Escolar Documentos
Profissional Documentos
Cultura Documentos
THE RESIDENCE OF
Mr.V.K.G BIMAL RANDIKA
* The tenderer is advised to visit the site of the proposed work, Note
as it is his responsibility to aseetain the Conditions,governing
access to the site, the external working space,storage area, etc.,
* A list of typical general items are stated above, the tenderer is Note
requested to price only the items that are affecting the contract
* The contractor shall be responsible for the safety of his own Note
material,plant and the likes located or stored on site
5 Allowing for supplying water for use during construction. Item 1.0 60,000.00
It shall be responsibility of the contractor to find the sources
of supply and make the internal arrangements and payment
for the consumption to authorities for 9 months
( connection charges will be be borne by the Owner)
6 Allow for supplying temporary electracity to site for the works Item 1.0 80,000.00
including internal arrangement and payment to authorities for
Page 2 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
9months. (connection charges will be borne by the Owner)
Page 3 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
B EXCAVATION AND EARTH WORKS
3 Earth filling within foundation & column bases in approved Cube 26.00 6,000.00
selected imported materials,0'-9" thick layers well rammed .
and consolidated
4 Allow for Anti-Termite treatment to ground floor area and 3'0" Sqr 18.0 3,500.00
beyond the proposed building. Rate shall include for drilling
and injecting the chemicals along the foundation & soaking
the soil in the floor area with the chemical by a specialist
contractor approved by the consultant.
Page 4 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
Page 5 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
C CONCRETE WORK
CONCRETE
UP TO DPC LEVEL
1 2" thick lean cement concrete ( Grade 15) screed for Sqr 2.0 9,500.00
under column footing and staircase footing
5 Concrete for 3" thick Ground floor slab on compacting Cube 0.75 49,000.00
earth
FORMWORK
UP TO DPC LEVEL
Page 6 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
REINFORCEMENT
UP TO DPC LEVEL
Page 7 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
Lintels
22 9" x 6" lintel with 2T 10 @ R6" Reinforcement with L.Ft 125.0 600.00
formwork
Page 8 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
D MASONRY WORK
UP TO DPC LEVEL
Rubble Work
2 9" thick brickwork in cement and sand 1:5 Sqr 9.0 32,000.00
3 6" thick brickwork in cement and sand 1:5 Sqr 8.0 25,000.00
4 4 1/2" thick brickwork in cement and sand 1:5 Sqr 5.0 26,840.00
Page 9 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
E ASPHALT WORK
Horizontal D.P.M
Tanking
Page 10 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
1 Supply and installation type D1, size 4'-0" x 8'-6" Single sash, Nr 1.0 95,000.00
Timber door with 3" x 4" hardwood timber frame complete as
per the detail drawing and specification.
2 Supply and installation type D2 size 3'-0" x 7'-0" Timber framed Nr 8.0 66,000.00
Single sash solid door
3 Supply and installation type D3 size 2'-6" x 7'-0" Timber framed Nr 4.0 58,000.00
Single sash solid door
4 Supply and installation type W1, size 6'-0" x 6'-6"timber frame, Nr 3.0 64,000.00
Glazed louvered window
5 Supply and installation type W2, size 4'-0" x 6'-6"timber frame, Nr 3.0 59,500.00
Glazed louvered window
Page 11 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
SANITARY FITTINGS
Sanitary fittings are include in the rate.
