker local


control cabinet:

ON/NEUTRAL/ OFF control switch or ON and OFF push


buttons. The push buttons shall be momentary contract
type with rear terminal connections. The close push
button shall be of green colour and the open push
button red colour. There shall be separate switch for
electrical operation of the VCB.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 25 /72


MECHANICAL EMERGENCY TRIP DEVICE: suitable for
manual operation in the event of failure of electrical
supplies. The device shall be accessible without
opening any access doors and distinctly labeled. It shall be
shrouded and protected against inadvertent operation.

Means shall be provided for manual operation of these


circuit breakers during failure of auxiliary power in
addition to electrical operation.

Means shall be provided to prevent the mechanism


from responding to a close signal when the trip coil is
energized or to reclosing from a sustained close signal
either opening due to a trip signal or failure to hold in the
closed position.

The circuit breaker shall be able to perform 10,000 operating


cycles at no load in accordance with IEC:17A /474/CD for
circuit breakers for auto reclosing duties.

8.0 Motor
The motor for spring charging shall be single phase 230 Volt A C.
Continuous motor rating shall be at least ten percent above the
maximum load demand of the driven equipment. It shall remain
within its rated capacity at all operating points that will arise in
service. It shall be protected by MCB. The motor shall comply with
IEC: 34 or IS:996.

9.0THERMAL RATING OF SWITCHGEAR


All current carrying parts including breaker relay shall be governed by
IEC 62271-1. All isolating contacts shall be silver plated.

10.0 AUXILIARY POWER SUPPLY:

The operating mechanism shall be suitable to operate with the


following auxiliary Power supplies.

a) 230V,50Hz Single phase A.C - For spring charging motor


b)DC supply 48 Volts - For close and open coils.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 26 /72


The DC supply shall be from Battery Bank.
The mechanism shall be designed to operate satisfactorily despite
fluctuations of Auxiliary power supplies as under:

AC supply: Voltage from 85% to 115% of normal voltage


Frequency: from -5% to +3% in variationof normal frequency

DC supply: Voltage for voltage variation of Tripping : 70% - 110%


Voltage variation of Closing : 85% - 110%

11.0 INTERLOCKS
Circuit breaker can be inserted only in open position. Likewise circuit
breaker in closed position cannot be withdrawn. Attempt to draw out
closed breaker shall not trip the breaker.

For AIS, the circuit breaker shall operate only in one of the three
defined positions i.e. service, test and isolated. The breaker shall not
close in any of the intermediate positions.

For GIS, the 3-position of the DISCONNECTOR switch shall be ON-


OFF-EARTH.

The circuit breaker cannot be inserted into service position till auxiliary
contacts are made. Similarly interlock shall prevent auxiliary contacts
from being disconnected, if circuit breaker is in service position.

12.0 SAFETY SHUTTERS


For AIS,Safety shutters shall be metallic and shall be provided to cover
up the fixed High voltage contacts on bus bar and cable sides when the
truck is moved to Test / isolated position.The shutters shall move
automatically through a Linkage with the movement of the truck and
shall be of gravity fall type only.It shall be possible to padlock shutters
individually, i.e. on withdrawl of the breakers the shutters shall
automatically operate to cover the contacts.Further, all the
compartments are electrically & mechanically segregated from each
other.Hence it is possible to work on the Busbar compartment being
completely isolated from the breaker compartment.There shall be
positive indications for TEST/SERVICE position; However isolated
position is indicative by the open door itself. But, 33kV GIS is Fixed Type
and Mounted inside the stainless tank insulted with SF 6 Gas. The
Stainless Tank is sealed for Life time.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 27 /72


For GIS, Safety shutters are not applicable.

13.0 FIXED ISOLATING CONTACTS

Switch gear cubicle shall have seal off bushing arrangement between
the circuit breaker compartment and bus bar/C.T. cum cable
compartment, i.e. the fixed isolating contacts shall be embedded in
Epoxy Resign Cast bushing so these act as seal off bushing to prevent
transfer of arc from one compartment to the other in the event of internal
arc within the cubicle & must be tested for internal arc 25 kA for 1 sec in
all three HV compartments as per new IEC 62271-200.

But, 33kV GIS is Fixed Type and Mounted inside the stainless tank
insulted with SF6 Gas. The Stainless Tank is sealed for Life time.

14.0 AUXILIARY SWITCH AND AUXILIARY PLUG &SOCKET

There shall be minimum 6NO and 6NC contacts in breaker auxiliary


switch (10 amps DC rating) and shall be provided in each circuit
breaker.However, additional contact shall be made available by using
Contact Multiplier Relay/Contact Multiplication Relay.

15.0 ELECTRICAL & MECHANICAL POSITION INDICATION.


In addition to mechanical position indication in breaker for test and
service position, electrical indication shall also be provided through limit
switch. There shall be minimum 2NO +2 NC contacts available in each
position for electrical indication and for any other interlocking purpose.

15.0 CURRENT TRANSFORMER


Current transformers, three per circuit breaker, shall be of indoor,
single phase, resin cast and shall comply with IEC:185 and IS:2705,
suitable for operation in hot and humid atmospheric conditions
described in service condition. They shall be mounted inside the Panel.

16.1 Core

16.1.1 High grad non- ageing cold rolled grain oriented (CRGO M4
or better grade) silicon steel of low hysteresis loss and
permeability shall be used for the core so as to ensure
specified accuracy at both normal and over currents. The flux
density shall be limited to ensure that there is no saturation
during normal service.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 28 /72


16.1.2 The instrument security factor of the core shall be low enough
so as not to cause damage to the instruments in the event of
maximum short circuit current.

16.2 Windings

16.2.1 The secondary windings shall be made of electrolytic


copper with suitable insulation. The conductor shall be of
adequate cross-section so as to limit the temperature rise
even during short circuit conditions. The insulation of
windings and connections shall be free from composition liable
to soften, ooze, shrink or collapse during service.

16.2.2Polarity shall be indelibly marked on each current transformer and


at the lead and termination at associated terminal blocks. CTs
with multi ratio winding shall be clearly tabulated to show the
connections required for different ratios. Similar numbers shall
be marked on terminal block arrangement and wiring
diagram. Apart from the above marking and those to be
provided as per IEC-185 or IS-2705, other markings shall be
provided in consultation with owner.

16.2.3The continuous current rating of the primary winding shall be


one hundred and twenty percent of the normal rated current.

16.2.4Secondary windings of current transform ers shall be


used for metering,instrumentation and protection and shall
be rated for continuous current of one hundred and twenty
percent of normal rated current of primary winding.

Current transformers shall be three core window/bar primary for higher


rating or wound primary for lower rating. Maximum VA burden shall be of
15 VA and shall be rated for full short circuit current 25 KA for 3 second.
Out of three cores one Core having 0.2s class (Metering) & other two
cores having PS (Protection) class accuracy.

Current Ratio: 400-200/1-1-1 Amp


No. of Cores: 03
Burden: 15 VA for each core

Technical Requirements
SI. Particulars Requirements
No
1 Function To control 33kV Feeder & HV side of 33/11kV
power transformers of ratings between 3.15MVA to
12.5MVA

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 29 /72


2 Requirement The CTs in the 33 kV Indoor VCB switchgear panel
should have three cores as follows.
3 Transformation Ratio Category- A (For TFR) Category- B (For Feeder)
400-200/1-1-1-A 400-200/1-1-1 A
4 Rated Burden (VA) Core:1: 15 VA , Core:1: 15 VA ,
Core:2: 15 VA, Core:2: 15 VA,
Core:3:15 VA Core:3:15 VA
5 Class of Accuracy Core:1: 0.2s , Core:1: 0.2s ,
Core:2: PS, Core:2: PS,
Core:3: PS Core:3: PS
6 Instrument Security Factor Core- 1:- <5 Core- 1:- <5
7 Purpose Core:1: Metering , Core:1: Metering ,
Core:2: Differential, Core:2: Spare
Core:3:O/C& Core:3:O/C& E/F
E/F & REF & REF
Rated/Highest system
8 33/36kV
Voltage
9 Short Time Rating 25KA rms for 3 seconds
10 Power frequency 1 min
voltage withstand level/ 70 KV/170KV
Insulation Level:
-Impulse Voltage1.2/50 s
wave withstand level -

17.0 Tests
The CTs shall be tested in accordance with the requirements of
the type tests and routine tests as per the latest issues
IEC:185 or IS:2705.The tests to be conducted shall include:
17.1 Type Tests:
Type tested equipment/materials are acceptable. Type tests
should have been conducted in last five years. The Type Test
must have been as per OPTCL requirement. If OPTCL desires
another type test, it has to be conducted. In such case OPTCL
will bear the transportation of equipment/material and type test
charges.
L igh t n in g im pu lse vo lt a ge :
Power frequency wet withstand voltage;
Temperature rise;
Short time current;

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 30 /72


Composite error;
Accuracy test (for measuring core);
Instrument security current (for measuring core);
17.2 Routine tests
Verification of terminal marking and polarity;
Power frequency dry withstand test on primary windings;
Power frequency dry withstand test on secondary
windings;
Power frequency dry withstand test between sections;
Over voltage inter-turn test;
Composite error;
Turn ratio;
Accuracy test (for measuring core);
Current error and phase displacement (for protection core);
Knee point voltage and magnetizing current test (for PS
class); Secondary winding resistance (for PS class).

17.2 INDOOR VOLTAGE TRANSFORMER (IVT):


The 33 kV Indoor voltage transformers (IVT) are required to meet the
following basic technical requirements (Reference standards: IEC:186,
IS:3156 and associated standards listed in the specification):
SI. Particulars Requirements
No
1 Type Single phase

2 Nominal system voltage, phase to phase 33 kV


3 Application Instrumentation, Metering and
Protection
4 Number of secondary windings 2
5 Rated normal burden*-(Core-I/II) Each Core shall be 15VA
6 Rated primary voltage 33000V/3
7 Rated secondary voltage 110V/3-110V/3
8 Class of accuracy-(Core-I/II) 0.2/3P

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 31 /72


Rated insulation level: (Primary winding)
9
(Phase to earth)
One minute power frequency withstand
i) 70kV
voltage to earth rms
Impulse withstand voltage to earth with
ii) 1.2/50 sec wave of +ve and ve polarity 170kV
(peak)
One minute power frequency withstand
10
voltage of secondary winding (rms)
i)Between phase to earth 3kV
ii)Between sections 3kV
11 Rated voltage factor
Continuous
i) 1.2
For
ii) 30 seconds 1.5
iii)

* The burden indicated is the minimum acceptable to the Owner.


