The document outlines a project plan for constructing a bridge with 8 milestones: 1) Concept Phase, 2) Project Proposal, 3) Site Investigation, 4) Foundation, 5) Bridge Construction, 6) Road Construction, 7) Finalization, and 8) Handover. It details 36 tasks with start and end nodes, estimated durations, earliest and latest start and finish times, and total float. The critical path runs through tasks A to AF.
The document outlines a project plan for constructing a bridge with 8 milestones: 1) Concept Phase, 2) Project Proposal, 3) Site Investigation, 4) Foundation, 5) Bridge Construction, 6) Road Construction, 7) Finalization, and 8) Handover. It details 36 tasks with start and end nodes, estimated durations, earliest and latest start and finish times, and total float. The critical path runs through tasks A to AF.
The document outlines a project plan for constructing a bridge with 8 milestones: 1) Concept Phase, 2) Project Proposal, 3) Site Investigation, 4) Foundation, 5) Bridge Construction, 6) Road Construction, 7) Finalization, and 8) Handover. It details 36 tasks with start and end nodes, estimated durations, earliest and latest start and finish times, and total float. The critical path runs through tasks A to AF.
Node Node (day) Float Path Milestone 1 Concept Phase A Find several suitable location for bridge 1 2 2 0 0 2 2 0 C B Determine the client scope and requirement 2 3 14 2 2 16 16 0 C C Community Engagement (Public Consultation) 3 4 7 16 16 23 23 0 C D Produce Project Proposal 4 6 7 23 23 30 30 0 C E Develop option analysis and recommendation 4 5 7 23 23 30 30 0 C F Finalization of conceptual design 6 7 14 30 30 44 44 0 C Milestone 2 Project Proposal G Propose the conceptual design to stakeholders 7 8 14 44 44 58 58 0 C H Seek for permits and approval required 8 10 30 58 58 88 88 0 C I Tender invitation for contractor 8 9 14 58 74 72 88 16 NC J Review of tender design and time frame 10 11 14 88 88 102 102 0 C Milestone 3 Site Investigation K Site Hoarding and Logistic work 11 12 30 102 102 132 132 0 C L Levelling survey 12 13 30 132 162 162 192 30 NC M Geotechnical Investigation and Analysis 12 14 60 132 132 192 192 0 C N Environmental management and Risk Analysis 12 15 30 132 162 162 192 30 NC Milestone 4 Foundation O Landscaping (cut and fill) 14 16 30 192 192 222 222 0 C P Setting out by surveyor 16 18 180 222 222 402 402 0 C Q Setup Cofferdam (casing underwater) 16 17 30 222 222 252 252 0 C R Foundation for abutment & pier 17 18 150 252 252 402 402 0 C Milestone 5 Bridge Construction S Setting out by surveyor 18 20 270 402 402 672 672 0 C T Construction of tower 18 19 60 402 402 462 462 0 C U Stay cable and deck construction 19 20 210 462 462 672 672 0 C Milestone 6 Road Construction V Landscaping 20 21 30 672 672 702 702 0 C W Setting out by surveyor 21 24 180 702 702 882 882 0 C X Foundation for elevated road 21 22 30 702 702 732 732 0 C Y Column, column cap and concrete girder construction 22 23 90 732 732 822 822 0 C Z Precast slab + road construction 23 24 60 822 822 882 882 0 C Milestone 7 Finalization AA Lighting, electrical installation and drainage system 24 25 20 882 892 902 912 10 NC AB Steel protection coat and painting 24 27 30 882 882 912 912 0 C AC Traffic signs & Road marking 24 26 7 882 905 889 912 23 NC Milestone 8 Handover AD Safety inspection & System check 27 28 14 912 912 926 926 0 C AE Construction site cleaning 28 29 7 926 926 933 933 0 C AF Handover to stakeholders 29 30 7 933 933 940 940 0 C