CLIENT:

PERUNDING RNR SEPAKAT INFRA QUEST


PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 45 M MONOPOLE
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 MONOPOLE Rumaizi

FOUNDATION CALCULATION

150 Ft Monopole 3 Tower (soil bearing = 100KN/M2)

(a) Specification

Vertical dead load (SLS) = 200 kN


Horizontal dead load (SLS) = 52 kN
Moment (SLS) = 1640 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 85 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.4 m
Height of stump above grd = 0.15 m
Earth thickness = 1.8 m
Base length, l = 5.8 m
Base width, b = 5.8 m
Base depth, h = 0.6 m
Stump length = 1.95 m
Stump width = 2.1 m

(b) Maximum earth pressure(SLS)

Weight of base = 484.4 kN


Weight of soil above = 947.1 kN
Weight of stump = 206.4 kN
Total axial load- soil = 890.8 kN
Total axial load = 1837.9 kN
Total moment = 1741.4 kNm
Base area, A = 33.6 m2
Modulus, Z = 32.52 m3
Maximum Pressure, Pmax = 80.0 kN/m2 O.K
Minimun Pressure, Pmin = 27.1 kN/m 2

(c) Resistance to Overturning Moment(SLS)

Disturbing Moment = 1741.4 kNm


Overtaking Moment(stump) = 598.5 kNm
Overtaking Moment(base) = 1404.8 kNm
Overtaking Moment(tower load) = 580.0 kNm
Overtaking Moment(soil on base) = 2746.5 kNm

Total Overtaking Moment = 5329.8 kNm

Allowable Factor Of Safety (F.O.S) = 1.5

Actual Factor Of Safety (F.O.S) = 3.1 O.K

(d) Resistance to horizontal load

Passive resistance, R = 918.93 kN


Horizontal load = 52 kN
F.O.S = 17.67 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 120.0 kN/m2


Minimum pressure, Pmin = 40.6 kN/m2
Distance at face of col = 1.85 m
Pmax, at col face = 68.80 kN/m2
Shear at col face = 174.69 kN
Moment, at face of column = 161.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00326
z/d = 0.996 >0.95
As = M/0.87fyz = 893.0 mm 2

Asmin = 0.13bh/100 = 4524.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 22.5
Number of bar provided = 24.0 NOS
bar spasing = 248 mm

provide 24 Y16 at 248 c/c


Area, A = 4825.498

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 90.99 kN/m2
Distance at 1.5d = 1.049 m
Vertical shear F = 642.0 kN
Shear stress v = 0.207 N/mm2
100As/bd = 0.156
Design stress vc = 0.361 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 14.808 m
Area = 13.70 m2
Pav for punching sheer = 105.52 kN/m2
V = 2103.54 kN
v = 0.266 N/mm2
vc = 0.361 N/mm2 O.K

Pav for shear Max Vmax = 39.72 kN/m2


Vmax = 1161.04 kN
vmax = 0.26 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 2100 mm


stump size,b = 2100 mm
compression load,N = 300 KN
horizontal load = 78.0 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2040 mm
d/h = 0.97

Moment from horiz. load,M1 = 152.10 KN/m


Applied moment,M2 = 2460.00 KN/m
Total moment,M = 2612.10 KN/m
N/bh = 0.06802721
M/bh2 = 0.28205377

from chart, 100Asc/bh = 0.4


Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 3778.6 mm2

number of bar req. = 56.15


number of bar prov. = 60 NOS
USE 60Y20 Asc =
JOB NO:
RNRS/0973
CALC SHEET:
1
DATE:
21/12/09
CHECKED BY:
Ir. Rosli
4 Y16 at 248 c/c
mm2
mm2
18849.6 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMP POLE TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

30m Lamp Pole Tower (soil bearing = 130KN/M2)

(a) Specification

Vertical dead load (SLS) = 61.076 kN


Horizontal dead load (SLS) = 23.086 kN
Moment (SLS) = 520.363 kNm

Soil Density = 18 kN/m3


Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2

Soffit Depth of Excavation = 3 m


Height of stump above grd = 0.9 m
Earth thickness = 2.55 m
Base length, l = 3.25 m
Base width, b = 3.25 m
Base depth, h = 0.45 m
Stump length = 3.45 m
Stump width = 1.6 m

(b) Maximum earth pressure(SLS)

Weight of base = 114.1 kN


Weight of soil above = 367.3 kN
Weight of stump = 212.0 kN
Total axial load- soil = 387.1 kN
Total axial load = 754.4 kN
Total moment = 600.0097 kNm
Base area, A = 10.6 m2
Modulus, Z = 5.72 m3
Maximum Pressure, Pmax = 141.5 kN/m2 O.K
Minimun Pressure, Pmin = 68.2 kN/m 2

(c) Resistance to Overturning Moment(SLS)


Disturbing Moment = 600.0 kNm

Overtaking Moment(stump) = 344.4 kNm


Overtaking Moment(base) = 185.4 kNm
Overtaking Moment(tower load) = 99.2 kNm
Overtaking Moment(soil on base) = 596.9 kNm

Total Overtaking Moment = 1226.0 kNm

Allowable Factor Of Safety (F.O.S) = 2.0

Actual Factor Of Safety (F.O.S) = 2.043 O.K

(d) Resistance to horizontal load

Passive resistance, R = 377.22 kN


Horizontal load = 23.086 kN
F.O.S = 16.34 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 212.3 kN/m2


Minimum pressure, Pmin = 102.3 kN/m2
Distance at face of col = 0.83 m
Pmax, at col face = 132.42 kN/m2
Shear at col face = 142.19 kN
Moment, at face of column = 58.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 384 mm

M/bd2fcu = 0.00408
z/d = 0.995 >0.95
As = M/0.87fyz = 450.7 mm 2

Asmin = 0.13bh/100 = 1901.3 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 9.5
Number of bar provided = 15.0 NOS
bar spasing = 225 mm

provide 15 Y16 at 225 c/c


Area, A = 3015.936
(f) Vertical shear(ULS)

1.5d = 576 mm
Pressure at 1.5d = 188.18 kN/m2
Distance at 1.5d = 0.249 m
Vertical shear F = 162.0 kN
Shear stress v = 0.130 N/mm2
100As/bd = 0.242
Design stress vc = 0.418 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.008 m
Area = 7.57 m2
Pav for punching sheer = 200.23 kN/m2
V = 598.49 kN
v = 0.142 N/mm2
vc = 0.418 N/mm2 O.K

Pav for shear Max Vmax = 54.98 kN/m2


Vmax = 439.94 kN
vmax = 0.18 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 91.614 KN
horizontal load = 34.6 KN
bar size = 25 mm Area = 490.875
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1537.5 mm
d/h = 0.96

Moment from horiz. load,M1 = 119.47 KN/m


Applied moment,M2 = 780.54 KN/m
Total moment,M = 900.01 KN/m
N/bh = 0.03578672
M/bh2 = 0.21973011

from chart, 100Asc/bh = 0.4


Asc = 10240 mm2
Asmin = 10240 mm2
M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1727.5 mm2

number of bar req. = 20.86


number of bar prov. = 24 NOS
USE 32Y20 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
5 Y16 at 225 c/c
mm2
mm2
11781 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMP POLE TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

30m Lamp Pole Tower (soil bearing = 50 KN/M2)

(a) Specification

Vertical dead load (SLS) = 61.076 kN


Horizontal dead load (SLS) = 23.086 kN
Moment (SLS) = 520.363 kNm

Soil Density = 18 kN/m3


Safe bearing pressure, pb = 50 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2

Soffit Depth of Excavation = 2.4 m


Height of stump above grd = 0.9 m
Earth thickness = 1.95 m
Base length, l = 5 m
Base width, b = 5 m
Base depth, h = 0.45 m
Stump length = 2.85 m
Stump width = 1.6 m

(b) Maximum earth pressure(SLS)

Weight of base = 270.0 kN


Weight of soil above = 787.6 kN
Weight of stump = 175.1 kN
Total axial load- soil = 506.2 kN
Total axial load = 1293.8 kN
Total moment = 586.1581 kNm
Base area, A = 25.0 m2
Modulus, Z = 20.83 m3
Maximum Pressure, Pmax = 48.4 kN/m2 O.K
Minimun Pressure, Pmin = 7.9 kN/m 2

(c) Resistance to Overturning Moment(SLS)


Disturbing Moment = 586.2 kNm

Overtaking Moment(stump) = 437.8 kNm


Overtaking Moment(base) = 675.0 kNm
Overtaking Moment(tower load) = 152.7 kNm
Overtaking Moment(soil on base) = 1969.1 kNm

Total Overtaking Moment = 3234.6 kNm

Allowable Factor Of Safety (F.O.S) = 2.0

Actual Factor Of Safety (F.O.S) = 5.518 O.K

(d) Resistance to horizontal load

Passive resistance, R = 646.91 kN


Horizontal load = 23.086 kN
F.O.S = 28.02 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 72.6 kN/m2


Minimum pressure, Pmin = 11.8 kN/m2
Distance at face of col = 1.70 m
Pmax, at col face = 43.88 kN/m2
Shear at col face = 98.98 kN
Moment, at face of column = 84.1 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 384 mm

M/bd2fcu = 0.00380
z/d = 0.996 >0.95
As = M/0.87fyz = 646.6 mm 2

Asmin = 0.13bh/100 = 2925.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 14.5
Number of bar provided = 21.0 NOS
bar spasing = 245 mm

provide 21 Y16 at 245 c/c


Area, A = 4222.31
(f) Vertical shear(ULS)

1.5d = 576 mm
Pressure at 1.5d = 53.60 kN/m2
Distance at 1.5d = 1.124 m
Vertical shear F = 354.5 kN
Shear stress v = 0.185 N/mm2
100As/bd = 0.220
Design stress vc = 0.405 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.008 m
Area = 7.57 m2
Pav for punching sheer = 63.09 kN/m2
V = 1099.38 kN
v = 0.260 N/mm2
vc = 0.405 N/mm2 O.K

Pav for shear Max Vmax = 30.37 kN/m2


Vmax = 681.52 kN
vmax = 0.28 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 91.614 KN
horizontal load = 34.6 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1540 mm
d/h = 0.96

Moment from horiz. load,M1 = 98.69 KN/m


Applied moment,M2 = 780.54 KN/m
Total moment,M = 879.24 KN/m
N/bh = 0.03578672
M/bh2 = 0.21465751

from chart, 100Asc/bh = 0.4


Asc = 10240 mm2
Asmin = 10240 mm2
M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1684.8 mm2

number of bar req. = 32.59


number of bar prov. = 36 NOS
USE 36Y20 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
1 Y16 at 245 c/c
mm2
mm2
11309.76 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 240M LAMP POLE TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

240m Heavy Duty Lamp Pole Tower (soil bearing = 75 KN/M2)

(a) Specification

Vertical dead load (SLS) = 34.15 kN


Horizontal dead load (SLS) = 15.87 kN
Moment (SLS) = 291.8 kNm

Soil Density = 18 kN/m3


Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2

Soffit Depth of Excavation = 3 m


Height of stump above grd = 0.9 m
Earth thickness = 2.55 m
Base length, l = 3.6 m
Base width, b = 3.6 m
Base depth, h = 0.45 m
Stump length = 3.45 m
Stump width = 1.4 m

(b) Maximum earth pressure(SLS)

Weight of base = 140.0 kN


Weight of soil above = 504.9 kN
Weight of stump = 162.3 kN
Total axial load- soil = 336.4 kN
Total axial load = 841.3 kN
Total moment = 346.5515 kNm
Base area, A = 13.0 m2
Modulus, Z = 7.78 m3
Maximum Pressure, Pmax = 70.5 kN/m2 O.K
Minimun Pressure, Pmin = 18.6 kN/m 2

(c) Resistance to Overturning Moment(SLS)

Disturbing Moment = 346.6 kNm


Overtaking Moment(stump) = 292.1 kNm
Overtaking Moment(base) = 251.9 kNm
Overtaking Moment(tower load) = 61.5 kNm
Overtaking Moment(soil on base) = 908.8 kNm

Total Overtaking Moment = 1514.4 kNm

Allowable Factor Of Safety (F.O.S) = 2.0

Actual Factor Of Safety (F.O.S) = 4.370 O.K

(d) Resistance to horizontal load

Passive resistance, R = 420.65 kN


Horizontal load = 15.87 kN
F.O.S = 26.51 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 105.8 kN/m2


Minimum pressure, Pmin = 27.9 kN/m2
Distance at face of col = 1.10 m
Pmax, at col face = 64.93 kN/m2
Shear at col face = 93.90 kN
Moment, at face of column = 51.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 384 mm

M/bd2fcu = 0.00324
z/d = 0.996 >0.95
As = M/0.87fyz = 396.9 mm 2

Asmin = 0.13bh/100 = 2106.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 10.5
Number of bar provided = 15.0 NOS
bar spasing = 250 mm

provide 15 Y16 at 250 c/c


Area, A = 3015.936 mm2

(f) Vertical shear(ULS)

1.5d = 576 mm
Pressure at 1.5d = 86.33 kN/m2
Distance at 1.5d = 0.524 m
Vertical shear F = 181.2 kN
Shear stress v = 0.131 N/mm2
100As/bd = 0.218
Design stress vc = 0.404 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.208 m
Area = 6.51 m2
Pav for punching sheer = 96.06 kN/m2
V = 619.30 kN
v = 0.158 N/mm2
vc = 0.404 N/mm2 O.K

Pav for shear Max Vmax = 38.94 kN/m2


Vmax = 428.29 kN
vmax = 0.20 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 1400 mm


stump size,b = 1400 mm
compression load,N = 51.225 KN
horizontal load = 23.8 KN
bar size = 25 mm Area = 490.875 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1337.5 mm
d/h = 0.96

Moment from horiz. load,M1 = 82.13 KN/m


Applied moment,M2 = 437.70 KN/m
Total moment,M = 519.83 KN/m
N/bh = 0.0261352
M/bh2 = 0.18944142

from chart, 100Asc/bh = 0.4


Asc = 7840 mm2
Asmin = 7840 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1146.9 mm2

number of bar req. = 15.97


number of bar prov. = 16 NOS
USE 16Y25 Asc = 7854
RNRS/0746
1
14/02/09
Ir. Rosli
mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMP POLE TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

30m Lamp Pole Tower (soil bearing = 75 KN/M2)

(a) Specification

Vertical dead load (SLS) = 61.076 kN


Horizontal dead load (SLS) = 23.086 kN
Moment (SLS) = 520.363 kNm

Soil Density = 18 kN/m3


Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2

Soffit Depth of Excavation = 3.6 m


Height of stump above grd = 0.9 m
Earth thickness = 3.15 m
Base length, l = 4.7 m
Base width, b = 4.7 m
Base depth, h = 0.45 m
Stump length = 4.05 m
Stump width = 1.6 m

(b) Maximum earth pressure(SLS)

Weight of base = 238.6 kN


Weight of soil above = 1107.4 kN
Weight of stump = 248.8 kN
Total axial load- soil = 548.5 kN
Total axial load = 1655.8 kN
Total moment = 613.8613 kNm
Base area, A = 22.1 m2
Modulus, Z = 17.30 m3
Maximum Pressure, Pmax = 60.3 kN/m2 O.K
Minimun Pressure, Pmin = 10.6 kN/m 2

(c) Resistance to Overturning Moment(SLS)


