Você está na página 1de 61

TABLE OF CONTENT

SECTION DOC.No DESCRIPTION

1 INT-01 Rev.1 INTRODUCTION

2 DEF-01 DEFINITIONS

3 FC-01 BUILDING PERMIT APPLICATION FLOW CHART

4 PR-001 PROJECT RECORD SHEET

5 GR-01 Rev.1 GENERAL REQUIREMENT

6 FEE-01 Rev.1 FEE SCHEDULE

7 DRG-01 Rev.2 DRAWINGS REQUIRED TO OPTAIN A PERMIT

8 DCS-01 Rev.2 APPLICABLE DESIGN CODES AND STANDARDS

9 ARC-01 Rev.2 ARCHITECTURAL APPROVAL


(SUBMISSION REQUIREMENT)

10 FM-001 REQUEST FOR ARCHITECTURAL APPROVAL

11 FM-001A ARCHITECTURAL CHECKLIST

12 APPENDIX A CAR PARK CALCULATION TABLE

13 APPENDIX B SANITARY FITTINGS CALCULATION TABLE

14 ST-001 STRUCTURAL SUBMISSION CHECKLIST

15 SIT-01 Rev.1 TEMPORARY FENCE, SITE PREPARATION AND MOBILIZATION

16 FM-002 REQUEST OF TEMPORARY FENCE, SITE PREPARATION &


MOBILISATION PERMIT

17 SIT-02 Rev.1 EXCAVATION PERMIT

18 FM-004 REQUEST FOR EXCAVATION PERMIT

19 STR-01 Rev.1 FOUNDATION AND SUBSTRUCTURE PERMIT

20 FM-003 REQUEST FOR FOUNDATION AND SUBSTRUCTURE PERMIT

21 STR-02 Rev.1 STRUCTURAL APPROVAL


(SUBMISSION REQUIREMENT)

22 FM-005 REQUEST FOR STRUCTURAL APPROVAL

23 APPENDIX S REQUIREMENTS FOR STRUCTURAL ENGINEERING SUBMISSION

24 EXP-01 PERMIT REVISION, EXPIRATION, AND RENEWAL PROCESS

25 IN-01 MUNICIPAL INSPECTION PROCESS

26 BCC-01 BUILDING COMPLETION CERTIFICATE


ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

INTRODUCTION

DOCUMENT NO INT-01 Rev. 1 Date 6/25/2007

1.0 INTRODUCTION

The manual is a collection of procedural guidelines, application forms, worksheets


and forms used by the Building Permits Directorate (BPD). The intent is that many
of these individual sections will be available as handouts at the Building Permits
Directorate. When all of these documents are assembled in sequential order into a
larger bound document they comprise the complete policy manual for Building
Permits Directorate.

The policies and procedures manual have been developed to clearly define the
processes in place at the BPD. This manual will be revised from time to time as
improvements are made to the processes or as new rules and regulations are
determine. The Abu Dhabi Municipality reserves the right to change the policies and
procedures at any time.

2.0 FORMAT OF THE MANUAL


The manual is a collection of procedural guidelines and application forms used by
the BPD. Developers, designers and contractors are to ensure that they are familiar
with these procedures and strictly adhere to their conditions. Submittals that do not
adhere to the requirements of these documents will not be processed.

3.0 PERMIT AND PLAN REVIEW TYPES


To simplify the process, Abu Dhabi Municipality has agreed to these types of permits
and plan approvals:
A. Temporary Fence, Site Preparation and Mobilization Permit (SIT-01).
B. Excavation Permit (SIT-02).
C. Building Permit
a. Architectural Approval (ARC-01 Rev.2).
b. Structural Approval (STR-02 Rev.1).
c. Foundation & Sub-Structure Permit (STR-01 Rev.1).
D. Building Completion Certificate. Refer to (BCC-01).

INT-01-Rev.1 Page 1 of 1
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

DEFINITIONS

Document No DEF-01 Rev. 0 Date 9/21/2006

DEFINITIONS

ADM Abu Dhabi Municipality.

BPD Building Permit Directorate.

Consultant Any Architect or Engineer registered through Abu Dhabi Municipality.

Contractor Any Contractor registered through Abu Dhabi Municipality.

__________________________________________________________________
DEF-01 Page 1 of 1
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
BUILDING PERMIT APPLICATION FLOW CHART
Document No FC-01 Rev. 0
Date 25/6/2007

BUILDING PERMIT APPLICATION - FLOW CHART

STAGE 1
PROJECT PRE-QUALIFICATION

STAGE 2
PRELIMINARY PLANNING & CONCEPT APPROVAL

1) Project Presentation & Design Report


2) Concept/Schematic Design Drawings
3) Completed Checklists & Forms
4) Town Planning Approval of Master Plan
5) Town Planning approved Affection Plan & Land Use.
6) Roads & Transportation Authority Approval of TIS for Master Plan
7) Civil Aviation Authority for height clearance of Master Plan
8) Other special approval (ie. Ministry of Education, Health Authority, UAE
Armed Forces, Tourism Authority, Environmental Agency etc)

If all in order, project coordinator gives instruction for consultant to proceed with
the relevant permit application and full design submission.

TYPES OF PERMIT APPLICATION STAGE 3

1) Temporary fence, site preparation DESIGN REVIEW


& mobilization permit Full Architectural & Structural
Submission
2) Excavation permit

3) Foundation & Sub-Structure STAGE 4


permit
FINAL BUILDING PERMIT

___________________________________________________________________
FC-01 Page 1 of 1
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Project Record Sheet

PROJECT TITLE:
.......
DESCRIPTION:

...........

LOCATION : ...

SITE AREA : .. BUILDING HEIGHT : .

DEVELOPER / OWNER :
..
CONTACT NAME :
....................

MOBILE NO : EMAIL: ...

PROJECT MANAGER :
..
CONTACT NAME :
....................

MOBILE NO : EMAIL: ...

CONSULTANT :
..
CONTACT NAME :
....................

MOBILE NO : EMAIL: ...

OFFICIAL USE

SIGNATURE : _______________________________ DATE : _______________

PR-001
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
GENERAL REQUIREMENTS
Document No GR-01 Rev. 2
Date 6/25/2007

1.0 INTRODUCTION:
The following is a list of general requirements applied to all submittals. Consultants,
Contractors and Architects are required to provide all essential information and to
comply with these requirements prior to submitting any drawings.

2.0 General Requirements:


2.1 Comprehensive approved Master Plan Report / Project Summary
Report 2 copies of A3 size report and an electronic copy of the same
shall be submitted. The report should outline and explain the following
aspects of the proposal with supporting drawings and relevant
illustrations:
Design Concept & Intent Zoning & Land Use
Site Accessibility Traffic & Transportation
Car Parking Provision Public & Handicap Amenities
Life Safety Structural Concept
MEP Concept Utility & Services
Sustainability & Efficiency Wind Effect Assessment
Utility & Services Statement Day lighting Assessment
Vertical Transportation Environmental Assessment
Waste Management Faade Lighting Strategy
Landscaping & Greening Faade Maintenance
Occupancy/Population Density Schedule of Areas

The summary report shall include but not limited to the above
mentioned. The consultant should by all means include additional
information deem important that will facilitate the authority's approval.

2.2 Each developer shall have control on building design to achieve their
master plan guidelines. Therefore, preliminary and final architectural
drawings for building permit should bear the "No Objection" from the
relevant developer before the submission to ADM.

2.3 Approved Development Master Plan / Site Plan a copy of colored


A1/A0 size print approved by Town Planning Department (scale 1:500
to 1:1000) shall be submitted, to include but not limited to the following
information:

___________________________________________________________________
GR-01-Rev.2 Page 1 of 3
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
GENERAL REQUIREMENTS
Document No GR-01 Rev. 2
Date 6/25/2007

Plot Limit & Number Topography Public Amenities


Land Use, Zoning & Existing & Occupancy /
Phasing Proposed Levels Population Density
Ingress & Egress Set-out
Service Corridor
Points Coordinates
Service Access Way Utility Buildings Retaining Structures
Landscaping Tunnels & Bridges Boundary Wall
2.4 No objection letters from appropriate Authorities. (see BCC-01)
2.5 Appointment letters
2.5.1 Appointment letter for Architects / Consultants.
2.5.2 Appointment letter for Contractor.
2.5.3 All appointment letters shall be signed and sealed by the owner
/ developer.
2.6 Official valid trade licences from.
2.6.1 Consultants.
2.6.2 Contractors and Sub-Contractors.
2.7 Applicable forms signed and sealed by owner, Consultant and or
contractor.
2.8 Applicable fees.
2.9 Developers will bear the responsibility of clearing their sites during and
after construction completion.
2.10 Electronic format of all submitted drawings.
2.11 Hard copies of drawings. (see DRG-01-Rev.2)

3.0 General notes:


The following are general notes that all submittals shall comply with.
3.1 Consultants and Contractors shall adhere and comply with the
applicable design codes & standards. (see DCS-01-Rev.2)
3.2 Documents are clear and legible.
3.3 Documents are in a sequential order and signed and sealed by the
appropriate Consultant.
3.4 Application form fully completed.
3.5 All timelines in this procedure are subject to work load.
3.6 If authority's comments are not clear, a scheduled appointment can be
arranged with the respective municipality engineers/architects.
3.7 Appendix S Requirements for Structural Engineering
Submission shall also be referred to when preparing structural related
submittals.