The Contractor shall ensure that the rated outputs of the voltage
transformers are adequate to meet at least 120 percent of the
connected load (burden).

18.0 GENERAL FOR IVT

18.1

The voltage transformers to be supplied under this


specification shall be Epoxy Resin Cast of Indoor type with
3nos single phase in a separate Panel complying with
IEC:185 and IS:3156, suitable for operation in hot and humid
atmospheric conditions described in this document.

18.2 Duty requirement

33 KV Voltage Transformer for all the indicating instruments


and measuring meters in the primary substation on 33 kV
side. It shall be of indoor, 1-Phase or 3- phase Epoxy Resin
Cast type complying with IEC 185.

18.3 Core

High grade non-ageing cold rolled grain oriented (CRGO-


M4 or better) silicone steel of low hysteresis loss and
permeability shall be used for core so as to ensure

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 32 /72


accuracy at both normal and or over Voltages. The flux
density shall be limited to 1.6 Tesla at normal voltage and
frequency. There shall be no saturation at any stage during
operation.

The instrument security factor of the core shall be low enough


so as not to cause damage to the instruments in the event of
maximum short circuit current or over voltages.

18.4 Windings

The primary and secondary windings shall be electrolytic


copper of high purity and conductivity and covered with
double paper insulation. The conductor shall be of adequate
cross-section so as to limit the temperature rise even
during maximum over voltages.

The insulation of windings and connections shall be free from


composition liable to soften, ooze, shrink or collapse during service.

18.5 The secondary windings of the voltage transformers shall


also be suitable for continuous over voltage corresponding
to the maximum system voltage at the primary winding. The
winding supports shall be suitably reinforced to withstand
normal handling and the thermal and dynamic stresses during
operation without damage.

18.6 The voltage transformer secondary circuits will be taken out


to form the star point and earthed at one point outside the
voltage transformers.

18.7 Both primary and secondary winding terminals shall be


clearly and indelibly marked to show polarity in accordance
with IEC: 186.The connections required for different
secondary windings in case of multi-winding voltage
transformers shall be clearly indicated in terminal blocks and
the wiring diagrams.

18.8 Fuse protection in IVT


For AIS, the Primary winding shall be protected by HRC
Fuses in suitable holder, designed by the manufacturers.
The secondary windings shall be protected by HRC
cartridge fuses in fuse holder consisting of carriers and
bases. The carriers and bases shall be of high grade flame
retarding and non-hygroscopic molded insulating materials
with hard glass surface. Each fuse shall be identified with

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 33 /72


engraved plastic label. Potential Transformer shall be 3nos
single phase & there shall be two cores. One core having
0.2 Class (Metering) & other having 3P Class
(Protection).Bus IVT shall be in a separate Panel with
extended Bus bar. Digital display voltmeter shall be
installed on IVT panel.

For GIS, Fuse Protection in is not applicable, since the


IVTs are directly Plug-in type with disconnecting switch.
19.0 TEST AND INSPECTIONS
19.1 The voltage transformers shall be tested in accordance with
the requirements of the type tests and routine tests as
provided in the latest issues of IEC:186 or IS:3516.
The tests to be conducted shall include;

19.2 Type tests:


Lightning impulse volta ge test;
High voltage power frequency wet withstand voltage;
Temperature rise test;
Short circuit withstand capability test;
Determination of limits of voltage error and phase displacement

19.3 Routine tests:


Verification of terminal marking and polarity;
Power frequency withstand tests on primary winding;
Power frequency dry withstand tests on secondary winding;
Power frequency withstand tests between sections;
Determination of limits of voltage errors and phase displacement;
Insulating Resistance measurement.
Partial discharge measurement.

Voltage Ratio: 33000/3 / 110/3-110/3.


No. of Cores: 03
Burden: 15VA for Metering, 15 VA for protection

20.0 PRESSURE DISCHARGE FLAPS


Pressure discharge flaps shall be provided at the top in all high voltage
compartments for the exit of hot gases in the event of internal arc in any
of the compartments.

21.0 BUSBARS
Bus bar material shall be of high conductivity electrolytic copper only and
accessibility of the same shall be from top only. All bus bars shall be
tubular/rectangular design insulated with heat shrinkable BPTM

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 34 /72


compound sleeves and joints shall have sufficient clearances in order to
meet the BIL (70kV RMS and 170 kip) withstand. Phase identification
shall be made at the end by colored tape.

Note: - In GIS switchgear, Bus bars, VCB, Disconnect or shall be in the


SF6 Gas chamber. The bus bar shall not be solid insulated.

22.0 EARTH BUS


There shall be a continuous copper bus at the bottom of the panel. Earth
bus shall be robust and shall be capable of carrying full short circuit
current 25kA for 1 second. Doors, covers and all non-current carrying
metallic parts shall be earthed through flexible copper breading of
adequate size. This also includes instrument casting and cable armor
which are also connected to the earth bus. Earth bus must be tested for
25kA for 1 sec.

23.0 BUS & CABLE EARTHING


Each feeder shall be provided with fault make type Earth switch duly
interlocked with circuit breaker. Unless the breaker is tripped & brought
to test position, the earthling switch cannot be operated. Earth Switch
should be fully type tested for STC withstand of 25kA for 1seconds.

24.0 CABLE COMPARTMENT


For Visit shall be at the rear side with rear bolted box type back covers.
There shall be an inspection window at the rear back cover enabling
operator to have visual inspection without opening back cover in live
condition. Viewing window at the rear side shall be of poly carbonate
only and shall be tested for internal arc. The gland plate of cable
chamber shall be of minimum 3mm thickness MS sheet in two halves
section.
Sufficient headroom of maximum 750 mm shall be provided for cable
termination.
For GIS, the GIS Cable compartment cover is interlocked with
disconnector switch & CB. Therefore, unless the earth switch & CB is
closed we cannot open the cable compartment door which ensures more
saftey.
25.0 LOW VOLTAGE COMPARTMENT
Low voltage compartment shall be mounted at the front on the top of
breaker compartment and shall also have hinged type of door. All wiring
shall be routed through PVC ducts and shall be terminated on to stud
type terminal with plastic cover. For current transformer terminal shall be
disconnecting link type only. The wire shall be of 1.1kV grade and
suitable for 2kVrms for 1 minute power frequency high voltage.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 35 /72


26.0 CONTROL AND POWER CABLE ENTRY
Control cable entry shall be from front and there should be a possibility
of terminating to LV chamber from both right hand and left hand side.
Power cable entry shall be from rear bottom. Provision shall be available
for entry of power cable from rear bottom.

The CR Panel (Instrument Chamber) should be mounted on top of


the VCBPanel.

Control panel (inbuilt) with protective relay and meter shall be provided
by the supplier suitable for above breakers. The equipment shall
have protection scheme with the following relays:

27.0 PROTECTION RELAYS FOR FEEDER:


The offered relays shall be multifunction numerical type only. The
auxilliary relays for lockout, transfer fault indication etc can be electro-
mechanical type. All Numerical relays shall have minimum following
features:

Relay shall be IEC 61850 compliant Numerical & suitable for 1A


secondary CT current &110V IVT secondary supply.

27.1 Over current & Earth fault relay:


Relay shall have 3 phase directional and non-direction (site
selectable feature) over current and earth fault protection. It shall
have three stages with first stage programmable as IDMT or DT.
The second and third stages shall be programmable as DT or
instantaneous.

Relay shall have thermal overload protection.


Relay shall have negative sequence over current protection.
Relay shall have adoptive & creative logics for meeting the
requirement
Relay shall have 4 shots auto reclose function built-in
Relay shall be with under and over voltage protection elements
provided
Relay shall have under frequency protection facility at least two
stages.

28.0 PROTECTION RELAYS FOR TRANSFORMER:


The offered relays shall be multifunction numerical type only. The
auxiliary relays for lockout, transfer fault indication etc can be electro-
mechanical type. All Numerical relays shall have minimum following
features.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 36 /72


Relay shall be IEC 61850 compliant Numerical & suitable for 1A
secondary CT current &110V IVT secondary supply.

28.1 Over current & Earth fault relay:


Relay shall have 3 phase directional and non-direction (site
selectable feature) over current and earth fault protection. It shall
have three stages with first stage programmable as IDMT or DT.
The second and third stages shall be programmable as DT or
instantaneous.
Relay shall have thermal overload protection.
Relay shall have negative sequence over current protection.
Relay shall have adoptive & creative logics for meeting the
requirement
Relay shall have 4 shots auto reclose function built-in
Relay shall be with under and over voltage protection elements
provided
Relay shall have under frequency protection facility at least two
stages.

28.2 Transformer Differential Relay:


The Transformer Differential protection relay shall consist of two winding
protection, two REF protections, V/F protection etc.Differential protection
besides REF protection is required for 3.15MVA, 5.0MVA &8.0MVA
Transformer. Over Fluxing Protection is standard protection of
transformers.The input to this relay is the secondary IVT supply.
However, setting will be decided at the time of commissioning.

28.3 Specification for Numerical Directional & Non-Directional Over


Current and Earth Fault Protection.
28.3.1. General
A comprehensive communicable numerical protection should be offered
by the relay. High level of security should be built-in the relay to avoid
any mal operation causing over protection of the system or any non-
operation of the relay causing under protection. Should have flexibility to
customize the relay for intended applications as may be desired at site,
in other words the relay should not have very limited features rendering it
equipment specific. The relay should have high immunity to electrical
and electromagnetic interference. It should have also continuous
supervision of hardware and software to ensure enhanced system
reliability and availability.The relay should have auto diagnostic fault
indication to facilitate fault location and repair after detection of internal
relay fault. The compulsory features required by the relay to be fulfilled
are listed as below

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 37 /72


28.3.2. Application
The relay will be required for applications where time graded Directional
& Non-Directional (site selectable feature) O/C and E/F protection is
required. The Directional & Non-Directional (site selectable feature)
earth fault protection should provide suitable sensitivity for most systems
where the earth fault current is limited. Typically the relay should be
applied for all incoming transformers, capacitors and plant feeders for
any application. The relay should be designed in such a way that it
operates for a wide range of AC and DC auxiliary power supplies.

28.3.3 General requirements


The relay in addition to protection and control should display and store
all parameters necessary for post fault analysis. The relay shall have a
back light LCD display. It shall be possible to view the measurement
values. The relay shall record all the events affecting the relay
performance. All the time stamped data should be available via a RS232
serial communication port for access locally and/or remotely via a
computer. All the events, faults and disturbance records shall be
extracted via a RS485 /RS232/USB/RJ45(Ethernet)serial port.