Disturbing Moment = 613.9 kNm

Overtaking Moment(stump) = 584.8 kNm


Overtaking Moment(base) = 560.6 kNm
Overtaking Moment(tower load) = 143.5 kNm
Overtaking Moment(soil on base) = 2602.3 kNm

Total Overtaking Moment = 3891.2 kNm

Allowable Factor Of Safety (F.O.S) = 2.0

Actual Factor Of Safety (F.O.S) = 6.339 O.K

(d) Resistance to horizontal load

Passive resistance, R = 827.92 kN


Horizontal load = 23.086 kN
F.O.S = 35.86 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 90.5 kN/m2


Minimum pressure, Pmin = 16.0 kN/m2
Distance at face of col = 1.55 m
Pmax, at col face = 55.36 kN/m2
Shear at col face = 113.01 kN
Moment, at face of column = 87.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 384 mm

M/bd2fcu = 0.00421
z/d = 0.995 >0.95
As = M/0.87fyz = 673.1 mm 2

Asmin = 0.13bh/100 = 2749.5 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 13.7
Number of bar provided = 20.0 NOS
bar spasing = 242 mm

provide 20 Y16 at 242 c/c


Area, A = 4021.248
(f) Vertical shear(ULS)

1.5d = 576 mm
Pressure at 1.5d = 68.40 kN/m2
Distance at 1.5d = 0.974 m
Vertical shear F = 363.6 kN
Shear stress v = 0.201 N/mm2
100As/bd = 0.223
Design stress vc = 0.407 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.008 m
Area = 7.57 m2
Pav for punching sheer = 79.43 kN/m2
V = 1153.04 kN
v = 0.273 N/mm2
vc = 0.407 N/mm2 O.K

Pav for shear Max Vmax = 37.24 kN/m2


Vmax = 727.38 kN
vmax = 0.30 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 91.614 KN
horizontal load = 34.6 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1540 mm
d/h = 0.96

Moment from horiz. load,M1 = 140.25 KN/m


Applied moment,M2 = 780.54 KN/m
Total moment,M = 920.79 KN/m
N/bh = 0.03578672
M/bh2 = 0.22480272

from chart, 100Asc/bh = 0.4


Asc = 10240 mm2
Asmin = 10240 mm2
M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1764.5 mm2

number of bar req. = 32.59


number of bar prov. = 36 NOS
USE 36Y20 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
0 Y16 at 242 c/c
mm2
mm2
11309.76 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMP POLE TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

30m Lamp Pole Tower (soil bearing = 130KN/M2)

(a) Specification

Vertical dead load (SLS) = 61.076 kN


Horizontal dead load (SLS) = 23.086 kN
Moment (SLS) = 520.363 kNm

Soil Density = 18 kN/m3


Safe bearing pressure, pb = 130 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2

Soffit Depth of Excavation = 2.4 m


Height of stump above grd = 0.9 m
Earth thickness = 1.95 m
Base length, l = 3.45 m
Base width, b = 3.45 m
Base depth, h = 0.45 m
Stump length = 2.85 m
Stump width = 1.6 m

(b) Maximum earth pressure(SLS)

Weight of base = 128.5 kN


Weight of soil above = 327.9 kN
Weight of stump = 175.1 kN
Total axial load- soil = 364.7 kN
Total axial load = 692.6 kN
Total moment = 586.1581 kNm
Base area, A = 11.9 m2
Modulus, Z = 6.84 m3
Maximum Pressure, Pmax = 116.3 kN/m2 O.K
Minimun Pressure, Pmin = 55.0 kN/m 2

(c) Resistance to Overturning Moment(SLS)


Disturbing Moment = 586.2 kNm

Overtaking Moment(stump) = 302.1 kNm


Overtaking Moment(base) = 221.7 kNm
Overtaking Moment(tower load) = 105.4 kNm
Overtaking Moment(soil on base) = 565.7 kNm

Total Overtaking Moment = 1194.8 kNm

Allowable Factor Of Safety (F.O.S) = 2.0

Actual Factor Of Safety (F.O.S) = 2.038 O.K

(d) Resistance to horizontal load

Passive resistance, R = 346.32 kN


Horizontal load = 23.086 kN
F.O.S = 15.00 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 174.4 kN/m2


Minimum pressure, Pmin = 82.5 kN/m2
Distance at face of col = 0.93 m
Pmax, at col face = 105.54 kN/m2
Shear at col face = 129.49 kN
Moment, at face of column = 59.9 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 384 mm

M/bd2fcu = 0.00392
z/d = 0.996 >0.95
As = M/0.87fyz = 460.2 mm 2

Asmin = 0.13bh/100 = 2018.3 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 10.0
Number of bar provided = 16.0 NOS
bar spasing = 223 mm

provide 16 Y16 at 223 c/c


Area, A = 3216.998
(f) Vertical shear(ULS)

1.5d = 576 mm
Pressure at 1.5d = 148.44 kN/m2
Distance at 1.5d = 0.349 m
Vertical shear F = 194.4 kN
Shear stress v = 0.147 N/mm2
100As/bd = 0.243
Design stress vc = 0.419 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.008 m
Area = 7.57 m2
Pav for punching sheer = 161.44 kN/m2
V = 698.86 kN
v = 0.165 N/mm2
vc = 0.419 N/mm2 O.K

Pav for shear Max Vmax = 45.96 kN/m2


Vmax = 429.42 kN
vmax = 0.17 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 91.614 KN
horizontal load = 34.6 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1540 mm
d/h = 0.96

Moment from horiz. load,M1 = 98.69 KN/m


Applied moment,M2 = 780.54 KN/m
Total moment,M = 879.24 KN/m
N/bh = 0.03578672
M/bh2 = 0.21465751

from chart, 100Asc/bh = 0.4


Asc = 10240 mm2
Asmin = 10240 mm2
M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1684.8 mm2

number of bar req. = 32.59


number of bar prov. = 36 NOS
USE 36Y20 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
6 Y16 at 223 c/c
mm2
mm2
11309.76 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMPOLE TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim PILE CAP
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 LP-3 Rumaizi

FOUNDATION CALCULATION

24m Hvdty Lampole Tower (9 nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 34.15 kN


Horizontal dead load (SLS) = 15.87 kN
Moment (SLS) = 291.8 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 50 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.9 m
Earth thickness = 0.3 m
Base length, l = 2.4 m
Base width, b = 2.4 m
Base depth, h = 0.6 m
Stump length = 1.2 m
Stump width = 1.6 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 9 m


total pile frction load base on SI result = 94 kN
total pile comp capacity base on SI resul = 165 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 66 kN


actual pile capacity in tension = 47 kN

distance betweenf piles = 0.900 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.900 m
x2,distance of pile from ctr col = 0.000 m
pile nos for row 1 = 3.0 nos
pile nos for row 1 = 3.0 nos
pile nos for row 2 = 0.0 nos
total pile nos = 9.0 nos
pile size = 0.200 m
distance of pile edge = 0.2 m
size of pile cap = 2.400 m

weight of stump = 73.7 kN


weight of pilecap = 82.9 kN
total vertical load = 190.8 kN

total ind. pile load due to vert. load = 21.2 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 310.844 kNm


2nd. Moment inertia of pile group, I = 4.860
pile load at row 2 due to moment, Mx/I = 0.0 O.K
pile load at row 1 due to moment, Mx/I = 57.6 Please Check

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 21.2 O.K


pile load at row 1 = 78.8 Please Check

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 297.7 kNm


Moment for top bar, M2 = 217.6 kNm
Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M1/bd2fcu = 0.01450
z/d = 0.984 >0.95
As = M/0.87fyz = 1466.5 mm2
Asmin = 0.13bh/100 = 1872.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required (bottom) = 9.3
Number of bar provided (bottom) = 15.0 NOS (B)
bar spasing = 164 mm

provide 15 Y16 at 164 c/c (B)


Area, A = 3015.936 mm2

M2/bd2fcu = 0.01060
z/d = 0.988 >0.95
As = M/0.87fyz = 1071.8 mm 2
Adopt diameter bar = 16 mm
area A = 201.062 mm2
Number of bar required (top) = 9.3
Number of bar provided (top) = 12.0 NOS (T)
bar spasing = 209 mm
provide 12 Y16 at 209 c/c (T)
Area, A = 2412.749 mm2

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 1


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.06 m
shear = 259.0 KN
Shear stress v = 0.202 N/mm2
enhance shear stress factor, 2d/av = 17.800 (applied for pile spasing=,< 3xdia)
100As/bd = 0.235
Design stress vc = 0.415 N/mm2 O.K

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 259.04 kN
v = 0.202 N/mm2
vc = 0.415 N/mm2 O.K

f) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 51.225 KN
horizontal load = 23.8 KN
bar size = 25 mm Area = 490.875 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1537.5 mm
d/h = 0.96

Moment from horiz. load,M1 = 28.57 KN/m


Applied moment,M2 = 437.70 KN/m
Total moment,M = 466.27 KN/m
N/bh = 0.02000977
M/bh2 = 0.11383447

from chart, 100Asc/bh = 0.4


Asc = 10240 mm2
Asmin = 10240 mm2

M/bd2fcu = 0.00000
z/d = 1.000 >0.95
As = M/0.87fyz = 797.7 mm 2
number of bar req. = 20.86
number of bar prov. = 24 NOS
USE24Y25 Asc = 11781
RNRS/0924
1
27/07/09
Ir. Rosli
mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMPOLE TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim PILE CAP
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 LP-3 Rumaizi

FOUNDATION CALCULATION

30m heavy duty Lampole Tower ( 9 nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 49.29 kN


Horizontal dead load (SLS) = 16.44 kN
Moment (SLS) = 328.93 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.9 m
Earth thickness = 0.3 m
Base length, l = 2.4 m
Base width, b = 2.4 m
Base depth, h = 0.6 m
Stump length = 1.2 m
Stump width = 1.6 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 12 m


total pile frction load base on SI result = 267 kN
total pile comp capacity base on SI resul = 338 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 135.2 kN


actual pile capacity in tension = 133.5 kN

distance betweenf piles = 0.900 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.900 m
x2,distance of pile from ctr col = 0.000 m
pile nos for row 1 = 3.0 nos
pile nos for row 1 = 3.0 nos
pile nos for row 2 = 0.0 nos
total pile nos = 9.0 nos
pile size = 0.200 m
distance of pile edge = 0.2 m
size of pile cap = 2.400 m

weight of stump = 73.7 kN


weight of pilecap = 82.9 kN
total vertical load = 206.0 kN

total ind. pile load due to vert. load = 22.9 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 348.658 kNm


2nd. Moment inertia of pile group, I = 4.860
pile load at row 2 due to moment, Mx/I = 0.0 O.K
pile load at row 1 due to moment, Mx/I = 64.6 O.K

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 22.9 O.K


pile load at row 1 = 87.5 O.K

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 330.6 kNm


Moment for top bar, M2 = 244.1 kNm
Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M1/bd2fcu = 0.01610
z/d = 0.982 >0.95
As = M/0.87fyz = 1628.2 mm2
Asmin = 0.13bh/100 = 1872.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required (bottom) = 9.3
Number of bar provided (bottom) = 12.0 NOS (B)
bar spasing = 209 mm

provide 12 Y16 at 209 c/c (B)


Area, A = 2412.749 mm2

M2/bd2fcu = 0.01189
z/d = 0.987 >0.95
As = M/0.87fyz = 1202.1 mm 2
Adopt diameter bar = 16 mm
area A = 201.062 mm2
Number of bar required (top) = 9.3
Number of bar provided (top) = 12.0 NOS (T)
bar spasing = 209 mm
provide 12 Y16 at 209 c/c (T)
Area, A = 2412.749 mm2

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 1


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.06 m
shear = 290.5 KN
Shear stress v = 0.227 N/mm2
enhance shear stress factor, 2d/av = 17.800 (applied for pile spasing=,< 3xdia)
100As/bd = 0.188
Design stress vc = 0.385 N/mm2 O.K

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 290.55 kN
v = 0.227 N/mm2
vc = 0.385 N/mm2 O.K

f) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 73.935 KN
horizontal load = 24.7 KN
bar size = 25 mm Area = 490.875 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1537.5 mm
d/h = 0.96

Moment from horiz. load,M1 = 29.59 KN/m


Applied moment,M2 = 493.40 KN/m
Total moment,M = 522.99 KN/m
N/bh = 0.02888086
M/bh2 = 0.12768237

from chart, 100Asc/bh = 0.4


Asc = 10240 mm2
Asmin = 10240 mm2

M/bd2fcu = 0.00000
z/d = 1.000 >0.95
As = M/0.87fyz = 894.7 mm 2
number of bar req. = 20.86
number of bar prov. = 24 NOS
USE24Y25 Asc = 11781
RNRS/0924
1
27/07/09
Ir. Rosli
mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT COMINTEL
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 1370M RTM TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim PILE CAP
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 LP-3 Rumaizi

FOUNDATION CALCULATION

30m Lampole Tower ( 4 nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 1226 kN


Horizontal dead load (SLS) = 222 kN
Moment (SLS) = 0 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 2.1 m
Height of stump above grd = 0.3 m
Earth thickness = 1.2 m
Base length, l = 2.6 m
Base width, b = 2.6 m
Base depth, h = 0.9 m
Stump length = 1.5 m
Stump width = 1.2 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 24 m


total pile frction load base on SI result = 551 kN
total pile comp capacity base on SI resul = 940 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 376 kN


actual pile capacity in tension = 275.5 kN

distance betweenf piles = 0.900 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.900 m
x2,distance of pile from ctr col = 0.000 m
pile nos for row 1 = 3.0 nos
pile nos for row 1 = 3.0 nos
pile nos for row 2 = 0.0 nos
total pile nos = 9.0 nos
pile size = 0.250 m
distance of pile edge = 0.275 m
size of pile cap = 2.600 m

weight of stump = 51.8 kN


weight of pilecap = 146.0 kN
total vertical load = 1423.9 kN

total ind. pile load due to vert. load = 158.2 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 333 kNm


2nd. Moment inertia of pile group, I = 4.860
pile load at row 2 due to moment, Mx/I = 0.0 O.K
pile load at row 1 due to moment, Mx/I = 61.7 O.K

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 158.2 O.K


pile load at row 1 = 219.9 O.K

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 831.1 kNm


Moment for top bar, M2 = 233.1 kNm
Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

M1/bd2fcu = 0.01547
z/d = 0.983 >0.95
As = M/0.87fyz = 2633.8 mm2
Asmin = 0.13bh/100 = 3042.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (bottom) = 9.7
Number of bar provided (bottom) = 13.0 NOS (B)
bar spasing = 208 mm

provide 13 Y20 at 208 c/c (B)


Area, A = 4084.08 mm2

M2/bd2fcu = 0.00434
z/d = 0.995 >0.95
As = M/0.87fyz = 738.7 mm 2
Adopt diameter bar = 20 mm
area A = 314.160 mm2
Number of bar required (top) = 9.7
Number of bar provided (top) = 13.0 NOS (T)
bar spasing = 208 mm
provide 13 Y20 at 208 c/c (T)
Area, A = 4084.08 mm2

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 1


pile dia./5 = 0.05 m
distance at critacal shear, av = 0.25 m
shear = 277.5 KN
Shear stress v = 0.129 N/mm2
enhance shear stress factor, 2d/av = 6.640 (applied for pile spasing=,< 3xdia)
100As/bd = 0.189
Design stress vc = 0.386 N/mm2 O.K