2 Low level closet with cistern "P" or "S" trap, plastic seat and
lidetc., and supported by m.s. brackets including all necessary
connection to working order.( Prime cost Rs. 30000) No 2.0 37,000.00
4 Chromium plated mixer shower fixed complete to working order. No 2.0 38,000.00
( Prime cost Rs. 29000)
5 Chromium plated towel rail fixed to wall with brackets No 2.0 5,000.00
( Prime cost Rs. 2500)
6 Soap tray fixed to wall.( Prime cost Rs. 1500) No 2.0 3,000.00
Page 12 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
7 2'-0"x 3'-0" mirror fixed to wall with timber frame work No 2.0 6,000.00
( Prime cost Rs. 3500)
8 Fixing of 6" x 6"x 6" concrete floor Gully complete with grating. No 4.0 2,500.00
( Prime cost Rs. 1000)
12 1" dia. P.V.C pipe to the overhead tank and from the overhead L.ft 11.0 280.00
tank, buried in floor and clipped to wall with necessary fittings
13 3/4' dia P.V.C pipes bedded or clipped to wall including - do L.ft 8.0 260.00
Drainage System
Sewer pipesin
Page 13 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
Waste Pipes
16 Vertical pipe 2" type 600 pipe Antisyphonic line with vent L.ft 25.0 500.00
18 Waste Manhole size 12" x 12"x 24" internally with 4" thick - No 2.0 15,000.00
concrete floor Gully complete with grating to complte with
all connections to working order
19 sewerage Manhole size 12" x 12"x 24" internally with 4" thk - No 2.0 15,000.00
concrete floor Gully complete with grating to complte with
all connections to working order
20 Supply & install hume pipe waste water pit size 3'0" dia,4'0" Item 1.0 35,000.00
deep internally with excavation ,9" thick brick walls
concrete cover slab 4" dia, P.V.C. pipe etc., complete
21 Supply & install hume pipe septic tank size 8'0"x3'0" dia., Item 1.0 55,000.00
internally with excavation 9" thick brick walls concrete
cover slab 4" dia. P.V.C.pipes ect, to complete
22 Supply & install hume pipe soakage pit size 3'0" dia, 4'0" deep Item 1.0 45,000.00
internally with excavation ,9" thick brick walls,concrete
cover slab, 4" dia. P.V.C. pipe etc., to complete
23 Double bowl stainless steel kitchen sink with chromium plated Item 1.0 16,000.00
pillar tap, rubber plug, chain waste etc., and supporting brick
works, 2" tk. RCC slab including all necessary connection to
working order.( Prime cost Rs.9000)
Page 14 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
Page 15 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
H FLOOR, WALL & CEILING FINISHES
FLOOR FINISHES
Rates for floor and wall tiles shall include for including laying
to the pattern and design shown in the approved tile layout
laying of sample areas for approval Note
2 Supply & lay selected 24" x 24" Non-slip Ceramic glazed floor
tiles with Tile and good quality ,approved colour and patten
bedded on the 1/2" thick 1:3 cement and sand screed.
The joints to be filled with tile grout match in living Sqr 4.0 48,000.00
3 Supply & lay selected 16" x 16" semi- gloss Ceramic tiles floor
tiles with good quality and approved manufacturer colour &
patten bedded on the 1/2" thick 1:3 cement & sand screed.
The joints to be filled with tile grout match in kitchen. Sqr 2.0 36,000.00
WALL FINISH
INTERNAL WORK
6 Plaster 16mm thick internal smooth plaster in cement and
sand 1:5 finished smooth with two coats of approved acrylic
filler or equivalent.(Filler coat will be measured with painting)
to Masonry walls/ RCC surface Sqr 12.0 8,500.00
8 Supply & lay selected 12" x 12" Porcelain polished wall tiles
approved colour and patten bedded on the 1/2" thick 1:3
cement and sand screed. The joints to be filled with tile grout Sqr 4.0 34,500.00
match to wall tiles
EXTERNAL WORK
Page 16 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
sand 1:5 finished smooth with two coats of approved acrylic
filler or equivalent.( Filler coat will be easured with painting)
to Masonry walls/ RCC surface Sqr 8.0 8,500.00
Page 17 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
10 Plastering 5/8" thick to reveals width not exceeding 6" in
walls with cement,lime and sand plaster finished smooth
neat with lime floating to reveals Lft 205.0 175.00
CEILING FINISH
WALL FINISH
EXTERNAL WORK
Page 18 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
I PAINTING WORK
GROUND LEVEL +1'-6" TO FIRST FLOOR LEVEL +12'-0"
EXTERNAL
1 Prepare and apply one primer under coat and two finishing coats of
weather proof paints to plinth Sqr 2.00 7,500.00
2 Prepare and apply one primer under coat and two finishing coats of
weather proof paints to walls Sqr 9.0 9,000.00
INTERNAL
3 Prepare and apply two coats of approved colour and emulsion paint
with primer undercoat to walls Sqr 13.0 9,000.00
4 Prepare and apply two coats of approved colour and emulsion paint
with primer undercoat to ceiling Sqr 12.0 9,500.00
Page 19 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
3 4" x 4" Colour bond Zn/Al Rain water square down pipe .47mm
thick clipped with brass screws to plastic plugs built in to wall
at at 6'-0" centres approx. Rate to include for Zn/Al bends,
Nozzles( square & Round),brackets, gutter box swan necks,
shoes, etc., Lft 45.0 380.00
Page 20 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
K ELECTRICAL INSTALLATION
1 Allow a sum for cable from meter to main panel Item 1.0 60,000.00
2 Allow for main wiring from main panel to sub panels Item 1.0 48,000.00
4 Supply and install Moulded Case Circit beaker (MCCB) system 30V
as per detail drawing and specification and all connection Item 1.0 30,000.00
working order
Page 21 of 68
NO DESCRIPTION OF WORK UNIT QTY RATE
14 Exterior Light Nr 7.0 3,500.00
* Rates shall include for light fittings supply and fixing all
complete to working order including necessary accessories Note
Note:- The Samples must be approved by the Architect and Item in the Bill Of Quantities can be deleted or Added a
per requested by the client.