___________________________________________________________________
GR-01-Rev.2 Page 2 of 3
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
GENERAL REQUIREMENTS
Document No GR-01 Rev. 2
Date 6/25/2007

4.0 Time-line Schedule for Approvals:

Category Document No. First Second


Review Review
Architectural Approval ARC-01 Rev.2 5 days 5 days

Temporary Fence, Site SIT-01 1 day -


Preparation & Mobilization
Approval

Site Excavation Approval SIT-02 Rev.1 1 day -

Foundation & Sub-Structure STR-01 Rev.1 5 days 5 days


Approval

Structural Approval STR-02 Rev.1 21 days 10 days

END OF PROCEDURE

___________________________________________________________________
GR-01-Rev.2 Page 3 of 3
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

FEE SCHEDULE
Document No FEE-01 Rev. 1 Date 6/25/2007

1.0 INTRODUCTION

This document outlines the fee structure that are to be implemented within the
Building Permits Directorate at Abu Dhabi Municipality.

2.0 FEE SCHEDULE

TABLE 1.4.10A PERMIT FEE SCHEDULE

Type of Permit Fees in Unit Notes


AED
Construction of a new building 2000 -
Demolition of a building 100 Per/floor
Issue a final certificate 500 -
Additions 500 -
Maintenance works 500 -
Permit renewal 200 -

TABLE 1.4.10B INSURANCE SCHEDULE

Type of Permit Fees in Unit Notes


AED
Insurance
Building Demolition 10000 -
New erection work 10000 -
Additions to existing buildings 1000 -

END OF THE PROCEDURE

___________________________________________________________________
FEE-01-Rev1 Page 1 of 1
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
STANDARD TITLE BLOCK
Document No DRG-01A Rev. 0 5/6/2007

___________________________________________________________________
DRG-01A Page 1 of 1
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
DRAWINGS REQUIRED TO OBTAIN PERMITS
Document No DRG-01 Rev. 2 6/25/2007

1.0 INTRODUCTION

This section explains in detail drawings and documents that are required for various
permits issued by the Building Permits Directorate. Applicants shall be aware that there
may be changes over time.

2.0 SCALE AND LEGIBILITY OF DRAWINGS

The following scales should be adopted:

Key / Location Plan 1:10,000


Landscape Plan 1: 500 to 1: 1,000
Site Plan 1: 500 to 1: 1,000
Plans, Elevations, Sections 1: 100 to 1: 200
Detail Designs 1: 20 to 1: 50

If any other scale is used, prior approval must be obtained from the Building Permits
Directorate of Abu Dhabi Municipality

Please note that the lettering on drawings must be readable and allow for reductions to
be made. To accomplish this, lettering on a full size drawing must be easily readable.

When drawings are submitted they are to be folded to match the requirements of the
Municipality.

3. DRAWING SUBMISSION REQUIREMENT

3.1. All drawings accompanying any application for approval shall be prepared,
stamped and signed by the Qualified Consultant, who holds a valid trade
license and registered with the Abu Dhabi Municipality.

3.2. All drawings shall


3.2.1. Be produced in 1 set of paper prints and properly packaged in the
prescribed box-files and clearly labeled for initial approval.
3.2.2. Be produced in 3 sets of paper prints and properly packaged in the
prescribed box-files and clearly labeled. The drawings must reflect the
final revision / correction, demonstrating full compliance with all
authority comments for final building permit approval.
3.2.3. Be accompanied by a drawing list for each set of drawings.
3.2.4. Be produced in a clear, legible manner and following the drawing
numbering according to the Building Permits Directorate:

___________________________________________________________________
DRG-01-Rev2 Page 1 of 4
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
DRAWINGS REQUIRED TO OBTAIN PERMITS
Document No DRG-01 Rev. 2 6/25/2007

For Architectural Drawings:


i. Drawing List A000
ii. Site Plan/Landscape Plan A010 (10 series ie. 10-99)
iii. Floor Plans A100 (100 series ie. 100-199)
iv. Elevations A200 (200 series ie. 200-299)
v. Sections A300 (300 series ie. 300-399)
vi. Details A400 (400 series ie. 400-499)

For Structural Drawings:


All Drawings - S100 (100 series ie. 100-199)

3.2.4. Bear a title block in accordance to the format set out by the Building
Permits Directorate, and reserve a space for authority's
comments/signature/stamp at the bottom right corner of the title block
(see DRG-01A)
3.2.5. Be fully annotated with appropriate notations and symbols. All
dimensions shall be in metric (mm)
3.2.6. Demarcate clearly the new building works from the existing building by
suitable annotation and markings.
3.2.7. Delineate clearly the different phasing of building works within the
development by suitable annotation and markings.
3.2.8. Delineate clearly the building works to be deleted, demolished or
removed by suitable annotation and markings.
3.2.9. Be numbered serially where the first plan is numbered as 1 of 'n' and
the last plan as 'n' of 'n'. ( 'n' being the total number of pages of the
relevant plans)

3.3. All building plans shall, where applicable, consist of or contain the following:

3.3.1. Landscape Plan (colored), showing


a) Hardscape footpaths, walkways, plazas, courtyards, ramps etc.
b) Softscape water features, pools, lawn, garden terraces etc.
c) Free-standing structures gazebo, pergolas, tensile structure etc.
3.3.2 Site Plan, showing
a) The location and layout of the site with boundary lines/plot limits
verged in red.
b) The outline of the building to be erected or building works to be
carried out in color or otherwise.

___________________________________________________________________
DRG-01-Rev2 Page 2 of 4
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
DRAWINGS REQUIRED TO OBTAIN PERMITS
Document No DRG-01 Rev. 2 6/25/2007

c) The north point and the number of the lot and adjoining lots in
accordance to the affection plan issued by the Municipality.
d) The distance between the new building to be erected or the building
works to be carried out and the lot boundary.
e) The retaining wall structure (if any) and perimeter fencing / gate /
boundary wall.
f) The existing and proposed platform levels and slopes.
g) The ingress and egress to the site, to include clear markings of fire
engine access way.

3.3.3 Plans, showing


a) The purpose of every room or space in the building.
b) The finished floor level and the structural slab level.
c) The types of materials to be used for the main elements of the
buildings.
d) The grid lines or dimensions between columns, corridors, staircase
landing and the thickness of walls and columns.
e) The number on car lot and total provision, if it is to be used for car
parking.
f) The gradient of slope for ramps, pedestrians and vehicular.
g) The type of plant, equipment or water tank proposed to be installed
and the location of the equipment and every plant room or water
tank room.
h) Clear statements indicating every part of the building that is to be
air-conditioned or mechanically ventilated.
i) The reference section lines and elevation references on all plans.
j) In respect of the ground floor
The existing and proposed platform levels of the site and
adjoining lots.
The relationship between the internal and adjoining external
spaces.
The distance between the new building and the lot boundary.
k) Other details or plans if required by the Building Permit Directorate.

___________________________________________________________________
DRG-01-Rev2 Page 3 of 4
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
DRAWINGS REQUIRED TO OBTAIN PERMITS
Document No DRG-01 Rev. 2 6/25/2007

3.3.4 Elevations, showing


a) All architectural elevations/ facades of building(s) within the
development.
b) The grid lines or dimensions consistent with those on the floor plans.
c) The finished floor level of each storey and the overall building
height.
d) Any cut-out spaces with suitable markings.
e) All glazing components with suitable notations and symbols.
f) Annotated finished materials for the building envelope.

3.3.5 Sections, showing


a) The name of every space in the building traversed by the section line.
b) The clear headroom of every space in the building.
c) The vehicular ramps in car parking structure(s) above & below
ground level.
d) Any atrium space and/or high volumetric spaces in the building.
e) The vertical circulation of the building eg. staircases, escalators, lifts
etc.
f) Perimeter gates, retaining walls, tunnels and suspended structure(s)
eg. canopies, bridges etc.

3.3.6 Details, showing


a) typical staircase details

b) typical building faade details

c) canopy details
d) skylight details
e) boundary wall details
f) any others (as requested)

END OF PROCEDURE

___________________________________________________________________
DRG-01-Rev2 Page 4 of 4
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
APPLICABLE DESIGN CODES AND STANDARDS
Document No DCS-01 Rev. 2 Date 6/25/2007

1.0 INTRODUCTION
In addition to Abu Dhabi Municipality, Building Regulations and Guidelines, the
following list of design codes and standards would be acceptable.

