Escolar Documentos
Profissional Documentos
Cultura Documentos
SURVEYING
International College of Business and Technology
TRAINING REPORT
Basic Industrial Training Report
At
Admission No : GL/HNDQS/02/16
Acknowledgement
During my industrial training period I gathered lot of experience and good knowledge
I must thank to all the lecturers and the staff of ICBT campus and facilitating me to
have a good training period. The theoretical knowledge that I have gathered equipped
training within 6 months period and facilitating me to obtain maximum benefits and
Further I must thank to all the staff of Trio Ruhuna site including Mr.Herath; Project
and all the trainees for assisting me do my best within this training period.
Also I must thank my parents and all my friends for helping me through any means to
2
Table of content
Acknowledgement2
Table of content..3-5
List of figures.6-8
List of tables...9
4.02 Formwork..19-28
3
4.03 Reinforcement29-31
4.03.1 Covering
4.03.2 Stools
4.04 Concrete32-39
4.04.6 Admixtures
4.05.1 Lintels
4.05.2 Stiffners
4.06 Plastering44
4
4.09 Handling documentations.50-51
5.2 Variations
Conclusion....63
Appendices64-66
Remarks....67
5
List of Figures
Figure 1.1 Construction Project...8
6
Figure 4.04.1 Concrete mixer33
7
Figure 4.10.4 Wacker........53
8
List of Tables
9
1.0 Profile of the project
10
10. Estimated cost : LKR 235,834,699 (Excluding VAT)
11
2.0 Description of the project
Ruhuna University is one of the most beautiful constructions in Sri Lanka. It is one of
the most famous designs by the well known architect Geoffrey Bawa. He is the Sri
Lankas most influential architect who linked our architecture with the modern world.
His creations are well designed accordance with the cultural heritage.
When considering about the Bawass architecture, he concerns about the tropical sun,
ocean breeze, lush greenery and flowing water. Ruhuna University with all these
sceneries. There is the saying: In a rainy day, it is capable to travel from one end of
12
Figure 2.1.2 Sky image of the Ruhuna University
The location of the project was such a marvelous place. It was needed to construct
the management and the finance faculty. As it is a main section in the Ruhuna
University the project needed to give a full consideration regarding its architecture
and construction works to keep the existing standard. That was the main challenge
When considering about the site location. It is inside the university premises and it
covers a big land area. From one side it has a sea view as it is very much closer to the
A2 main street. From another side there is a view of greenery with lot of trees. On
other sides there are lots of university buildings. There is a good access to the site as
the it is closer to the main street. There is a fare climate for the Southern area of the
13
Figure 2.1.3 The satellite image of the site area
manage in human resources. There should be a perfect hierarchy and the duties and
responsibilities must be equally divided among them. But to reach the success each
and everyone from to top bottom should work for by sharing their responsibilities. In
this project too, the human resource had been properly manage and there was no
14
Figure 2.2.1 Organization chart
15
2.3 Overall scope of the project
The contractor of this project is the Trio Constructions (Pvt) Ltd. It is a ICTAD M1
This report is prepared by the experience and the knowledge that have gathered from
the training period. The train establishment, Trio Constructions (Pvt) Ltd helped to
16
2.0 Knowledge and the experience gained from the training
Diploma in Quantity Surveying. This Industrial training report has been prepared
during the training which has been gained under the Trio Constructions (Pvt) Ltd. The
training was a very good opportunity as, the construction field is a practical field.
Though there are lot of academic knowledge they could be easily understand by this
training.
During this six months period of time, Lot of experience could be collected regarding
knowledge in particular parts which could be covered and those sections are described
in the following.
Setting out
Formwork
Reinforcement
Concrete
Brickwork
Plastering
Quality controlling
Handling documentations
17
4.01 Setting out
The basic instruments that use for setting out are steel tape, Theodalite and the
engineering level. There are important aspects to be considered when doing setting
out.