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 277.50 kN
v = 0.129 N/mm2
vc = 0.386 N/mm2 O.K

f) Stump design(ULS)

stump size,h = 1200 mm


stump size,b = 1200 mm
compression load,N = 1839 KN
horizontal load = 333.0 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1140 mm
d/h = 0.95

Moment from horiz. load,M1 = 499.50 KN/m


Applied moment,M2 = 0.00 KN/m
Total moment,M = 499.50 KN/m
N/bh = 1.27708333
M/bh2 = 0.2890625

from chart, 100Asc/bh = 0.4


Asc = 5760 mm2
Asmin = 5760 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1152.5 mm 2
number of bar req. = 18.33
number of bar prov. = 20 NOS
USE20Y20 Asc = 6283.2
RNRS/0827
1
Apr-08
Ir. Rosli
mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESABINA IND SDN BHD RNRS/0913
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 45M MONOPOLE TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim PILE CAP 27/07/09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 MONO/4 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

45m monopole Tower ( 9 nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 145 kN


Horizontal dead load (SLS) = 38 kN
Moment (SLS) = 1106 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 1.15 m
Height of stump above grd = 1.5 m
Earth thickness = 0 m
Base length, l = 2.400 m
Base width, b = 2.400 m
Base depth, h = 1.15 m
Stump length = 1.5 m
Stump width = 2 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 12 m


total pile frction load base on SI result = 433 kN
total pile comp capacity base on SI resul = 1321 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 528.4 kN


actual pile capacity in tension = 216.5 kN

distance betweenf piles = 0.900 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.900 m
x2,distance of pile from ctr col = 0.000 m
pile nos for row 1 = 3.0 nos
pile nos for row 1 = 3.0 nos
pile nos for row 2 = 0.0 nos
total pile nos = 9.0 nos
pile size = 0.200 m
distance of pile edge = 0.2 m
size of pile cap = 2.400 m

weight of stump = 144.0 kN


weight of pilecap = 159.0 kN
total vertical load = 448.0 kN

total ind. pile load due to vert. load = 49.8 kN


check pile capacity on tension
normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 1163 kNm


2nd. Moment inertia of pile group, I = 4.860
pile load at row 2 due to moment, Mx/I = 0.0 O.K
pile load at row 1 due to moment, Mx/I = 215.4 O.K

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 49.8 O.K


pile load at row 1 = 265.1 O.K

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 1002.2 kNm


Moment for top bar, M2 = 814.1 kNm
Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 1080 mm

M1/bd2fcu = 0.01193
z/d = 0.987 >0.95
As = M/0.87fyz = 2440.9 mm2
Asmin = 0.13bh/100 = 3588.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (bottom) = 11.4
Number of bar provided (bottom) = 15.0 NOS (B)
bar spasing = 164 mm

provide 15 Y20 at 164 c/c (B)


Area, A = 4712.4 mm2

M2/bd2fcu = 0.00969
z/d = 0.989 >0.95
As = M/0.87fyz = 1982.7 mm 2

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (top) = 11.4
Number of bar provided (top) = 12.0 NOS (T)
bar spasing = 209 mm
provide 12 Y20 at 209 c/c (T)
Area, A = 3769.92 mm2
(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 1


pile dia./5 = 0.04 m
distance at critacal shear, av = -0.14 m
shear = 969.2 KN
Shear stress v = 0.374 N/mm2
enhance shear stress factor, 2d/av = -15.429 (applied for pile spasing=,< 3xdia)
100As/bd = 0.182
Design stress vc = 0.380 N/mm2 O.K

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 969.17 kN
v = 0.374 N/mm2
vc = 0.380 N/mm2 O.K

f) Stump design(ULS)

stump size,h = 2000 mm


stump size,b = 2000 mm
compression load,N = 217.5 KN
horizontal load = 57.0 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1940 mm
d/h = 0.97

Moment from horiz. load,M1 = 85.50 KN/m


Applied moment,M2 = 1659.00 KN/m
Total moment,M = 1744.50 KN/m
N/bh = 0.054375
M/bh2 = 0.2180625

from chart, 100Asc/bh = 0.4


Asc = 16000 mm2
Asmin = 16000 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 2365.2 mm 2

number of bar req. = 50.93


number of bar prov. = 24 NOS
USE24Y25 Asc = 7539.84 mm2
RNRS/0913
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 30M LAMPOLE TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim PILE CAP
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 LP-3 Rumaizi

FOUNDATION CALCULATION

30m Lampole Tower ( 4 nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 61.2 kN


Horizontal dead load (SLS) = 23.09 kN
Moment (SLS) = 520.4 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.9 m
Earth thickness = 0.3 m
Base length, l = 2.4 m
Base width, b = 2.4 m
Base depth, h = 0.6 m
Stump length = 1.2 m
Stump width = 1.6 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 12 m


total pile frction load base on SI result = 284 kN
total pile comp capacity base on SI resul = 604 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 241.6 kN


actual pile capacity in tension = 142 kN

distance betweenf piles = 0.900 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.900 m
x2,distance of pile from ctr col = 0.000 m
pile nos for row 1 = 3.0 nos
pile nos for row 1 = 3.0 nos
pile nos for row 2 = 0.0 nos
total pile nos = 9.0 nos
pile size = 0.200 m
distance of pile edge = 0.2 m
size of pile cap = 2.400 m

weight of stump = 73.7 kN


weight of pilecap = 82.9 kN
total vertical load = 217.9 kN

total ind. pile load due to vert. load = 24.2 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 548.108 kNm


2nd. Moment inertia of pile group, I = 4.860
pile load at row 2 due to moment, Mx/I = 0.0 O.K
pile load at row 1 due to moment, Mx/I = 101.5 O.K

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 24.2 O.K


pile load at row 1 = 125.7 O.K

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 475.2 kNm


Moment for top bar, M2 = 383.7 kNm
Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M1/bd2fcu = 0.02314
z/d = 0.974 >0.95
As = M/0.87fyz = 2340.5 mm2
Asmin = 0.13bh/100 = 1872.0 mm2 <As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required (bottom) = 11.6
Number of bar provided (bottom) = 15.0 NOS (B)
bar spasing = 164 mm

provide 15 Y16 at 164 c/c (B)


Area, A = 3015.936

M2/bd2fcu = 0.01869
z/d = 0.979 >0.95
As = M/0.87fyz = 1889.8 mm 2

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required (top) = 9.4
Number of bar provided (top) = 12.0 NOS (T)
bar spasing = 209 mm
provide 12 Y16 at 209 c/c (T)
Area, A = 2412.749

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 1


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.06 m
shear = 456.8 KN
Shear stress v = 0.356 N/mm2
enhance shear stress factor, 2d/av = 17.800 (applied for pile spasing=,< 3xdia)
100As/bd = 0.235
Design stress vc = 0.415 N/mm2 O.K

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 456.76 kN
v = 0.356 N/mm2
vc = 0.415 N/mm2 O.K

f) Stump design(ULS)

stump size,h = 1600 mm


stump size,b = 1600 mm
compression load,N = 91.8 KN
horizontal load = 34.6 KN
bar size = 25 mm Area = 490.875
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 1537.5 mm
d/h = 0.96

Moment from horiz. load,M1 = 41.56 KN/m


Applied moment,M2 = 780.60 KN/m
Total moment,M = 822.16 KN/m
N/bh = 0.03585938
M/bh2 = 0.20072314
from chart, 100Asc/bh = 0.4
Asc = 10240 mm2
Asmin = 10240 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 1406.5 mm2

number of bar req. = 20.86


number of bar prov. = 24 NOS
USE24Y25 Asc =
JOB NO:
RNRS/0924
CALC SHEET:
1
DATE:
27/07/09
CHECKED BY:
Ir. Rosli
ile assume as similar

5 Y16 at 164 c/c (B)


mm2

2 Y16 at 209 c/c (T)


mm2

ng=,< 3xdia)

mm2
11781 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 150 ft MONOPOLE 3 TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

150 Ft Monopole 3 Tower ( 16 nos 250x250 RC pile )

(a) Specification

Vertical dead load (SLS) = 200 kN


Horizontal dead load (SLS) = 52 kN
Moment (SLS) = 1640 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 25 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 1.5 m
Earth thickness = 0 m
Base length, l = 3.1 m
Base width, b = 3.1 m
Base depth, h = 0.9 m
Stump length = 1.5 m
Stump width = 2.1 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 18 m


total pile frction load base on SI result = 354 kN
total pile comp capacity base on SI resul = 656 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 262.4 kN


actual pile capacity in tension = 177 kN

distance betweenf piles = 0.750 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.375 m
x2,distance of pile from ctr col = 1.125 m
pile nos for row 1 = 5.0 nos
pile nos for row 1 = 4.0 nos
pile nos for row 2 = 4.0 nos
total pile nos = 16.0 nos
pile size = 0.2 m
distance of pile edge = 0.3 m
size of pile cap = 3.050 m

weight of stump = 158.8 kN


weight of pilecap = 200.9 kN
total vertical load = 559.7 kN

total ind. pile load due to vert. load = 35.0 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 1718 kNm


2nd. Moment inertia of pile group, I = 11.250
pile load at row 2 due to moment, Mx/I = 171.8 O.K
pile load at row 1 due to moment, Mx/I = 57.3

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 206.8 O.K


pile load at row 1 = 92.2

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 1496.4 kNm


Moment for top bar, M2 = 1202.6 kNm
Cover bar = 125 mm
Diameter bar = 20 mm
Effective depth, dav = 755 mm

M1/bd2fcu = 0.02869
z/d = 0.967 >0.95
As = M/0.87fyz = 5213.3 mm2
Asmin = 0.13bh/100 = 3568.5 mm2 <As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (bottom) = 16.6
Number of bar provided (bottom) = 18.0 NOS (B)
bar spasing = 165 mm

provide 27 Y20 at 142 c/c (B)


Area, A = 5654.88 mm2

M2/bd2fcu = 0.02306
z/d = 0.974 >0.95
As = M/0.87fyz = 4189.6 mm 2
Adopt diameter bar = 20 mm
area A = 314.160 mm2
Number of bar required (top) = 13.3
Number of bar provided (top) = 15.0 NOS (T)
bar spasing = 200 mm
provide 23 Y20 at 168 c/c (T)
Area, A = 4712.4 mm2

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 3


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.035 m
shear = 1374.4 KN
Shear stress v = 0.597 N/mm2
enhance shear stress factor, 2d/av = 43.143 (applied for pile spasing=,< 3xdia)
100As/bd = 0.246
Design stress vc = 0.421 N/mm2 Please Check

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 1374.40 kN
v = 0.597 N/mm2
vc = 0.421 N/mm2 Please Check

f) Stump design(ULS)

stump size,h = 2100 mm


stump size,b = 2100 mm
compression load,N = 300 KN
horizontal load = 78.0 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2040 mm
d/h = 0.97

Moment from horiz. load,M1 = 117.00 KN/m


Applied moment,M2 = 2460.00 KN/m
Total moment,M = 2577.00 KN/m
N/bh = 0.06802721
M/bh2 = 0.27826369

from chart, 100Asc/bh = 0.4


Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 3322.6 mm 2
number of bar req. = 56.15
number of bar prov. = 60 NOS
USE 60Y20 Asc = 18849.6
RNRS/0746
1
14/02/09
Ir. Rosli
mm2
CLIENT:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 150 ft MONOPOLE 3 TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

150 Ft Monopole 3 Tower ( 16 nos 250x250 RC pile )

(a) Specification

Vertical dead load (SLS) = 145 kN


Horizontal dead load (SLS) = 38 kN
Moment (SLS) = 1106 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 25 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 1.5 m
Earth thickness = 0 m
Base length, l = 2.850 m
Base width, b = 2.850 m
Base depth, h = 0.9 m
Stump length = 1.5 m
Stump width = 2.1 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 12 m


total pile frction load base on SI result = 433 kN
total pile comp capacity base on SI resul = 1321 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 528.4 kN


actual pile capacity in tension = 216.5 kN

distance betweenf piles = 0.750 m


x1,distance of pile from ctr col = 0.0 m
x1,distance of pile from ctr col = 0.375 m
x2,distance of pile from ctr col = 1.125 m
pile nos for row 1 = 5.0 nos
pile nos for row 1 = 4.0 nos
pile nos for row 2 = 4.0 nos
total pile nos = 16.0 nos
pile size = 0.2 m
distance of pile edge = 0.2 m
size of pile cap = 2.850 m

weight of stump = 158.8 kN


weight of pilecap = 175.4 kN
total vertical load = 479.2 kN

total ind. pile load due to vert. load = 30.0 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 1163 kNm


2nd. Moment inertia of pile group, I = 11.250
pile load at row 2 due to moment, Mx/I = 116.3 O.K
pile load at row 1 due to moment, Mx/I = 38.8

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 2 = 146.3 O.K


pile load at row 1 = 68.7

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 1065.7 kNm


Moment for top bar, M2 = 814.1 kNm
Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

M1/bd2fcu = 0.01809
z/d = 0.979 >0.95
As = M/0.87fyz = 3377.1 mm2
Asmin = 0.13bh/100 = 3334.5 mm2 <As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (bottom) = 10.7
Number of bar provided (bottom) = 15.0 NOS (B)
bar spasing = 196 mm

provide 27 Y20 at 142 c/c (B)


Area, A = 4712.4

M2/bd2fcu = 0.01382
z/d = 0.984 >0.95
As = M/0.87fyz = 2579.9 mm 2

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (top) = 10.6
Number of bar provided (top) = 15.0 NOS (T)
bar spasing = 196 mm
provide 23 Y20 at 168 c/c (T)
Area, A = 4712.4

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 3


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.035 m
shear = 930.4 KN
Shear stress v = 0.393 N/mm2
enhance shear stress factor, 2d/av = 47.429 (applied for pile spasing=,< 3xdia)
100As/bd = 0.199
Design stress vc = 0.392 N/mm2 Please Check

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 930.40 kN
v = 0.393 N/mm2
vc = 0.392 N/mm2 Please Check

f) Stump design(ULS)

stump size,h = 2100 mm


stump size,b = 2100 mm
compression load,N = 217.5 KN
horizontal load = 57.0 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2040 mm
d/h = 0.97

Moment from horiz. load,M1 = 85.50 KN/m


Applied moment,M2 = 1659.00 KN/m
Total moment,M = 1744.50 KN/m
N/bh = 0.04931973
M/bh2 = 0.18837059
from chart, 100Asc/bh = 0.4
Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 2249.3 mm2

number of bar req. = 56.15


number of bar prov. = 60 NOS
USE 60Y20 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
ile assume as similar

7 Y20 at 142 c/c (B)


mm2

3 Y20 at 168 c/c (T)


mm2

ng=,< 3xdia)

mm2
18849.6 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 150 ft MONOPOLE 3 TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim PILE
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

150 Ft Monopole 3 Tower ( 25nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 200 kN


Horizontal dead load (SLS) = 52 kN
Moment (SLS) = 1640 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 25 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 1.5 m
Earth thickness = 0 m
Base length, l = 3.8 m
Base width, b = 3.8 m
Base depth, h = 0.9 m
Stump length = 1.5 m
Stump width = 2.1 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 18 m


total pile frction load base on SI result = 354 kN
total pile comp capacity base on SI resul = 656 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 262.4 kN


actual pile capacity in tension = 177 kN

distance betweenf piles = 0.750 m


x1,distance of pile from ctr col = 0.0 m
x2,distance of pile from ctr col = 0.750 m
x3,distance of pile from ctr col = 1.500 m
pile nos for row 1 = 5.0 nos
pile nos for row 2 = 5.0 nos
pile nos for row 3 = 5.0 nos
total pile nos = 25.0 nos
pile size = 0.2 m
distance of pile edge = 0.3 m
size of pile cap = 3.8 m

weight of stump = 158.8 kN


weight of pilecap = 311.9 kN
total vertical load = 670.7 kN

total ind. pile load due to vert. load = 26.8 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 1718 kNm


