1.-An API certificate for an authorized pressure vessel inspector is valid for _______ years
from its date of issuance.
2
7
2.-If a conflict exists between the ASME code and API 510 for a vessel that has been placed in
service, the requirements of
The owner/used will decide which code takes precedence
A. The API 510 inspector will dictate which code takes precedence.
Pressure vessel in an oil refinery, vol. 4 cu. Ft., & operates at 70 psig and 70F
4.-Which of the following should not be considered alterations per API 510?
Replacement of a 6 reinforced nozzle with a 12 reinforced nozzle
All of the above should be considered alterations in accordance with API 510
5.-A 12 in. nozzle is being installed in a vessel where the largest existing opening is 10 in. This
is considered
A repair
An alteration
A rerating
A maintenance activity
6.-Per API 510 a repair and or alteration can be performed:
Only by the owner/user of the equipment
-4, 100
-4, 120
None of the above
8.-The primary reason for inspection is:
To determine the physical condition of the vessel and to determine the type, rate and
causes of deterioration
Because it is mandated by law.
Visual
Radiographic
Liquid penetrant
11.-Pressure relief valves shall be tested and repaired by repair organizations experienced in
valve maintenance. Each repair organization shall have:
A large enough shop to perform the required work.
Licensed Engineer
13.-Under what conditions is an internal field inspection of a newly installed pressure vessel
waived?
The contractor installing the vessel assures the owner-user that the vessel is satisfactory
for its intended service.
A manufacturers date report assuring the vessel is satisfactory for its intended service is
available.
The owner-user assures the inspector that the vessel is satisfactory for its intended
service.
Manufacturer orally assures the owner-user that the vessel is satisfactory for its
intended service.
14.-For a corroded area of considerable size in which the circumferential stresses govern, the
least thickness along the most critical element of the area may be averaged over a length not
exceeding the following for vessels with inside diameters less than or
1/4 the vessel diameter or 5 inches, whichever is less.
1000
5000
10000
16.-The remaining life of a vessel is calculated using which of the following formulas? (b API
510 6.4)
tactual-tminimum/corrosion allowance
tactual-trequired/corrosion rate
tprevious-tactual/corrosion rate
tprevious-tminimum/corrosion allowance
17.-Widely scattered pits may be ignored per API 510 as long as:
The sum of their dimensions along any straight line within the circle does not exceed
2.5 l inches
No pit depth is greater than one-half the vessel wall thickness exclusive of the
corrosion allowance
The total area of pits does not exceed 8 square inches within any 9 inch Dia. circle.
2 years
3 years
1 year
21.-The period between internal or on stream inspections shall not exceed one-half the
estimated remaining life of the vessel based on corrosion rate or _________ years whichever
is less.
5
4
15
10
22.-RBI assessments must be reviewed and approved at _________ year intervals.
5
RL
10
23.-Scattered pits in a pressure vessel may be temporarily repaired using?
Concrete
Metallic linings
Both A & B
Calculated temperature
Operating temperature
.729 inches
.745 inches
.645 inches
27.-In the above question (), what is the total required thickness of the weld overlay repair in
order to meet the five year run and maintain a CA of .125 inches, if the base metal is 70 KSI
tensile strength and the weld metal is 60 KSI tensile strength?
.285 inches
.245 inches
.145 inches
.229 inches
28.-An existing pressure vessel is inspected on a giver year and found to be .500 thick in both
the shell and heads. The next inspection is conducted three (3) years later, and the thickness
of the shell and heads is noted to be .325 (uniform). The vessels
2.4 years Remaining Life / 2 years Internal Inspection Interval
0.035
0.025
0.0025
30.-A vessel is ultrasonically inspected when it is new and could in June 1987 and found to be
.800 thick in the shell. The next inspection is performed in June 1995 and the vessel shell
thickness is found to be .600 thick. The vessel I.D. is 27! And it is
June 97
January 99
March 97
June 98
31.-The corrosion rate for a vessel is known to be 0.004 inches per year based on a five (5)
year inspection interval. Which of the following cannot be used to exempt the vessel from
internal inspection if it remains in the same service?
No questionable condition is found on external inspection.
The vessel is not considered to be subject to environmental cracking or hydrogen
damage from the fluid being handled
The operating temperature does not exceed the lower temperature limits for the creep
rupture range of the vessel material.
The vessel is strip lined.
32.-A pressure vessel has a measured shell thickness of .750 inches. The minimum thickness
required is .500 inches and the corrosion rate is .065 inches/year. The next inspection is due
in?
3.8 years
1.9 years
2 years
4 years
33.-A probable corrosion rate for a new vessel cannot be determined by corrosion rates of
known similar services or owner/user experience. On stream determinations must be made
after approximately _________ of service.
30 days
1000 hours
500 hours
3 months
34.-The definition of tminimum is?
Minimum allowable thickness in inches for a given location or component
A. .021 inches/year
A. .0021 inches/year
A. .005 inches/year
36.-Using the information and answer obtained in the before question, if the minimum required
thickness is .400 inches, what is the remaining life (years) of this vessel?
9.76 years
1.8 years
5 years
15 years
37.-Local PWHT may be substituted for 360 degree banding on local repairs if:
A preheat of 200 Deg. F is maintained during the welding repair.
Both B & C
38.-A rerating nameplate must include:
The name of the organization responsible for the rerate.
0.035
0.35
0.025
40.-The pressure vessel engineer must additionally consider which of the following when
welding P-No. 5 stainless cladding which is in hydrogen service at elevated temperatures?
Weld rod diameter
Effects of temper embrittlement
A rerating
Owner/User
Maintenance manager
43.-The rerating of a pressure vessel will be considered complete when the authorized
pressure vessel inspector
Signs the hydrostatic test chart.
30
20
40
45.-An owner-user organization is responsible for developing, documenting, implementing,
executing and assessing pressure vessel inspection systems and inspection procedures that
will meet the requirements of API 510. These systems and procedures will be:
Kept as a standard procedure
Kept in-hand
350
200
250
47.-In accordance with API 510, fillet welded lap patches may be used:
Only on vessels constructed of P-1 materials
3 years
1 year
2 years