28.3.4 Operating Principle


The sampling frequency of the digital/analogue converter should be
synchronised to power frequency by suitable frequency tracking
methods to improve both accuracy of measurement and harmonic
rejection. The relay should necessarily have software filtering to prevent
induced ac signals in the external wiring causing operation of logic
inputs.

28.3.5. Functional Description


a) Directional O/C protection:
The relay should have 4 independent time delayed Directional O/C
stages which can be selectable either as directional or non-directional.
MTA shall be adjustable anywhere within -180 degrees to + 179
degrees. The first and second stages shall be programmable to have
either a DMT characteristics or IDMT characteristics (as per IEEE/IEC
Standards for O/C Relay, Stage- 1 & 2 can be used either a DT or IDMT
characteristics & 3rd & 4th Stage shall be with Instantaneous Definite
Time. However, directional or non-directional features are site
selectable) described as follows:
1. The low set phase current should start when the current of any phase
exceeds the set value.
The first and the second current stage shall have a current setting range
of 0.10 - 4.00 In and time setting range of 0.06 sec to 300 sec.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 38 /72


2. The Third, fourth stage of protection shall be with instantaneous
operation or DT having a current setting range as 0.1 to 20 I n and a time
delay of 0.06 sec to 300 sec for stage III and IV. These stages may have
the flexibility to be configured for a busbar protection scheme using
blocking logic at a later date. Facility available in the relays for this
flexibility may be highlighted.

b) Directional Earth fault Protection:


The relay should have at least 2 independent time delayed
Directional/NonDirectional E/F stages suitable for networks with
different earthing types( solidly earthed, resistive earthed, Petersen coil
earthed systems).The relay shall also be suitable where ever a selective
and sensitive earth fault protection is needed. It shall also be possible to
detect intermittent earth faults. MTA shall be adjustable anywhere within
-180 degrees to + 179 degrees. The first and second stage shall be
programmable to have either a DT characteristics or IDMT
characteristics described as follows:
The low set phase current should start when the current of any
phase exceeds the set value. For E/F Relay, Stage- 1 & 2 can be used
either a DT or IDMT characteristics. 3rd & 4th Stage shall be with
Instantaneous Definite Time. However, directional or non-directional
features are site selectable.
Both the stages Shall have a current setting range of 0.01 to 8 Amp
and time setting range of 0.1 sec to 300 sec. The lower setting is critical
to take care of systems which have low earth fault currents. Additionally
there shall be four non-directional earth fault stages where the first stage
can be programmed either to IDMT or DT and the rest 3 stages shall be
of definite time type.

c) Sensitive Earth Fault/Restricted Earth Fault.


The relay shall have five CT input to take care of transformers
applications where Restricted Earth fault and standby earth fault is
required. It shall be possible to either measure the value of neutral
current through available C.T I/Ps or derive it internally within the relay
and use the same for applications as described above. The Relay shall
be able to accept input from Core balance current transformer to detect
earth faults of very low amplitude. The setting range shall be settable to
a minimum of 0.005 Amps. The relay shall have restricted earth fault
protection feature of high Impedance type.

d) Over Voltage & Under Voltage


If the system goes for very high under and over voltages in case of
Supply or Load unbalance it shall be possible to grade the system for
Voltage protections. Relay shall have 3 under voltage stages and 3 over
voltage stages respectively.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 39 /72


e) Residual voltage protection:
The relay shall have at least 2 residual voltage stages in order to
give an unselective backup for existing earth fault protection. The stages
shall have a setting range of 1-60 %U0N with a time delay settable from
0.3 300.0s ( in steps of 0.1 s).

f) Under frequency/Over Frequency /ROCOF:

The relay shall have four frequency stages out of which it shall be
possible to program at least 2 of them to under or over frequency to be
suitable for various load sharing applications. The under frequency
stages shall be settable any where within a frequency range of 40.0 -
60.0 Hz. With the flexibility to block any mal operation on event on under
voltage. All stages shall be of definite time type with a setting range of
0.10 300.0 s ( in steps of 0.02 s).

The relay shall also have the facility to detect a rate of change of
frequency for load shedding applications , to speed up operation time in
over- and under-frequency situations and to detect loss of grid. Pick up
setting shall be settable from 0.2 10.0 Hz/s (step 0.1 Hz/s).

g)The relay in addition to the above basic function should also


provide the following functions:

1. The relay should have the protection feature which allows the relay to
trip the upstream circuit breaker when a local breaker failure condition
is detected and should be energised both from operation of the relay
or by an external trip.

2.The relay shall also have the feature of auto reclosure with
independently programmable dead time and reclaim time for each
shot. The function shall be programmable for at least 4 shots of auto
reclosure.

3. The relay should measure the following standard quantities:

i.) It shall be possible to view the current voltage phasors as well in


the graphical mimic display.However, MIMIC display is not
mandatory.
ii.) Phase current(Positive, negative and zero sequence currents)
iii.) Phase Voltage(Positive, negative and zero sequence voltages)
iv.) Neutral current
v.) Frequency
vi.) Active and Reactive Power

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 40 /72


vii.) Power factor
viii.) Harmonics of current and voltages which shall be possible to view
as a diagram on the display. Display of harmonics in relay is not
mandatory.
ix.) Relay should be able to measure the true RMS value up to
15thharmonics

4. The relay shall have at least two independent setting groups. The
relay shall automatically switch from one setting group to another
depending on system conditions (such as failure of incomer supply,
which causes fault level to decrease etc.)

5. The relay shall have a facility to have communication on IEC61850


protocol through redundant rear port (i.e. RJ45 or FO) for SAS
connectivity without use of any external converter. Further, the test
levels of EMI as indicated in IEC 61850 shall be applicable to these.
The relay shall support peer to peer communication.
The relays shall generate GOOSE messages as per IEC 61850
standards for interlocking/tripping and also to ensure interoperability with
third party relays.
a) Necessary user friendly configuration tool shall be provided to
configure the relays. It should be compatible with SCL/SCD
files generated by a third party system.
b) Goose signals shall be freely configurable for any kind of
signals using graphic tool/user friendly software.

Bidder shall also ensure adequate hardware.


6. The Relay shall have facility for Time synchronization on IRIG B or
SNTP port.

h. Relay hardware:
The relay should be modular type. It will be installed on the top of the
Switchgear Panel. Standard terminal blocks should be located at the
rear of the relay providing connections for all input and output circuits.
i. Output relays:
The relay should have up to 2-CT inputs. They should provide at least 6
optically isolated inputs and atleast7 programmable outputs.They should
be arranged in response to any or all of the available functions by
suitably setting the output relays. The protection and control function to
which these relays respond should be selectable via the menu system of
the relay.One output relay shall be permanently assigned for self-
supervision.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 41 /72


H. The Relay shall also have the following functionality/Features..
* Thermal overload protection.
Negative sequence over current.
Permanent Self-Test.
i.) Circuit breaker maintenance information.
ii.) Broken conductor detection by measuring I2/I1 .
iii.) Cold load pickup function to change the settings when the protected
object is connected to a network i.e., at starting allowing the set value
being lower than the connected inrush current.

iv.) The relay shall also have the feature of Inrush blocking through 2 nd
harmonic detection.

v.) Disturbance recorder & Event recorder facilities.8 fault records shall
be possible in each protection stage.

vi.) Front RS232/USB port for communication to LAPTOP .


vii.) The relay shall have a facility for C.T. Supervision, P.T. Supervision
and Trip Circuit Supervision.

Relay shall support customer-defined programmable logic for


Boolean signals. It shall be possible to form equations using AND,
OR, NOT gates.

29.0 Detail on Differential Protection:


a) Transformer differential protection scheme shall be of numerical relay
(low impedance type) suitable for two winding Transformer.
b) Shall be triple pole type with faulty phase identification/indication.
c) Shall have an operating time not greater than 30ms at 5 times the
rated current.
d) Shall have three instantaneous high set over current units.
e) Shall have an adjustable bias setting range of 10 50%.
f) Suitable for rated 1 amp current.
g) Shall have 2nd harmonics or other inrush restraint features and also
should be stable under normal over fluxing conditions. Magnetizing
inrush features shall not be achieved any intentional time delay.
h) Shall have an operating current setting of 15% or less.
I) Shall have an internal feature of the relays to take care of the angle
and ratio correction.
j) Shall have provision of self monitoring and diagnostic feature.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 42 /72


k) Shall have provision of recording features to record graphic from of
instantaneous values during faults and disturbances for the pre and post
fault period and during running conditions.
l) Current in all the windings in separate analog channels and voltage in
one channel.

The disturbance recorder shall have the facility to record the following
external digital channel signals apart from the digital signals pertaining to
differential relay.
* REF protection operated.
* HV breaker status
*LV breaker status.
* Buchholz /OLTC Buchholz /PRV alarm/trip.
* WTI/OTI alarm/trip
* MOG alarm
Necessary hardware and software for automatic up-loading the
data captured by disturbance recorder to the personal computer.
Downloading from the relay memory to the computer memory will be
done.

The relay shall have three stages of definite time overcurrent


protection as backup operating with separate measuring systems for the
evaluation of the three phase currents, the negative sequence current
and the residual current.
In addition the relay shall have three stages of Inverse time overcurrent
protection operating on the basis of one measuring system each for the
three phase currents ,the negative sequence current and the residual
current.
Shall have feature of two nos. of independent REF protection for two
winding power transformers.

This function should be provided to maximize the sensitivity of the


protection of earth faults. The REF function should be a Low impedance
element. The REF function should be able to share CTs with the biased
differential function. As in traditional REF protections, the function should
respond only to the fundamental frequency component of the currents.

Shall have feature of V/F protection of different stage setting.


1. over fluxing protection to suit the transformer.
2. Wide range of setting to suit the worst condition of the highest
system voltage and worst system frequency).
3. Alarm and trip setting separately.
4. Thermal slope setting.
Shall be numerical type and shall have continuous self-monitoring
and diagnostic feature.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 43 /72


29.1Additional Protection Function

1. Differential Unit protection (87) which includes:

*Three phase differential protection


*Digital correction of vector group and Ratio
*Homopolar DC component relay filter, which is used to remove the
Homopolar component from the phase currents is DC component and
the relay shall have the filter component.

*Instantaneous Differential Trip.


*2ndand 5th harmonic restraint features.

