At the Heart of

Uninterrupted
Operations

Mitigating Operational Risk for an


Airline through Operational Acceptance Testing

CASE STUDY
Synopsis Business Challenge

With great expansion comes great complexity, and The clients diverse airline applications were not
higher risk of system instability. Pursuing an well-integratedincluding air cargo, airport
aggressive growth strategy, a leading commercial management, crew management, and ight
airline was expanding in the US, Europe, and the operations systems. Their existing infrastructure
Middle East. To keep up with the pace of was incapable of handling legacy applications,
expansion, the client implemented new technology operating systems, and databases, which added
systems. This led to a complex IT landscape with another layer of complexity.
issues in application integration, which resulted in
increased occurrences of system failure. We The client needed a technology partner who could
responded with a comprehensive operational address:
acceptance testing (OAT) solution that mitigated
Unanticipated interruptions and complexity in
functional risk, increased operational eciency,
discovering the root cause of emergency
and enabled 99% system reliability within the
issues in the staging phase
expected timeframe.
Lack of sucient time for functional
About the Client operational acceptance testing (OAT) due to
One of the largest commercial airlines in the US, frequent releases in a short duration
the client ranks high in terms of customer
The need to provide quality to the airlines
experience and services.
integrated systems via OAT according to
business requirements

www.niit-tech.com
The need to reduce cost and improve guides, release notes, and backout / rollback plans.
overall system stability We followed a stringent process to dene clear
scope of functionality before proceeding to
Our Solution production, which included functional, system,
regression and user acceptance testing, followed
After analyzing the clients IT environment, our
by OAT. Our team enhanced work item tracking,
team determined that systems functionality was
bug tracking, and change control
working as expected in the test environment, but
methodologiesall of which helped the airline
there were defects in the staging/pre-production
standardize its testing processes.
environment. They inferred that the defects were
related to improper conguration on the server Delivering More Value
and the client, database, and network. There were
inadequacies in the infrastructure design, build More System Stability: Our OAT solution
deployment, monitoring, and health checks. They enabled the client to foresee issues/risks
also found limited systems documentation for that may result in system failure. 99% of
release notes, deployment guides, infrastructure risks related to functionality were mitigated
setup guides, technical implementation plans, and after four levels of testing before going live,
operational guides such as rollback and and the client was able to achieve 99%
backup/recovery procedures. Another issue was system reliability within a specied period.
the lack of a disaster recovery / IT service
continuity plan. More Operational Eciency: A 99% increase
in operational eciency helped enhance
Operational Acceptance Testing for business operations using systems support.
Pre-production Verication
More Savings: The client saved signicant
In this phase, the physical infrastructure and the costs on defect amelioration due to reduced
applications were evaluated for failover, availability, post-production defects and smoother
backup and restore, alert and monitor, test operations. There were no critical issues in
conguration and deployment, and backout plans. production after one year of
This entailed review and update of procedural implementation
documents such as implementation plans, build

The NIIT Technologies Advantage

Since the systems were core to the clients business operations, our approach
to operational acceptance testing (OAT) had to be non-disruptive. We achieved
this by ensuring service continuity capability of the IT infrastructure while
enabling backup and restore capability for the applications. Another
imperative was making the OAT process comprehensive. To do so, testing of
the infrastructure and systems was carried out basis multiple business and
operational needsspanning failover, disaster recovery, backup and restore,
end-to-end environment stability, SLA / OLA monitoring, performance on
dierent tier 1, 2, and 3 browsers and devices, business continuity, and
implementation / operational guide verication, and business continuity.

For more information, contactmarketing@niit-tech.com

2016 NIIT Technologies. All rights reserved.

NIIT Technologies is a leading global IT solutions organization, dierentiated on the strength of domain expertise; it
B_226_251116

services clients in travel and transportation, banking and nancial services, insurance, manufacturing, and media verticals.
Leading with its service vision New Ideas, More Value, NIIT Technologies is committed to delivering new ideas combined
with operational excellence to provide exceptional value to its clients. The Company is focused on helping businesses
design sustainable, optimizable and winning digital operating models, enabling them to become agile, scalable, and exible.
Visit us atwww.niit-tech.com