m Lps. 596.18
Act: Columna, 0.30mx0.30m, Acero:
4#5 y 2#4, anillos de 3/8@20cm
Materiales Total: Lps. 475.77
N Nombre Material U Rend. Precio U. Subtotal
1 Concreto 3000 psi m^3 0.09 2265.15 203.86
2 Varilla #3 lisa ln 0.13 90.4 11.75
3 Varilla #4 ln 0.22 182.16 40.08
4 Varilla #5 ln 0.44 297.65 130.97
5 Alambre de Amarre lb 0.15 13.27 1.99
6 Madera % 10% 43.21
7 Clavos u 6.00 0.11 0.66
8 Aceite % 10% 43.25
Mano de Obra Total: Lps. 92.02
N Nombre U Rend. Precio U. Subtotal
1 Albail Jr 0.12 363.64 43.64
2 Peon Jr 0.12 90.00 10.80
3 Armador Jr 0.118 227.00 26.79
4 Ayudante Jr 0.12 90.00 10.80
Herramientas Total: Lps. 28.39
N Nombre U Rend. Precio U. Subtotal
1 Herramientas menores % 5% 28.39
Ficha de Costo Unitario
m^2 Total: Lps. 315.49
Act: Castillo
Materiales Total: 269.36
N Nombre Material U Rend. Precio U. Subtotal
1 Concreto m^3 0.03 2,265.10 67.95
2 Varilla #4 l 0.444 182.16 80.87
3 Varilla #3 l 0.61 120.00 73.20
4 Madera m 10% 24.42
5 Clavos u 6.00 0.11 0.66
6 Aceite 10% 22.26
Mano de Obra Total: Lps. 31.11
N Nombre Material U Rend. Precio U. Subtotal
1 Albail Jr 0.05 363.64 18.18
2 Peon Jr 0.05 90.00 4.51
3 Armador Jr 0.021 227.00 4.73
4 Ayudante Jr 0.041 90.00 3.69
Herramientas Total: Lps.15.90
N Nombre Material U Rend. Precio U. Subtotal
1 Herramientas menores % 5% 15.02
Ficha de Costo Unitario
m^3 Total: Lps. 322.18
Act: Jambas
Materiales Total: Lps. 275.73
N Nombre Material U Rend. Precio U. Subtotal
1 Varilla #4 ln 0.444 182.16 80.87
2 Varilla#3 ln 0.61 120.00 73.20
3 Alambre de amarre lb 2.1 13.27 27.86
4 Concreto m^3 0.02 2265.10 45.30
5 Madera m 10% 25.06
6 Clavos u 6.00 0.11 0.66
7 Aceite 10% 22.78
Mano de Obra Total: Lps. 31.11
N Nombre U Rend. Precio U. Subtotal
1 Albail Jr 0.05 363.64 18.18
2 Armador Jr 0.021 227.00 4.73
3 Peon Jr 0.05 90.00 4.51
4 Ayudante Jr 0.041 90.00 3.69
Herramientas Total: Lps. 14.64
N Nombre U Rend. Precio U. Subtotal
1 Herramientas menores % 5% 15.34
Ficha de Costo Unitario
m^3 Total: Lps. 338.52
Act: Cargador
Materiales Total: 292.77
N Nombre Material U Rend. Precio U. Subtotal
1 Varilla #4 l 0.444 182.16 80.87
2 Varilla#3 l 0.61 120.00 73.20
3 Alambre de amarre lb 2.10 13.27 27.86
4 Concreto m^3 0.02 2265.10 45.30
5 Madera m 19.13 19.13 38.27
6 Clavos u 6.00 0.11 0.66
7 Aceite 10% 26.61
Mano de Obra Total: Lps.31.11
N Nombre U Rend. Precio U. Subtotal
1 Albail Jr 0.05 363.64 18.18
2 Armador Jr 0.021 227.00 4.73
3 Peon Jr 0.05 90.00 4.51
4 Ayudante Jr 0.041 90.00 3.69
Herramientas Total: Lps.14.64
N Nombre U Rend. Precio U. Subtotal
1 Herramientas menores % 5% 14.64
Ficha de Costo Unitario