2. Restricted Earth Fault Protection (87G)


3. Current Unbalance (46), which protects against current unbalances
resulting from anomalies in the power system or unbalanced loads.
4. Thermal image (49), which protects the transformer against damage
resulting from heating up during overloads.
5. Breaker Failure Protection(50BF),Which verifies the breaker correct
actuation for clearing a fault,otherwise, the trip of the necessary breakers
to clear that fault
6. Phase over current protection (3*50/51) with time delayed and two
instantaneous levels, as a backup protection for Transformer external
faults, if external faults are not cleared by primary protections
7.Over Excitation protection (V/Hz) (24) with two independent levels,
which prevents transformers from at a greater flow density than that
for which they were designed. And also avoiding heating and
consequent damage in the transformer due to over excitation.
8. Over Excitation protection (5th harmonic)
9. Neutral Earth fault with time delayed and Instantaneous for each
winding as for backup protection
10. Frequency protection (81O/U)
11. Over Voltage protection (59)
12. Ground Over current Protection (50G/51N), which act as an over
current function by using the current measured at the grounding of the
power transformer, being its function to detect faults to earth.

29.2 Automatisms
1, The user can configure up to 15 logic signals that can be assigned to
output relays, Leds or input for protection functions blocking features.
2, A lockout relay (86) function is needed. Relay programme with this
function will act when differential unit acts (At instantaneous) so that they
can be used as a locking device for breaker close circuits.

29.3 Monitoring Functions

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 44 /72


1. Breaker monitoring needed
2. Trip and close circuit supervision needed for detecting any anomalies
in the circuit with the open or close.
3.The unit temperature measurement supervision needed.(to know
transformer oil and winding temperature, which is optional)
4.The Battery voltage (DC supply )supervision needed.

29.4 Data Acquisition Functions

I. The following Measurements should be available


*Current in each winding (A)
*Average current in each winding (A)
*Differential current (A)
*Voltage (KV)
*Frequency (Hz)

29.5Oscillograph data recorder

I.All the units should needed an Oscillograph data recorder with the next
characteristics,
*Each Record comprises the samples from analog signals and the status
of 32 selectable digital signals
*16 or more samples per cycle.
*Configurable pickup.
*Records in non volatile memory.
*The disturbances are collected and exported in COMTRADE
format.
II. Event Recording:
The relay should store minimum 8 numbers or more last events in
a nonvolatile memory, which can retrieved from a PC with the following
data,
*Date and time of the Event.
*Descriptive text of Event.
*Values of Electrical parameters.
III. A queue of minimum 8 disturbance records is stored in the
nonvolatile memory.
IV. Fault Recorder
Minimum 5 or more faults are stored in the nonvolatile memory, with
the following data
*Date and time of the fault pickup, beginning and end.
*Prefault and fault values of electrical parameters.
*Duration and Type of Fault.
*Level of Electrical parameters at the faults occurrence time.
V.Time synchronizationVia communicationVia demodulated IRIG-B/
SNTP input
VI. Setting Group
Independent setting groups should be available.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 45 /72


VII. Communication Ports
As indicated above .

29.6 Other technical characteristics

*Have self diagnostic feature and watchdog output.

*Have front RS232 port/USB port and rear Redundant port remote
communications. The communication shall be on IEC 61850.

*Closed terminal needed for 06 CT input for differential (LV & HV


side of Transformer), 02 CT input (HV & LV neutral of Transformer)
for REF and three voltage input (for over fluxing protection, PT supply
from LV/HV side).

* Have programmable minimum of 5 digital Inputs, minimum of 8


digital outputs, minimum of 13 numbers programmable LED .

* Necessary latest version /communication software should be


supplied for configuration, setting modification, event analysis, and
SCADA communication.

*Programmable system frequency should be 50 Hz and operating


range should be fn = +/-5HZ.

*The contact of the relay shall have the following Minimum rating.

Make and carry continuously : 5A


Make and carry for minimum 1Sec. : 30A
* Current balancing transformers, shall form a part of the relay. The
successful Bidder shall furnish sufficient data to prove stability of the
equipment up to 10 times full load through fault current. Interposing C.Ts
if necessary for current balancing shall be within the scope of supply.
I.C.Ts shall be of universal type of setting different ratios.

30.0 OVER FLUXING RELAY:(V/f)

(a)Suitable relay with v/f characteristics shall be provided to defeat the


over fluxing condition of the transformer.

(b)The relay shall be a separate electromechanical relay to be


connected in parallel to the over fluxing relay, if, available in any of the
numerical relay i.e. if the same software is available in the numerical
differential protection relay.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 46 /72


(c) Shall have inverse time characteristics, matching with transformer
over fluxing withstand capability curve. The input to this relay is the
secondary IVT supply. However, setting will be decided at the time of
commissioning.
(d)Shall provide an independent alarm with the time delay continuously
adjustable between 0.1 to 6.0 seconds at values of v/f between 100% to
130 % of rated values.
(e)Tripping time shall be governed by v/f Vs time characteristic of the
relay.
(f) have a set of characteristics for various time multiplier settings. The
maximum operating time of the relay shall not exceed 3 seconds and
1.5 seconds at v/f values of 1.4 and 4.5 times, the rated values,
respectively.
(g)have an accuracy of operating time, better than +/-10 %.

31.0 TESTS
Following tests as indicated should have been conducted for the
above relays:

31.1 Soak test:


All solid state equipment/system shall be subject to the Hot Soak
Test as a routine test in accordance with the procedure detailed in
the following paragraph.

All solid state equipment shall be burn-in tested for minimum of 120
hours continuously under operational conditions. During the last 48
hours of testing, the ambient temperature of the test chamber shall
be 50C. The temperature of the interior shall not exceed 65C.

31.2 Type tests:


1. Impulse voltage withstand test as per Clause 6.1 of IS 8686 (for
a test voltage appropriate to Class III as per Clause 3.2 of IS-
8686).
2. High Frequency Disturbance test as per Clause 5.2 of IS 8686
(for a test voltage appropriate to Class III as per Clause 3.2 of IS
8686).Type tests listed under IEC-Technical Committees
recommendation `TEC-57' (IEC 61850 Communications, IEC
60255 -Insulation / Dielectric / EMC / Mechanical / Enviornmental
etc) and functional type tests listed under CIGRE Study
Committee 34 (Protection) Report on simulator, Network analyser
or PTL as applicable.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 47 /72


31.3 Routine tests: Contact insulation resistance test as per Clause
10.5 of IS-3231.
Insulation withstand capability as per Clause 10.5 of IS-3231 on all
AC/DC relays.

32.0 MULTIFUNCTION METER

GENERAL: Multifunction Meter will be installed on the top of the


Switchgear Panel.

*. Each bay should be provided with a Multifunction meter having


following features:-
* Features: By level monitoring of all electrical parameters of
V,I,,cos,Hz,KVA,KVAR,KW&KWH.TrueRMS
measurement
* Accuracy: 0.2s
*. User selectable display ranges. (CT/PT).
*. Auto scrolling/Manual display
*. RS 485 communication port with MODBUS RTU
protocol.Compatible for data logging & SCADA application.
*. Inbuilt Real time clock with calendar.
*. 3phase,4 wire,3 element or as per requirement.(to be decided
during detail Engineering).
*. Quadrant of operation: 04 Quadrant.
*. Display: Bright red 7-segment LED display.
*. HMI: Through Front panel tactile keys.
*. Indication: Phase voltage, Phase current ,Line voltage,
Frequency, Power factor, KVA,KVAR,KW,KVAH,KVARH,KWH.
*. Voltage input: 63.5/110V
*. Current Input: 1 A
*. Auxiliary supply: 85-250 V AC or 48 V DC
*. VA burden: 15VA
*. Frequency Range: 45 to 55 Hz
*. Power factor range: 0.1 lag -1 -0.1 lead
*. Over voltage: 130% continuously & 200% for 30 sec
*. Over current: 2 times continuous, 20 times for 1 sec.
*. Response time: 200 ms
*. Class of accuracy: 0.2s as per IEC 60687, IS 14697
*. Complies to EMI: IEC 61000-4-5,3,4
*. Display resolution: upto 1 decimal
*.Output: Two communication port with optical isolation.RS 485
communication port with MODBUS RTU protocol.
*.CT shorting provision should be there.
*.Mounting: Flush panel mounting.
*. Dimensions:144X144 mm
*.Ambient condition: working: 0-55 deg cent,5-95% RH.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 48 /72


32.1
(a) A flag operated master trip relay should be provided (48 V DC with
N/C contact in series with the relay coil): Electromechanical relay
having sufficient output contact (N/O & N/C) should be available for
interlock, indication & other SCADA purpose.

(b) Other electromechanical auxiliary relays as required as per the


scheme to be provided.
(for contact multiplication, Transformer trouble shooting like Oil temp
Al& trip, Winding temp Al & Trip, Bucholtz Alarm & Trip, MOG
alarm, PRV Trip etc)

(c) A12 Window static annunciator with Test, Accept & Reset
arrangement and with Buzzer & Bell.

32.2 Test terminal Blocks- Test terminal Block need be provided


for testing meters in test position.

32.3 Indication Lamp(24DC Red- Breaker 'ON'


LED type) Green Breaker 'OFF'
Amber- Breaker 'AUTO TRIP'
Blue- Spring charge indication.
White-Healthy Trip illuminated push bottom switch
33.0 Panel wiring and accessories.

Wiring: Each panel shall be supplied with all internal wiring complete.

33.1 Panel wiring shall be suitably bunched and clamp for neat
appearance. The conductors used for wiring purpose shall be
PVC insulated 1100 volt grade semi- flexible heat resistant,
flame retardant and vermin proof electrolytic copper cable
conforming to IEC:227, 502 or IS:1554. The wiring shall be
securely supported and taken though PVC through PVC
troughs. Each wire shall be continuous from end to end
without any joint in between. All panel wiring shall be
capable of withstanding a voltage of 2kV AC 50Hz for one
minute.

33.2 Cable and wire for connections within the switchgear


and between the switchgear and terminal blocks shall have
a minimum temperature rating of 90 degree Celsius. The size
of the conductors for panel wiring shall be not less than
2.5mm2. For CT secondary wiring, two such wires shall be
used in parallel.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 49 /72


33.3 Panel wiring protection

The panels shall be equipped with links and HRC cartridge


fuses conforming to IEC:269 or IS:13703 in 1100 Volt grade
phenolic moulded fuse holder consisting of fuse carrier and
base or miniature circuit breakers conforming to IEC:947-2 or
IS:13947-2 at appropriate locations. The carriers and bases
shall be made of high grade flame retardant and non
hygroscopic phenolic moulded material with hard glass
surface. Each fuse or MCB shall be identified with engraved
plastic label.

33.4 In general, fuses and MCBs shall be limited to the minimum


required for safety.
The protection scheme shall include fuses for VT secondary
circuits and DC supply to each panel and fuses for MCB for
spring charging motor and incoming AC supply.