2nd. Moment inertia of pile group, I = 28.125
pile load at row 3 due to moment, Mx/I = 91.6 O.K
pile load at row 2 due to moment, Mx/I = 45.8

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 3 = 118.5 O.K


pile load at row 2 = 72.6

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 1625.1 kNm


Moment for top bar, M2 = 1202.6 kNm
Cover bar = 125 mm
Diameter bar = 20 mm
Effective depth, dav = 755 mm

M1/bd2fcu = 0.02501
z/d = 0.971 >0.95
As = M/0.87fyz = 5661.6 mm2
Asmin = 0.13bh/100 = 4446.0 mm2 <As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (bottom) = 18.0
Number of bar provided (bottom) = 27.0 NOS (B)
bar spasing = 142 mm

provide 27 Y20 at 142 c/c (B)


Area, A = 8482.32 mm2

M2/bd2fcu = 0.01851
z/d = 0.979 >0.95
As = M/0.87fyz = 4189.6 mm 2
Adopt diameter bar = 20 mm
area A = 314.160 mm2
Number of bar required (top) = 14.2
Number of bar provided (top) = 23.0 NOS (T)
bar spasing = 168 mm
provide 23 Y20 at 168 c/c (T)
Area, A = 7225.68 mm2

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 3


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.41 m
shear = 1030.8 KN
Shear stress v = 0.359 N/mm2
enhance shear stress factor, 2d/av = 3.683 (applied for pile spasing=,< 3xdia)
100As/bd = 0.296
Design stress vc = 0.447 N/mm2 O.K

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 1030.80 kN
v = 0.359 N/mm2
vc = 0.447 N/mm2 O.K

f) Stump design(ULS)

stump size,h = 2100 mm


stump size,b = 2100 mm
compression load,N = 300 KN
horizontal load = 78.0 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2040 mm
d/h = 0.97

Moment from horiz. load,M1 = 117.00 KN/m


Applied moment,M2 = 2460.00 KN/m
Total moment,M = 2577.00 KN/m
N/bh = 0.06802721
M/bh2 = 0.27826369

from chart, 100Asc/bh = 0.4


Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 3322.6 mm 2
number of bar req. = 56.15
number of bar prov. = 60 NOS
USE 60Y20 Asc = 18849.6
RNRS/0913
1
Mar-09
Ir. Rosli
mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA B1NA RNRS/0913
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 150 ft MONOPOLE 3 TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim PILE Mar-09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi Ir. Rosli

FOUNDATION CALCULATION

150 Ft Monopole 3 Tower ( 25nos 200x200 RC pile )

(a) Specification

Vertical dead load (SLS) = 293 kN


Horizontal dead load (SLS) = 129 kN
Moment (SLS) = 3439 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 25 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 460 N/mm2
Soffit Depth of Excavation = 1.15 m
Height of stump above grd = 1.5 m
Earth thickness = 0 m
Base length, l = 3.8 m
Base width, b = 3.8 m
Base depth, h = 1.15 m
Stump length = 1.5 m
Stump width = 2.1 m

(b) Check for individual Load on pile group(SLS)

pile length base on SI result = 12 m


total pile frction load base on SI result = 433 kN
total pile comp capacity base on SI resul = 1321 kN
factor of safety for pile capacity in com. = 2.5
factor of sefety for pile capacity in ten. = 2

actual pile capacity in compression = 528.4 kN


actual pile capacity in tension = 216.5 kN

distance betweenf piles = 0.750 m


x1,distance of pile from ctr col = 0.0 m
x2,distance of pile from ctr col = 0.750 m
x3,distance of pile from ctr col = 1.500 m
pile nos for row 1 = 5.0 nos
pile nos for row 2 = 5.0 nos
pile nos for row 3 = 5.0 nos
total pile nos = 25.0 nos
pile size = 0.2 m
distance of pile edge = 0.3 m
size of pile cap = 3.8 m

weight of stump = 158.8 kN


weight of pilecap = 398.5 kN
total vertical load = 850.3 kN

total ind. pile load due to vert. load = 34.0 kN

check pile capacity on tension


normally pile is critical in tension capacity which is tension and compression on individual pile assume as similar
due to applied moment. Most critical on the piles farthest away.

Total moment = 3632.5 kNm


2nd. Moment inertia of pile group, I = 28.125
pile load at row 3 due to moment, Mx/I = 193.7 O.K
pile load at row 2 due to moment, Mx/I = 96.9

check pile capacity on compression


pile to be checked for total load due to moment and vertical load

pile load at row 3 = 227.7 O.K


pile load at row 2 = 130.9

(c) Design of the moment reinforcement(ULS)

Moment for bottom bar, M1 = 3078.4 kNm


Moment for top bar, M2 = 2542.8 kNm
Cover bar = 125 mm
Diameter bar = 20 mm
Effective depth, dav = 1005 mm

M1/bd2fcu = 0.02674
z/d = 0.969 >0.95
As = M/0.87fyz = 8056.8 mm2
Asmin = 0.13bh/100 = 5681.0 mm2 <As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required (bottom) = 25.6
Number of bar provided (bottom) = 27.0 NOS (B)
bar spasing = 142 mm

provide 27 Y20 at 142 c/c (B)


Area, A = 8482.32 mm2

M2/bd2fcu = 0.02208
z/d = 0.975 >0.95
As = M/0.87fyz = 6654.8 mm2
Adopt diameter bar = 20 mm
area A = 314.160 mm2
Number of bar required (top) = 21.2
Number of bar provided (top) = 23.0 NOS (T)
bar spasing = 168 mm
provide 23 Y20 at 168 c/c (T)
Area, A = 7225.68 mm2

(d) Vertical shear(ULS)

for this case critical shear sestion at pile row 3


pile dia./5 = 0.04 m
distance at critacal shear, av = 0.41 m
shear = 2179.5 KN
Shear stress v = 0.571 N/mm2
enhance shear stress factor, 2d/av = 4.902 (applied for pile spasing=,< 3xdia)
100As/bd = 0.222
Design stress vc = 0.407 N/mm2 Please Check

(e) Punching shear and maximum shear

0.8fcu1/2 = 4.89897949 m
V = 2179.50 kN
v = 0.571 N/mm2
vc = 0.407 N/mm2 Please Check

f) Stump design(ULS)
stump size,h = 2100 mm
stump size,b = 2100 mm
compression load,N = 439.5 KN
horizontal load = 193.5 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2040 mm
d/h = 0.97

Moment from horiz. load,M1 = 290.25 KN/m


Applied moment,M2 = 5158.50 KN/m
Total moment,M = 5448.75 KN/m
N/bh = 0.09965986
M/bh2 = 0.58835439

from chart, 100Asc/bh = 0.4


Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00002
z/d = 1.000 >0.95
As = M/0.87fyz = 7025.3 mm2

number of bar req. = 56.15


number of bar prov. = 60 NOS
USE 60Y20 Asc = 18849.6 mm2
RNRS/0913
CLIENT:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 150 ft MONOPOLE 3 TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

150 Ft Monopole 3 Tower (soil bearing = 100KN/M2)

(a) Specification

Vertical dead load (SLS) = 293 kN


Horizontal dead load (SLS) = 129 kN
Moment (SLS) = 3439 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.4 m
Height of stump above grd = 0.15 m
Earth thickness = 1.65 m
Base length, l = 7 m
Base width, b = 7 m
Base depth, h = 0.75 m
Stump length = 1.8 m
Stump width = 2.1 m

(b) Maximum earth pressure(SLS)

Weight of base = 882.0 kN


Weight of soil above = 1324.3 kN
Weight of stump = 190.5 kN
Total axial load- soil = 1365.5 kN
Total axial load = 2689.8 kN
Total moment = 3671.2 kNm
Base area, A = 49.0 m2
Modulus, Z = 57.17 m3
Maximum Pressure, Pmax = 92.1 kN/m2 O.K
Minimun Pressure, Pmin = 36.4 kN/m 2

(c) Resistance to Overturning Moment(SLS)

Disturbing Moment = 3671.2 kNm


Overtaking Moment(stump) = 666.8 kNm
Overtaking Moment(base) = 3087.0 kNm
Overtaking Moment(tower load) = 1025.5 kNm
Overtaking Moment(soil on base) = 4635.1 kNm

Total Overtaking Moment = 9414.4 kNm

Allowable Factor Of Safety (F.O.S) = 1.5

Actual Factor Of Safety (F.O.S) = 2.6 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1344.92 kN


Horizontal load = 129 kN
F.O.S = 10.43 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 138.1 kN/m2


Minimum pressure, Pmin = 54.5 kN/m2
Distance at face of col = 2.45 m
Pmax, at col face = 70.70 kN/m2
Shear at col face = 255.82 kN
Moment, at face of column = 313.4 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 680 mm

M/bd2fcu = 0.00323
z/d = 0.996 >0.95
As = M/0.87fyz = 1360.0 mm 2

Asmin = 0.13bh/100 = 6825.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 21.7
Number of bar provided = 33.0 NOS
bar spasing = 216 mm

provide 33 Y20 at 216 c/c


Area, A = 10367.28

(f) Vertical shear(ULS)

1.5d = 1020 mm
Pressure at 1.5d = 98.77 kN/m2
Distance at 1.5d = 1.430 m
Vertical shear F = 1185.7 kN
Shear stress v = 0.249 N/mm2
100As/bd = 0.218
Design stress vc = 0.404 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 16.56 m
Area = 17.14 m2
Pav for punching sheer = 118.45 kN/m2
V = 3773.92 kN
v = 0.335 N/mm2
vc = 0.404 N/mm2 O.K

Pav for shear Max Vmax = 41.80 kN/m2


Vmax = 1863.92 kN
vmax = 0.33 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 2100 mm


stump size,b = 2100 mm
compression load,N = 439.5 KN
horizontal load = 193.5 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2040 mm
d/h = 0.97

Moment from horiz. load,M1 = 348.30 KN/m


Applied moment,M2 = 5158.50 KN/m
Total moment,M = 5506.80 KN/m
N/bh = 0.09965986
M/bh2 = 0.59462261

from chart, 100Asc/bh = 0.4


Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00002
z/d = 1.000 >0.95
As = M/0.87fyz = 7966.0 mm2

number of bar req. = 56.15


number of bar prov. = 60 NOS
USE 60Y20 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
3 Y20 at 216 c/c
mm2
mm2
18849.6 mm2
CLIENT:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 100 ft MONOPOLE 3 TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

100 Ft Monopole 3 Tower (soil bearing = 100KN/M2)

(a) Specification

Vertical dead load (SLS) = 152.8 kN


Horizontal dead load (SLS) = 55.2 kN
Moment (SLS) = 1243.34 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.35 m
Height of stump above grd = 0.15 m
Earth thickness = 1.5 m
Base length, l = 4.5 m
Base width, b = 4.5 m
Base depth, h = 0.85 m
Stump length = 1.65 m
Stump width = 2.1 m

(b) Maximum earth pressure(SLS)

Weight of base = 413.1 kN


Weight of soil above = 427.7 kN
Weight of stump = 174.6 kN
Total axial load- soil = 740.5 kN
Total axial load = 1168.2 kN
Total moment = 1334.42 kNm
Base area, A = 20.3 m2
Modulus, Z = 15.19 m3
Maximum Pressure, Pmax = 124.4 kN/m2 O.K
Minimun Pressure, Pmin = 51.3 kN/m 2

(c) Resistance to Overturning Moment(SLS)

Disturbing Moment = 1334.4 kNm


Overtaking Moment(stump) = 392.9 kNm
Overtaking Moment(base) = 929.5 kNm
Overtaking Moment(tower load) = 343.8 kNm
Overtaking Moment(soil on base) = 962.3 kNm

Total Overtaking Moment = 2628.5 kNm

Allowable Factor Of Safety (F.O.S) = 1.5

Actual Factor Of Safety (F.O.S) = 2.0 O.K

(d) Resistance to horizontal load

Passive resistance, R = 584.11 kN


Horizontal load = 55.2 kN
F.O.S = 10.58 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 186.6 kN/m2


Minimum pressure, Pmin = 76.9 kN/m2
Distance at face of col = 1.20 m
Pmax, at col face = 116.36 kN/m2
Shear at col face = 181.80 kN
Moment, at face of column = 109.1 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 784 mm

M/bd2fcu = 0.00131
z/d = 0.999 >0.95
As = M/0.87fyz = 410.6 mm 2

Asmin = 0.13bh/100 = 4972.5 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 24.7
Number of bar provided = 25.0 NOS
bar spasing = 183 mm

provide 25 Y16 at 206 c/c


Area, A = 5026.56

(f) Vertical shear(ULS)

1.5d = 1176 mm
Pressure at 1.5d = 185.24 kN/m2
Distance at 1.5d = 0.024 m
Vertical shear F = 20.1 kN
Shear stress v = 0.006 N/mm2
100As/bd = 0.142
Design stress vc = 0.351 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 17.808 m
Area = 19.82 m2
Pav for punching sheer = 185.95 kN/m2
V = 79.90 kN
v = 0.006 N/mm2
vc = 0.351 N/mm2 O.K

Pav for shear Max Vmax = 54.85 kN/m2


Vmax = 868.90 kN
vmax = 0.13 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 2100 mm


stump size,b = 2100 mm
compression load,N = 229.2 KN
horizontal load = 82.8 KN
bar size = 25 mm Area = 490.875
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 2037.5 mm
d/h = 0.97

Moment from horiz. load,M1 = 136.62 KN/m


Applied moment,M2 = 1865.01 KN/m
Total moment,M = 2001.63 KN/m
N/bh = 0.05197279
M/bh2 = 0.21613541

from chart, 100Asc/bh = 0.4


Asc = 17640 mm2
Asmin = 17640 mm2

M/bd2fcu = 0.00001
z/d = 1.000 >0.95
As = M/0.87fyz = 2899.1 mm2

number of bar req. = 35.94


number of bar prov. = 40 NOS
USE 40Y25 Asc =
JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/02/09
CHECKED BY:
Ir. Rosli
5 Y16 at 206 c/c
mm2
mm2
19635 mm2
CLIENT:
PERUNDING RNR SEPAKAT CELCOM
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 90 4-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

90m Tower 4-leg-(soil bearing = 100KN/M2)-CELCOM

(a) Specification

Vertical dead load (SLS) = 1251.07 kN


Horizontal dead load (SLS) = 151.97 kN
Vertical uplift (SLS) = 1049.1 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.3 m
Base length, l = 4.8 m
Base width, b = 4.8 m
Base depth, h = 0.7 m
Stump length = 2.45 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 11.93 m
Length of tie Beam = 11.93 m

(b) Maximum earth pressure(SLS)

Weight of base = 387.1 kN


Weight of soil above = 1022.6 kN
Weight of stump = 47.6 kN
Weight of tie beam = 51.5 kN
Total axial load- soil = 1737.3 kN
Total axial load = 2759.9 kN
Total moment = 372.3265 kNm
Base area, A = 23.0 m2
Modulus, Z = 18.43 m3
Maximum Pressure, Pmax = 95.6 kN/m2 O.K
Minimun Pressure, Pmin = 55.2 kN/m 2
(c) Check for uplift

