HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/HDL
From :I Gede Andi Dipayadnya
Date / Time :01 January 2009
To :Rinaldi
CC : Mr. Entjo S./Mr. Sentot H.

I. HSE Matters

NIL

II. Work In progress and Today Activities

Item 80168/C
Replace 12 Corroded Oil Line from M-310 to V-460
Status: Scaffolding erection still in progress, planning to be completed in 3
days. Theres no activity on 1st January 2009.
Remaining: After scaffolding completed continued with stringing pipe
spool, fit up, double joint, radiography inspection, and tie in (after spading
and flushing).
Notes: Due to revision, 1 pcs spool still in fabrication progress. TOP for this
item not yet received from CPA/PRD/PRO.
Time of Activity: 27 November until now.

III. Main Events on the Period.

Item 80169/C
Replace 12 Corroded Oil Line From M-319 to V-470
Status: The job was completed on 27 December 2008. Vessel already put
on services on 25 December 2008, then continued with top coat painting
due to lack thickness of line pipe as per INS recommendation.
Remaining: NIL
Time of Activity: 17-27 November 2008
Item 80255/C
Replace Heavy Corroded 10 Spool Gas Outlet V-450
Status: Hot bolting started on 27 December 2008, all bolts and nuts
already in severe corrosion condition. 2 pcs spool at upstream and
downstream of PCV-450 already replaced, and then vessel put on service
again on 31 December 2008 (21.30 LT) after leak test completed.
Remaining: Replace 3 pcs existing U-bolt
Time of activity: Started on 27 December 2008

IV. High Priority Job to be done in forthcoming days


70205/C
Process P/F, 1 Air Instrument Spools Corroded Section replacement
80079/C
M-310 Lower Oil Recovery Line Corroded Section Replacement
80472/C
M-310 Oil Recovery Inlet to V-230 Corroded Section Replacement

V. Pending Job and to be solved

- 80168/C
Replacement 12 Corroded Oil Line From M-310 to V-460 Separator

VI. Miscellaneous Items

- Contractors crew under PT. KRS, foreman: Mr. Gusrianto


- LCT. Teluk Bontang (MOP still valid until 05 January 2009)
VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Rinaldi )