Você está na página 1de 3

Republic of the Philippines Supreme Court Manila Third Division engaged the services of respondent Rosal Infrustructure Builders

Gentlemen: Quoted hereunder, for your information, is a resolution of ( RIB ) as sub-contractor, executing a contract for the
the Third Division of this Court dated construction of Check Dam No. 1 along Sadyo River, Binga, Itogon,
Benguet. In this contract the parties agreed to submit disputes arising
September 30, 1996 G.R. No. 125706 CHINA CHANG JIANG therefrom to arbitration before the Arbitration of the International
ENERGY CORPORATION (PHILIPPINES) versus ROSAL Chamber of Commerce.
INFRASTRUCTURE BUILDERS, represented by its General Manager,
ALBERTO S. SURLA, CONSTRUCTION INDUSTRY ARBITRATION When a dispute arose between the parties, respondent RIB filed a
COMMISSION, PRUDENCIO F. BARANDA, and the COURT OF APPEALS. complaint before respondent CIAC for arbitration. Petitioner filed its
answer with compulsory counterclaim and raised therein the issue of
lack of jurisdiction on the part of CIAC. In its order dated August 1,
Petitioner questions the validity of Construction Industry Arbitration 1995, respondent CIAC considered the question of jurisdiction merely as
Commission (CIAC) Resolution 3-93 amending Section 1, Article III of a special defense which can be included as part of the issues of the
CIAC Rules of Procedure Governing Construction Arbitration Terms of Reference. Petitioner filed a motion for reconsideration which
promulgated by the CIAC pursuant to its rule-making power granted was denied by respondent CIAC in its order dated October 4, 1995.
under Section 21 of Executive Order No. 1008, which pertinently Petitioner raised the sole issue of lack of jurisdiction in a petition for
provides as follows: certiorari and prohibition, with a prayer for a temporary restraining order
Article III and writ of preliminary injunction with respondent Court of Appeals. In a
decision dated February 27, 1996, respondent court dismissed the
Effect of the Agreement to Arbitrate petition. Petitioner filed a motion for reconsideration but the same was
denied by respondent court in a resolution dated July 22, 1996.
Section 1. Submission to CIAC Jurisdiction An arbitration clause in a
construction contract or a submission to arbitration of a construction Hence, the instant petition.
dispute shall be deemed an agreement to submit an existing or future
controversy to the CIAC jurisdiction, not withstanding the reference to a We find no meritorious basis in the petition to sustain a reversal of the
different arbitral institution or arbitral body in such contract or submission ruling of respondent court upholding the jurisdiction of the CIAC in this
case, Executive Order No. 1008, otherwise known as the
Construction Industry Arbitration Law defines the jurisdiction of
the CIAC thusly:

Petitioner is the operator of the Binga Hydroelectric Plant in Itogon, Section 4. Jurisdiciton The CIAC shall have original and exclusive
Benguet, under a Rehabilitate Operate and Leaseback Contract ( ROL jurisdiction over disputes arising from, or connected with contracts entered
Contract ) with the National Power Corporation whereby it is into by parties involved in construction in the Philippines, whether the
mandated to engage in the rehabilitation of the power plant, including dispute arises before or after the completion of the contract, or after the
the construction of check dams. On February 21, 1994, petitioner abandonment or breach thereof. These disputes may involve government
or private contracts. For the Board to acquire jurisdiction, the parties to a dispute shall be deemed an agreement to submit an existing or future
dispute must agree to submit the same to voluntary arbitration controversy to CIAC jurisdiction, notwithstanding the reference to a
different arbitral institution or arbitral body in such contract or submission.
Petitioner contends that this Court had already interpreted this When a contract contains a clause for the submission of a future
particular provision of the law in the case of Tesco Services Incorporated controversy to arbitration, it is not necessary for the parties to enter into a
v. Vera, 209 SCRA 440 (1994) to mean that respondent CIAC can acquire submission agreement before the claimant may invoke the jurisdiction of
jurisdiction over the dispute only when the parties have agreed to submit the CIAC.
their dispute to voluntary arbitration before respondent CIAC itself.
Petitioner submits that CIAC Resolution No. 3-93 is null and void
This contention is erroneous. insofar as it prohibits the parties from submitting the dispute for
The ruling of this court in the above-cited Tesco case must be read in arbitration to an arbitral body other than respondent CIAC because, so it
light of facts obtaining and the governing law in relation to the applicable is contended, it goes beyond the basic law it seeks to implement, E.O.
rules in force during that period. When we ruled in Tesco that CIAC has No. 1008 (Rollo, p.26).
no jurisdiction over the dispute, we were applying the prevailing rules of We do not agree.
procedure duly promulgated by the CIAC pursuant to its rule making
power provided in Section 21 of its enabling law. Section 1 of the said A mere cursory reading of Section 1, Article III, of the CIAC Rules, as
rules specifically required that a party to a construction contract wishing amended by Resolution No. 3-93 reveals no restriction whatsoever on
to have recourse to arbitration by the CIAC shall submit its Request for any party from submitting a dispute for arbitration to an arbitral body
Arbitration in sufficient copies to the Secretariat of the CIAC. Since the other than the CIAC. On the contrary, the new rule, as amended merely
Court found that there was no Request for Arbitration filed with the implements the letter and the spirit of its enabling law, E.O. No. 1008,
Secretariat of the CIAC because private respondent LAROSA in the case which vests jurisdiction upon the CIAC in the following manner
filed a petition for injunction with the Regional Trial Court of Quezon
City, the inevitable conclusion had to be that CIAC did not acquire : Section 4. Jurisdiction The CIAC shall have original and exclusive
jurisdiction over the disputes arising from the sub-contract agreement jurisdiction over disputes arising from, or connected with, contracts
between TESCO and LAROSA in said case. Accordingly, this Court entered into by parties involved in construction in the Philippines, whether
sustained the jurisdiction of the regular court in that particular instance. the dispute arises before or after the completion of the contract, or after the
The abandonment or breach thereof. These disputes may involve government
or private contract. For the Board to acquire jurisdiction, the parties to a
Tesco ruling is not binding in the case at bench. dispute must agree to submit the same to voluntary arbitration
(Emphasis supplied.)
Significantly, the 1998 CIAC rules of procedure before the CIAC which
were applied by this Court in Tesco had been duly amended by CIAC What the law merely requires for a particular construction
resolutions No. 2-91 and 3-93 to now read as follows: contract to fall within the jurisdiction of CIAC is for the parties to agree
to submit the same to voluntary arbitration. Unlike in the original
Section 1. Submission to CIAC Jurisdiction An arbitration clause in a version of Section 1, as applied in the Tesco case, the law does not
construction contract or a submission to arbitration of a construction
mention that the parties should agree to submit disputes arising from Now that Section 1, Article III, as amended, is submitted to test in
their agreement specifically to the CIAC for the latter to acquire the present petition, we rule to uphold its validity with full certainty.
jurisdiction over such disputes. Rather, it is plain and clear that as long However, this should not be understood to mean that the parties may no
s the parties agree to submit to voluntary arbitration, regardless of what longer stipulate to submit their disputes to a different forum or arbitral
forum they may choose, their agreement will fall within the jurisdiction of boy. Parties may continue to stipulate as regards their preferred forum in
the CIAC, such that, even if they specifically choose another forum, the case of voluntary arbitration, but in so doing, they may not divest the
parties will not be precluded from electing to submit their dispute before CIAC of jurisdiction as provided by law. Under the elementary principle
the CIAC because this right has been vested upon each party by law, i.e. on the law on contracts that laws obtaining in a jurisdiction form part of
E.O. No. 1008. all agreements, when the law provides that the Board acquires
jurisdiction when the parties to the contract agree to submit the same to
This Court s pronouncements in the case of Hi-Precision Steel voluntary arbitration, the law in effect, automatically gives the parties an
Center, Inc. vs. Lim Kim Steel Builders, Inc. 228 SCRA 397 (1993) find alternative forum before whom they may submit their disputes. That
relevance, to wit: alternative forum is the CIAC. This, to the mind of the Court, is the real
Voluntary arbitration involves the reference of a dispute to an spirit of E.O. No. 1008, as implemented by Section 1, Article III of the
impartial body, the members of which are chosen by the parties CIAC Rules.
themselves which parties freely consent in advance to abide by the The herein interpretation is not, in its strict sense, a reversal of a
arbitral award issued after proceedings where both parties had the previous pronouncement in the Tesco case necessitating a ruling by the
opportunity to be heard. The basic objective is to provide a speedy and Court En Banc considering the variance in the factual circumstances, as
inexpensive method of settling disputes by allowing the parties to avoid well as the governing procedural rules applicable to the two distinct
the formalities, delay, expenses and aggravation which commonly cases.
accompany ordinary litigation, especially litigation which goes through
the entire hierarchy of courts. Executive Order No. 1008 created an The Court also takes this opportunity to dispel any mistaken
arbitration facility to which the construction industry in the Philippines notion that substantial rights were created or modified by the CIAC in its
can have recourse. The executive order was enacted to encourage the Resolution No. 2-91 and 3-93, as regards matters of jurisdiction. We
early and expeditious settlement of disputes in the construction would also like to clarify that such rights were vested as early as of the
industry, a public policy the implementation of which is necessary and time E.O. No. 1008 which took effect February 1985. Howeer, said
important for the realization of national development goals. provision had not been properly implemented in the original version of
Section 1 of the CIAC Rules. Thus, amendments through Resolutions No.
These noble objectives are what Resolutions No. 2-91 and 3-93 2-91 and 3-93 were called for.
seek to implement which Section 1, prior to its amendment, effectively
curtailed. Rather unfortunately, this particular provision of the CIAC WHEREFORE, premises considered, the instant petition is hereby
Rules was not the one at issue in the Tesco case. Thus, no ruling on that DISMISSED and the appealed decision is hereby AFFIRMED. SO
point could be passed upon. ORDERED.

Você também pode gostar