2.0 THE RECOGNIZED CODES


All new construction in Abu Dhabi after April 1st, 2006 should conform to one of the
model codes listed hereafter:
International Building Code, 2006 edition
Published by the International Code Council
www.iccsafe.org
Building Regulations and Guidelines
Green Book
Municipality of Abu Dhabi
1994 Edition
The following table provides a list of acceptable design codes and standards:

Applicable Standards Edition Comments


BSI Latest edition Overall Construction
British Standards Institution
ACI Latest edition Concrete Construction
American Concrete Institute
AISC
American Institute for Steel Latest edition Structural Steel Works
Construction
Uniform Building Code for
UBC 1997 -
Seismic Design

3.0 USE OF ONE CODE ONLY


It is crucial that the designer does not design a building using two different
international codes. The designer should decide well in advance the code he intends
to use and ensure that the same is used throughout the design and construction
phase.
If it became necessary to combine the two international standards, for example the
Contractor may have to use steel produced to the British Standards for the design to
AISC standards, the design consultant should carefully verify that the substitution
will not have an adverse effect on the integrity of the structure designed and shall
submit approval letter to BPD prior to job commencement.

4.0 MIXING OF CODE PROVISIONS

Mixing of different code provisions is not allowed unless an application for alternate
materials and methods is submitted with the drawings and/or specifications for
approval.

END OF PROCEDURE

___________________________________________________________________
DCS-01-Rev.2 Page 1 of 1
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
ARCHITECTURAL APPROVAL
Document No ARC-01 Rev. 2 6/25/2007

1.0 INTRODUCTION
This section explains in detail the scope of the architectural approval. It elucidates
on the procedures required by the Municipality to carry out an unbiased and uniform
architectural assessment as part of the Municipality aim to better serve each
development application.
A complete set of architectural drawings as described in Document No
DRG-01-Rev 1 shall be submitted for the initial architectural approval.
2.0 PURPOSE
The purpose of this review is to ensure that the building complies with applicable
code as outlined in DCS-01-Rev.2
3.0 APPLICATION FORM & CHECKLIST
The Consultant is to complete the following forms and checklists :
a) Application form ( FM-001 ) Request for Architectural Approval
b) Architectural Checklist ( FM-001A ) Planning & Building Design

4.0 DOCUMENTS REQUIRED


The following documents are the minimum requirement for architectural approval:

4.1 Exterior elevations (in color).


4.2 Perspectives exploring all sides of building (in color).
4.3 Design narrative and building use.
4.4 Floor plan.
4.4.1 Basement Plan if applicable.
4.4.2 Ground floor plan.
4.4.3 Mezzanine floor plan.
4.4.4 Typical floor plan.
4.4.5 Penthouse plans if applicable.
4.4.6 Roof Plan.
4.5 Sections and details.
See DRG-01-Rev 1 for additional drawings, formats and more specific information
on detailed drawings.
5.0 APPROVAL BY OTHER AUTHORITIES:
In addition to the authorities described in BCC-01 item 6.0, other relevant authority
approval may be required by the Building Permits Directorate where applicable.

Subject to the type, location and complexity of the development, the Building Permits
Directorate will advise the consultant accordingly.

___________________________________________________________________
ARC-01-Rev2 Page 1 of 3
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
ARCHITECTURAL APPROVAL
Document No ARC-01 Rev. 2 6/25/2007

6.0 PROJECT PRESENTATION:

Depending on the complexity of the development and dynamic nature of the design,
the Building Permits Directorate will inform the project team ie. consultants,
engineers, project manager to prepare a project presentation for the concerned
members from the Municipality.

The project team is expected to deliver a comprehensive and concise project


summary with emphasis on the following aspects of the proposal:

a) Design concept and planning strategy


b) Land use, zoning and phasing
c) Population density
d) Project mobilization date and expected completion date
e) Site accessibility vehicular and pedestrian
f) Car parking zoning and management
g) Life safety strategy
h) Logistics and waste management
i) Environmental and sustainability strategy
j) Landscaping
k) Wind impact assessment (if applicable)
l) Design for building security (if applicable)
m) Handicap and public amenities provision

The project team is not required to go in-depth into specialized and technical details,
and should limit the presentation to less than 20 minutes and commit 10 minutes for
Question & Answer.

Once the municipality is satisfied, the consultants can then proceed to submit the
developed design drawings for approval.

In addition to the responsibility of the consultant / designer to comply with the


applicable codes and standards described in DCS-01-Rev.2, the onus of ensuring
quality, safety and compliance to the Master Plan guidelines shall remain the
responsibility of the developer. (see GR-01-Rev.2, item 2.2 )

7.0 TIMELINE FOR APPROVAL

The municipality will process the architectural approval or issue a clear correction list
within Five (5) working days of receiving complete submittal as per 4.0
Documents Required for approval.

If the Municipality deems the submittal is incomplete and issues the authority
comments, the Municipality will refer to this issuance as the First Correction List".

The applicant should respond to the corrections requested within 30 days (45 days
for large projects) to avoid permit application expiration.

___________________________________________________________________
ARC-01-Rev2 Page 2 of 3
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
ARCHITECTURAL APPROVAL
Document No ARC-01 Rev. 2 6/25/2007

Once the corrected documents are resubmitted, the municipality will have 5 working
days to perform a 2nd review. If documents still have corrections to be made the
municipality will issue a "Second Correction List" and so forth up to a maximum of 3
reviews.

If the same non-compliance persists after the 3rd review or resubmission, the
Building Permits Directorate reserves the right to cancel the application and the
applicant shall make a fresh submission and pay the applicable fees to the
municipality.

END OF PROCEDURE

___________________________________________________________________
ARC-01-Rev2 Page 3 of 3
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Request for Architectural Approval

Owner

Area Sector Plot

Consultant Name and Contact Information

Contractor Name and Contact Information

Office Use:

FM-001 Rev 0
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Architectural Checklist (1) Planning Consideration


S/no. Item Complied Remarks
1 Proposed building structure(s) are within plot
boundary in accordance with Affection Plan.
Proposed building(s) achieve required setback
distances from plot boundaries and building-to-
2 building distances, in accordance with local codes
and/or Master Plan development control regulation (if
applicable)
Traffic impact study (if applicable) specific to the
3 development shall be submitted to Roads
Department to obtain approval.
Environmental impact study (if applicable) specific to
4 the development shall be submitted to Environmental
Agency Department to obtain approval.
Provision of adequate ingress and egress points for
5
both private and public vehicles.
Provision of service & fire-fighting access way
6 (approved by Civil Defense Department) to be clearly
annotated on site plan.
Provision of on-site/off-street car/bus/coach parking
facilities and calculation/analysis sheet for the
development(s). In compliance with
7
local/international standards or the Master Plan
development control regulation (if applicable)
Refer Appendix A: Car Parking Calculation Table
Provision of adequate refuse collection/disposal
8 area(s) with appropriate waste management
strategy.
Provision of electrical substation and other utility
9
service spaces as required by service authorities.
Outline of future and/or other proposed phased
10
building(s) within the plot boundary.
Provision of public amenities (ie landscaped garden,
11 plazas, toilets, footpaths, handicap facilities, prayer
rooms, car parking, taxi pick-up area, etc.
Location of plant rooms, refuse centre, loading
docks, back-of-house facilities and other utility
12 structures (ground or roof top level) shall be
aesthetically screened from the general public and
be provided with a dedicated ingress/egress access.

FM-001A Rev 0
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Architectural Checklist (2) Building Design Consideration


S/no. Item Complied Remarks

Habitable space(s) shall meet local/international


1 standards in terms of sizes, ceiling/floor height,
ventilation and daylight requirements.

Provision of adequate exit/escape passageway,


fire/smoke-stop lobby, firemen lifts and escape
2 staircases, fire control room shall meet Civil Defense
requirement and/or comply with approved
international fire codes.

Provision of adequate handicap facilities and barrier-


3 free accessibility for special needs people (disabled)
shall meet international barrier-free codes.

Provision of adequate sanitary facilities/public


amenities shall meet occupancy needs in
accordance to local/international standards or Master
4
Plan development control regulation (if applicable)
Refer AppendixB: Sanitary Fittings Calculation
Table

Internal/external horizontal circulation elements (ie


5 driveways, ramps, corridors, stairs) shall meet
local/international standards.

Internal/external vertical circulation elements (ie


6 staircases, lifts) shall meet local/international
standards.

Plot fencing/boundary wall shall be within plot


7 boundary and designed to comply with local
standards

Vehicular and pedestrian ramps shall meet the


8 minimum gradient/slope in accordance to
local/international standards.

Provision of protective/safety barriers (ie railings,


parapet walls) along trafficable platforms/public
9
accessible routes shall meet local/international
standards.

Proposed building projections beyond plot limits (ie


shading devices, balcony, terrace, signage &
10
billboards) shall comply with local codes and shall
subject to further review by relevant authorities.

FM-001A Rev 0
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Architectural Checklist (2) Building Design Consideration


S/no. Item Complied Remarks

Proposed basement space(s) shall be limited to non-


habitable usage for services (ie workshops, car
11 parking, MEP rooms). All basement levels shall be
adequately ventilated and achieves minimum
headroom of 2.4m from finished floor level.