Uplift force = 1049.100 kN


Length of sand with 35deg. = 8.02 m
Wt of sand with 35 incline = 2009.3 kN
Uplift resistance load = 2495.5 kN
F.O.S = 2.38 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1379.94 kN


Horizontal load = 151.97 kN
F.O.S = 9.08 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 143.4 kN/m2


Minimum pressure, Pmin = 82.8 kN/m2
Distance at face of col = 1.95 m
Pmax, at col face = 118.79 kN/m2
Shear at col face = 255.64 kN
Moment, at face of column = 249.2 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 634 mm

M/bd2fcu = 0.00431
z/d = 0.995 >0.95
As = M/0.87fyz = 1160.2 mm 2

Asmin = 0.13bh/100 = 4368.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 21.7
Number of bar provided = 22.0 NOS
bar spasing = 224 mm

provide 18 Y16 at 206 c/c


Area, A = 4423.373

(f) Vertical shear(ULS)

1.5d = 951 mm
Pressure at 1.5d = 130.79 kN/m2
Distance at 1.5d = 0.999 m
Vertical shear F = 657.4 kN
Shear stress v = 0.216 N/mm2
100As/bd = 0.145
Design stress vc = 0.353 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.208 m
Area = 7.85 m2
Pav for punching sheer = 137.10 kN/m2
V = 2082.38 kN
v = 0.293 N/mm2
vc = 0.353 N/mm2 O.K

Pav for shear Max Vmax = 113.11 kN/m2


Vmax = 2514.35 kN
vmax = 1.10 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1876.605 KN
horizontal load = 228.0 KN
uplift load = 1258.9 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 558.49 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 558.49 KN/m
N/bh = 2.3167963
M/bh2 = 0.76610391

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 3070.54 mm2 O.K


JOB NO:
RNRS/0746
CALC SHEET:
1
DATE:
14/9/02
CHECKED BY:
Ir. Rosli
8 Y16 at 206 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT CELCOM
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 75M 4-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

75m Tower 4-leg-(soil bearing = 100KN/M2)-CELCOM

(a) Specification

Vertical dead load (SLS) = 1000.864 kN


Horizontal dead load (SLS) = 85.809 kN
Vertical uplift (SLS) = 854.486 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.2 m
Base length, l = 4.1 m
Base width, b = 4.1 m
Base depth, h = 0.6 m
Stump length = 2.35 m
Stump width = 0.75 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 10 m
Length of tie Beam = 5.9 m

(b) Maximum earth pressure(SLS)

Weight of base = 242.1 kN


Weight of soil above = 714.9 kN
Weight of stump = 31.7 kN
Weight of tie beam = 25.5 kN
Total axial load- soil = 1300.1 kN
Total axial load = 2015.0 kN
Total moment = 201.65115 kNm
Base area, A = 16.8 m2
Modulus, Z = 11.49 m3
Maximum Pressure, Pmax = 94.9 kN/m2 O.K
Minimun Pressure, Pmin = 59.8 kN/m 2
(c) Check for uplift

Uplift force = 854.486 kN


Length of sand with 35deg. = 7.18 m
Wt of sand with 35 incline = 1504.0 kN
Uplift resistance load = 1803.2 kN
F.O.S = 2.11 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1007.52 kN


Horizontal load = 85.809 kN
F.O.S = 11.74 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 142.3 kN/m2


Minimum pressure, Pmin = 89.7 kN/m2
Distance at face of col = 1.68 m
Pmax, at col face = 120.83 kN/m2
Shear at col face = 220.41 kN
Moment, at face of column = 184.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00526
z/d = 0.994 >0.95
As = M/0.87fyz = 1020.1 mm 2

Asmin = 0.15bh/100 = 3690.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 18.4
Number of bar provided = 19.0 NOS
bar spasing = 222 mm

provide 18 Y16 at 206 c/c


Area, A = 3820.186

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 131.12 kN/m2
Distance at 1.5d = 0.874 m
Vertical shear F = 490.0 kN
Shear stress v = 0.224 N/mm2
100As/bd = 0.174
Design stress vc = 0.375 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 136.73 kN/m2
V = 1542.10 kN
v = 0.307 N/mm2
vc = 0.375 N/mm2 O.K

Pav for shear Max Vmax = 116.01 kN/m2


Vmax = 1884.95 kN
vmax = 1.18 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 750 mm


stump size,b = 750 mm
compression load,N = 1501.296 KN
horizontal load = 128.7 KN
uplift load = 1025.4 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 694 mm
d/h = 0.93

moment from horiz. load,M1 = 302.48 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 302.48 KN/m
N/bh = 2.66897067
M/bh2 = 0.71698187

from chart, 100Asc/bh = 0.4


Asc = 2250 mm2
Asmin = 2250 mm2
number of bar req. = 7.16
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2500.93 mm2 O.K


JOB NO:
RNRS/0746
CALC SHEET:
3-Jan
DATE:
14/9/02
CHECKED BY:
Ir. Rosli
8 Y16 at 206 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT CELCOM
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 75M 4-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

75m Tower 4-leg-(soil bearing = 100KN/M2)-CELCOM

(a) Specification

Vertical dead load (SLS) = 1000.864 kN


Horizontal dead load (SLS) = 85.809 kN
Vertical uplift (SLS) = 854.486 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 3.6 m
Base width, b = 3.6 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.75 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 10 m
Length of tie Beam = 6.4 m

(b) Maximum earth pressure(SLS)

Weight of base = 186.6 kN


Weight of soil above = 595.1 kN
Weight of stump = 34.4 kN
Weight of tie beam = 27.6 kN
Total axial load- soil = 1249.6 kN
Total axial load = 1844.6 kN
Total moment = 218.81295 kNm
Base area, A = 13.0 m2
Modulus, Z = 7.78 m3
Maximum Pressure, Pmax = 124.6 kN/m2 O.K
Minimun Pressure, Pmin = 68.3 kN/m 2
(c) Check for uplift

Uplift force = 854.486 kN


Length of sand with 35deg. = 6.96 m
Wt of sand with 35 incline = 1473.6 kN
Uplift resistance load = 1722.3 kN
F.O.S = 2.02 O.K

(d) Resistance to horizontal load

Passive resistance, R = 922.32 kN


Horizontal load = 85.809 kN
F.O.S = 10.75 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 186.8 kN/m2


Minimum pressure, Pmin = 102.4 kN/m2
Distance at face of col = 1.43 m
Pmax, at col face = 153.42 kN/m2
Shear at col face = 242.43 kN
Moment, at face of column = 172.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00561
z/d = 0.994 >0.95
As = M/0.87fyz = 954.6 mm 2

Asmin = 0.15bh/100 = 3240.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 16.1
Number of bar provided = 18.0 NOS
bar spasing = 206 mm

provide 18 Y16 at 206 c/c


Area, A = 3619.123

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 172.20 kN/m2
Distance at 1.5d = 0.624 m
Vertical shear F = 403.3 kN
Shear stress v = 0.210 N/mm2
100As/bd = 0.188
Design stress vc = 0.385 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 179.52 kN/m2
V = 1333.48 kN
v = 0.265 N/mm2
vc = 0.385 N/mm2 O.K

Pav for shear Max Vmax = 144.63 kN/m2


Vmax = 1792.99 kN
vmax = 1.12 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 750 mm


stump size,b = 750 mm
compression load,N = 1501.296 KN
horizontal load = 128.7 KN
uplift load = 1025.4 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 694 mm
d/h = 0.93

moment from horiz. load,M1 = 328.22 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 328.22 KN/m
N/bh = 2.66897067
M/bh2 = 0.7780016

from chart, 100Asc/bh = 0.4


Asc = 2250 mm2
Asmin = 2250 mm2
number of bar req. = 7.16
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2500.93 mm2 O.K


JOB NO:
RNRS/0701
CALC SHEET:
3-Jan
DATE:
14/9/02
CHECKED BY:
Ir. Rosli
8 Y16 at 206 c/c
mm2
mm2

3769.92 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT CELCOM RNRS/0701
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 3-Jan
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING 14/9/02
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-CELCOM

(a) Specification

Vertical dead load (SLS) = 936.59 kN


Horizontal dead load (SLS) = 58.27 kN
Vertical uplift (SLS) = 817.43 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.2 m
Base length, l = 3.9 m
Base width, b = 3.9 m
Base depth, h = 0.6 m
Stump length = 2.35 m
Stump width = 0.75 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 7.7 m
Length of tie Beam = 3.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 219.0 kN


Weight of soil above = 644.5 kN
Weight of stump = 31.7 kN
Weight of tie beam = 16.4 kN
Total axial load- soil = 1203.8 kN
Total axial load = 1848.2 kN
Total moment = 136.9345 kNm
Base area, A = 15.2 m2
Modulus, Z = 9.89 m3
Maximum Pressure, Pmax = 93.0 kN/m2 O.K
Minimun Pressure, Pmin = 65.3 kN/m 2

(c) Check for uplift

Uplift force = 817.430 kN


Length of sand with 35deg. = 6.98 m
Wt of sand with 35 incline = 1406.5 kN
Uplift resistance load = 1673.6 kN
F.O.S = 2.05 O.K

(d) Resistance to horizontal load

Passive resistance, R = 924.12 kN


Horizontal load = 58.27 kN
F.O.S = 15.86 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 139.5 kN/m2


Minimum pressure, Pmin = 97.9 kN/m2
Distance at face of col = 1.58 m
Pmax, at col face = 122.71 kN/m2
Shear at col face = 206.48 kN
Moment, at face of column = 162.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00487
z/d = 0.995 >0.95
As = M/0.87fyz = 898.6 mm 2

Asmin = 0.15bh/100 = 3510.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 17.5
Number of bar provided = 20.0 NOS
bar spasing = 200 mm

provide 20 Y16 at 200 c/c


Area, A = 4021.248 mm2

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 131.24 kN/m2
Distance at 1.5d = 0.774 m
Vertical shear F = 408.6 kN
Shear stress v = 0.196 N/mm2
100As/bd = 0.193
Design stress vc = 0.388 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 135.37 kN/m2
V = 1310.09 kN
v = 0.261 N/mm2
vc = 0.388 N/mm2 O.K
Pav for shear Max Vmax = 118.71 kN/m2
Vmax = 1738.86 kN
vmax = 1.09 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 750 mm


stump size,b = 750 mm
compression load,N = 1404.885 KN
horizontal load = 87.4 KN
uplift load = 980.9 KN
bar size = 20 mm Area = 314.16 mm2
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 694 mm
d/h = 0.93

moment from horiz. load,M1 = 205.40 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 205.40 KN/m
N/bh = 2.49757333
M/bh2 = 0.48687822

from chart, 100Asc/bh = 0.4


Asc = 2250 mm2
Asmin = 2250 mm2
number of bar req. = 7.16
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2392.48 mm2 O.K


RNRS/0701
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/9 Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1308 kN


Horizontal dead load (SLS) = 136 kN
Vertical uplift (SLS) = 1261 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.6 m
Height of stump above grd = 0.15 m
Earth thickness = 3 m
Base length, l = 4.1 m
Base width, b = 4.1 m
Base depth, h = 0.6 m
Stump length = 3.15 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 9.912 m
Length of tie Beam = 5.812 m

(b) Maximum earth pressure(SLS)

Weight of base = 242.1 kN


Weight of soil above = 970.2 kN
Weight of stump = 48.4 kN
Weight of tie beam = 25.1 kN
Total axial load- soil = 1623.6 kN
Total axial load = 2593.8 kN
Total moment = 428.4 kNm
Base area, A = 16.8 m2
Modulus, Z = 11.49 m3
Maximum Pressure, Pmax = 133.9 kN/m2 O.K
Minimun Pressure, Pmin = 59.3 kN/m 2
(c) Check for uplift

Uplift force = 1261.000 kN


Length of sand with 35deg. = 8.30 m
Wt of sand with 35 incline = 2571.0 kN
Uplift resistance load = 2886.6 kN
F.O.S = 2.29 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1296.88 kN


Horizontal load = 136 kN
F.O.S = 9.54 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 200.8 kN/m2


Minimum pressure, Pmin = 88.9 kN/m2
Distance at face of col = 1.65 m
Pmax, at col face = 155.79 kN/m2
Shear at col face = 294.20 kN
Moment, at face of column = 242.7 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 530 mm

M/bd2fcu = 0.00843
z/d = 0.991 >0.95
As = M/0.87fyz = 1351.4 mm 2

Asmin = 0.15bh/100 = 3690.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 11.7
Number of bar provided = 21.0 NOS
bar spasing = 200 mm

provide21 Y16 at 200 c/c


Area, A = 6597.36

(f) Vertical shear(ULS)

1.5d = 795 mm
Pressure at 1.5d = 177.48 kN/m2
Distance at 1.5d = 0.855 m
Vertical shear F = 663.1 kN
Shear stress v = 0.305 N/mm2
100As/bd = 0.304
Design stress vc = 0.425 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.56 m
Area = 5.71 m2
Pav for punching sheer = 189.15 kN/m2
V = 2099.17 kN
v = 0.414 N/mm2
vc = 0.425 N/mm2 O.K

Pav for shear Max Vmax = 144.87 kN/m2


Vmax = 2342.61 kN
vmax = 1.38 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1962 KN
horizontal load = 204.0 KN
uplift load = 1513.2 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 642.60 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 642.60 KN/m
N/bh = 3.065625
M/bh2 = 1.25507813

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 3690.73 mm2 O.K


JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
1 Y16 at 200 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (110 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/13 Rumaizi

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 110KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1909 kN


Horizontal dead load (SLS) = 212 kN
Vertical uplift (SLS) = 1760 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 110 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.6 m
Height of stump above grd = 0.15 m
Earth thickness = 2.8 m
Base length, l = 5.5 m
Base width, b = 5.5 m
Base depth, h = 0.8 m
Stump length = 2.95 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 9.912 m
Length of tie Beam = 4.412 m

(b) Maximum earth pressure(SLS)

Weight of base = 580.8 kN


Weight of soil above = 1658.2 kN
Weight of stump = 45.3 kN
Weight of tie beam = 19.1 kN
Total axial load- soil = 2554.2 kN
Total axial load = 4212.3 kN
Total moment = 625.4 kNm
Base area, A = 30.3 m2
Modulus, Z = 27.73 m3
Maximum Pressure, Pmax = 107.0 kN/m2 O.K
Minimun Pressure, Pmin = 61.9 kN/m 2
(c) Check for uplift

Uplift force = 1760.000 kN


Length of sand with 35deg. = 9.42 m
Wt of sand with 35 incline = 3331.6 kN
Uplift resistance load = 3976.8 kN
F.O.S = 2.26 O.K

(d) Resistance to horizontal load

Passive resistance, R = 2106.17 kN


Horizontal load = 212 kN
F.O.S = 9.93 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 149.8 kN/m2


Minimum pressure, Pmin = 86.6 kN/m2
Distance at face of col = 2.35 m
Pmax, at col face = 122.80 kN/m2
Shear at col face = 320.29 kN
Moment, at face of column = 376.3 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 730 mm

M/bd2fcu = 0.00514
z/d = 0.994 >0.95
As = M/0.87fyz = 1521.4 mm 2

Asmin = 0.13bh/100 = 5720.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 18.2
Number of bar provided = 28.0 NOS
bar spasing = 200 mm

provide28 Y16 at 200 c/c


Area, A = 8796.48

(f) Vertical shear(ULS)