Steel tape should be aligned and parallel to the line along which measuring
require.
Steel tape
Figure 4.01.1 - Theodalite
Theodalite
Engineering level
18
4.01.2 Setting out for columns
Firstly, the setting out should be done for lining grids of the building. Then the pecks
are erected for all the grids. First threads are fixing to the pecks and the centre of the
column is taking as the intersection point of threads. Then level line is drawing by
plotting two points on either side using plumb bob. Then the distances are measured
and four lines are drawing. This method is used for all column shaft, kicker and
1000mm level setting out is very important for slab works. Normally it is 1m up from
the existing floor level. First the level machine should be fix and level properly. Then
the temporary bench mark reading must be taken first. After that the level of columns
are determining by the drawings and 1000mm should be added for that. Further the
TBM reading must be added for them. Then those levels are marking in every
column.
Two points are marking in each column in order to draw a line. Then that line is
drawing around the column by using the speed level. Drawing 1000mm level line is
very useful when taking measurements for the slabs. Especially when adjusting beam
bottoms.
19
4.02 Formwork
important part.
It should rigidly constructed and efficiently propped and braced vertically and
The joints of the formwork should be tight as not to leak any concrete from
them.
reusable.
The formwork should be set accurately to the lines and levels and it should be
a plane surface.
concrete.
20
For slabs, beams, column sides and beam 25mm to 40mm thick
bottoms
Timber formwork
The timber formwork used for any application should be well seasoned and it should
be light in weight. Formwork should be easily workable with nails without cracking.
It should be free from loose knots. Timber which is exposing to concrete work should
posses smooth and even surface on all faces. The normal sizes for the timber
Plywood formwork
Resin bonded plywood sheets are attached to timber frames in required sizes. There is
a no cost for surface finishing as it is possible to have smooth finish. Also plywood
formwork can be use of larger panels so that it reduces the labour cost for fixing and
dismantling. This is profitable as plywood formwork can be reusable than the timber
formwork.
21
Steel formwork
This type of formwork is consisting of steel plates which consist of fabricated panels
stiffened along edges by steel angles. These can be held together by using suitable
clamps, bolts and nuts. These steel formworks are largely used for large projects and
where large number of reuses can be uses. Further this can be considered as most
When compare with timber formwork steel are stronger and can be highly reusable.
Also these can be shuttered and de-shuttered easily and speedily. The quality of the
surface which is exposed to the concrete surface is very high. So no more treatments
are needed for steel formwork. Also it is advantageous as steel formwork does not
absorb the moisture from the concrete and does not shrinkage.
There are several situations where formwork is used. They are as follows.
22
4.02.1 Column formwork
All types of formwork can be used for column formwork. To keep these columns
steadily, 50mm diameter GI pipes, T jacks, Form ties and tighten brackets can be
used. Further thread bars, 2*2 timber bars are normally used for this purpose. Firstly
the formwork panels are made accordance with the given dimensions. Then it is fixed
to the kicker which is about 100mm height. The height of the kicker can be also
varied.
Column formwork
23
300
2X2
Pipe timber
700
support Plumb bob
700
bob
GI pipes
700
Column formwork
300
188
There are three sides in a beam formwork. Beam bottom formwork is thicker than the
other side boards. It is because the bottom formwork carried concrete and the
reinforcement weight of the beam. In the training site there were beams wide 225mm
and 300mm. The depth of the beams changed as 300mm, 500mm and 550mm. Beam
24
formwork lengths are equal to the length between the columns. Further slab thickness
Additionally 50mm 2*2 timbers must be fixed for the bottom boards in order to give
the rigidity. Before placing the boards 1000mm level must be checked and kicker
must be placed. Then the beam boards must be fixing with relevant to the kicker
formwork in the column. Then only all the beam formworks are in same level. Beam
bottoms should be adjusted in 600mm intervals with adjustable props. After adjusting
the bottoms the side boards are fix to that using nails. The depth of the side board
must be
Depth of side board = Beam depth Slab thickness Thickness of ply wood of slab.