Ensure the wind effect at pedestrian levels are within


the comfort level (to be verified by Wind Tunnel
12
Test), otherwise, adequate wind-breaking features
shall be provided to meet the required comfort levels.

Proposed building faade and embellishments shall


13
not contradict the local culture.

Ensure adequate day lighting for all habitable spaces


14 within the development, and complying to local
and/or international standards.

Ensure adequate ventilation for both habitable and


15 non-habitable spaces within the development, and
complying to local and/or international standards.

Provision of minimum of 1.0m wide pedestrian


sidewalks or pavement at building(s) perimeter. The
16
sidewalk/pavement shall be minimum 150mm above
the surrounding road/street levels.

The internal ground level of all buildings shall


17 achieve a minimum of 450mm above the surround
road/street levels.

FM-001A Rev 0
BUILDING PERMITS DIRECTORATE APPENDIX A
CAR PARKING CALCULATION TABLE
______________________________________________________________________________________________________________________________________________________________________________

CAR PARKING CALCULATION TABLE

Project Title : Project description Use of building(s) detailing number of floor of building(s), and number of basement levels per building.
Location : Precinct/District - Sector number Plot number (as per Affection Plan )

(a) (b) (c) (d) (e) (f) (g) (h)


Phase Description of Parking Rate Parking Spaces Total Parking Parking Excess Drawings of Drawings of
Land Use Required for Spaces (Shortfall) Existing Proposed
Proposed Provided by Parking Spaces Development
Development Proposed Parking
Development Facilities
Refer approved
Square meters by Square meters Number of spaces
parking rates from
Use a separate land use type or multiply parking to be provided as
Roads Department Column (e) minus
row for each phase number of rate, by land use an element of the Yes / No Yes / No
Refer IBC section column (d)
of the project residential units by type, aggregated to proposed
1106 for accessible
type total development.
parking rates

Reasons for Waiver :


Supporting documents shall be submitted to substantiate the shortfall / under provision of the required car parking spaces / facilities in the proposed development
Subject to the approval of the Authority.

Waiver : Approved / Rejected Date : _____________

NOTE :

1. The development description shall describe the intensity of each land use. For large development whose precise mix of uses is not known at the time of preliminary
architectural review application, an estimated mix of land uses shall be established as the basis of car park computation & analysis. The applicant shall follow-up with the
final & updated car park analysis table during the final building permit application, ensuring sufficient parking supply to meet all of the parking demand generated by the
proposed development.
2. The local car parking rates (Roads Department) shall be adopted as the basis for car parking computation.
3. Alternatively, the consultant shall adopt the car parking standards/rates set out in the approved Master Plan Development Control Package issued by the Developer (if
applicable)
BUILDING PERMITS DIRECTORATE APPENDIX B
SANITARY FACILITIES CALCULATION TABLE
______________________________________________________________________________________________________________________________________________________________________________

SANITARY FACILITIES CALCULATION TABLE

Project Title : Project description Use of building(s) detailing number of floor of building(s), and number of basement levels per building.

Location : Precinct/District - Sector number Plot number (as per Affection Plan )

(a) (b) (c) (d) (e) (e) (f) (g) (h) (k)
Sanitary Appliances Excess / Excess / Excess / Baby / Excess /
Descriptionof Male Shortfall Female Shortfall Shortfall Toddler Shortfall
Requirement Disabled
Land Use & Changing
based on International Code
Expected (+/-) (+/-) (+/-) Room) (+/-)
(ie International Plumbing
Occupancy
Code-Chapter 4) Prv Req Prv Req Prv Req Prv Req
Square meters WB
by land use type
& occupancy WC Stating the rates and
within the space requirements as per codes.
UR
SH

Legend : WB=Wash Basin, WC=Washing Cistern, UR=Urinals, SH=Showers, Prv=Provided, Req=Required

Reasons for Waiver :


Supporting documents shall be submitted to substantiate the shortfall / under provision of the required sanitary facilities in the proposed development
Subject to the approval of the Authority.

Waiver : Approved / Rejected Date : _____________


NOTE :

1. The development description shall describe the intensity of each land use. For large development whose precise mix of uses is not known at the time of preliminary architectural review
application, an estimated mix of land uses shall be established as the basis of sanitary facilities computation & analysis. The applicant shall follow-up with the final & updated sanitary facilities
calculation table during the final building permit application, ensuring sufficient sanitary appliances to meet all of the amenities demand generated by the proposed development.
2. The latest IBC 2006 sanitary appliances rates/requirement shall be adopted as the basis for sanitary facilities calculation if no local standards can satisfy the current program.
3. Alternatively, the consultant shall adopt the sanitary facilities/appliance standards/rates set out in the approved Master Plan Development Control Package issued by the Developer (if
applicable)
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Structural Checklist

ENABILIG WORKS
S/no. Item Complied Remarks
1 Traffic impact study approved by Road
Section, if applicable for the project.
2 Approved site plan.
3 Service clearance for site. (NOC)
Copy of receipt from architectural section of
Building Permit Directorate confirming
4
submittal of architectural drawings to the
Directorate.
5 Soil investigation report.
6 Shoring layout.
7 Shoring sections and details.
Detailed calculations for shoring from
8
specialist and approved by the consultant.
9 Depth of excavation.

ST-001 Rev 0
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Structural Checklist

SUB-STRUCTRE
S/no. Item Complied Remarks

Completion of requirements for enabling


1
works as applicable.
2 Design philosophy and design criteria.

Foundation / substructure plans with


3
complete details.

Calculations for column loads by tributary


4 area method and by approved computer
software.

Columns and shear wall layout showing


5 reactions from the most critical load
combinations. (Design load)

Detailed design calculations for proposed


foundation, including columns and shear
6
walls, as well as basement retaining walls,
at foundation level.
Schedule of columns with reinforcement
7
and sizes and sections.

Structural framing (Schematic design) for all


8 floors showing the assumed sizes of
structural elements.

An electronic copy of the structural 3D


model for the lateral stability analysis. The
9
study should include all structural elements
and all the applied loads.
10 Wind tunnel study if required.

ST-001 Rev 0
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

S/no. Item Complied Remarks

Piling plan as applicable, showing the


11 reactions from the most critical load
combinations (Service loads).

Brief specifications and applicable notes for


12 the foundation & piles, presented on
drawings.

Pile design by specialist and approved by


13
the consultant.

Piling details showing pile length,


14 reinforcement details, pile size and capacity,
cut off & toe levels.

Proposed location of tower crane within the


15
approved plot area

This check list should cover the latest Abu


16 Dhabi Municipality requirements for
structural Section submissions.

ST-001 Rev 0
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Structural Checklist

SUPERSTRUCTURE
S/no. Item Complied Remarks

1 Final structural drawings.


2 Detailed design calculations.

Schedule of columns with reinforcement


3
and sizes and detailed sections.

Detailed sectional plans and elevations for


4 shear walls showing all dimensions and
reinforcement.

Schedule of beams, with reinforcement and


5 sizes, including typical beam elevation and
sections.
6 General notes for structural elements.

Plans, sections and details of swimming


7 pools, reinforced concrete water tanks, and
significant architectural features.

Plan & section for staircases showing all


8
dimensions and steel reinforcement.

ST-001 Rev 0
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


TEMPORARY FENCE, SITE PREPARATION AND
MOBILIZATION PERMIT
Document No SIT-01 Rev.1 Date 7/03/2006

1.0 INTRODUCTION

Before starting any new construction project on any site you must first build an
approved site fence around the property for protection of the site and the public.

2.0 WORK ALLOWED UNDER THIS PERMIT

The purpose of this type of permit is to allow the applicant or owner to begin
construction while the full working drawings for the project are still being reviewed.
The scope of construction under this permit will only include site preparation,
grading, and construction of the perimeter fence. The applicant may not pour
concrete or drive piling for the foundation under this permit.

3.0 APPLICATION FORM

Application form at the Building Permits Directorate (See FM-002) to be completed


and submitted.

4.0 DOCUMENTS REQUIRED

To obtain the fence permit, refer to the general requirements GR-01 Rev2 and you
will also need to submit the following documents:

4.1 Site plan showing limits of fence construction with the overall dimensions.
4.2 Fence Elevations.
4.3 Sections and details showing anchorage, material, color, design, etc.
4.4 Specifications.
4.5 Letter from contactor and consultants summarizing safety measures on
site during construction.
4.6 Location & details of site office, if available.

See DRG-01 Rev2 for drawing formats and more specific information on drawings.

See Appendix S for more detail submission requirements.

5.0 APPROVAL OF THIS PERMIT TYPE

After completing all steps the Building Permits Directorate will inspect and verify that
the fences are erected properly, as per requirement.