1.5d = 1095 mm
Pressure at 1.5d = 135.38 kN/m2
Distance at 1.5d = 1.255 m
Vertical shear F = 984.2 kN
Shear stress v = 0.245 N/mm2
100As/bd = 0.219
Design stress vc = 0.381 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.96 m
Area = 8.94 m2
Pav for punching sheer = 142.58 kN/m2
V = 3038.37 kN
v = 0.348 N/mm2
vc = 0.381 N/mm2 O.K

Pav for shear Max Vmax = 118.21 kN/m2


Vmax = 3500.19 kN
vmax = 1.50 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 2863.5 KN
horizontal load = 318.0 KN
uplift load = 2112.0 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 938.10 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 938.10 KN/m
N/bh = 4.47421875
M/bh2 = 1.83222656

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS
USE 20Y20 Asc =

Area of bar req. due to uplift = 5151.22 mm2 O.K


JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
8 Y16 at 200 c/c
mm2
mm2

6283.2 mm2
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A Rumaizi

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1909 kN


Horizontal dead load (SLS) = 212 kN
Vertical uplift (SLS) = 1760 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 130 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.6 m
Height of stump above grd = 0.15 m
Earth thickness = 2.9 m
Base length, l = 5 m
Base width, b = 5 m
Base depth, h = 0.7 m
Stump length = 3.05 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.6 m
Length between ftg = 9.912 m
Length of tie Beam = 9.912 m

(b) Maximum earth pressure(SLS)

Weight of base = 420.0 kN


Weight of soil above = 1412.9 kN
Weight of stump = 46.8 kN
Weight of tie beam = 85.6 kN
Total axial load- soil = 2461.5 kN
Total axial load = 3874.4 kN
Total moment = 646.6 kNm
Base area, A = 25.0 m2
Modulus, Z = 20.83 m3
Maximum Pressure, Pmax = 129.5 kN/m2 O.K
Minimun Pressure, Pmin = 67.4 kN/m 2
(c) Check for uplift

Uplift force = 1760.000 kN


Length of sand with 35deg. = 9.06 m
Wt of sand with 35 incline = 3105.4 kN
Uplift resistance load = 3657.9 kN
F.O.S = 2.08 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1937.18 kN


Horizontal load = 212 kN
F.O.S = 9.14 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 155.4 kN/m2


Minimum pressure, Pmin = 80.9 kN/m2
Distance at face of col = 2.10 m
Pmax, at col face = 124.11 kN/m2
Shear at col face = 293.48 kN
Moment, at face of column = 308.2 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 630 mm

M/bd2fcu = 0.00621
z/d = 0.993 >0.95
As = M/0.87fyz = 1443.5 mm 2

Asmin = 0.15bh/100 = 5250.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 16.7
Number of bar provided = 21.0 NOS
bar spasing = 245 mm

provide21 Y20 at 245 c/c


Area, A = 6597.36

(f) Vertical shear(ULS)

1.5d = 945 mm
Pressure at 1.5d = 138.19 kN/m2
Distance at 1.5d = 1.155 m
Vertical shear F = 847.7 kN
Shear stress v = 0.269 N/mm2
100As/bd = 0.209
Design stress vc = 0.375 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.76 m
Area = 7.24 m2
Pav for punching sheer = 146.79 kN/m2
V = 2607.60 kN
v = 0.385 N/mm2
vc = 0.413 N/mm2 O.K

Pav for shear Max Vmax = 118.15 kN/m2


Vmax = 2878.17 kN
vmax = 1.43 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 2863.5 KN
horizontal load = 318.0 KN
uplift load = 2112.0 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 969.90 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 969.90 KN/m
N/bh = 4.47421875
M/bh2 = 1.89433594

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS
USE 20Y20 Asc =

Area of bar req. due to uplift = 5151.22 mm2 O.K


JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
1 Y20 at 245 c/c
mm2
mm2

6283.2 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/0832
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 11/3/2009
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2-S19 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1103 kN


Horizontal dead load (SLS) = 128 kN
Vertical uplift (SLS) = 903 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.5 m
Base length, l = 3.8 m
Base width, b = 3.8 m
Base depth, h = 0.5 m
Stump length = 2.65 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.6 m
Length between ftg = 9.841 m
Length of tie Beam = 9.841 m

(b) Maximum earth pressure(SLS)

Weight of base = 173.3 kN


Weight of soil above = 690.0 kN
Weight of stump = 40.7 kN
Weight of tie beam = 85.0 kN
Total axial load- soil = 1402.0 kN
Total axial load = 2092.0 kN
Total moment = 339.2 kNm
Base area, A = 14.4 m2
Modulus, Z = 9.15 m3
Maximum Pressure, Pmax = 134.2 kN/m2 O.K
Minimun Pressure, Pmin = 60.0 kN/m2

(c) Check for uplift

Uplift force = 903.000 kN


Length of sand with 35deg. = 7.30 m
Wt of sand with 35 incline = 1693.3 kN
Uplift resistance load = 1992.3 kN
F.O.S = 2.21 O.K
(d) Resistance to horizontal load

Passive resistance, R = 1046.01 kN


Horizontal load = 128 kN
F.O.S = 8.17 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 161.0 kN/m2


Minimum pressure, Pmin = 72.0 kN/m2
Distance at face of col = 1.50 m
Pmax, at col face = 125.88 kN/m2
Shear at col face = 215.17 kN
Moment, at face of column = 161.4 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 430 mm

M/bd2fcu = 0.00919
z/d = 0.990 >0.95
As = M/0.87fyz = 1107.5 mm 2

Asmin = 0.15bh/100 = 2850.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 9.1
Number of bar provided = 18.0 NOS
bar spasing = 218 mm

provide18 Y20 at 218 c/c


Area, A = 5654.88 mm2

(f) Vertical shear(ULS)

1.5d = 645 mm
Pressure at 1.5d = 140.99 kN/m2
Distance at 1.5d = 0.855 m
Vertical shear F = 490.6 kN
Shear stress v = 0.300 N/mm2
100As/bd = 0.346
Design stress vc = 0.444 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 8.36 m
Area = 4.37 m2
Pav for punching sheer = 151.00 kN/m2
V = 1520.90 kN
v = 0.423 N/mm2
vc = 0.488 N/mm2 O.K

Pav for shear Max Vmax = 116.51 kN/m2


Vmax = 1607.85 kN
vmax = 1.17 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1654.5 KN
horizontal load = 192.0 KN
uplift load = 1083.6 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 508.80 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 508.80 KN/m
N/bh = 2.58515625
M/bh2 = 0.99375

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2642.93 mm2 O.K


CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/0832
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (75 KN/M2) 24/10/08
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/0832/18 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 75 KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1909 kN


Horizontal dead load (SLS) = 212 kN
Vertical uplift (SLS) = 1760 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.275 m
Base length, l = 6.6 m
Base width, b = 6.6 m
Base depth, h = 0.725 m
Stump length = 2.425 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.6 m
Length between ftg = 9.912 m
Length of tie Beam = 9.912 m

(b) Maximum earth pressure(SLS)

Weight of base = 757.9 kN


Weight of soil above = 1952.9 kN
Weight of stump = 37.2 kN
Weight of tie beam = 85.6 kN
Total axial load- soil = 2789.8 kN
Total axial load = 4742.7 kN
Total moment = 514.1 kNm
Base area, A = 43.6 m2
Modulus, Z = 47.92 m3
Maximum Pressure, Pmax = 74.8 kN/m2 O.K
Minimun Pressure, Pmin = 53.3 kN/m2

(c) Check for uplift

Uplift force = 1760.000 kN


Length of sand with 35deg. = 9.79 m
Wt of sand with 35 incline = 3169.2 kN
Uplift resistance load = 4050.0 kN
F.O.S = 2.30 O.K

(d) Resistance to horizontal load

Passive resistance, R = 2371.35 kN


Horizontal load = 212 kN
F.O.S = 11.19 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 89.7 kN/m2


Minimum pressure, Pmin = 64.0 kN/m2
Distance at face of col = 2.90 m
Pmax, at col face = 78.42 kN/m2
Shear at col face = 243.81 kN
Moment, at face of column = 353.5 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 655 mm

M/bd2fcu = 0.00499
z/d = 0.994 >0.95
As = M/0.87fyz = 1592.8 mm 2

Asmin = 0.15bh/100 = 7177.5 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 22.8
Number of bar provided = 33.0 NOS
bar spasing = 203 mm

provide33 Y20 at 203 c/c


Area, A = 10367.28 mm2

(f) Vertical shear(ULS)

1.5d = 982.5 mm
Pressure at 1.5d = 82.25 kN/m2
Distance at 1.5d = 1.918 m
Vertical shear F = 1088.2 kN
Shear stress v = 0.252 N/mm2
100As/bd = 0.240
Design stress vc = 0.393 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.06 m
Area = 7.65 m2
Pav for punching sheer = 85.99 kN/m2
V = 3088.29 kN
v = 0.426 N/mm2
vc = 0.432 N/mm2 O.K

Pav for shear Max Vmax = 76.85 kN/m2


Vmax = 3298.61 kN
vmax = 1.57 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 2863.5 KN
horizontal load = 318.0 KN
uplift load = 2112.0 KN
bar size = 20 mm Area = 314.16 mm2
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 771.15 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 771.15 KN/m
N/bh = 4.47421875
M/bh2 = 1.50615234

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS
USE 20Y20 Asc = 6283.2 mm2

Area of bar req. due to uplift = 5151.22 mm2 O.K


RNRS/0832
CLIENT:
PERUNDING RNR SEPAKAT INFRAQUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim RAFT (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/15 Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-TOWER MASTER

(a) Specification

Vertical dead load (SLS) = 1251.07 kN


Horizontal dead load (SLS) = 151.97 kN
Vertical uplift (SLS) = 1049.1 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 1.05 m
Height of stump above grd = 0.75 m
Earth thickness = 0 m
Base length, l = 16.5 m
Base width, b = 16.5 m
Base depth, h = 1.05 m
Stump length = 0.75 m
Stump width = 0.9 m

(b) Maximum earth pressure(SLS)

Weight of base = 6860.7 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 43.7 kN
Total axial load = 12039.9 kN
Total moment = 455.91 kNm
Base area, A = 272.3 m2
Modulus, Z = 748.69 m3
Average Pressure, Pav = 44.2 kN/m2 O.K

(c) Check for uplift

Uplift force = 2098.200 kN


Uplift resistance load = 9030.0 kN
F.O.S = 4.30 O.K

(d) Resistance to horizontal load


Passive resistance, R = 6019.97 kN
Horizontal load = 607.88 kN
F.O.S = 9.90 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 980 mm

Asmin = 0.13bh/100 = 1365.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 230 mm

since the thickness is 1.2m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1876.605 KN
horizontal load = 228.0 KN
uplift load = 1258.9 KN
bar size = 20 mm
link size = 6 mm Area = 314.16
cover = 40 mm
Eff. Depth, d = 844 mm
d/h = 0.94

moment from horiz. load,M1 = 170.97 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 170.97 KN/m
N/bh = 2.3167963
M/bh2 = 0.2345216

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS

USE 12Y20 Asc =


Area of bar req. due to uplift = 3070.54 mm 2
O.K
JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
mm2

3769.92
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim RAFT (100 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/15 Rumaizi

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 100KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 779 kN


Horizontal dead load (SLS) = 84 kN
Vertical uplift (SLS) = 690 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.9 m
Earth thickness = 0 m
Base length, l = 9 m
Base width, b = 8.2 m
Base depth, h = 0.9 m
Stump length = 0.9 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 1594.1 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 41.5 kN
Total axial load = 4055.5 kN
Total moment = 75.6 kNm
Base area, A = 73.8 m2
Modulus, Z = 110.70 m3
Average Pressure, Pav = 55.0 kN/m2 O.K

(c) Check for uplift

Uplift force = 690.000 kN


Uplift resistance load = 3041.6 kN
F.O.S = 4.41 O.K

(d) Resistance to horizontal load


Passive resistance, R = 2027.75 kN
Horizontal load = 84 kN
F.O.S = 24.14 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

Asmin = 0.13bh/100 = 1170.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 269 mm

since the thickness is 1.2m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1168.5 KN
horizontal load = 126.0 KN
uplift load = 828.0 KN
bar size = 20 mm
link size = 6 mm Area = 314.16
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 113.40 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 113.40 KN/m
N/bh = 1.82578125
M/bh2 = 0.22148438

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc =


Area of bar req. due to uplift = 2019.51 mm 2
O.K
JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
mm2

3769.92
CLIENT:
PERUNDING RNR SEPAKAT INFRAQUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim RAFT (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/15 Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-TOWER MASTER

(a) Specification

Vertical dead load (SLS) = 1001 kN


Horizontal dead load (SLS) = 109 kN
Vertical uplift (SLS) = 739 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 1.05 m
Height of stump above grd = 0.75 m
Earth thickness = 0 m
Base length, l = 9.9 m
Base width, b = 11 m
Base depth, h = 1.05 m
Stump length = 0.75 m
Stump width = 0.9 m

(b) Maximum earth pressure(SLS)

Weight of base = 2744.3 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 43.7 kN
Total axial load = 5878.5 kN
Total moment = 81.75 kNm
Base area, A = 108.9 m2
Modulus, Z = 179.69 m3
Average Pressure, Pav = 54.0 kN/m2 O.K

(c) Check for uplift

Uplift force = 739.000 kN


Uplift resistance load = 4408.9 kN
F.O.S = 5.97 O.K

(d) Resistance to horizontal load


Passive resistance, R = 2939.25 kN
Horizontal load = 109 kN
F.O.S = 26.97 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 980 mm

Asmin = 0.13bh/100 = 1365.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 230 mm

since the thickness is 1.2m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1501.5 KN
horizontal load = 163.5 KN
uplift load = 886.8 KN
bar size = 20 mm
link size = 6 mm Area = 314.16
cover = 40 mm
Eff. Depth, d = 844 mm
d/h = 0.94

moment from horiz. load,M1 = 122.63 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 122.63 KN/m
N/bh = 1.8537037
M/bh2 = 0.16820988

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS

USE 12Y20 Asc =


Area of bar req. due to uplift = 2162.93 mm 2
O.K
JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
mm2

3769.92
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRAQUEST RNRS/0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim RAFT (150 KN/M2) 24/7/09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3-10 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-ROHAS

(a) Specification

Vertical dead load (SLS) = 691 kN


Horizontal dead load (SLS) = 81 kN
Vertical uplift (SLS) = 562 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.6 m
Earth thickness = 0 m
Base length, l = 9.9 m
Base width, b = 11 m
Base depth, h = 0.9 m
Stump length = 0.6 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 2352.2 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 27.6 kN
Total axial load = 4508.2 kN
Total moment = 48.6 kNm
Base area, A = 108.9 m2
Modulus, Z = 179.69 m3
Average Pressure, Pav = 41.4 kN/m2 O.K

(c) Check for uplift

Uplift force = 562.000 kN


Uplift resistance load = 3381.1 kN
F.O.S = 6.02 O.K

(d) Resistance to horizontal load

Passive resistance, R = 2254.09 kN


Horizontal load = 81 kN
F.O.S = 27.83 O.K
(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

Asmin = 0.13bh/100 = 1170.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 269 mm

since the thickness is 0.9m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1036.5 KN
horizontal load = 121.5 KN
uplift load = 674.4 KN
bar size = 20 mm
link size = 6 mm Area = 314.16 mm2
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 72.90 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 72.90 KN/m
N/bh = 1.61953125
M/bh2 = 0.14238281