The side boards must be drilled in 600mm intervals and in order to lock the beam.
25
4.02.3 Slab formwork
In slab formwork 3*4 are placed in along the shorter span. 2 diameter GI pipes are
laid and fix by nails on 2*4 timber joists along the longer span at 300mm intervals.
Then the plywood sheets are laid on these for the slab.
It is very important to consider about the wastage when laying plywood sheets. The
slab formwork is done on the side boards of the beam as the weight of the slab is
distributed to the beams. 2*2 timber pieces are used to connect those plywood sheets
each other. For further safety masking taps are sticks along the joint of two plywood
sheets.
26
4.02.4 Staircase formwork
Stair case formwork is so much similar to slab formwork. The bottom level of the
staircase is marked and a chord is drawn along that inclined line. Joist on adjustable
props are places in 750mm intervals, 50mm below the chord. Then the GI pipes are
laid across those joists in 300mm intervals. Two side boards are fix to the bottom
board and then a chord which is parallel to bottom board is drawn with keeping waist
thickness in side boards. Rise and thread is drawn by using the spirit level and the
tape. Then stop boards are placed between side boards along the marked lines.
27
4.02.5 Retaining wall formwork
Ordinary plywood boards are used for retaining wall formwork. As the height of
retaining wall in the site is high, several steps of formwork have made for concreting.
Normally the height of a one step is 1.2m to 1.1m. Form oil, Form ties, Pre cones, GI
pipes, T and U jacks, scaffoldings are also necessary for the formwork procedure.
Removing of formwork
After laying the concrete, the formwork is de-shuttered when concrete is hardened.
Special consideration must be done when removing them as the formwork can be
reusable.
After the de-shuttered formwork, the nails and other attachments must be removed
from the boards. Further the concrete or mortar should be also cleaned and prepare
them for re using. Then the formwork should be horizontally stored and covered. This
28
4.03 Reinforcement
In generally there are two types of reinforcement. They are mild steel and yield steel.
Reinforcement bars are one of the most widely using materials in the site. So it is
approved. There is a special way to demonstrate the bar details in a drawing and that
16 Y 12 5 150 B
No. Of bars
Bar mark
Bar spacing
Bar location
4.03.1 Covering
This is very important because the reinforcement get corrosive if covering is not done.
The reinforcement reacts with the air. Covering is depending on the condition where
concrete is laying and its environmental condition. To get the covering space, the
cover blocks are used. They are also made from concrete. The normal sizes for the
29
Beam bottom, Side and top : 25mm
4.03.2 Stools
Stools are used to separate top reinforcement mesh and the bottom reinforcement
mesh. T/10 bars are used to bind stools and the strength must be enough to bear the
If the full length exceeds the normal length of a bar, laps are provided. Normally the
d2 d1
Lap length = 50 x d2
In columns there are main bars which lie to the top of the floor height. There are laps
as it is not practicable to bind straightly without lapping. The stirrups in the columns
A length of stirrup is normally similar to the perimeter of the column. But the
covering space should be deducted and the 20 x diameter is added for binding.
30
Further in 400 x 400 columns more two stirrups are bind in the middle of the column
to give more rigidity. The stirrups tightened the column and keep it vertically.
When binding reinforcement in beams an extra consideration must be given as the top
net and the bottom net is connecting to the beam. According to drawings L shaped
bars and plain bars are use for beams in this site. The main beams should be laid first
In this site all the slabs used T/10 bars for the top net and bottom net of the slab
reinforcement. Mainly there are tension and compression bars starting from beams.
The top bars overcome the hogging moment. When there is a slope between slab
levels in toilet areas and balconies the bend of the reinforcement is done at beams.
31
4.04 Concrete
Concrete is a remarkable material that can be cast in to almost any shape. It will
There are various grades in concrete which are specified for particular constructions.