6.0 CONSTRUCTION OF THE FENCE

The following specifications shall be considered in constructing the temporary fence:

___________________________________________________________________
SIT-01-Rev1 Page 1 of 3
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


TEMPORARY FENCE, SITE PREPARATION AND
MOBILIZATION PERMIT
Document No SIT-01 Rev.1 Date 7/03/2006

Install a signboard showing the project name, owners name, consultants name,
contractors name, the building permit number and the date of the permit. This sign
should be clearly visible and legible from the project entrance.

The sections of the fence shall be made from non-combustible material and to
be painted with appropriate color.
The fence shall be properly fixed into the ground.
The distance between the sections of the fence shall not exceed 5 cm and the
height from the ground shall not exceed 10 cm.
The height of the fence shall be greater than 2.5 meters.
The width of the fence entrance shall be less than 5 meters.
Refer to applicable codes for other requirements.

7.0 SPECIAL ARRANGEMENT FOR BIG PROJECTS

Some projects are too big and might require large staging areas. In this event, a
large storage area might translate into constructing a temporary fence on an
adjacent property (see diagram below). Consultants and/or contractors are required
to submit written approval from plot 2 owner / developer, explicitly allowing them to
construct such a fence on his property.

Plot #1 Plot #2
Proposed Fence

All projects or new constructions need to obtain their temporary fence prior to
obtaining any other building permits.

8.0 TIMELINE FOR REVIEW

The review teams will complete their review and approve the permit or they will
provide a clear correction list within less than one (1) working day of receiving the
complete submittal as per 4.0 Documents Required, for review. If the Municipality
deems the submittal incomplete and or issues a First Correction List, the
Municipality will refer to the first review of the project the as first review.

The applicant should respond to the corrections requested within six months to avoid
permit application expiration.

___________________________________________________________________
SIT-01-Rev1 Page 2 of 3
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


TEMPORARY FENCE, SITE PREPARATION AND
MOBILIZATION PERMIT
Document No SIT-01 Rev.1 Date 7/03/2006

9.0 END OF THIS PERMIT PHASE

Once the full building permit is issued, the Temporary fence, site preparation and
mobilization permit phase will be terminated, although temporary fencing should
remain until the end of the project (final completion certificate).

END OF PROCEDURE

___________________________________________________________________
SIT-01-Rev1 Page 3 of 3
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Request of Temporary Fence, Site


Preparation & Mobilization Permit

Owner

Area Sector Plot

Consultant Name and Contact Information

Contractor Name and Contact Information

Office Use:

FM-002 Rev 0
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


EXCAVATION PERMIT
Document No SIT-02 Rev. 1 Date 7/03/2007

1.0 INTRODUCTION

Site fence has to be erected and approved by ADM inspector before the contractor
can submit for excavation permit.

2.0 WORK ALLOWED UNDER THIS PERMIT

The purpose of this type of permit is to allow the applicant or owner to begin
excavation of the site while the full working drawings for the project are still being
reviewed. The scope of construction under this permit will only include excavation,
dewatering, shoring and soil compaction. The applicant may not pour concrete or
drive piling for the foundation under this permit.

3.0 APPLICATION FORM

Please obtain an application form from the Building Permits Directorate (See FM-
004) to be completed.

4.0 DOCUMENTS REQUIRED

Following documents have to be submitted.

4.1 Traffic impact study approved by the roads section.


4.2 Approved site plan
4.3 Service clearance for site
4.4 Soil investigation report
4.5 Shoring layout
4.6 Shoring section and details
4.7 Detailed calculations for shoring from specialist and approved by
consultant
4.8 Depth of excavation

See DRG-01 Rev2 for drawing formats and more specific information on drawings.

See Appendix S for more detail submission requirements.

5.0 TIMELINE FOR REVIEW

The review teams will complete their review and approve the excavation permit or
they will provide a clear correction list within One (1) working day of receiving
complete submittal as per 4.0 Documents Required, for review. If the
Municipality deems the submittal incomplete and/or issues a First Correction List,
the Municipality will refer to the first review of the project the first review.

The applicant should respond to the corrections requested within six months to avoid
permit application expiration.

___________________________________________________________________
SIT-02-Rev1 Page 1 of 2
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


EXCAVATION PERMIT
Document No SIT-02 Rev. 1 Date 7/03/2007

6.0 END OF THIS PERMIT PHASE

Once the full building permit is issued this excavation permit phase will be
terminated

END OF PROCEDURE

___________________________________________________________________
SIT-02-Rev1 Page 2 of 2
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Request For Excavation Permit

Owner/Developer:

Area: Sector: Plot:

Consultant Name and Contact Information:

Contractor Name and Contact Information:

Office Use:

FM-004 Rev 0
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

FOUNDATION AND SUB-STRUCTURE


Document No STR-01 Rev.1 7/3/2007

1.0 INTRODUCTION
Structural concept design must be approved prior to submitting to foundation and
pile permit. ADM reserve the right of granting this type of permit based on project
size.
2.0 WORK ALLOWED UNDER THIS PERMIT
The scope of construction works under this permit will only include foundation and
piling works. Other works, such as basement construction, shall not commence
under this permit.

3.0 APPLICATION FORM


The Applicant must complete the Standard Application Form (FM-003), Request for
Foundation and Piling Permit and submit to the BPD.

4.0 DOCUMENTS REQUIRED


The following documents need to be submitted together with the application:

4.1 Completion of requirements for enabling works as applicable


4.2 Design philosophy and design criteria
4.3 Foundation \ Substructure Plans with complete details
4.4 Calculation for column loads by tributary area method and approved by
computer software
4.5 Columns and shear wall layout showing reactions from the most critical
load combinations ( Design load )
4.6 Detailed design and drawings for proposed foundation, including
columns and shear walls, as well as basement retaining walls, at
foundation level
4.7 Schedule of columns with reinforcement and sizes and sections.
4.8 Structural framing (Schematic design) for all floors showing the
assumed sizes of structural elements.
4.9 An electronic copy of the structural 3D model for the lateral stability
analysis. The study should include all structural elements and all the
applied loads.
4.10 Wind tunnel study if required.
4.11 Piling plan as applicable, showing the reactions from the most critical
load combinations ( Service loads )

___________________________________________________________________
STR-01-Rev1 Page 1 of 2
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

FOUNDATION AND SUB-STRUCTURE


Document No STR-01 Rev.1 7/3/2007

4.12 Brief specifications and applicable notes for foundation & piles,
presented on drawings.
4.13 Pile design by specialist and approved by the consultant
4.14 Piling details showing pile length, reinforcement details, pile size and
capacity, cut off & toe levels.
4.15 Proposed location of tower crane within the approved plot area

Refer to Section GR-01 Rev2 for drawing formats and other information required to
be shown on the drawings.

See Appendix S for more detail submission requirements.

5.0 REQUESTS FOR INSPECTIONS


The Contractor must submit their request for inspection to the Building Permits
Directorate at least 2 working days prior to the commencement of the piling works,
foundation casting, pile load testing or any other works that required such an
inspection.

6.0 TIMELINE FOR REVIEW


The review teams will complete their review and approve the submittal or they will
provide a clear correction list within five (5) working days of receiving the complete
submittal, as per Section 4.0, Documents Required, for review. If the
Municipality deems the submittal incomplete, and/or issues a First Correction List,
the Municipality will refer to the first review of the project as the "first review"
After the re-submission of the amended document to the Municipality, the review
teams will have 5 working days to perform the 2nd review.
The reviewing process will continue until all requirements have been complied with
and the design approved by the Municipality.

7.0 END OF THIS PERMIT PHASE


Once the full building permit is issued, this permit for Foundation and Piling Works
shall be terminated automatically.

END OF PROCEDURE

___________________________________________________________________
STR-01-Rev1 Page 2 of 2
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Request For Foundation and Sub-Structure Permit

Owner

Area Sector Plot

Consultant Name and Contact Information

Contractor Name and Contact Information

Office Use:

FM-003 Rev 0
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

FULL STRUCTURAL APPROVAL


Document No STR-02 Rev. 1 Date 07/02/2007

1.0 INTRODUCTION
The purpose of this type of permit is to allow the applicant to proceed with a full
scale construction after all other requirements are met.

2.0 APPLICATION FORM


The Applicant must complete the (FM-005) form, and submit to the BPD along with
the necessary documents.

3.0 DOCUMENTS REQUIRED


The permit application process is very much the same as for a normal review and
the permit process, since the applicant must also obtain a full building permit for the
project to be allowed to proceed.

3.1 Final structure drawings.


3.2 Detailed design calculations
3.3 Detailed sectional plans and elevations for shear walls showing all
dimensions and reinforcement
3.4 Schedule of beams, with reinforcement and sizes, including typical
beam elevation and sections
3.5 General notes for structural elements
3.6 Plans, sections and details of swimming pools, reinforced concrete
water tanks, and significant architectural features
3.7 Plan and section for staircases showing all dimensions and steel
reinforcement

See DRG-01 Rev2 for drawing formats and more specific information on the
drawings.

See Appendix S for more detail submission requirements.

If the plans are acceptable, a letter stating this approval is sent back to the project
coordinator's office center. This letter will be placed into the project file at the BPD.