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc = 3769.92


Area of bar req. due to uplift = 1644.88 mm 2
O.K
RNRS/0945
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRAQUEST RNRS/0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim RAFT (150 KN/M2) 24/7/09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3-9 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-ROHAS

(a) Specification

Vertical dead load (SLS) = 788 kN


Horizontal dead load (SLS) = 87 kN
Vertical uplift (SLS) = 609 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.6 m
Earth thickness = 0 m
Base length, l = 9.9 m
Base width, b = 11 m
Base depth, h = 0.9 m
Stump length = 0.6 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 2352.2 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 27.6 kN
Total axial load = 4799.2 kN
Total moment = 52.2 kNm
Base area, A = 108.9 m2
Modulus, Z = 179.69 m3
Average Pressure, Pav = 44.1 kN/m2 O.K

(c) Check for uplift

Uplift force = 609.000 kN


Uplift resistance load = 3599.4 kN
F.O.S = 5.91 O.K

(d) Resistance to horizontal load

Passive resistance, R = 2399.59 kN


Horizontal load = 87 kN
F.O.S = 27.58 O.K
(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

Asmin = 0.13bh/100 = 1170.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 269 mm

since the thickness is 0.9m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1182 KN
horizontal load = 130.5 KN
uplift load = 730.8 KN
bar size = 20 mm
link size = 6 mm Area = 314.16 mm2
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 78.30 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 78.30 KN/m
N/bh = 1.846875
M/bh2 = 0.15292969

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc = 3769.92


Area of bar req. due to uplift = 1782.44 mm 2
O.K
RNRS/0945
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRAQUEST RNRS/0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim RAFT (150 KN/M2) Aug-09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 S10 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-SEGENTING

(a) Specification

Vertical dead load (SLS) = 691 kN


Horizontal dead load (SLS) = 81 kN
Vertical uplift (SLS) = 562 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 0.9 m
Height of stump above grd = 0.6 m
Earth thickness = 0 m
Base length, l = 9.9 m
Base width, b = 11 m
Base depth, h = 0.9 m
Stump length = 0.6 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 2352.2 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 27.6 kN
Total axial load = 4508.2 kN
Total moment = 48.6 kNm
Base area, A = 108.9 m2
Modulus, Z = 179.69 m3
Average Pressure, Pav = 41.4 kN/m2 O.K

(c) Check for uplift

Uplift force = 562.000 kN


Uplift resistance load = 4508.2 kN
F.O.S = 8.02 O.K

(d) Resistance to horizontal load

Passive resistance, R = 2254.09 kN


Horizontal load = 81 kN
F.O.S = 27.83 O.K
(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

Asmin = 0.13bh/100 = 1170.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 269 mm

since the thickness is 1.2m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1036.5 KN
horizontal load = 121.5 KN
uplift load = 674.4 KN
bar size = 20 mm
link size = 10 mm Area = 314.16 mm2
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 72.90 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 72.90 KN/m
N/bh = 1.61953125
M/bh2 = 0.14238281

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc = 3769.92


Area of bar req. due to uplift = 1644.88 mm 2
O.K
RNRS/0945
CLIENT:
PERUNDING RNR SEPAKAT INFRAQUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim RAFT (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/15 Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-SEGENTING

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 1.2 m
Height of stump above grd = 0.6 m
Earth thickness = 0 m
Base length, l = 9.9 m
Base width, b = 11 m
Base depth, h = 1.2 m
Stump length = 0.6 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 3136.3 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 27.6 kN
Total axial load = 6414.3 kN
Total moment = 69 kNm
Base area, A = 108.9 m2
Modulus, Z = 179.69 m3
Average Pressure, Pav = 58.9 kN/m2 O.K

(c) Check for uplift

Uplift force = 851.000 kN


Uplift resistance load = 6414.3 kN
F.O.S = 7.54 O.K

(d) Resistance to horizontal load


Passive resistance, R = 3207.13 kN
Horizontal load = 115 kN
F.O.S = 27.89 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 1130 mm

Asmin = 0.13bh/100 = 1560.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 201 mm

since the thickness is 1.2m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm
link size = 6 mm Area = 314.16
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 103.50 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 103.50 KN/m
N/bh = 2.49609375
M/bh2 = 0.20214844

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc =


Area of bar req. due to uplift = 2490.73 mm 2
O.K
JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
mm2

3769.92
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim RAFT (100 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T2/15 Rumaizi

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 100KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1909 kN


Horizontal dead load (SLS) = 212 kN
Vertical uplift (SLS) = 1760 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 1.2 m
Height of stump above grd = 0.6 m
Earth thickness = 0 m
Base length, l = 11.5 m
Base width, b = 13 m
Base depth, h = 1.2 m
Stump length = 0.6 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 4305.6 kN


Weight of soil above = 0.0 kN
Total Weight of stump = 27.6 kN
Total axial load = 10115.5 kN
Total moment = 127.2 kNm
Base area, A = 149.5 m2
Modulus, Z = 286.54 m3
Average Pressure, Pav = 67.7 kN/m2 O.K

(c) Check for uplift

Uplift force = 1760.000 kN


Uplift resistance load = 10115.5 kN
F.O.S = 5.75 O.K

(d) Resistance to horizontal load


Passive resistance, R = 5057.77 kN
Horizontal load = 212 kN
F.O.S = 23.86 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 1130 mm

Asmin = 0.13bh/100 = 1560.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 201 mm

since the thickness is 1.2m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 2863.5 KN
horizontal load = 318.0 KN
uplift load = 2112.0 KN
bar size = 20 mm
link size = 6 mm Area = 314.16
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 190.80 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 190.80 KN/m
N/bh = 4.47421875
M/bh2 = 0.37265625

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS

USE 20Y20 Asc =


Area of bar req. due to uplift = 5151.22 mm 2
O.K
JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
mm2

6283.2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60m light duty
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m light duty

(a) Specification

Vertical dead load (SLS) = 280.2 kN


Horizontal dead load (SLS) = 224.1 kN
Moment (SLS) = 9184.9 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2 m
Height of stump above grd = 0.15 m
Earth thickness = 1.1 m
Base length, l = 12.5 m
Base width, b = 12.5 m
Base depth, h = 0.9 m
Stump length = 1.25 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 3375.0 kN


Weight of soil above = 3081.1 kN
Weight of stump = 19.2 kN
Total axial load- soil = 3674.4 kN
Total axial load = 6755.5 kN
Total moment = 9465.025 kNm
Base area, A = 156.3 m2
Modulus, Z = 325.52 m3
Maximum Pressure, Pmax = 52.6 kN/m2 O.K
Minimun Pressure, Pmin = 5.6 kN/m 2

(c) Resistance to Overturning Moment(SLS)

Disturbing Moment = 9465.0 kNm

Overtaking Moment(stump) = 120.0 kNm


Overtaking Moment(base) = 21093.8 kNm
Overtaking Moment(tower load) = 1751.3 kNm
Overtaking Moment(soil on base) = 19256.7 kNm

Total Overtaking Moment = 42221.7 kNm

Allowable Factor Of Safety (F.O.S) = 1.5

Actual Factor Of Safety (F.O.S) = 4.5 O.K

(d) Resistance to horizontal load

Passive resistance, R = 3377.74 kN


Horizontal load = 224.1 kN
F.O.S = 15.07 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 78.9 kN/m2


Minimum pressure, Pmin = 8.3 kN/m2
Distance at face of col = 5.85 m
Pmax, at col face = 38.07 kN/m2
Shear at col face = 342.09 kN
Moment, at face of column = 1000.6 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

M/bd2fcu = 0.00387
z/d = 0.996 >0.95
As = M/0.87fyz = 3557.7 mm 2

Asmin = 0.13bh/100 = 14625.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 46.6
Number of bar provided = 50.0 NOS
bar spasing = 253 mm

provide 25 Y16 at 206 c/c


Area, A = 15708 mm2

(f) Vertical shear(ULS)

1.5d = 1245 mm
Pressure at 1.5d = 46.75 kN/m2
Distance at 1.5d = 4.605 m
Vertical shear F = 3616.2 kN
Shear stress v = 0.349 N/mm2
100As/bd = 0.151
Design stress vc = 0.358 N/mm2 O.K
(g) Punching shear and maximum shear

Perimeter = 13.16 m
Area = 10.82 m2
Pav for punching sheer = 62.82 kN/m2
V = 9135.85 kN
v = 0.836 N/mm2
vc = 0.358 N/mm2 Please Check

Pav for shear Max Vmax = 35.27 kN/m2


Vmax = 5489.02 kN
vmax = 2.07 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 420.3 KN
horizontal load = 336.2 KN
bar size = 25 mm Area = 490.875 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 737.5 mm
d/h = 0.92

Moment from horiz. load,M1 = 420.19 KN/m


Applied moment,M2 = 13777.35 KN/m
Total moment,M = 14197.54 KN/m
N/bh = 0.65671875
M/bh2 = 27.7295654

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2

M/bd2fcu = 0.00109
z/d = 0.999 >0.95
As = M/0.87fyz = 56809.9 mm2

number of bar req. = 0.00


number of bar prov. = 40 NOS
USE 40Y25 Asc = 19635
RNRS/0746
1
14/02/09
Ir. Rosli
mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA B1NA
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60m light duty
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m light duty

(a) Specification

Vertical dead load (SLS) = 143.3 kN


Horizontal dead load (SLS) = 118.3 kN
Moment (SLS) = 3918.3 kNm
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 1.5 m
Height of stump above grd = 0.15 m
Earth thickness = 0.6 m
Base length, l = 7 m
Base width, b = 7 m
Base depth, h = 0.9 m
Stump length = 0.75 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 1058.4 kN


Weight of soil above = 522.3 kN
Weight of stump = 11.5 kN
Total axial load- soil = 1213.2 kN
Total axial load = 1735.5 kN
Total moment = 4007.025 kNm
Base area, A = 49.0 m2
Modulus, Z = 57.17 m3
Maximum Pressure, Pmax = 94.9 kN/m2 O.K
Minimun Pressure, Pmin = 45.3 kN/m 2

(c) Resistance to Overturning Moment(SLS)

Disturbing Moment = 4007.0 kNm

Overtaking Moment(stump) = 40.3 kNm


Overtaking Moment(base) = 3704.4 kNm
Overtaking Moment(tower load) = 501.6 kNm
Overtaking Moment(soil on base) = 1828.0 kNm

Total Overtaking Moment = 6074.3 kNm

Allowable Factor Of Safety (F.O.S) = 1.5

Actual Factor Of Safety (F.O.S) = 1.5 O.K

(d) Resistance to horizontal load

Passive resistance, R = 867.75 kN


Horizontal load = 118.3 kN
F.O.S = 7.34 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 142.3 kN/m2


Minimum pressure, Pmin = 68.0 kN/m2
Distance at face of col = 3.10 m
Pmax, at col face = 49.16 kN/m2
Shear at col face = 296.72 kN
Moment, at face of column = 459.9 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

M/bd2fcu = 0.00318
z/d = 0.996 >0.95
As = M/0.87fyz = 1635.2 mm 2

Asmin = 0.13bh/100 = 8190.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 26.1
Number of bar provided = 28.0 NOS
bar spasing = 256 mm

provide 25 Y16 at 206 c/c


Area, A = 8796.48 mm2

(f) Vertical shear(ULS)

1.5d = 1245 mm
Pressure at 1.5d = 86.56 kN/m2
Distance at 1.5d = 1.855 m
Vertical shear F = 1485.7 kN
Shear stress v = 0.256 N/mm2
100As/bd = 0.151
Design stress vc = 0.358 N/mm2 O.K
(g) Punching shear and maximum shear

Perimeter = 13.16 m
Area = 10.82 m2
Pav for punching sheer = 114.42 kN/m2
V = 4368.00 kN
v = 0.400 N/mm2
vc = 0.358 N/mm2 Please Check

Pav for shear Max Vmax = 37.14 kN/m2


Vmax = 1796.06 kN
vmax = 0.68 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 214.95 KN
horizontal load = 177.5 KN
bar size = 25 mm Area = 490.875 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 737.5 mm
d/h = 0.92

Moment from horiz. load,M1 = 133.09 KN/m


Applied moment,M2 = 5877.45 KN/m
Total moment,M = 6010.54 KN/m
N/bh = 0.33585938
M/bh2 = 11.7393311

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2

M/bd2fcu = 0.00046
z/d = 0.999 >0.95
As = M/0.87fyz = 24050.5 mm2

number of bar req. = 0.00


number of bar prov. = 40 NOS
USE 40Y25 Asc = 19635
RNRS/0746
1
14/02/09
Ir. Rosli
mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/1088
PROJECT: CALC SHEET:
PT759,Tingkat 1&2,Bgn MDT 3,Jln Masjid, 76M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Wakaf Bharu,Tumpat, Kelantan Darul Naim RAFT FOUNDATION 12/12/2010
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3/13 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1152.7 kN


Horizontal dead load (SLS) = 170.5 kN
Vertical uplift (SLS) = 1008 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2 m
Height of stump above grd = 0.15 m
Earth thickness = 1.1 m
Base length, l = 12.5 m
Base width, b = 12.5 m
Base depth, h = 0.9 m
Stump length = 1.25 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 3375.0 kN


Weight of soil above = 3081.1 kN
Total Weight of stump = 57.6 kN
Total axial load = 10087.0 kN
Total moment = 213.125 kNm
Base area, A = 156.3 m2
Modulus, Z = 325.52 m3
Average Pressure, Pav = 64.6 kN/m2 O.K

(c) Check for uplift

Uplift force = 1008.000 kN


Uplift resist. load (40% of total load) = 4034.8 kN
F.O.S = 4.00 O.K

(d) Resistance to horizontal load

Passive resistance, R = 5043.49 kN


Horizontal load = 170.5 kN
F.O.S = 29.58 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

Asmin = 0.13bh/100 = 1170.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 269 mm

since the thickness is 0.9m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1729.05 KN
horizontal load = 255.8 KN
uplift load = 1209.6 KN
bar size = 20 mm
link size = 10 mm Area = 314.16 mm2
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 319.69 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 319.69 KN/m
N/bh = 2.70164063
M/bh2 = 0.62438965

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc = 3769.92


Area of bar req. due to uplift = 2950.24 mm2 O.K
RNRS/1088
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/1088
PROJECT: CALC SHEET:
PT759,Tingkat 1&2,Bgn MDT 3,Jln Masjid, 60M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim RAFT FOUNDATION 28/11/2010
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3/08 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 955 kN


Horizontal dead load (SLS) = 88.5 kN
Vertical uplift (SLS) = 899.7 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2 m
Height of stump above grd = 0.15 m
Earth thickness = 1.1 m
Base length, l = 7.5 m
Base width, b = 7.5 m
Base depth, h = 0.9 m
Stump length = 1.25 m
Stump width = 0.8 m

(b) Maximum earth pressure(SLS)

Weight of base = 1215.0 kN


Weight of soil above = 1101.1 kN
Total Weight of stump = 57.6 kN
Total axial load = 5353.9 kN
Total moment = 110.625 kNm
Base area, A = 56.3 m2
Modulus, Z = 70.31 m3
Average Pressure, Pav = 95.2 kN/m2 O.K