34.0 Terminal blocks

Terminal blocks of brass studs rated for 10 amps continuous


current,1100volt. DC grade covered by moulded insulating materials
with adequate electrical clearances shall be provided for
terminating the panel wiring and outgoing connections. The
termination shall be made by crimping lugs or bare conductor with
insulating sleeves at ends. The arrangement can be horizontal or
vertical as per standard practice adopted by the manufacturer. All
terminals must be numbered and wire termination provided
with numbered ferrules for identification. All numbering and
marking including those in wiring diagram shall follow the guidelines
provided in IS:11353. All circuit breaker auxiliary contracts including
spare contacts shall be wired to the terminal blocks. Ten percent spare
terminals shall be provided.

35.0 Colour and numbering

The wiring used for 230V AC supply for illumination lamp, panel heater
and otherdevices shall be coloured. The colour of wires connecting
directly to Earth shall be green. CT & PT connection wires shall be of
R, Y & B colour. Engraved core identification plastic ferrules marked to
correspond with the panel wiring diagram shall be fixed at both ends
of each wire. Ferrules shall fit tightly on the wire and shall not fall off
when the fire is disconnected from the terminal block. Number 6 and
9, if used shall be under scored to enable differentiation.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 50 /72


36.0 Circuit diagram

A durable copy of the circuit wiring diagram shall be affixed to the


inner side of the door of the switchgear compartment. Labels shall be
provided inside the compartment to describe the functions of the
various items of equipment.

The scope of the supply shall include the panel mounting foundation
bolts, nutsand washers necessary for making the supporting.

37.0 DISCONNECTORS (In GIS Panel):

Disconnector shall be provided in the GIS Switchgear panel. There


shall be interlock with the VCB.
Rating: 630A.
SCC: 25 KA for 3 sec.
Internal Arc 25 kA 1 sec
Material: Electrolyte copper.

38.0 AUXILIARY SUPPLY

Control supply for closing and tripping shall be 48 Volts D.C.through


external battery source. 230 Volts single phase A.C. supply shall
also be available for the operation of spring charging motor and
cubicle space heater.

39.0 DIMENSION

The dimension for 33kV GIS shall not exceed


600mm (Width) X 2000mm (Depth) X2500mm (Height)

The dimension for 33kV AIS shall not exceed


1200mm (Width) X3200mm (Depth) X 2700mm (Height)

The dimension for 11kV AIS shall not exceed


800 mm (Width)X2100mm (Depth)X2500mm (Height)

40.0 TYPE TEST OF THE 33 KV SWITCH GEAR (VCB) PANEL.


Following type test reports shall be submitted during the detailed
Engineering and approval of drawings.
All short circuit duties including single phase and double line to
ground as per IEC62271-100or as per latest amended IEC.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 51 /72


Short time rating for 3 seconds as per IEC 62271-100,62271-
200 or as per latest amended IEC.
Temperature rise test as per IEC 62271-200or as per latest
amended IEC.
Capacitor bank switching for 400A minimum & cable charging 25
A test as per IEC 62271-100 For test duties 1 to 4 or as per latest
amended IEC.
Degree of protection test as per IEC 62271-200 or as per latest
amended IEC.
Lightning impulse voltage test as per IEC 62271-100 ,62271-200
or as per latest amended IEC.
Internal arc test of 25 kA 1sec in all the three high voltage
compartments as per IEC 62271-200 or as per latest amended
IEC.

41.0 QUALIFYING REQUIREMENT.

The equipment offered shall be procured from short listed vendor at E-


23 and shall have been successfully Type Tested during last five years
on the date of bid opening. The front page of the Type Test report
showing the evidences of the tests, duly signed by the bidder shall be
uploaded along with the bid.

The following Type tests of VCB should have done:

1) Short Time withstand current


2) Temperature Rise
3) Lightning Impluse Test
4) Internal Arc Test
5) Make & Break Test duties
6) Power frequency voltage test
7) Partial discharge test
8) Resistance measurement test
9) Tightness test
10 )Closing Characteristic test
11) Opening Characteristic tests

The VCB shall be ofM2, C2 & E2 duty class.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 52 /72


PART - B

TECHNICAL SPECIFICATION
FOR
11KV Indoor Switchgear Panel for AIS

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 53 /72


1.0 REQUIREMENTS
This specification covers design, engineering, manufacture, testing, and inspection of
11 KV indoor Air Insulated Switchgear Panel (provided with Vacuum circuit Breaker & CT,
IVT etc) for use in the 33/11KV primary substations under the distribution networks. 11
kV Switchgear shall have Vacuum breakers & CT etc. The 11kV side of 33/11kV Sub-
station shall be of AIS switchgear irrespective of AIS / GIS Sub-station. Hence, there
shall not be any Disconnector on 11kV side Indoor Switchgear. There shall be separate
Indoor Panel (2nos.) for IVT at 11kV side. The Switchgear must have type tested.

1.1 Description of the Switchgear Panels for 11 kV AIS.

Indoor switchgear for AIS should be provided in a cubicle, which shall be erected inside
a building. Separate Switchgear Panels for feeder & transformer of 11 kV AIS system
are to be considered. Care should be taken during manufacturing of the same as the
equipment like VCB & CT are to be installed in the panel individually. The 11kV side of
33/11kV Sub-station shall be of AIS switchgear irrespective of AIS / GIS Sub- Station.
Hence there shall not be any Disconnector on 11kV side Indoor Switchgear. There
shall be separate Indoor Panels (2nos.)for IVT at 11kV side. Vibration is inevitable
as mechanical operation for closing the VCB may cause problem and its performance
will be affected. Foundation shall be designed to take care of the vibration and dynamic
force during closing and tripping.

The circuit breakers switchgear panels to be supplied against this specification shall be
required to control the LV side of 33/11 kV power transformers in the primary sub-stations
and also the incoming 11kV feeders or the outgoing feeders in these sub-stations. The
switchgear panels shall be suitable for 3 phase 50Hz solidly grounded neutral system and
shall have normal current carrying capacity of 630 Amp & Bus-bar shall be 1250 Amp for
Indoor Switchgear and symmetrical short circuit breaking capability as mentioned
hereunder.

2.0STAND ARDS:

Expect where modified by this specification, the circuit breakers and the accessories shall
be designed, manufactured and tested in accordance with latest editions of the following
standards.
IEC/ISO/BS IS Subject
IEC:56 High voltage alternating current circuit breakersgeneral
IEC: 62271-100 & Requirement.
200
IEC:694 IS : 12729 Common clauses of high voltage switch-gear and control gear
standards (for voltage exceeding 1000 V).
IEC:60 IS : 9135 High Voltage testing techniques.
I EC:427 IS:13516 Method of synthetic testing of HV A.C circuit breakers.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 54 /72


IEC: 1233 HV AC Circuit breakers- inductive load switching.
IEC: 17A/CD:474 HV AC Circuit breakers- capacitive switching.
IEC:529 IS: 13947 Degree of protection provided by enclosure.

IEC:137 IS: 2099 Insulating bushing for AC voltages above 1000V

IEC:233 IS : 5621 Hollow insulators for use in electrical equipment & testing.
IEC:273 IS: 5350 Characteristics of indoor and outdoor post insulators for
systems with nominal voltages greater than 1000V.
Guide for selection of insulators in respect of polluted
IEC:815 IS: 13134
conditions.
IEC: 34 IS : 996 AC motors
ISO:1460 BS:729 IS:2629 Hot dip galvanizing
IS:2633 Method of testing uniformity of zinc coated articles.
IS: 5 Colour for ready missed paints and enamels
IS: 6005 Code of practice for phosphating or iron and steel.
P.V.C Insulated cables for voltages up to and including 1100
IEC: 227 IS:1554
Volt.
IEC:269 IS:13703 Low voltage fuses for voltages not exceeding 1000Volt.
ISO:800 IS:1300 Phenolic moulding materials.
IS:13118 Guide for uniform marking and identification of conductors and
apparatus terminals.
IEC: 185 IS: 2705 Current transformers.
IEC: 296 IS: 335 Specification for unused insulating oil for transformer and
switchgear.
IEC:186 IS: 3156 Potential transformers.
CBIP Technical Report No. 88 revised July, 1996 read with amendment issued
(April, 99, September, 99 and also any other amendment thereafter): Specification for
AC Static Electrical Energy Meter.

3.0 BASIC TECHNICAL REQUIREMENTS:

The Vacuum circuit breakers shall comply toE2, M2 and C2 category and are
required to meet the following basic technical requirements.
(Reference standards IEC:62271 - 100 & 200 or as per latest amended IEC and associated
standards listed in this specification.
Basic Technical Requirements
SI. No Particulars Requirements
1 Service type Indoor
2 No. of Poles 3
3 Nominal system voltage 11kV

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 55 /72


4 Highest system voltage 12kV
5 Rated normal current at 50C
For Bus-bar 1250A
For Interrupter 630A
For Outgoing Feeders/ For Incomer & Bus Sections 630A
6 Rated Internal Arc tested for 1 Sec 25kA
7 Rated short circuit making current (peak) 62.5 kA
8 Rated short time current withstand capability for 3 sec. 25kA(Panel)/25kA
9. Rated insulation level: (Interrupter)
One minute power frequency withstand voltage to earth 28kV
(wet and dry) rms
Impulse withstand voltage to earth with 1.2/50 sec, 75kV
wave of +ve and ve polarity (Peak)
10 First pole to clear factor 1.5
11 Rated operating sequence (for auto reclosing) 0-0.3 Sec- CO-3 min-CO
12 Maximum break time 3 cycles
13 Rated out of phase breaking current 25% of the symmetrical short
circuit breaking current
14 Maximum pole scatter 10 mili seconds
15 Rated Auxiliary supply for spring charge motor, lamp & 230V A.C
heater circuit.
16 Rated supply voltage for trip/close coil 48 V D.C

4.0 SYSTEM CONDITIONS:


The breakers are to be suitable for indoor operation. Please refer chapter E3 of
Technical Specification on SYSTEM conditions.