___________________________________________________________________
STR-02-Rev1 Page 1 of 2
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE

FULL STRUCTURAL APPROVAL


Document No STR-02 Rev. 1 Date 07/02/2007

4.0 ISSUANCE OF THIS TYPE OF PERMIT


Once the Municipality is satisfied that the review is acceptable, it will issue a full
structural permit allowing the applicant to proceed with construction of the structural
system.

5.0 TIMELINE FOR REVIEW


The review teams will complete their review and approve the submittal or they will
provide a clear correction list within twenty one (21) working days of receiving the
complete submittal, as per Section 4.0, Documents Required, for review. If the
Municipality deems the submittal incomplete, and/or issues First Correction List, the
Municipality will refer to the first review of the project the "first review". The applicant
should ensure to respond to each item listed in the Structural Engineer's review. If
the comments are unclear, a meeting can be scheduled between the applicant and
the engineer who reviewed the plan.

The applicant should respond to the corrections requested within six months to avoid
permit application expiration.

Once the corrected plans are submitted back to the Municipality, the review team will
have 10 working days to perform a second review. If corrections have been made,
the plans will be approved. If further corrections are needed, the Municipality will
issue a Second Correction List.

END OF PROCEDURES

___________________________________________________________________
STR-02-Rev1 Page 2 of 2
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

Request for Structural Approval

Owner

Area Sector Plot

Consultant Name and Contact Information

Contractor Name and Contact Information

Office Use:

FM-005 Rev 0
REQUIREMENTS FOR STRUCTURAL
ENGINEERING SUBMISSIONS

January 2007

APPENDIX S
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

ABU DHABI MUNICIPALITY


REQUIREMENTS FOR STRUCTURAL ENGINEERING SUBMISSIONS

TABLE OF CONTENTS

1. PILING ... .................................................................................................................................. ..1


1.1 Geotechnical Report ...................................................................................................1
1.2 Information to be Shown on Drawings ... ......................................................................2
1.2.1 Shoring ............................................................................................................. ..2
1.2.2 Piling ... ...........................................................................................................2
1.3 Calculations... ......................................................................................................... .2
1.3.1 Application Codes ... .........................................................................................3

2. SUPERSTRUCTURE ............................................................................................................... .4
2.1 General Requirements ... ............................................................................................ ..4
2.2 Design Checklist .........................................................................................................4
2.3 Additional Foundation Requirements ..............................................................................6
2.4 Additional Vertical Element Requirements ... ............................................................... ..7
2.5 Additional Horizontal Element Requirements............................................................... .8
2.6 Modelling of Superstructure and Specialist Design Considerations... ..........................9

APPENDIX S January 2007


Page i
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

1. PILING

1.1 Geotechnical Report


Detailed geotechnical investigation reports shall be submitted with the structural drawings for
every project by the consultant. The consultant shall ensure that the required amount of
boreholes are carried out to the required depth by the geotechnical engineer, to the
requirements of the nominated Code of Practice for site investigations.

Geotechnical investigation reports are to contain, but not be limited to, the following
information as applicable:

Parameters for the geotechnical design of piles


Assessment of geotechnical conditions of pile construction and installation
Potential for ground heave, damage to adjacent structures or neighbouring piles
Vibration effects and potential for damage to adjacent structures
Near surface conditions for lateral load design
Spring stiffness of vertical and lateral soil (varying with depth), as required for
design purposes (for piles and rafts)
Allowable bearing capacity of the founding material
Allowable shaft adhesion
Recommendations for reasonable footing systems
Short term and long term design parameters, in particular for retaining walls
Allowable and tieback restraint parameters for shoring design
Potential for slope instability
Potential for liquefaction and design requirements and/or ground improvement
techniques to overcome the phenomenon
Assessment of site conditions on pile durability (sulphates, chlorides, PH in soil and
water)
Groundwater level, dewatering requirements and possible affect on surrounding
buildings
Earthquake ground classification factor in accordance to the requirements of the
Uniform Building Code
Excavation of soil and rock
Porosity of the soil for possible concrete aggression
Any other comments relevant to design and construction as may be revealed by the
investigation and testing

Subsequent to completion of soil investigation works and all necessary laboratory testing, the
consultant must submit documents certifying that:

All soil investigation works and laboratory works have been witnessed by a qualified
representative of the consultant
All works have been carried out in accordance with the nominated Code of Practice
for site investigations.
Proper equipment and tools, duly calibrated, have been used by qualified and
experienced personnel during all soil investigation and testing works, and that the
test results have been reviewed and approved by the consultant.

APPENDIX S January 2007


Page 1
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

1.2 Information to be Shown on Drawings


1.2.1 Shoring

Drawings containing excavation plan and sections showing and dewatering details
by specialist contractor.

Detailed calculations.

Guarantee letter from consultant

1.2.2 Piling

Piling plan showing pile length, reinforcement, legend for pile capacity, pile testing
cut-off levels etc.

Pile caps layout including column and shear wall location with dimensions

Pile caps sections showing raft thickness and bottom level at raft in relation to
Datum

Structural framing (general arrangements) for all floors including column


locations, floating column location if any, beams, slabs etc. including the load
transfer mechanism

1.3 Calculations
Design philosophy, complete design criteria and assumptions

Column load calculation by area method

Column load calculation by analytical method

Stability analysis for wind and seismic loads including drift and check for human
comfort criteria is to be enclosed

Loads on columns, shear walls including wind and seismic moments are to be
marked in the drawing of pile copy layout for critical load cases

Pile reactions for all critical load cases

Modulus of sub grade reaction and seismic parameters approved by geotechnical


investigation consultant

Pile capacity calculation by specialised piling contractor

A soft copy of the structural model including all the structural elements shall be
submitted on CD, together with the above mentioned calculations

Each drawing shall be signed by design engineer

APPENDIX S January 2007


Page 2
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

1.3.1 Application Codes

Dead and Live Loads

BS 6399:1996 Part-1

BS 6399: 1988 Part-3

Adopted dead and live loads shall satisfy the recommendations of Abu Dhabi
Municipality

Seismic Loads

UBC 97 Volume 2, Division 3V

Zone 2A

Wind Load

ASCE -7-02 Chapter 6

Shall be based on basic wind speed of 40 m/sec

Reliable wind tunnel study reflecting climatic site conditions where it look provision
is not applicable

Serviceability Limits

All buildings shall be designed to limit maximum drift under 50 year wind load to
1/500 of building height

All buildings shall be designed to limit inter story drift to 1/500 of the height and no
more than 10 year under serviceability 10 year wind 38m/sec

Adequate provisions shall be adopted to eliminate risk and damage to non-


structural elements due to inter story drift, creek, shrinkage, etc.

Wind induced vibration due to 10 year wind shall be limited to 15mg for residential
and hotel building and 20mg for office towers

APPENDIX S January 2007


Page 3
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

2. SUPERSTRUCTURE

2.1 General Requirements


The requirements of the Abu Dhabi Municipality Building Regulations and Guidelines for
Structural Design -1994 shall be applicable unless superseded with this document.

Design of the superstructure and foundations shall be based on the requirements of the
latest and relevant British, American or Australian Standards and the Uniform Building
Code for earthquake loads for Zone 2A.

Structural design of all projects submitted to the Municipality for approval, shall ensure
that the work is carried out by licensed and qualified consultants, with structural
engineers having the necessary qualifications and experience.

Design philosophy, complete design criteria and assumptions shall be submitted.

Whenever requested by the Structural Engineering Section of the Buildings Directorate,


detailed design calculations based on the above stated Codes of Practice shall be
submitted.

Consultants shall ensure that structures are economically designed (as appropriate), and
must ensure that designs and details are buildable.

All Stage Two drawings shall be accompanied by a letter of guarantee from the certifying
consultant and shall clearly identify the primary designer responsible for the design.

2.2 Design Checklist


Consultants submitting structural drawings for approval must ensure they have designed
the foundations and the superstructure in accordance with the following general checklist:

Fire Rating Requirements

Structural adequacy
Integrity
Insulation

Durability Requirements

Corrosion resistance
Chemical attack resistance
Crack control
Waterproofing

APPENDIX S January 2007


Page 4
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

Loading Requirements

Dead loads
Live load (including any pattern load and heavy load/compactus requirements)
Wind load
Earthquake loads
Earth pressures
Water pressures
Buoyancy loads
Ground movements and differential foundation settlements.
Dynamic effects/vibration resonance loads
Thermal loads
Creep
Moisture variation (shrinkage and swelling)
Expansion loads
Axial shortening of columns
Pre-stress (hyperstatic reactions)
Impact and breaking loads
Fatigue
Construction loads

Serviceability requirements

Deflections/sag (including allowance long term creep and shrinkage effects)


Hogging (especially for post tensioned beams and cantilever back spans)
Axial shortening/extension
Rotation due to torsional effects
Crack control (minimum pre stress level for post tensioned concrete)
Allowance for articulation of masonry wall as required
Allowance for brittle finishes

Stability Requirements

Overturning and uplift


Buoyancy
Sliding

Strength Requirements

Flexural strength (including minimum strength requirements)


Beam shear strength (including minimum strength requirements)
Punching shear strength
Torsional strength.
Bearing strength
Anchor strength for post tensioned beams
Foundation strength
Pre stress levels within acceptable limits

Detailing Requirements

Tendon placement priority over reinforcement


Tendon/reinforcement clash at columns etc.
Penetrations through slabs and beams
Set downs, steps and sloping surfaces

APPENDIX S January 2007


Page 5
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

2.3 Additional Foundation Requirements


Buildings with basements require approval of all basement floor plans from the Town
Planning Department of the Buildings Directorate and all concerned Service Departments.