Page 22 of 68
ATE FOR
THE RESIDENCE OF
G BIMAL RANDIKA
NDIK', WALASGALA
AMOUNT
30,000.00
20,000.00
25,000.00
35,000.00
60,000.00
80,000.00
Page 23 of 68
AMOUNT
250,000.00
Page 24 of 68
AMOUNT
25,000.00
20,000.00
156,000.00
63,000.00
Page 25 of 68
AMOUNT
264,000.00
Page 26 of 68
AMOUNT
19,000.00
33,250.00
49,000.00
24,500.00
36,750.00
24,500.00
76,500.00
459,000.00
25,500.00
18,750.00
25,000.00
25,000.00
187,500.00
43,750.00
Page 27 of 68
AMOUNT
55,000.00
Page 28 of 68
AMOUNT
16,500.00
22,000.00
114,750.00
393,750.00
90,000.00
75,000.00
Page 29 of 68
AMOUNT
1,815,000.00
171,000.00
288,000.00
200,000.00
134,200.00
Page 30 of 68
AMOUNT
793,200.00
15,600.00
43,750.00
210,000.00
Page 31 of 68
AMOUNT
269,350.00
95,000.00
528,000.00
232,000.00
192,000.00
178,500.00
172,000.00
336,000.00
75,000.00
42,000.00
Page 32 of 68
AMOUNT
1,850,500.00
60,000.00
74,000.00
22,000.00
76,000.00
10,000.00
6,000.00
Page 33 of 68
AMOUNT
12,000.00
10,000.00
7,000.00
18,750.00
7,500.00
3,080.00
2,080.00
960.00
18,000.00
Page 34 of 68
AMOUNT
12,500.00
3,500.00
30,000.00
30,000.00
35,000.00
55,000.00
45,000.00
16,000.00
Page 35 of 68
AMOUNT
554,370.00
Page 36 of 68
AMOUNT
108,000.00
192,000.00
72,000.00
34,500.00
23,400.00
102,000.00
59,500.00
138,000.00
Page 37 of 68
AMOUNT
68,000.00
Page 38 of 68
AMOUNT
35,875.00
35,000.00
102,000.00
407,000.00
63,000.00
Page 39 of 68
AMOUNT
1,440,275.00
15,000.00
81,000.00
117,000.00
114,000.00
76,000.00
Page 40 of 68
AMOUNT
403,000.00
945,000.00
24,700.00
17,100.00
19,760.00
20,900.00
Page 41 of 68
AMOUNT
1,027,460.00
60,000.00
48,000.00
35,000.00
30,000.00
9,000.00
20,000.00
16,000.00
7,000.00
80,000.00
10,500.00
17,000.00
87,500.00
17,500.00
Page 42 of 68
AMOUNT
24,500.00
7,000.00
52,500.00
15,200.00
3,500.00
7,600.00
8,800.00
105,000.00
28,000.00
45,000.00
42,000.00
70,500.00
13,500.00
18,000.00
3,000.00
881,600.00
Page 43 of 68
PROPOSED ESTIMATE FOR THE RESIDENCE OF
Mr.V.K.G BIMAL RANDIKA
SUMMERY SHEET
TRADE DESCRIPTION OF WORK AMOUNT
A PRELIMINARIES Rs.
SUB TOTAL
Note:- The Samples must be approved by the Architect and Item in the Bill Of Quantities can be deleted or
Added as per requested by the client.
STIMATE FOR THE RESIDENCE OF
.V.K.G BIMAL RANDIKA
AMOUNT
250,000.00
264,000.00
1,815,000.00
793,200.00
269,350.00
1,850,500.00
554,370.00
1,440,275.00
403,000.00
1,027,460.00
881,600.00
9,548,755.00
477,437.75
10,026,192.75
1 excavation
col
F1 7 3 3 3.5 220.5
F2 8 3 4 3.5 336
556.5 5.57
C1 col-lean
F1 7 3 3 63
F2 8 3 4 96
159 1.59
22 slab 38.6
6" 139.06
36.23
40.63
5" 154.18
143.65
140.9
63.25
28.47
174.42 959.39 9.59
E5 2 3 10 60
2 9.75 9.5 185.25
2 6.5 10 130
2 8.5 10 170
5 10 50
5.75 10 57.5
10.167 10 101.67
13.25 10 132.5
4 11.5 10 460
2 3.417 10 68.34
3.33 10 33.3
5.83 10 58.3
2 9 10 180
ddt 2 9 -8.5 -153
3 -7 -21
2.5 -8.5 -21.25
2 -3 -6
5.75 -8.5 -48.875
11.5 -8.5 -97.75
1338.985 1338.99 13.39
F1 815 8.15
815 8.15