According to the grade of the concrete, characteristic strength, aggregates size and
cement content is set out. Generally the grade of the concrete is the strength in
N/mm2 after 28 days of curing. The mix proportions are varies according to the grade
of the concrete.
30 1: 1: 2
25 1: 1 : 3
20 1: 2: 4
10 1: 3: 6
32
4.04.2 Mixing concrete
Concrete mixing is the blending of materials which are required for the production of
equipments for this purpose. Concrete is made by mixing the aggregates, Portland
There are three types as drum mixer, pan mixer and continuous mixer. Also concrete
Ready mix concrete is already mixed concrete and delivered to the site by ready mix
trucks with the quantity that client required. Concrete is batched in a batching plant
under computerized controlling mechanism. The quality of ready mix is very high as
well a greater quantity could be prepared. It saves the time, reduces the labour hiring
costs and it lessen the material wastage. The disadvantage of ready mix is the
33
problems effect while transportation. Also there is a no proper way to check the
concrete all the necessary materials should be transported to the mixing place. The
needed.
Transporting is the ringing of mixed concrete to the location or the site. It may take
few hours or few minutes. It is very important to transport concrete before the setting
time of the concrete. While transporting Delay, Segregation, Slump loss, Wastage
must be avoided.
34
There are several methods of transporting concrete such as dumper, crane, buckets,
Placing of concrete is also a very good step in the concreting procedure. It is very
4.04.6 Admixtures
Supercrete
reduction with retarding effect for hot whether constructions. This can produce
Adcrete
This is liquid water which reducing the set retarding admixture for concrete. It contain
reducing the water and controlling setting time. The advantages of adcrete are as
follows.
35
Improve workability
Reduce segregation
Increase strength
Reduce cracking
Curing is maintained proper concrete moisture content and temperature long enough
Keeping formwork
Submerge in water
36
Better
durable
concrete
Lessen the
chance of Achieving
concrete high strength
scalling
Proper
Lessen the Curing Avoid
surface surface
dusting cracking
Having good
Improve
surface
water
wearing
tightness
resistance
Defects of the concrete are highly effect for the concrete structure. It may cause minor
and major damages to the strength, durability and serviceability of the structure. Few
concrete surface due to the usage of different brand of cement change in mix
37
Dusting: White powders come on concrete surface due to finishing during
rain, not curing well, use of low grade concrete etc. This can be repaired by
Cracking: cracks are due to various reasons and that will effect on durability,
Honeycombing:
some spots and these are effect to strength and durability. This may due to
formwork etc. This can be prevented by compacting well, using good water
Blistering: These are hollow; low profile bumps on concrete surface filled
with either air or bleed water. This is occurring in thick slabs or on hot or
windy days. This can be repaired by grind off the weakened layer to an even
finish.
38
4.05 Brick work
It is important to consider about the size of the bricks. The standard size of a brick is
as follows.
The cement sand ratio used for the mortar in masonry is 1:5. Other than those factors
arrangement of bricks in a pattern to take the strength and to distribute the load. There
are different types of bonds. Though there are four types of main bonds, this
Stretcher bond
39
Header bond
When considering about the brickworks, there are some important other items too.
They are
Lintels
Stiffners
Sill beams
4.05.1 Lintels
Lintels are small concrete works done above the openings. Lintels are made in order
to avoid the load passing to the door or window frame. In this site normally the lintel
height is 150mm. the lintel lays along the opening and extra 300mm are kept in both
either sides. But the height of the lintel increases to 225mm when there is a canopy
There are 225mm and 112.5mm width lintels. 112.5mm lintels are most often laid
when there is a high brick work. It is not possible to build the brickwork up without a
40
support in the middle. So a lintel is also laid in such cases too. The lintel is laid
Four T/12 reinforcement bars are laid in 225mm wide lintels while two T/12
reinforcement bars are laid in 112.5mm lintels. Stirrups for them are laying from R/6
reinforcement bars. The lintels are also concrete by using grade 25 concrete.