5.0 11 KV VACUUMCIRCUIT BREAKERS

5.1 GENERAL
The circuit breakers mounted on a withdrawable truck for AIS along with CT, Control &
relay Panels shall be suitable for indoor installations with vacuum as interrupting
media incorporating separate interrupters of 630A rating for each phase mounted on
single frame. Internal Arc withstand for 11kV & 33kV VCB must be 25kA for 1 sec.
There is no line PT in the scope. Bus IVT will be in a separate Panel.There shall
be a common drive mechanism actuating for interrupters, which must work in
synchronism. These shall be a common drive mechanism actuating the interrupters,
which must work in synchronism. These breakers shall be provided with suitable local
control while provision shall be made for remote control. All the signals going in DCS
shall be through hardwire.
5.2 The entire circuit breaker with its operating mechanism shall be mounted on a
horizontal draw-out type chassis/ trolley inserted into a floor standing sheet
steel(Withdrawable truck for AIS)enclosure suitable for withstanding
electromagnetic/ electro-dynamic forces of both symmetrical and asymmetrical faults.
It shall have plug- in off load type isolating main and auxiliary contacts with all
necessary safety features, door limit switch etc.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 56 /72


5.3 The Panel shall be fabricated from 2 mm thick CRCA Sheet Steel/ Alu-Zinc while
load bearing member and cable entry plate shall be of 3mm thick. The partition
/inside wall suitable for coupling with identical units on either sides to form Switch
board. The circuit breaker Panel shall be such that when the withdrawable part is
being removed the metal shutters can be opened with a lever, for an example to
inspect the mating contacts or locked with a padlock. The upper portion (access to
the Bus bar) and the lower portion (access to the termination compartment) can be
unscrewed with the metal shutters closed. This makes it possible to work in the
Busbar compartment with the termination compartment fully partitioned off, and
vice versa. The breaker shall be provided with three distinct positions namely
Service, Test and Isolate.
5.4 The circuit breakers shall be fitted with spring mechanism type. The inherent design
of the circuit breakers shall be such that they shall satisfactorily perform all test duties
and interrupt out-of-phase current and produce very low over voltage (<2.5pu) on all
switching circuit, capacitive and inductive to IEC:62271 - 100 & 200and other
associated standards mentioned in the clause of this specification.

5.5 The connecting terminal for Cables shall have silver plating of at least 10
micron thickness. The design of the circuit breaker shall be such that inspection and
replacement of contacts, coils, vacuum bottles and any worn or damaged
components can be carried out quickly and with ease. The contact gaps shall be
adjustable to allow for wear.

5.6 The mechanism and the connected interrupters shall satisfy the mechanical
endurance requirements of IEC: 62271 - 100 & 200 or as per latest amended IEC
and all additional requirements specified herein.

6.0 Interrupting media (Vacuum):

6.1 The vacuum bottles shall be easily replaceable on site and the mechanism
shall be conveniently adjustable to permit resetting the contact gap. The current
rating of the vacuum interrupters shall be 630Amp.

6.2 The vacuum circuit breaker poles shall be sealed to prevent contamination of the
spaces surrounding the interrupters. The bidder shall demonstrate how this is
achieved by supplying technical details with the bid.

7.0 Auxiliary contacts

7.1 Auxiliary contacts (6NO + 6NC) of 48 Volt D.C grade and 10 amps DC rating
shall be provided in each circuit breaker.However, additional contact shall be
made available by using contact multiplier relay/Contact multiplication relay
can be used.

8.0 Indication

8.1
A mechanically operated circuit breaker position indicator of non -
corroding material shall be provided in a location visible from the operating
side of the breaker without the necessity to open the mechanism door. The

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 57 /72


word 'OFF' in white letter on green background shall be used to indicate
that the breaker is in the opening position and the word 'ON' in white letters
on a red background to indicate that the breaker is in the closed position. The
drive for the device shall be positive in both directions and provision shall be
made for local and remote electrical indication.

8.2 Indication of spring charging condition shall be provided as mentioned in


this Specification. Mechanical counters to record the number of closing
operations shall be provided for each circuit breaker mechanism.

9.0 Operation and controls

9.1 The breaker shall normally be operated by electrical control with electrical
trippingby2 nos. Shunt trip coils. Provision shall be made for local electrical
operation and mechanical operation.There shall be a separate switch for
electrical operation of the VCB.
9.2 The following facilities shall be provided in the circuit breaker local control
cabinet:
ON/NEUTRAL/ OFF control switch or ON and OFF push buttons. The push
buttons shall be momentary contact type with rear terminal connections.
The close push button shall be of green colour and the open push
button red colour.There shall be a separate switch for electrical
operation of the VCB.

Mechanical push to trip button shall be provided for manual tripping with
front door closed in the event of failure of electrical supplies. The
device shall be accessible without opening any access doors and
distinctly labeled. It shall be shrouded and protected against inadvertent
operation.
Means shall be provided for manual operation of these circuit breakers
during failure of auxiliary power in addition to electrical operation.
9.2 Means shall be provided to prevent the mechanism from responding to a
close signal when the trip coil is energized or to reclosing from a sustained
close signal either opening due to a trip signal or failure to hold in the closed
position.

9.3 The circuit breaker shall be able to perform 10,000 operating cycles at no
load in accordance with IEC:17A/474/CD for circuit breakers for auto reclosing
duties.

10.0 CURRENT TRANSFORMERS

10.1 Current transformers, three per circuit breaker, shall be of indoor, single
phase,resin cast and shall comply with IEC:185 and IS:2705, suitable for
operation in hot and humid atmospheric conditions described in service
condition. They shall be mounted inside the panel. The Class of insulation for

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 58 /72


CT's shall be CLASS E or better. The CT/PT's shall be cast Epoxy Resin
Cast type and shall be either window or wound type.

10.2 Core

10.2.1 High grad non-ageing Cold Rolled Grain Oriented (CRGO M4 or better
grade) silicon steel of low hysteresis loss and permeability shall be used for
the core so as to ensure specified accuracy at both normal and over currents.
The flux density shall be limited to ensure that there is no saturation during
normal service.

10.2.2 The instrument security factor of the core shall be low enough so as not to
cause damage to the instruments in the event of maximum short circuit current.

10.3 Windings

10.3.1The secondary windings shall be made of electrolytic copper with suitable


insulation. The conductor shall be of adequate cross- section so as to limit
the temperature rise even during short circuit conditions. The insulation of
windings and connections shall be free from composition liable to soften,coze,
shrink or collapse during service.

10.3.2 Polarity shall be indelibly marked on each current transformer and at the lead
and termination at associated terminal blocks. CTs with multi ratio winding
shall be clearly tabulated to show the connections required for different
ratios. Similar numbers shall be marked on terminal block arrangement and
wiring diagram. Apart from the above marking and those to be provided as
per IEC 185 or IS 2705, other markings shall be provided in consultation with
the Owner.

10.3.3The continuous current rating of the primary winding shall be120%(one


hundred and twenty percent) of the normal rated current.

10.3.4 Secondary windings of current transformers shall be used for


metering,Instrumentation and protection and shall be rated for continuous
current of 120% (one hundred and twenty percent) of normal rated current of
primary winding.

Current transformers shall be three core window/bar primary. Maximum VA


burden shall be of 15 VA and shall be rated for full short circuit current 25 kA for
3 second. Out of three cores one Core having 0.2S class (Metering) & other
two cores having PS (Protection) class accuracy.

10.3.5. FEEDER PANEL:


Current Ratio: 400-200/1-1-1 Amp
No. of Cores: 03
Burden: 15 VA for each core

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 59 /72


10.3.6 TRANSFORMER PANEL:
Current Ratio: 400-200/1-1-1 Amp
No. of Cores: 03
Burden: 15 VA for each core

11.0 Fittings and accessories

11.1 Fittings and accessories listed below shall be supplied with each current
transformer:
Bimetallic connectors suitable for connecting 185-400mm2 XLPE
insulated Aluminimum Cables.
Two earthing terminals and strips with necessary nut, bolts and
washers;
N a m e a n d ra t in g p l a t e ;
LV terminals with connection diagram:
Mounting nuts, bolts and washers;

11.2 Any other fittings deemed essential by the Supplier shall also be supplied
with each current transformer.

11.3 Basic technical requirement for CT's

Knee Point Voltage shall be 400V for both 33kV & 11kV CT.
Maximum excitation current at Vk=25mA.

Ratings: The CTs shall confirm to the following ratings and other particulars of
the circuit breakers:

Technical Requirements
SI. Particulars Requirements
No
1 Function To control 11 kV Feeder & LV side of 33/11kV
power transformers of ratings between 3.15MVA
to 12.5MVA
2 Requirement The CTs in the 11 kV Indoor VCB switchgear
panel should have three cores as follows.
3 Transformation Ratio Category- A (For TFR) Category-B (For Feeder)
400 - 200/1-1-1-A 400-200/1-1-1 A

4 Rated Burden (VA) Core:1: 15 VA , Core:1: 15 VA ,


Core:2: 15 VA, Core:2: 15 VA,
Core:3:15 VA Core:3:15 VA
5 Class of Accuracy Core:1: 0.2S , Core:1: 0.2S ,
Core:2: PS, Core:2: PS,
Core:3: PS Core:3: PS
6 Instrument Security Core- 1:- <5 Core- 1:- <5
Factor

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 60 /72


7 Purpose Core:1: Metering , Core:1: Metering ,
Core:2: Differential, Core:2: Spare
Core:3:O/C& Core:3:O/C&
E/F & REF E/F & REF
Rated/Highest
8 11/12 kV
system Voltage
9 Short Time Rating 25 kA rms for 3 seconds
10 Power frequency 1 min
voltage withstand level/ 28 kV/75kVp
Insulation Level:
-Impulse Voltage1.2/50
s wave withstand
level -

12.0Tests
12.1 The CTs shall be tested in accordance with the requirements of the type tests
and routine tests as per the latest issues IEC:185 or IS:2705.
The tests to be conducted shall include:
12.2 Type Tests:
L igh t n in g im pu lse vo lt a ge :
Power frequency wet withstand voltage;
Temperature rise;
Short time current;
Composite error;
Accuracy test (for measuring core);
Instrument security current (for measuring core);

12.3 Routine tests


Verification of terminal marking and polarity;
Power frequency dry withstand test on primary windings
Power frequency dry withstand test on secondary windings
Power frequency dry withstand test between sections;
Over voltage inter-turn test;
Composite error;
Turn ratio;
Accuracy test (for measuring core);
Current error and phase displacement (for protection core);
Knee point voltage and magnetizing current test (for PS class);
Secondary winding resistance (for PS class).
Routine test of brought out equipment shall be carried out by the respective
Vendor in presence of the Owners(OPTCL) representative.

