MINUTES OF MEETING
Introduction:
This meeting will be held weekly to ensure that CIS HSE Manual and
associated procedures are adhered to.
Imam Hasan
Contractor CIS
Fidel Fernandez
TES-ISS-MOM-HSE-0002
Duba Green ISCCPP Project
MINUTES OF MEETING
AGENDA
3. Environmental Audit.
4. Site Security.
6. Emergency Response.
Any new Items for Agenda (Any other will be added during the meeting)
TES-ISS-MOM-HSE-0002
Duba Green ISCCPP Project
MINUTES OF MEETING
Reply/Responsibility Date of
Agenda Points Discussion
Sr. No Completion
Management tracker will now be replaced with A Dawson TR
1 Management Tracker these minutes of meeting to track and close out Closed
HSE Management issues.
CIS do not have the following HSE Personnel on Fidel CIS
power project site:
Deputy HSE To provide dates for the
Environmental In Charge mobilization of each the missing
Lifting/Rigging Supervisor CIS HSE personnel.
Azzam HSE In Charge
5 x HSE Officers (Power plant)
CIS HSE Manning
2 28-11-16
Levels
In addition there are also HSE personnel
missing from the substation project which may
affect the HSE manning levels on the power
project due to transfer coverage:
SSEM HSE Manager (Substation)
2 x HSE officers (Substation)
A Dawson TR
Environmental audit result was 3.2 out of a
SEC Environmental To email SEC Safety Manager Actioned
3 maximum 5. Audit report has not been shared
HSE Audit requesting a copy of the audit 21-11-2016
with Tractebel or CIS.
report.
Fidel CIS
To confirm the date and
There are many issues with the provision of
location of the meeting
4 Site Security security on site; these have been raised in the 28-11-16
arranged with CIS Senior
weekly management meeting.
Management and their Security
Contractor.
The medical review report from International A Dawson to transmit the Done.
SOS is to be transmitted by Tractebel to CIS. report to CIS.
Project Medical
5
Facilities CIS will review the recommendations within Fidel CIS to report back on
section 3 of the report and inform Tractebel actions to be taken. 05-12-2016
which actions will be taken.
CIS currently dont have a temporary fire truck Fidel CIS to report when the 28-11-16
for the construction site. temporary fire truck will be
delivered to site.
6 Emergency Response
CIS have not performed any evacuation drill as CIS are to arrange an 28-11-16
required by the contract. evacuation drill as soon as is
practical, date to be confirmed
TES-ISS-MOM-HSE-0002
Duba Green ISCCPP Project
MINUTES OF MEETING
by Fidel.
CIS now have a scaffolding inspector on site, CIS will provide a list of all CIS
there still some poor scaffolding practices being and subcontractor scaffolding
7 Scaffolding 28-11-16
observed by Tractebel HSE. supervision.
TES-ISS-MOM-HSE-0002
Duba Green ISCCPP Project
MINUTES OF MEETING
NEW ITEMS
CIS is requested to close SOR in
SOR Closed Out
15 CIS respond slowly to close SOR raised by OE timely manner and summit Action
status
hard copy for OE Acceptance.
Waste Staging Areas:
Requested CIS to ensure that proper barricade CIS HSE
16. Waste Managements and signage are visible Action
And waste removal onsite is being done in
regular basis to avoid accumulation.
CIS is requested to prepare site HSE documents CIS HSE
and Site HSE Facilities and ensure that all HSE
17. Internal Audits Action
requirement s and standard followed on site
OE will issue a guideline for the documentation.
TES-ISS-MOM-HSE-0002