4.05.2 Stiffners
Stiffners are also small concrete structures which are constructed in the joining places
of brick walls (Brick wall edges). Normally a stiffner is 225mm x 112.5mm. The
Stiffners are placed in the corners of the brick walls in order to give a proper bondage
and strength to those walls. 2 bars of T/12 reinforcement are laying for this stiffners
and R/6 S shaped stirrups are binding. They are also concrete by grade 25 concrete.
41
Figure 4.05.5 Stiffners
Sill beams are also so much similar to the lintels. But they are small concrete works
done under window. Sill beam lies under the window frame. Sill beam not only lies
along the opening, but also it extends to 300mm on either sides of the opening.
The normal height of a sill beam in this construction is 225mm and the width is also
225mm. the length depends on the length of the window. For this 4 T/12 bars must be
bind and R/6 stirrups must be bind. But in some case the sill spread along the wall
where the rest of the sill is concrete to only 100mm height. There only 2 bars are used
as reinforcement.
42
4.06 Plastering
After finishing the brickwork plastering of walls are starting. The mortar which is
taken for plastering is to the cement sand 1:5 ratio. Laying of plastering in this site
was done as normal by using trowel, wooden batten, delivering float, water etc.
The most significant thing is laying of a mesh which is generally called as chicken
mesh for the wall before plastering. That mesh is an aluminum mesh. The reason for
that is to equalize the expansion co-efficient This is specially laying at the ends of
walls which there is brickwork connecting to the concrete. As the expansion co-
efficient of bricks and concrete is different, when the heat comes there are trying to
expand different quantities. Then the plaster could not bear and it will crack soon. In
order to get rid of those the chicken mesh is laid. Then aluminum is getting expand
and it is same at every location. So there are problems for the plastering.
43
4.07 Health and Safety and security
H&S has become the one of the most important parts in a construction project. To
ensure that the construction work is under taken in as safe manner there should be a
During this training, it was easy to identify the places where the accidents could be
Demolition works
There were many safety measures that have been taken in the site, construction of
Safety clothes All the employees were provided with safety helmets, safety
Safety nets The entire building area was protected by safety nets.
Safety PolicyThe project deals with a H&S policy. Each and everyone who
policy.
44
Safety boards Safety boards were hanging at every side of site. There were
scaffolding etc.
Risk assessment The H&S representative finds out about all hazards and
risks that could happen and record those in suitable formats and take control
measures.
First aid box A well maintained first aid box was keeping in the site and
Reduce the pollution Working area is a urban area very much closer to the
town. Further it should be clean as it is a university and the surrounding is
very clean. So the construction itself had a good garbage disposal system,
There was a safety officer and a security officer in order to maintain the safety and
45
4.08 Quality controlling
Trio constructions (Pvt) Ltd is highly concerning about the quality of the
We at Trio Constructions (Pvt) Ltd always strive to meet the highest quality levels in
managing our human capacity and other resources. We also take every possible step
to continually improve our systems, standards and delight our most esteemed
Following are the tests which are use in the site to maintain the proper quality.
46
Casting
There are 150mm test cube moulds which the concrete is filled in three layers.
Approximately 50mm deep layers must be filled and each must be compacted either
by manually or by vibration. After compacting, the third layer the surface must be
When compacting manually, the standard rod weighing 1.8kg, 380mm long and
having ramming face 25mm2 is used. When making strokes it should distributed in
uniform manner over the mould. Normally each layer is subjected to 35 blows and it
Curing
After making them they should be kept in a damp atmosphere at temperature about 20
C for next 24 hours. Later the moulds are removed and the test cubes are taking off
and merged in water tank as soon as possible until they are taking out just before the
testing. When they are transporting to the laboratory they must be covered with wet
sacks.
Testing
The test cubes are tested in a machine approved by the engineers. That clean the test
cube and load is spared to two opposite sides of test cubes other than top and bottom
15MN/m2 per minute until the maximum load applied as crushing load.