13.0 POTENTIAL TRANSFORMER

13.1 BASIC TECHNICAL REQIREMENTS**

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 61 /72


The 11 kV Indoor voltage transformers(IVT) are required to meet the following basic
technical requirements (Reference standards: IEC:186, IS:3156 and associated
standards listed in the specification):
SI. Particulars Requirements
No
1 Type Single phase
2 Nominal system voltage, phase to phase 11 kV
3 Application Instrumentation, Metering and
Protection
4 Number of secondary windings 2
5 Rated normal burden* 15VAfor each Core
6 Rated primary voltage 11000/3
7 Rated secondary voltage 110V/3-110V/3
8 Class of accuracy 0.2/3P
9 Rated insulation level: (Primary winding)
(Phase
i) One to earth)
minute power frequency withstand 28kV
voltage towithstand
ii) Impulse earth (wetvoltage
and dry)tormsearth with 75kV
10 1.2/50minute
One ilsec wave of +ve
power and ve
frequency polarity
withstand
(peak)
voltage of secondary
i)Between phase to earth winding (rms) 3kV
ii) Between sections 3kV
11 Rated voltage factor
i) Continuous 1.2
ii) For 30 seconds 1.5

* The burden indicated is the minimum acceptable to the Owner. The


Contractor shall ensure that the rated outputs of the voltage transformers
are adequate to meet at least 120 percent of the connected load (burden).

**There is no line PT. Bus IVT (PT) will be in separate panel. Burden
will be 15VA for each Core.

13.2 GENERAL

The voltage transformers to be supplied under this specification shall be of Indoor,


single phase Epoxy Resign Cast type complying with IEC:185 and IS:3156
suitable for operation in hot and humid atmospheric conditions described in
this document.

13.3 Duty requirement

13.3.1 11 kV Voltage transformer for all the indicating instruments and measuring
meters in the primary substation on 11kV side. It shall be of indoor, 1-Phase
or 3- phase Epoxy Resign Cast type.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 62 /72


13.4 Core

13.4.1 High grade non-ageing Cold Rolled Grain Oriented (CRGO-M4 or better)
silicone steel of low hysteresis loss and permeability shall be used for
core so as to ensure accuracy at both normal and or over Voltages. The
flux density shall be limited to 1.6 Tesla at normal voltage and frequency.
There shall be no saturation at any stage during operation.

13.4.2 The instrument security factor of the core shall be low enough so as not to
cause damage to the instruments in the event of maximum short circuit
current or over voltages.

13.5 Windings

13.5.1 The primary and secondary windings shall be electrolytic copper of high
purity and conductivity and covered with double paper insulation or super
enamel coating. The conductor shall be of adequate cross-section so as
to limit the temperature rise even during maximum over voltages.

13.5.2 The insulation of windings and connections shall be free from composition
liable to soften, ooze, shrink or collapse during service.

13.5.3 The secondary windings of the voltage transformers shall also be suitable
for continuous over voltage corresponding to the maximum system voltage
at the primary winding. The winding supports shall be suitably reinforced to
withstand normal handling and the thermal and dynamic stresses during
operation without damage.

13.5.4 The voltage transformer secondary circuits will be taken out to form the star
point and earthed at one point outside the voltage transformers.

13.5.5 Both primary and secondary winding terminals shall be clearly and
indelibly marked to show polarity in accordance with IEC:186. The
connections required for different secondary windings in case of multi-
winding voltage transformers shall be clearly indicated in terminal blocks
and the wiring diagrams.

14.0 Fitting and Accessories

14.1Fittings and accessories listed below shall be supplied with each voltage
transformer:

HV terminals
Two earthing terminals with necessary nuts, bolts and washers
Name and rating plate
Secondary terminal box with LV terminal connections
Mounting nuts, bolts and washers
LV HRC cartridge fuses for the protection of secondary winding

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 63 /72


HV HRC cartridge fuses for the protection of Primary winding

14.2 Any other fitting deemed essential by the contractor shall also be supplied
along with each voltage transformer:

14.3 The name and rating plate shall contain all the particulars as provided in
IEC:186 and also the name of the Owner and year of manufacture. They
shall comply with the clause termed label in this specification.

15.0 Fuse protection


The Primary winding shall be protected by HRC Fuses in suitable
holder designed by the manufacturers.

15.1 The secondary windings shall be protected by HRC cartridge fuses in


fuse holder consisting of carriers and bases. The carriers and bases shall
be of high grade flame retarding and non-hygroscopic moulded insulating
materials with hard glass surface. Each fuse shall be identified with
engraved plastic label.

16.0 Circuit diagram

16.1 A durable copy of the circuit wiring diagram shall be affixed to the inner
side of the terminal box cover. Labels shall be provided inside the cover to
describe the functions of various items of equipment.
17.0 TERMINATION
17.1 The equipment shall be supplied with HV electrical connection terminals
of a size and rating appropriate for all the duties, including overload duty
specified for the equipment. The terminals shall be of the bi-metallic type.
18.0 EARTHING TERMINAL
18.1 Two earthling terminals complete with necessary hardware shall be
provided on each voltage transformer for connection to earth continuity
conductors. They shall be of electroplated brass and of adequate size to
carry the earth fault current.
18.2 The earthing terminals shall be identified by means of appropriate
symbol marked in a legible and indelible manner adjacent to the terminals.
19.0 TEST AND INSPECTIONS
19.1 The voltage transformers shall be tested in accordance with the
requirements of the Type tests and Routine tests as provided in the
latest issues of IEC:186 or IS:3516.
Type tested equipment/materials are acceptable. Type tests should have
been conducted in last five years. The Type Test must have been as per
OPTCL requirement. If OPTCL desires another type test, it has to be
conducted. In such case OPTCL will bear the transportation of
equipment/material and type test charges.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 64 /72


The tests to be conducted shall include;

19.2 Type tests:


Lightning impulse volta ge test
High voltage power frequency wet withstand voltage
Temperature rise test
Short circuit withstand capability test
Determination of limits of voltage error and phase displacement
19.3 Routine tests:
Verification of terminal marking and polarity
Power frequency withstand tests on primary winding
Power frequency dry withstand tests on secondary winding
Power frequency withstand tests between sections
Determination of limits of voltage errors and phase displacement
Insulating Resistance measurement
Partial discharge measurement

19.4 TEMPERATURE RISE:


The temperature rise of any part of the voltage transformer under
continuous operating and exposed in the direct rays of the sun shall
not exceed the permissible limits as provided in IEC publication 186 or
IS:3156. These shall not be exceeded when corrected for the
difference between the ambient temperature at site and the ambient
temperature specified in the standard 62271-200/100, with silver plate joint.
The correction proposed shall be stated in the bid.

20.0 PROTECTIVE RELAY & CONTROL PANEL

20.1 The CR Panel (Instrument Chamber) should be mounted on top of the


VCB Panel.
Control Panel (in-built) with protective relay and meter shall be provided by
the supplier suitable for above breakers. The equipment shall have
protection scheme with the following relays:
(i) Triple pole IDMTL type combined over current (3Nos) & Earth fault
(1No) relay (Draw out type) preferably Communicable numerical relay
of reputed make with supporting Protocol IEC:61850and that should be
type tested with IEC protocol 61850.
The detailed Specification are as indicated in 33 kV Indoor Switchgear Panel
(SlNo. 14)
21.0MULTIFUNCTION METER

GENERAL
Multifunction Meter will be installed on the top of the Switchgear Panel.

*. Each bay should be provided with a Multifunction meter having following


features:-
* Features: By level monitoring of all electrical parameters of
V,I,,cos,Hz,kVA,kVAR,kW&kWH.True RMS measurement

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 65 /72


* Accuracy: 0.2s.
*. User selectable display ranges. (CT/PT).
*. Auto scrolling/Manual display
*. RS 485 communication port with MODBUS RTU protocol.Compatible for data
logging & SCADA application.
*. Inbuilt Real time clock with calendar.
*. 3phase,4 wire,3 element or as per requirement.(to be decided during detail
Engineering).
*. Quadrant of operation: 04 Quadrant.
*. Display: Bright red 7-segment LED display.
*. HMI: Through Front panel tactile keys.
*. Indication: Phase voltage, Phase current ,Line voltage, Frequency, Power
factor, kVA,kVAR,kW,kVAH,kVARH,kWH.
*. Voltage input: 63.5/110V
*. Current Input: 1 A
*. Auxiliary supply: 85-250 V AC or 48 V DC
*. VA burden: 15VA
*. Frequency Range: 45 to 55 Hz
*. Power factor range: 0.1 lag -1 -0.1 lead
*. Over voltage: 130% continuously & 200% for 30 sec.
*. Over current: 2 times continuous, 20 times for 1 sec.
*. Response time: 200 ms
*. Class of accuracy: 0.2s as per IEC 60687, IS 14697
*. Complies to EMI: IEC 61000-4-5,3,4
*. Display resolution: upto 1 decimal
*.Output: Two communication port with optical isolation.RS 485 communication
port with MODBUS RTU protocol.
*.CT shorting provision should be there.
*.Mounting: Flush panel mounting.
*. Dimensions:144X144 mm
*.Ambient condition: working: 0-55 deg cent,5-95% RH

21.1
(a) A flag operated Master trip relay should be provided (48 V DC with N/C contact in
series with the relay coil): Electromechanical relay having sufficient output contact
(N/O & N/C) should be available for interlock, indication & other SCADA purpose.

(b) Other electromechanical auxiliary relays as required as per the scheme to be


provided.

(for contact multiplication, Transformer trouble shooting like Oil temp alarm& trip,
Winding temp alarm& Trip, Bucholtz Alarm & Trip, MOG alarm, PRV Trip etc)

(c) A 12 Window static annunciator with Test, Accept & Reset arrangement and with
Buzzer & Bell.

(i)Test terminal Blocks- Test terminal Block need be provided for


testing meters in test position.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 66 /72


ii) Indication Red- Breaker 'ON'
Lamp(48V DC Green- Breaker 'OFF'
LED type) Amber- Breaker 'AUTO TRIP
Blue- Spring charge indication.
White-Healthy Trip illuminated push bottom switch

21.2 In Built Control- Relay Panel in the In Door VCB (Mounted on the Top
of VCB Panel)

22.0 Panel wiring and accessories.

22.1 Wiring

Each panel shall be supplied with all internal wiring complete.


22.2 Panel wiring shall be suitably bunched and clamp for neat appearance.
The conductors used for wiring purpose shall be PVC insulated 1100 volt
grade semi-flexible heat resistant, flame retardant and vermin proof
electrolytic copper cable conforming to IEC:227, 502 or IS:1554. The wiring
shall be securely supported and taken though PVC through PVC. Each wire
shall be continuous from end to end without any joint in between. All panel
wiring shall be capable of withstanding a voltage of 2kV AC 50Hz for one
minute.
22.3 Cable and wire for connections within the switchgear and between
the switchgear and terminal blocks shall have a minimum temperature
rating of 90 degree Celsius. The size of the conductors for panel wiring shall
not be less than 2.5mm2. For CT secondary wiring, two such wires shall be
used in parallel.CT, PT & all other control wiring shall be 2.5 Sq mm.