The submitted drawings shall clearly indicate the distance to the outer face of any
permanent or temporary training system. (i.e. diaphragm walls, secant pile walls,
contiguous pile walls etc.) from the inner face of the basement walls.

Ground anchors supporting retaining systems for excavations, shall not extend into
adjacent plots or into areas of highly concentrated utilities and service lines in all
circumstances, clearances shall be obtained from the relevant service departments.

Pile foundations together with shallow foundations shall not be permitted to support the
same superstructure, unless isolated.

Foundations calculations shall (if required by the Municipality) address the design issues of
stability, durability. Serviceability and ultimate general requirements are:

Stability

Overturning and uplift


Buoyancy
Sliding.
Slope stability

Durability

Corrosion resistance
Chemical attack resistance
Crack control if required

Serviceability

Deflections/sag including allowance long term creep and shrinkage effects)


Axial shortening (in particular for piles)
Rotation of footings
Bearing stress

Ultimate

Punching shear
Beam shear
Flexural strength
Torsional strength
Anchor strength

*Geotechnical reports shall be submitted to the requirements of Part 1, Piling.

APPENDIX S January 2007


Page 6
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

2.4 Additional Vertical Element Requirements


Load calculation by tributary area method and moment shear factor method should
accompanied by plan drawings indicating the tributary areas. The use of software to
calculate column reactions is permitted, although should be accompanied by hand
calculations using the prior mentioned methods.

Calculations must show if columns are short or slender, according to the code provision.

All column design must be accompanied by moment interaction diagrams taking into
account slenderness effects.

Additional bending moments due to column beam/slab joints must be included in


calculations, including any secondary effects (hyper static reactions) from unbalanced
posttensioning reactions.

APPENDIX S January 2007


Page 7
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

2.5 Additional Horizontal Element Requirements


Edge beams around a radius and general torsionally loaded beams must allow for
additional longitudinal reinforcement and stirrups. All stirrups must be closed to ensure
adequate torsional resistance is achieved.

Slabs modelled using the finite element method must clearly indicate all assumptions
considered to predict deflections, and must ensure that full moment connections are not
modelled where they can develop into pinned connections.

Transfer slabs must be limit deflections to span/1000 to ensure that elements and partitions on
above floors do not crack.

Include:

All plans and sections relevant to the project for all structural elements
Class and, where appropriate, grade designation of concrete
Exposure classification
Reference number and date of issue of applicable design standard
Fire rating (if not specified on architectural drawings)
Loading (superimposed dead load and live load to all slab plans and wind and
earthquake loads)
Grade and type of reinforcement and tendons
General notes
Concrete cover to reinforcement
The finish and method of control for unformed surfaces
Class of formwork for the surface finish
Curing procedure and duration
The force required in each tendon, the maximum jacking force to be applied and
the order in which the tendons are to be stressed
The location and details of planned construction or movement joints connections
and splices, and the method to be used for their protection
The minimum period of time before stripping of forms and removal of shores
Any constraints on construction assumed in the design
Any special protective coatings
Characteristic compressive strength at 28 days
Characteristic flexural strength if required
Characteristic indirect tensile strength if required
Mean 7 days strength
Other early age strength
Slump of concrete.
Cement type
Maximum aggregate size
Water/cement ratio
Maximum 56 day shrinkage
Density if required.
Maximum water soluble acid (chloride ion) if required
Maximum sulphate content (SO3) if required
Temperature range at point of discharge if required
Testing requirements if required
Project assessment of concrete production if required

APPENDIX S January 2007


Page 8
REQUIREMENTS FOR STRUCTURAL APPENDIX S
ENGINEERING SUBMISSIONS

2.6 Modelling of Superstructure and Specialist Design


Considerations
Stability analysis for wind and seismic loads including drift

The following criteria applies (and should be corrected pending a wind tunnel test):

Maximum drift for a 50 year return period less than height/500


Maximum inter-story drift less than height/500 with a serviceability wind of
38m/sec.

Wind Tunnel Testing

The following serviceability requirements shall be adopted in the absence of accurate


wind tunnel testing for buildings:

Maximum root means square (rms) acceleration for a 5 year return period less
than 5 milli-gs, or
Maximum peak acceleration for a 5 year return period as specified in the table
below.

Period Peak Acceleration (milli-g)#


1 7.0
2 10.2
3 12.0
4 13.5
5 14.5
6 15.5
7 16.6
8 17.4
9 18.6
10 19.2
# Note: For office buildings, peak accelerations maybe 20% higher.

Specialist Design Considerations

Towers which have a natural frequency of less than 1Hz or height more than or equal to
twice the least plan dimension or are irregular vertically such as weak stories, transfer
slabs, transfer girders etc should carry out the following:.

Require dynamic analysis using response spectrum method for seismic load
Columns should be designed and studied due to shortening and creep where
required
Wind tunnel test required when the code provision is not applicable
An electronic copy of the structural 3D-Model including all structural elements, must
be submitted together with the abovementioned calculations, clearly stating all
methodology
All joints shall be seismically detailed (as required)
Framed building must ensure that plastic hinges develop in the beams and not the
columns to prevent entire collapse in an overload condition. It is therefore required
that the column is stiffer than the adjoining beam.

APPENDIX S January 2007


Page 9
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
PERMIT REVISION, EXPIRATION & RENEWAL PROCESS

Document No EXP-01 Rev. 0 Date 9/21/2006

1.0 INTRODUCTION:

Building Permits will expire if the related projects have not shown any progress for
significant durations of time. A re-application for a building permit is required If
applicants allow these permits to expire and Fees will have to be paid again.

2.0 PERMIT EXPIRATION:

The following table summarizes the length of inactivity allowed between each project
milestone that would cause a permit to expire.

Days until
Item Milestone Description Expiration

1 From the time a project receives an architectural review 365


approval to the time the applicant must re-apply for a
building permit or apply for a site preparation permit

2 From the time a project receives a site preparation 60


permit to the time when the applicant must re-apply for the
same construction permit.

3 Time from the Building Permits Directorate approval until the 60


time the applicant collects his permit and pays his fees
4 From the time that a permit is paid for and granted to the 90
time when work actually begins on the job site

5 From the time when construction activity on a job site 180


terminates to the time it commence again.

3.0 REQUEST FOR EXTENSION OF TIME

The applicant, prior to the expiration of their permit, can apply for a time extension
by writing a letter to the Building Permits Directorate stating the reason for an
extension. Only one extension of a building permit per project will be granted.

4.0 REVISION TO CURRENT PERMITS

It is the responsibility of the applicant to notify the Building Department about any
changes to the project design or configuration. All modifications have to be revised
and submitted to ADM for approval.

___________________________________________________________________
EXP-01 Page 1 of 2
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
PERMIT REVISION, EXPIRATION & RENEWAL PROCESS

Document No EXP-01 Rev. 0 Date 9/21/2006

5.0 RENEWAL OF EXPIRED PERMTIS

Once a permit has expired, the applicant has to re-apply from the beginning of the
application process. Municipality employees will endeavor to minimise the time
delay that re-applying may cause, but make no guarantees. It is clearly the
responsibility of the applicant to ensure that their permits do not expire.

END OF PROCEDURE

___________________________________________________________________
EXP-01 Page 2 of 2
Department of Municipalities & Agriculture
Abu Dhabi Municipality Building Permits Directorate

Phone 678-8888 Fax 677-2003

REQUEST FOR INSPECTION

PERMIT NUMBER: DATE: BUILDING NUMBER:


INSPECTION TYPE:

SPECIAL CONDITIONS:

Area: Sector: Plot:

Owner/Developer:

Consultant Name and Contact Information:

Contractor Name and Contact Information:

INSPECTION RESULTS: PASS FAIL DATE: INSPECTOR:


COMMENTS:

Office Use:

FIN-001 Rev 0
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


MUNICIPAL INSPECTION PROCESS
Document No IN-01 Rev. 0 Date 9/21/2006

1.0 INTRODUCTION

This document outlines the general process adopted for inspection requests and
performing inspection. This document defines ways of submission of an inspection /
re-inspection request. It highlights mandatory hold points, where Municipality
clearance is required prior to proceeding with construction activities (i.e., it indicates
when to submit an Inspection Request).

This document discusses the Inspection Request form, such as reports and/or
certificates, which typically result from an inspection.