47
Grade Minimum cement Min 28 days compressive strength N/mm2
Content in concrete Minimum target Characteristic
Kg/m3 Strength strength
Slump
This is also a simple test for controlling workability. A standard slump cones top
diameter is 100mm, bottom diameter is 200mm and the height is 300mm. the tamping
rod I 16mm diameter and 600mm long. Also 450mm2 waterproof base plate is using
The slump cone is filled with three layers and each layer is tamped with 25 strokes by
tamping rod. The top layer must be leveled. When it is completely filled, the slump
cone is removed and it is vertically raising. The height difference of the concrete and
48
4.09 Handling documentations
There are different types of documents in a site office. The basic documents at the site
Bills of Quantities
Other than the above documents there are daily maintaining records in the site office.
They are;
Weather records
Further there are number of files that are maintained at site office in order to have
Minutes of meetings
49
Other than site documents there are several valuable documents maintained in the site
Gate Pass
Material book
Stores requisition
All the documents are highly valuable and it is important to maintain them properly in
order to do the works easily. The copies of some above documents are attached in the
list of appendices.
50
4.10 Tools and machinery
Tools and machinery also plays an important role in a construction project. They
make the works more effective and easier. Those help in saving time, labour cost. As
well machinery reduces the wastage too. However with the development of the
technology, construction field is also renewing due to these tools and machinery.
Excavator
This is heavy construction equipment consisting with boom, stick, bucket and a
rotating platform known as the house. This accomplishes the movements by winches
and steel ropes. In this site basically and regularly excavator helps for loading sand,
aggregates for the tractor or the baby dumper to carry to the sites.
Tractor
Tractor makes all the transportations. This can carry some large amount than the
dumper. Specially in this site tractor helps for transporting cement, sand aggregates
51
and most vitally to transport the machinery to the site. Concrete mixtures could also
Dumper
A dumper is a vehicle designed for carrying bulk material, often on building sites. In
this site sand, aggregates and cement is transport to by dumper. It is useful as it take a
small space. So it can go through the site easily than other big vehicles.
Wacker
Wackers are small compactors which produce an impact force at very high rate (450 -
800 blows per minute) due to the impact force they are good for compaction. These
are used for the compaction of small areas where access is difficult and for the
compaction of backfill in trenches. Wacker consists of two main parts, the upper part
includes the engine and lower part includes the base plate with a vibrating mechanism
52
Poker vibrator
Poker vibrator is a device, which is used to vibrate and compact concrete to obtain a
well-compacted cast. poker vibrators were used in the site and both were powered
by kerosene oil.
Water pump
The water pumps are usually needed for bridge sites for de-watering purposes. Those
The bar cutting machine was used to cut bars. It is also powered by 3-phase
electricity.
Power Saw
The power saw was used by the carpenters to saw timber for formworks. This is also
electrically powered.
53
Figure 4.10.7 Bar cutting machine
Tile cutter
As this project was very big, several sections of work is divided for several sub
contractors. The sub contractors are taking money for their work done monthly. In
every month they must be paid. For that a detailed bill demonstrating all the work that
has done must be prepared and hand over to the site engineer. That is the duty of the
quantity surveyor. From this it develop several things such as knowledge of taking
items.
54
Item Unit Dimensions should be taken
Columns m Height
Lintel m Length
After preparing the sub contractor bills their quantity surveyors are comparing the bill
with their own bill. Sometimes if there are any variations joint measurements has to
55
4.12 Direct labour billing
Other than giving sub contracts for the sub contractors, the company itself employing
for some workers. They are paid for a per day rate for every 15 days. Every day those
direct labours obtain a target from the technical officers. Then they cover that from
their maximum. If the worker has to work over time, the company pays for that too.
