HANDOVER NOTES

Site / Place of Handover : Handil


Department / Service : CST/OPB/HDL
From :I Gede Andi Dipayadnya
Date / Time :08 Sep 2011
To : Agus DL
CC : Mr. Sentot H./ Mr. Sri Widadi

I. HSE Matters

NIL

II. Work In progress and Today Activities


Item. 11521C
Spool modification of 4 jetting line of V-450 and leaking valve replacement
Status:
Job remaining
- De-spading activity
- Leak test
- Touch up painting
- Dismantle scaffolding
The job will be completed today.

Item. 11599C
Assist for Intelligent pigging HL-HLB
Status:
- The job started today, after completion of job at V-450 area
- Before starting the job, please register work permit to Rigs Company Man

III. Main Events on the Period.

Item. 11624C
Install operating access for 2 valve at new API area
Status:
Completed

Item. 11622C
Scaffolding job to assist CPA/INS for inspection at HEOR area
Status:
Completed

Item. 11584C
Scaffolding job to assist CPA/INS for inspection of leg pile at CEB area
Status:
Completed

Item. 11650C
Internal repair and nozzle replacement of T-605, oily water sump tank
Status:
- Internal repair and nozzle replacement of T-605 already completed
- Remaining job is de-spading activity (3 ea), waiting for curing time as per
recommendation from CST/PAINT. The job could be done around 7 th October 2011.

Item. 11860C
Replacement of PSV. 8861 at LEX area
Status:
Completed

Item. 11679C
Scaffolding job to assist CPA/INS for inspection of air cooler A-5030 at
HEOR
Status:
Completed

Item. 11633C
Replacement of 1 corroded inergen line at AEB area
Status:
Completed

Item. 11634C
Replacement of CO2 line and install pipe support at TEG-125 CEB area
Status:
Completed
Item. 11621C
Scaffolding job to assist CPA/INS for inspection of TIK 1-1110 at HGL
Status:
Completed

Item. 11617H
Replacement 6 spool header at HM 02 Manifold
Status:
- Hot bolting completed
- Material already loaded at LCT. Daya Karya
- The job will be done when HGL shutdown (to avoid major shortfall)

Item. 11644C
Replacement of CO2 line and install additional pipe support at LEX area
Status:
Completed

Item. 11643C
Replacement 1 CO2 line at HP 1 area (lower deck)
Status:
- Need for drawing revision and additional material
- This job item status: HOLD

Item. 11861C
Replacement of PSV. 8293 at HP 2 area
Status:
- This job can not be done due to passing of up stream valve of PSV. 8293.
- Waiting for notification to replace the passing valve (3 #600 ball valve)

IV. High Priority Job to be done in forthcoming days


Item. 80124C
Internal repair of V-5040
Item. 11253C
Several corroded additional point repair
Item. 11179C
Corroded section repair V-5040 to flare

Item. 11194C
Replacement 3 MP condensate drain piping
V. Pending Job and to be solved

NIL

VI. Miscellaneous Items

- Contractors team under PT. Meindo, Foreman: Sukasmono


- MOP LCT. Daya Karya will be valid until 08 October 2011

VII. Signature of Leaving Personnel Signature of Incoming Personnel

( I Gede Andi Dipayadnya ) ( Agus DL )