This document is intended for use by Contractors, after issuance of a Building


Permit.

2.0 MAKING AN INSPECTION REQUEST

The contractor or the owner may request an Inspection / re-inspection by B P D.

Upon receipt of the request, the Inspection Request Desk will schedule the
inspector. The inspector is normally mobilized if the provided request is received
prior to 1:00 PM of any working day.

The Municipality will perform all inspection within two working days.

If the inspector can not be mobilized within a two days from receipt of the request,
the Inspection Request Desk will inform the Contractor by fax of the next earliest
available date.

Emergency inspections for routine work, as determined by the Building Official, and
in addition to the written request described above, shall be requested by telephone
number: 678-8888.

3.0 HOLD POINTS

The following table provides a guideline to the time to call for an inspection. The
Municipality Inspector may allow deviation from the standard inspection process if
there is a sufficient reason or site condition(s) that allow for an adjustment, without
causing adverse effects to the design of the buildings or structure.

Note that at the Building Permit issuance stage, the Contractor is advised on the
hold points applicable to the project in question and these are clearly listed on the
Project Inspection Card. This card must be kept at the job site.

IN-01 Page 1 of 4
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


MUNICIPAL INSPECTION PROCESS
Document No IN-01 Rev. 0 Date 9/21/2006

Serial Construction Activity


Remarks
No. Hold Points
1 Foundations Carried out by Civil/Structural Inspectors.
Check on reinforcement steel bars, dowels,
embedment, form work, against Municipality
approved drawings, prior to pouring
concrete.
Check on general preparatory works related
to foundation concrete cast.
For piling works, Municipalitys involvement
is limited to pile load test monitoring and/or
report review.
2 Columns and Walls Carried out by Civil/Structural Inspectors.
Check on steel reinforcement bars, dowels,
ties and links, splices, etc.
Column and walls dimensions and axes and
form work.
Check on masonry bearing block walls.
For steel structures, check framing and
connection details.
3 Concrete Slabs and Carried out by Civil/Structural Inspectors.
beams at each Floor Check on reinforcement steel bars, against
Level Municipality approved drawings, prior to
pouring concrete.
Checks on general preparatory works
related to concrete cast.
For steel structures, check framing and
connection details.
4 Backfilling Carried out by Drainage and/or Civil
(Limited to Backfilling of Inspector.
Underground Utilities of Checks on concerned works, against
Public Concern) Municipality approved drawings, prior to
covering underground utilities.
Checks on general works for connection to
main sewer line.
5 Infrastructure Carried out by Civil/Structural Inspectors
(Limited to locations part Checks against Municipality approved
of the Public Domain) drawings
Might cover items such as interlocking tiles
for walkways, asphalt roads and pavement,
lighting posts, etc.
Might be carried out at any stage of
construction
Checks on general preparatory works
related to these works

IN-01 Page 2 of 4
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


MUNICIPAL INSPECTION PROCESS
Document No IN-01 Rev. 0 Date 9/21/2006

Serial Construction Activity


Remarks
No. Hold Points
5 General (Health and Carried out by Municipality Inspectors
Safety) These are in general excluding specific
technical inspections; they rather focus on
compliance with applicable local rules and
regulations, cleanliness of site, issues
related to public safety, etc.
Typical outcome, if any, is a Violation
Notice.
6 Final Inspection Carried out by Municipality Inspectors /
Engineers, belonging to different disciplines
(e.g., civil, electrical, mechanical, etc.)
Covers visual inspection, document review
(e.g., reports issued by Special Inspectors),
accessibility to handicapped persons,
energy conservation essentials, etc.

5.0 INSPECTION REPORTS FROM MUNICIPALITY

When a municipal inspector visits a job site an inspection report (FIN-001) will be
generated. If the inspection is cancelled, the BPD inspector will indicate that it was
cancelled and by whom. The inspection report is a two-part carbon form, so that the
inspector can leave one copy with the superintendent and sends one copy back to
the BPD office.

If inspections result in a written request by the inspector to make corrective


measures on the job site, then it is the responsibility of the contractor to take
corrective actions and schedule for a re-inspection for that particular hold point. the
inspector will clearly indicate the nature of the problem and what is expected to be
done for a correction.

6.0 STOP WORK NOTICES

In case the contractor has created an unsafe condition as per ADM HSE rules and
regulations on the project, or is not co-operating with the inspection department, a
stop work order will be issued. This will terminate all work at the job site and may be
enforced by local police. This is an extreme step and can not happen without the
approval of the Director of the Building Permits Directorate.

7.0 FINAL INSPECTIONS BY MUNICIPALITY

Upon completion of all the work on a project the contractor can call for a final
inspection to be done by the BPD. After having finals by all other authorities. This
inspection can generally be scheduled within five (2) working days.
IN-01 Page 3 of 4
ABU DHABI MUNICIPALITY

BUILDING PERMITS DIRECTORATE


MUNICIPAL INSPECTION PROCESS
Document No IN-01 Rev. 0 Date 9/21/2006

If the project is not yet ready for a final a correction list will be created on the
Inspection Report form (FIN-001) and a copy will be given to the contractor. A re-
inspection will be performed upon compliance with inspector's correction report.

8.0 CODES AND STANDARDS

Refer to bulletin DCS-06 for a list of recommended codes and standards, which form
the basis of Municipality inspections, in addition to approved construction drawings.

9.0 SAFE ACCESS TO SITE

The Contractor shall ensure safe access to the Municipality Engineer on site. The
inspector may reject to carry out any inspection if deemed lacking sufficient safety
measures. In such a case, the visit will be accounted for in the inspection log. The
Contractor will then be asked to resubmit a second request for inspection.

END OF PROCEDURE

IN-01 Page 4 of 4
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
BUILDING COMPLETION CERTIFICATE
Document No BCC-01 Rev. Date 9/21/2006

1.0 INTRODUCTION

Prior to occupying any new building or any renovated or remodeled portion of an


existing structure, the owner / applicant must obtain a Building Completion
Certificate for the subject space.

2.0 PERMIT ON FILE WITH THE BUILDING PERMITS DIRECTORATE

This process assumes that the applicant has a valid permit from the Building Permits
Directorate which has not expired. If either of these conditions does not apply, the
applicant should meet with the Building Permits Directorate and obtain or renew a
building permit. A copy of this permit must accompany a certificate of occupancy.

3.0 WHAT MUST BE COMPLETED BEFORE FILING FOR A CERTIFICATE OF


OCCUPANCY

All interior and exterior work of buildings, including life-safety systems, exiting
components, ventilation, sanitation, habitability, occupancy and accessibility;
completed electrical, plumbing and mechanical systems, including roof-mounted
equipment and site hook-ups.

All specialty work provided by special inspection agencies, including soils,


excavation, fireproofing, steel and concrete and final letters from associated
agencies must be completed and on file with the Building Permits Directorate office;
all deferred submittal items must be completed and on file with the office, including
manufactured roof/floor trusses, stairs, elevators, etc. The Building Inspector will
determine whether all phases of the building systems are ready to be signed off.

4.0 FINAL INSPECTIONS BY BUILDING PERMITS DIRECTORATE

Prior to applying for a Certificate of Occupancy, the applicant should pass a final
inspection on the project. Upon successful completion of the final inspection, the
applicant can apply to the Building Permits Directorate for a Certificate of
Occupancy.

5.0 APPLY FOR THE COMPLETION CERTIFICATE

Please complete the application form for a certificate of completion, obtained from
the Building Permits Directorate and submit same to the Building Permits
Directorate, along with a copy of the successful final inspection noted on the project
inspection card. Any approval letters from other authorities (this varies by project
type) should also accompany your application.

_________________________________________________________________
BCC-01 Page 1 of 2
ABU DHABI MUNICIPALITY
BUILDING PERMITS DIRECTORATE
BUILDING COMPLETION CERTIFICATE
Document No BCC-01 Rev. Date 9/21/2006

6.0 APPROVALS BY OTHER AUTHORITIES

Depending on the type of project you are building various agencies will need to sign
off on your project before you can obtain from the Building Permits Directorate. Your
project coordinator can assist you with a list of agencies as follow:

1. Civil Defense
2. ADDC Water
3. ADDC Electricity
4. ADSSC
5. Civil Aviation
6. Adnoc
7. Etisalat

7.0 BUILDING COMPLETION CERTIFICATE

A sample of a certificate of occupancy is provided in the manual as form (FM-007).

8.0 TEMPORARY BUILDING COMPLETION CERTIFICATE

Temporary Building Completion Certificates are sometimes issued when certain


phases of a project are completed. Hence, it permits the tenants to occupy portions
of the project that has been completed.

Sign off approval for the whole project is still required.

As is the case of a building permit, the temporary Building Completion Certificate


has an expiration date. If the temporary Building Completion Certificate is allowed to
expire, a notice of violation may be issued to the permit holder.

END OF PROCEDURE

_________________________________________________________________
BCC-01 Page 2 of 2

Você também pode gostar