Sl.
No.
Hydrotest
1 Blind Flanges, Fasteners, Gaskets, valves
2 Pipe quantity

Procurement
1 Expansion Bellow
2 Sleeve Coupling
3 SOFF flanges
4 Paint & thinner for site works
5 CP rod
6 BS& B Valves
7 Cashco Pilot operated PSV
8 Remaining structural fasteners
9 Remaining gaskets
10 Remaining fasteners for pressure parts
11 Eye bolts
12 Earting Boss fasteners
13 Split Pin_Rumaitha
14 Gaskets_Rumaitha DODSAL Spare parts

Protego Skimmer
1 GAD submission
2 Buoyancy Calulation submission
3 Revised delivey date of 12 weeks or less

Shand & Jurs Level Gauge


1 SS 316L Material Confirmation
2 Epoxy coating as per manufacturers standard also colour

Fameco
1 Shop panting payment
2 Garnet procurement & Mobilization

Engineering
1 SOFF flanges for K1 nozzle_T-2491 & 2492
2 Elevation confirmation for skimmer nozzle_T-2491 & 2492
3 Level gauge Data Sheet Rev. 1_T-5121, 5122, 0891 & 0892
4 DS for Valves, Hatches & FA
5 Cathodic pipe supports_T-5121, 5122, 2291 & 2292
6 Linear heat sensing support
7 Pipe support cleats drawings_all tanks
8 Shell plate layout drawing_T-0891 & 0892
9 Grating drawings to be released to Osais_T-2291 & 2292
10 Spiral stairway layout drawing to be corrected_T-2292
11 Approval for Shell plate & Shell Nozzle drawings to be expedited_T-2291 & 2292
12 Personnel protection drawings_T-0891, 0892, 2492 & 2492
13 Roof plate & Nozzle orientation drawings_T-0891 & 0892

Fabrication
1 Level Gauge Bottom Anchor Bar (Alloy 825)_T-0891 & 0892
2 Nozzle S1_T-0891 & 0892
3 Nozzle LG1 & LG2_T-0891 & 0892
4 Roof Pipe Supports_ T-0891 & 0892
5 G, G1 & G2 nozzles & supports_T-5121 & T-5122
6 External shell & roof pipe supports plates _T-5121 & 5122
7 Al Jazira handrail inspection_T-5121
8 Remaining SP3 Shell plates_T-5121
9 Re-fabrication of RP3 & RP4 roof plate_T-2491 & 2492
10 Roof rafter_T-2491 & 2492
11 External shell & Roof Pipe Supports plates _T-2491 & 2492
12 External shell & Roof Pipe Supports plates _T-2291 & 2292
13 TP1, A & F nozzle RF pads_T-2291 & 2292
14 Anchor Chair_T-2291 & 2292
15 Shell manways_T-2291 & 2292
16 Handrails to be sent for galanizing_T-2291 & 2292
17 Roof PF & Spiral Stairway Brackets_T-2291 & 2292
18 Painted nozzles & Payment_Fameco
19 Grating Inspection_Oasis Metal Industries
Handover Notes
Action By/ Remark
Focal Point

Thanga Kumar Mr. Jeffry will give initial quantity. please ask Mr. Tangakumar to varify
Mustafa To check the route and finalise the quantity

Mayilraj
Mayilraj
Nikhil
Nikhil (MRQ 362-058) Famceo to give correct quantity
Nikhil
Shibil LPO to be issued
Shibil/Mayilraj LPO to be issued after final quote
Shibil LPO 37119
Shibil LPO to be placed. MRQ No 362-075
Shibil LPO 37476
Shibil LPO 37458
Shibil LPO to be placed. MRQ No 8222
Krishna to collect from Press Bolt and to be handed over to Mr. Mustafa
Shibil to arrange for collection and dispatched to site ASAP.

Syed
Syed
Syed

Naushad Supplier to confirm


Naushad Supplier to confirm

Jano
Belvin

Mayilraj Shell nozzle dwg to be modified


Mayilraj Shell nozzle dwg & GAD to be updated
Nikhil To be resubmitted
Mayilraj/Nikhil To be resubmitted
Mayilraj Drawing to submitted
Mayilraj Drawing to submitted
Mayilraj To be resubmitted
Sundar External Pipe support base plate locations to be updated
Sundar Any change in roof nozzle orientation in T-2291 to be considered
Sundar
Mayilraj TP1, A & F nozzle RF pads size revised
Mayilraj To be resubmitted
To be resubmitted incorporating field changes & LG1 & LG2

Painted inside. IRN to be done at DXB WS

Payment to be done before collection


to be dispatched
RP4 &3 to be refabricated and sent to site after IRN

to be re-fabricated as per latest drawings


to be dispatched
to be dispatched

to be dispatched