22.4 Panel wiring protection


The panels shall be equipped with links and HRC cartridge fuses conforming
to IEC:269 or IS:13703 in 1100 Volt grade phenolic moulded fuse holder
consisting of fuse carrier and base or miniature circuit breakers confirming to
IEC:947-2 or IS:13947-2 at appropriate locations. The carriers and bases
shall be made of high grade flame retardant and non hygroscopic phenolic
moulded material with hard glass surface. Each fuse or MCB shall be
identified with engraved plastic label.

22.5 In general, fuses and MCBs shall be limited to the minimum required for
safety.
The protection scheme shall include fuses for VT secondary circuits and
DC supply to each panel and fuses for MCB for spring charging motor and
incoming AC supply.

23.0 Terminal blocks

23.1 Terminal blocks of brass studs rated for 10 amps continuous current, 1100
volt DC grade covered by moulded insulating materials with adequate
electrical clearances shall be provided for terminating the panel wiring and
outgoing connections. The termination shall be made by crimping lugs or

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 67 /72


bare conductor with insulating sleeves at ends. The arrangement can be
horizontal or vertical as per standard practice adopted by the
manufacturer. All terminals must be numbered and wire termination
provided with numbered ferrules for identification. All numbering and
marking including those in wiring diagram shall follow the guidelines provided
in IS:11353. All circuit breaker auxiliary contracts including spare contacts shall
be wired to the terminal blocks. 10% (Ten percent) spare terminals shall be
provided.

24.0 Colour and numbering

The wiring used for 230V AC supply for illumination lamp, panel heater and
other devices shall be coloured. The colour of wires connecting directly to
Earth shall be green. CT & PT connection wires shall be of R, Y & B colour.

24.1 Engraved core identification plastic ferrules marked to correspond with the
panel wiring diagram shall be fixed at both ends of each wire. Ferrules shall fit
tightly on the wire and shall not fall off when the fire is disconnected from the
terminal block. Number 6 and 9, if used shall be under scored to enable
differentiation.

25.0 Circuit diagram

26.1 A durable copy of the circuit wiring diagram shall be affixed to the
inner side of the door of the switchgear compartment. Labels shall be
provided inside the compartment to describe the functions of the
various items of equipment.

26.2 The scope of the supply shall include the panel mounting foundation bolts,
nuts and washers necessary for making the supporting.

26.0 OPERATING MECHANISM

26.1 General
26.1.1 The operating mechanism of the circuit breaker shall be motor wound
spring charged type. It shall be electrically and mechanically trip free with
anti pumping device (as per IEC:694 definition). All working parts in the
mechanism shall be of corrosion resistant material. Self lubricating, wearing
resistant bearings shall be provided in the mechanism.

26.1.2 The mechanism shall fully close the circuit breaker and sustain it in the
closed position against the forces of the rated making current and shall
fully open the circuit breaker without undue contact bounce at a speed
commensurate with that shown by tests to be necessary to achieve the
rated breaking capacity in accordance with IEC:56 or IS:13118. The
mechanism shall be capable of being locked in either the open or closed
position. The mechanism shall be capable of fully closing and opening

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 68 /72


again after the auto-reclose time interval specified as 0.3 second in this
specification.

26.2Spring mechanism (In case of Spring Charged VCB)

26.2.1 The spring operating mechanism shall be with spring charging motor,
opening and closing springs with limit switches and all accessories
necessary for automatic charging. In normal operation, recharging of the
operating springs shall commence immediately and automatically upon
completion of the closing operation so that a complete sequence of closing and
opening operation should be possible.

26.2.2It shall be possible to hand charge the operating spring with the circuit breaker
ineither the open or closed position conveniently from the ground level.
Closure whilst a spring charging operation is in progress shall be prevented
and release of the springs shall not be possible until they are fully charged.

26.2.3 The state of charge of the operating springs shall be indicated by a


mechanical device showing 'SPRING CHARGED' when closing spring is
fully charged and operation is permissible and 'SPRING FREE' when
closing spring is not fully charged and the operation is not possible.
Provision shall be made for remote electrical indication of 'Spring Charged'
and 'Spring Free' conditions.

26.2.4 The operating mechanism shall be such that the failure of any auxiliary
spring shall not cause tripping or closing the circuit breaker but shall
not prevent tripping against trip command.

26.2.5 Closing action of the circuit breaker shall charge the opening spring
ready for tripping. From the close position with spring charged, one
open-close-open operation shall be possible without recharging the spring.

26.3 Motor

The motor for spring charging shall be single phase 230 Volt A. C
motor. Continuous motor rating shall be at least ten percent above the
maximum load demand of the driven equipment. It shall remain within its
rated capacity at all operating points that will arise in service. It shall be
protected by MCB. The motor shall comply with IEC:34 or IS:996.

26.4 AUXILIARY POWER SUPPLY

26.4.1The operating mechanism shall be suitable to operate with the following


auxiliary power supplies.

a) 230V,50Hz Single phase- For spring charging motor AC

b) DC supply 48 Volts- For close and open coils.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 69 /72


26.5 The DC supply shall be from Battery Bank

26.6 The mechanism shall be designed to operate satisfactorily despite fluctuations of


auxiliary power supplies as under:

AC supply: Voltage From 85% to 115% of normal voltage


Frequency variation From-5% to +3% in variation

DC supply: Voltage for voltage variation of Tripping : 70% - 110%


Voltage variation of Closing : 85% - 110%

26.7 Temperature Rise test:

The temperature rise and the maximum temperature of any part of the
circuit breaker under continuous load condition and exposed in the direct
rays of the sun shall not exceed the permissible limits as provided in
Table V of IEC publication 694 or table 4 of IS:12729. These limits shall not
be exceeded when corrected for the difference between the ambient
temperature at site and the ambient temperature specified in the standard.
The correction proposed shall be stated in the tender.

27.0 TESTS

27.1Type test and Routine test


The circuit breakers shall be subjected to routine and type tests in
accordance with the standards listed in this specification including the
following IEC and IS standards with the latest amendments:
Circu it b re a ke r IEC:62271 - 100 & 200and relevant other standards
Porcelain insulator IEC:233 and IS:5621 and relevant other
standards

The tests shall include but not limited to the following:


27.2 Short circuit tests
The circuit breaker shall satisfactorily perform the out of phase and short
circuit d u t ie s spe cif ied in IEC: 6 2 2 7 1 - 1 0 0 & 200,
I EC:17 A(Sect. )4 38 and IEC:17A/CD/474 and IS:13516.
The circuit breaker shall be capable of performing at least twenty five (25)
open operations at the rated short circuit current before maintenance or
inspection is required.

27.3 Dielectric tests


At zero gauge loss of vacuum inside the interrupter chamber, the open
contacts shall withstand continuously, the rated phase to ground voltage
and it shall be possible to break normal current in these conditions. During
the dielectric type tests, no flashover external or internal shall be
acceptable.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 70 /72


The circuit breakers shall be subjected to a power frequency AC voltage
test for one minute in dry and wet conditions and there shall be no external
flash over to earth.

27.4 Mechanical endurance

In addition to the requirements of IEC:56, an extended mechanical


endurance test is required to show that the circuit breaker is capable of at
least 10,000 operations at no load in accordance with
IEC:17A/474/CD or as per latest amended IEC. Between the specified
test series in IEC:17A/474/CD, some maintenance such as lubrication and
mechanical adjustment is allowed and shall be performed in accordance
with manufacturer's instructions. Change of contracts is not permitted.

27.5 Duty requirement tests

Apart from auto-reclosing and the other duties mentioned above, the
breakers shall be able to perform the following duties for which type
tests are to be conducted as per IEC:56 or IS:13118.
1. Breaking the steady and the transient magnetising current of the
transformer.
2. Breaking 25% of rated fault current at twice the rated voltage as per
IEC/IS.
3. Cable charging breaking current.
4. Single capacitor bank breaking current.
5. Capacitor bank in rush making current.

Test for the resistance of the main circuit shall also be conducted.

27.6 Temperature rise test

Temperature rise test is to be conducted on the circuit breaker and the


accessories in accordance with IEC:62271-100 & 200 or latest amended
IEC. The temperature rise shall be limited as per this specification.

28.0 PERFORMANCE REQUIREMENTS


The supplier shall declare the circuit breaker opening and closing times at 120
percent, 100 percent and 70 per cent of the rated voltage of the opening and
closing devices when measured at the terminals of the trip and closing coils.
The minimum make break time at rated voltage and total break time of the CB
shall be stated. The total break time must not exceed 60ms.

29.0 EARTHING
29.1 All metal parts not intended for carrying current or not alive shall be
connected to duplicate earthing system and suitable electroplated brass earthing
terminals shall be provided on each circuit breaker in conformity with

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 71 /72


IEC:62271-100 &200. Suitable identification mark for the earth terminals
shall be provided adjacent to the terminal.
29.2The size of the earth continuity conductor shall be large enough to reduce the
potential rise of the metal frame of the breaker in the even of fault to minimum
but in any case not more than 10V. The size of the conductor shall also be
adequate to restrict the temperature rise without causing any damage to the
earth connection in the case of fault. No riveted joints in the earth conducting
path shall be permissible and only bolted joints of adequate size shall be
provided with nuts, bolts and plain spring washers. The surfaces to be jointed
shall be perfectly flat without any unevenness to ensure that there is no contact
resistance.
29.3An earth busbar of copper strip shall be provided inside the local control cabinet
to which all earthing connections must be made. The earth busbar shall be
terminated into two electroplated brass earthing terminals of adequate size with
nuts, bolts and washers for connecting to earth continuity conductor mentioned
above.

30.0 QUALIFYING REQUIREMENT.

The equipment offered shall be procured from short listed Vendor at E-23 and
shall have been successfully Type Tested during last five years on the date of bid
opening. The front page of the Type Test report showing the evidences of the tests,
duly signed by the bidder shall be uploaded alongwith the bid.

The following Type tests of VCB should have been done:


1) Short Time withstand current
2) Temperature Rise
3) Lightning Impluse Test
4) Internal Arc Test
5) Make & Break Test duties
6) Power frequency voltage test
7) Partial discharge test,
8) Resistance measurement test
9) Tightness test
10 )Closing characteristic test
11) Opening Characteristic tests

The VCB shall be ofM2, C2 & E2 duty class.

VOL-II(TS) E4- SWITCHGEAR AIS & GIS PAGE 72 /72

Você também pode gostar