INSTALLATION INSTRUCTIONS RCWS


FOAMSEALR
(OC 23514-D)

1. Smooth top surface of foundation wall to have minimal variation.


2. Unroll FoamSealR sill plate gasket on top surface of foundation wall or fasten to bottom of sill plate on tilt-up
wall sections with ridged side toward roughest surface.
3. Overlap all end and perpendicular joints.
4. Pierce FoamSealR sill plate gasket at anchor bolt locations.
5. Set and anchor sill plate to foundation wall.

FOAMULAR

(ESR-1061)

1. FOAMULAR insulation boards measuring 2 ft by 8 ft (3 /5 m by 2 2 /5 m) or 4 ft by 8 ft (1 1/5 m by 2 2 /5 m)


should be installed horizontally or vertically with long joints and end joints in contact with one another.
2. When installed directly on framing members, the insulation boards measuring 2 ft by 8 ft (0.6 m by 2.4 m)
must be installed horizontally and framing members are spaced a maximum of 16-inches on center.
a. For wood framing, the insulation boards are attached using 3 /8 -inch-diameter-head (9 mm)
galvanized nails, 1-inch-crown (25 2 /5 mm) galvanized staples, 6d ring-shank nails with 1-inch
(25 2 /5 mm) plastic washers or equivalent fasteners long enough to penetrate framing a minimum
of 3 /4-inch (19 mm), or through the sheathing, whichever is less.

b. For steel framing, the insulation boards are attached using No. 6, Type S drywall screws, with 1-inch
(25 2 /5 mm) plastic washers, long enough to penetrate the framing a minimum of -inch (19 mm).
3. Fasteners must not be over-driven. Fasteners must be spaced a minimum of 12-inches on center around the
perimeter and 16-inches on center in the field.

JOINTSEALR

(OC 10015678-C)

1. Remove release liner backing material and center the adhesive tape over the joint to be sealed.
2. Continue to remove the liner and press the tape firmly in place over the joint. Lap intersections or joined tapes
a minimum of 3 -inches.
3. Using a J-Roller or laminate roller, roll the tape firmly in place to ensure intimate contact between tape and
substrate and to eliminate trapping air between the tape and substrate.
4. To obtain best adhesion, JointSealR Foam Joint Tape should be installed when outdoor temperatures are