So in every 15 days it is needed to prepare a bill for direct workers. That task also has
to fulfill by the quantity surveyors. After that a complete report of every worker with
their work done should be submitted to the head office for valuation and check
whether about the covering of labour wages by the work done. Normally they are
56
5.0 Observations made
Throughout my training period several observations could be done. Among them the
In the beginning of my training there was a big delay in this construction project. The
identification of delay events is one of the more difficult, time consuming and yet
important aspects of delay analysis. Delay to planned work scope can occur in only
three forms:
1. Delay to commencement
2. Extended duration
3. Suspension during performance
investigated which can number in the hundreds. Common causes for delays are:
57
5.2 Variations
Alterations to quantities.
Alterations to quality.
There were some variations in this project too. The timber for the whole building was
to be from Class I timber. Then there was a variation to use jack timber instead of
class I timber. Variation gives rise to an addition or deductions from the contract sum.
When valuing the variations it should not only the direct expenses. All the expenses
that result because of variation must be added. In this project the variation quotation is
Variations can cost lot of time, money of a contract. Other than unavoidable
uncertainties.
58
6.0 Problems encountered and solutions found
In any construction, there are so many problems happen. Those are arising when the
construction project is going. Some problems are predictable and some are not.
During my training period there were so many problems that the project has to
As there was an adverse weather during two months the progress of the project was
very slow. Every excavation has filled with mud and sometimes water. So more
labour cost and doubling of time for such activities have resulted by that.
Lack of machinery In the company there were only limited machines, vehicles and
tools. So sometimes two contractors may need the concrete mixture and poker at same
time. But when there are no two mixtures at the site the concreting is delaying. Those
59
Lack of skill labour Skill labours are needed for barbending, masonry and
carpentry works. But there were lot of unskilled labours. So working with them was
completely difficult task and it wastes the time. The technical officers faced lot of
Sub contractor delays Though the works are divided among sub contractors whole
contract and its responsibility is under the company. There were so many delays
which occurred by the sub contractors. Then the project organization has to forced
them for delay otherwise the total project would face for liquidated damages.
Changes in drawings Lot of drawings were changed after the first set of drawings.
Lack of tools and equipments in the stores Sometimes there is a scarcity in the
tools and equipments. The stores must be rich with all necessary tools and
situations. There was a big mechanical problem in the hired JCB and because of that
the workers could not work that day. Further concrete mixture and pokers are the
same. There was only limited number of those. One day all concrete works has to be
stopped due to problems in pokers. The consultants did not allow to continue
60
6.2 Solutions found
During this training period, lot of solutions too found for the above problems. They
Always the rain water should be de watered and cleaned as soon as possible
problems and try to get all required machinery for construction activities.
The sub contractors should aware to employ skilled labour for tasks and to
Sub contractors should given targets for fixed dates to finish several tasks and
There should be a direct contact between the drafting section to solve the
There should be a skilled mechanic to repair and maintain all the machinery,
tools and equipments of the stores. Always he should be stay in the site and
61
Conclusion
Civil Engineering construction works are not only an academic subject. Academic
subjects like text books, tutorials, and notes can only provide the necessary theoretical
important factor. Through his it was able to identify the ways of industry developing
talent and attitude and what are the responsibilities that should be recognize as a
As a student of trainee quantity surveyor, the wish was attached to the TRIO
industrial Training. It was able to gain a wide knowledge and great experience about
construction work from sites. There was excavation, foundation, structural, masonry,
concreting, leveling, reinforcement, and finishing works for learnt there technical
side. And also the training covered all the billing and measuring that needed to be
aware as a QS.
The site construction work has been temporary slow on several times due to delay of
payments and bad weather conditions. There were some delay in provide relevant
details and drawings also. This assisted to get a great practical knowledge in civil
engineering and practical knowledge in Quantity Surveying. Further this gives the
opportunity to solve my problems encountered with our project managers and Site
engineers. Overall the training period enrich me with lot of skills and experience in
62
Appendices
63
64
65
Remarks
66