ANALISA DAN HARGA SATUAN PEKERJAAN

A.4.1.1.17. 1 M2 Pasang Plastik Cor


Harga Satuan
No. URAIAN KODE Satuan Koefesian
( Rp. )
1 2 3 4 5 6
A Tenaga
1 Pekerja L.01 OH 0.013 100,000.00
2 Tukang Besi L.02 OH 0.004 110,000.00
4 Mandor L.04 OH 0.004 120,000.00
Jumlah Tenaga Kerja
B Bahan
1 Plastik Cor m2 1.100 10,500.00
Jumlah Harga Bahan
C Peralatan
Jumlah Harga Peralatan
D Jumlah Harga Tenaga, Bahan dan Perlatan ( A + B + C )
E Overhead + Profit ( Contoh 15% ) 15% x D
F Harga Satuan Pekerjaan ( D + E )
ANALISA DAN HARGA SATUAN PEKERJAAN

JUMLAH
( Rp. )
7

1,283.33
398.28
474.19
2,155.80

11,550.00
11,550.00

-
13,705.80
2,055.87
15,761.67