(c) Check for uplift

Uplift force = 899.700 kN


Uplift resist. load (40% of total load) = 2141.6 kN
F.O.S = 2.38 O.K

(d) Resistance to horizontal load

Passive resistance, R = 2676.94 kN


Horizontal load = 88.5 kN
F.O.S = 30.25 O.K

(e) Design of the moment reinforcement(ULS)

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 830 mm

Asmin = 0.13bh/100 = 1170.0 mm2/m

Adopt diameter bar = 20 mm


area A = 314.160 mm2
bar spasing = 269 mm
since the thickness is 0.9m, the moment reinf. Is nominal only and no more check for shear

(f) Design of Stump

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1432.5 KN
horizontal load = 132.8 KN
uplift load = 1079.6 KN
bar size = 20 mm
link size = 10 mm Area = 314.16 mm2
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 165.94 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 165.94 KN/m
N/bh = 2.23828125
M/bh2 = 0.32409668

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS

USE 12Y20 Asc = 3769.92


Area of bar req. due to uplift = 2633.27 mm2 O.K
RNRS/1088
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/1088
PROJECT: CALC SHEET:
PT759,Tingkat 1&2,Bgn MDT 3,Jln Masjid, 76M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING Dec-10
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3/12 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1152.7 kN


Horizontal dead load (SLS) = 170.5 kN
Vertical uplift (SLS) = 1008 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 4.4 m
Base width, b = 4.4 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.8 m
Depth of tie Beam = 0 m
Width of tie Beam = 0 m
Length between ftg = 9.875 m
Length of tie Beam = 5.475 m

(b) Maximum earth pressure(SLS)

Weight of base = 278.8 kN


Weight of soil above = 808.7 kN
Weight of stump = 39.2 kN
Weight of tie beam = 0.0 kN
Total axial load- soil = 1470.7 kN
Total axial load = 2279.4 kN
Total moment = 434.775 kNm
Base area, A = 19.4 m2
Modulus, Z = 14.20 m3
Maximum Pressure, Pmax = 106.6 kN/m2 O.K
Minimun Pressure, Pmin = 45.3 kN/m2

(c) Check for uplift

Uplift force = 1008.000 kN


Length of sand with 35deg. = 7.76 m
Wt of sand with 35 incline = 1718.9 kN
Uplift resistance load = 2036.8 kN
F.O.S = 2.02 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1139.68 kN


Horizontal load = 170.5 kN
F.O.S = 6.68 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 149.2 kN/m2


Minimum pressure, Pmin = 63.5 kN/m2
Distance at face of col = 1.80 m
Pmax, at col face = 114.14 kN/m2
Shear at col face = 237.03 kN
Moment, at face of column = 213.3 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 530 mm

M/bd2fcu = 0.00575
z/d = 0.994 >0.95
As = M/0.87fyz = 1187.8 mm 2

Asmin = 0.13bh/100 = 3432.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 10.9
Number of bar provided = 16.0 NOS
bar spasing = 287 mm

provide 16 Y20 at 287 c/c


Area, A = 5026.56 mm2

(f) Vertical shear(ULS)

1.5d = 795 mm
Pressure at 1.5d = 129.64 kN/m2
Distance at 1.5d = 1.005 m
Vertical shear F = 616.6 kN
Shear stress v = 0.264 N/mm2
100As/bd = 0.216
Design stress vc = 0.403 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.56 m
Area = 5.71 m2
Pav for punching sheer = 139.43 kN/m2
V = 1902.92 kN
v = 0.376 N/mm2
vc = 0.403 N/mm2 O.K

Pav for shear Max Vmax = 106.35 kN/m2


Vmax = 1990.85 kN
vmax = 1.17 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1729.05 KN
horizontal load = 255.8 KN
uplift load = 1209.6 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 652.16 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 652.16 KN/m
N/bh = 2.70164063
M/bh2 = 1.27375488

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS
USE 20Y20 Asc = 6283.2 mm2

Area of bar req. due to uplift = 2950.24 mm2 O.K


RNRS/1088
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/1088
PROJECT: CALC SHEET:
PT759,Tingkat 1&2,Bgn MDT 3,Jln Masjid, 76M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING 21/11/2010
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3/03 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 100KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1152.7 kN


Horizontal dead load (SLS) = 170.5 kN
Vertical uplift (SLS) = 1008 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.2 m
Base length, l = 4.8 m
Base width, b = 4.8 m
Base depth, h = 0.6 m
Stump length = 2.35 m
Stump width = 0.8 m
Depth of tie Beam = 0 m
Width of tie Beam = 0 m
Length between ftg = 9.875 m
Length of tie Beam = 5.075 m

(b) Maximum earth pressure(SLS)

Weight of base = 331.8 kN


Weight of soil above = 887.0 kN
Weight of stump = 36.1 kN
Weight of tie beam = 0.0 kN
Total axial load- soil = 1520.6 kN
Total axial load = 2407.6 kN
Total moment = 400.675 kNm
Base area, A = 23.0 m2
Modulus, Z = 18.43 m3
Maximum Pressure, Pmax = 87.7 kN/m2 O.K
Minimun Pressure, Pmin = 44.3 kN/m2

(c) Check for uplift

Uplift force = 1008.000 kN


Length of sand with 35deg. = 7.88 m
Wt of sand with 35 incline = 1685.7 kN
Uplift resistance load = 2053.5 kN
F.O.S = 2.04 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1203.81 kN


Horizontal load = 170.5 kN
F.O.S = 7.06 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 122.8 kN/m2


Minimum pressure, Pmin = 62.0 kN/m2
Distance at face of col = 2.00 m
Pmax, at col face = 97.47 kN/m2
Shear at col face = 220.30 kN
Moment, at face of column = 220.3 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 530 mm

M/bd2fcu = 0.00545
z/d = 0.994 >0.95
As = M/0.87fyz = 1226.6 mm2
Asmin = 0.13bh/100 = 3744.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 11.9
Number of bar provided = 20.0 NOS
bar spasing = 247 mm

provide 20 Y20 at 247 c/c


Area, A = 6283.2 mm2

(f) Vertical shear(ULS)

1.5d = 795 mm
Pressure at 1.5d = 107.55 kN/m2
Distance at 1.5d = 1.205 m
Vertical shear F = 666.3 kN
Shear stress v = 0.262 N/mm2
100As/bd = 0.247
Design stress vc = 0.421 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.56 m
Area = 5.71 m2
Pav for punching sheer = 115.19 kN/m2
V = 1995.98 kN
v = 0.394 N/mm2
vc = 0.421 N/mm2 O.K

Pav for shear Max Vmax = 92.40 kN/m2


Vmax = 2069.67 kN
vmax = 1.22 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1729.05 KN
horizontal load = 255.8 KN
uplift load = 1209.6 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 601.01 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 601.01 KN/m
N/bh = 2.70164063
M/bh2 = 1.17385254

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS
USE 20Y20 Asc = 6283.2 mm2

Area of bar req. due to uplift = 2950.24 mm2 O.K


CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 955 kN


Horizontal dead load (SLS) = 88.5 kN
Vertical uplift (SLS) = 899.7 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.5 m
Base length, l = 4 m
Base width, b = 4 m
Base depth, h = 0.5 m
Stump length = 2.65 m
Stump width = 0.8 m
Depth of tie Beam = 0 m
Width of tie Beam = 0 m
Length between ftg = 9.875 m
Length of tie Beam = 5.875 m

(b) Maximum earth pressure(SLS)

Weight of base = 192.0 kN


Weight of soil above = 691.2 kN
Weight of stump = 40.7 kN
Weight of tie beam = 0.0 kN
Total axial load- soil = 1187.7 kN
Total axial load = 1878.9 kN
Total moment = 234.525 kNm
Base area, A = 16.0 m2
Modulus, Z = 10.67 m3
Maximum Pressure, Pmax = 96.2 kN/m2 O.K
Minimun Pressure, Pmin = 52.2 kN/m 2

(c) Check for uplift


Uplift force = 899.700 kN
Length of sand with 35deg. = 7.50 m
Wt of sand with 35 incline = 1625.6 kN
Uplift resistance load = 1858.3 kN
F.O.S = 2.07 O.K

(d) Resistance to horizontal load

Passive resistance, R = 939.45 kN


Horizontal load = 88.5 kN
F.O.S = 10.62 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 134.7 kN/m2


Minimum pressure, Pmin = 73.1 kN/m2
Distance at face of col = 1.60 m
Pmax, at col face = 110.08 kN/m2
Shear at col face = 195.83 kN
Moment, at face of column = 156.7 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 430 mm

M/bd2fcu = 0.00706
z/d = 0.992 >0.95
As = M/0.87fyz = 1075.2 mm2
Asmin = 0.13bh/100 = 2600.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 8.3
Number of bar provided = 16.0 NOS
bar spasing = 260 mm

provide16 Y20 at 287 c/c


Area, A = 5026.56 mm2

(f) Vertical shear(ULS)

1.5d = 645 mm
Pressure at 1.5d = 120.01 kN/m2
Distance at 1.5d = 0.955 m
Vertical shear F = 486.5 kN
Shear stress v = 0.283 N/mm2
100As/bd = 0.292
Design stress vc = 0.446 N/mm2 O.K

(g) Punching shear and maximum shear


Perimeter = 8.36 m
Area = 4.37 m2
Pav for punching sheer = 127.36 kN/m2
V = 1481.40 kN
v = 0.412 N/mm2
vc = 0.446 N/mm2 O.K

Pav for shear Max Vmax = 103.92 kN/m2


Vmax = 1596.27 kN
vmax = 1.16 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1432.5 KN
horizontal load = 132.8 KN
uplift load = 1079.6 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 351.79 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 351.79 KN/m
N/bh = 2.23828125
M/bh2 = 0.68708496

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92

Area of bar req. due to uplift = 2633.27 mm2 O.K


RNRS/0832
1.0
26/10/10
Ir. Rosli
mm2
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A Rumaizi

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1362 kN


Horizontal dead load (SLS) = 150 kN
Vertical uplift (SLS) = 1151 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.6 m
Height of stump above grd = 0.15 m
Earth thickness = 3 m
Base length, l = 4.2 m
Base width, b = 4.2 m
Base depth, h = 0.6 m
Stump length = 3.15 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 9.841 m
Length of tie Beam = 5.641 m

(b) Maximum earth pressure(SLS)

Weight of base = 254.0 kN


Weight of soil above = 1020.0 kN
Weight of stump = 48.4 kN
Weight of tie beam = 24.4 kN
Total axial load- soil = 1688.8 kN
Total axial load = 2708.8 kN
Total moment = 472.5 kNm
Base area, A = 17.6 m2
Modulus, Z = 12.35 m3
Maximum Pressure, Pmax = 134.0 kN/m2 O.K
Minimun Pressure, Pmin = 57.5 kN/m 2
(c) Check for uplift

Uplift force = 1151.000 kN


Length of sand with 35deg. = 8.40 m
Wt of sand with 35 incline = 2646.0 kN
Uplift resistance load = 2972.8 kN
F.O.S = 2.58 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1354.38 kN


Horizontal load = 150 kN
F.O.S = 9.03 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 187.6 kN/m2


Minimum pressure, Pmin = 80.5 kN/m2
Distance at face of col = 1.70 m
Pmax, at col face = 144.23 kN/m2
Shear at col face = 282.06 kN
Moment, at face of column = 239.8 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 530 mm

M/bd2fcu = 0.00813
z/d = 0.991 >0.95
As = M/0.87fyz = 1334.9 mm 2

Asmin = 0.13bh/100 = 3276.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 10.4
Number of bar provided = 22.0 NOS
bar spasing = 195 mm

provide22 Y20 at 195 c/c


Area, A = 6911.52

(f) Vertical shear(ULS)

1.5d = 795 mm
Pressure at 1.5d = 164.51 kN/m2
Distance at 1.5d = 0.905 m
Vertical shear F = 669.2 kN
Shear stress v = 0.301 N/mm2
100As/bd = 0.310
Design stress vc = 0.428 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.56 m
Area = 5.71 m2
Pav for punching sheer = 176.06 kN/m2
V = 2099.99 kN
v = 0.414 N/mm2
vc = 0.428 N/mm2 O.K

Pav for shear Max Vmax = 134.03 kN/m2


Vmax = 2278.50 kN
vmax = 1.34 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 2043 KN
horizontal load = 225.0 KN
uplift load = 1381.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 708.75 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 708.75 KN/m
N/bh = 3.1921875
M/bh2 = 1.38427734

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 3368.78 mm2 O.K


JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
2 Y20 at 195 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A-18 Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 70KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1056 kN


Horizontal dead load (SLS) = 114 kN
Vertical uplift (SLS) = 911 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 70 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.4 m
Height of stump above grd = 0.15 m
Earth thickness = 1.85 m
Base length, l = 5 m
Base width, b = 5 m
Base depth, h = 0.55 m
Stump length = 2 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 7.841 m
Length of tie Beam = 2.841 m

(b) Maximum earth pressure(SLS)

Weight of base = 330.0 kN


Weight of soil above = 901.3 kN
Weight of stump = 30.7 kN
Weight of tie beam = 12.3 kN
Total axial load- soil = 1429.0 kN
Total axial load = 2330.3 kN
Total moment = 228 kNm
Base area, A = 25.0 m2
Modulus, Z = 20.83 m3
Maximum Pressure, Pmax = 68.1 kN/m2 O.K
Minimun Pressure, Pmin = 46.2 kN/m 2
(c) Check for uplift

Uplift force = 911.000 kN


Length of sand with 35deg. = 7.59 m
Wt of sand with 35 incline = 1528.2 kN
Uplift resistance load = 1901.2 kN
F.O.S = 2.09 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1165.16 kN


Horizontal load = 114 kN
F.O.S = 10.22 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 95.3 kN/m2


Minimum pressure, Pmin = 64.7 kN/m2
Distance at face of col = 2.10 m
Pmax, at col face = 82.48 kN/m2
Shear at col face = 186.71 kN
Moment, at face of column = 196.0 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 480 mm

M/bd2fcu = 0.00681
z/d = 0.992 >0.95
As = M/0.87fyz = 1205.3 mm 2

Asmin = 0.13bh/100 = 3575.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 11.4
Number of bar provided = 24.0 NOS
bar spasing = 213 mm

24Y20 at 213 c/c


Area, A = 7539.84

(f) Vertical shear(ULS)

1.5d = 720 mm
Pressure at 1.5d = 86.89 kN/m2
Distance at 1.5d = 1.380 m
Vertical shear F = 628.7 kN
Shear stress v = 0.262 N/mm2
100As/bd = 0.314
Design stress vc = 0.430 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 8.96 m
Area = 5.02 m2
Pav for punching sheer = 91.12 kN/m2
V = 1820.73 kN
v = 0.423 N/mm2
vc = 0.430 N/mm2 O.K

Pav for shear Max Vmax = 80.02 kN/m2


Vmax = 1949.38 kN
vmax = 1.27 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1584 KN
horizontal load = 171.0 KN
uplift load = 1093.2 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 342.00 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 342.00 KN/m
N/bh = 2.475
M/bh2 = 0.66796875

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 16 NOS
USE 16Y20 Asc =

Area of bar req. due to uplift = 2666.34 mm2 O.K


JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
17/01/09
CHECKED BY:
Ir. Rosli
mm2
mm2

5026.56 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT DESA BINA RNRS/0832
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 45M 3-LEGGED TOWER 1.0
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 17/01/09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A-18 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

45m Tower 3-leg-(soil bearing = 70KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 779 kN


Horizontal dead load (SLS) = 84 kN
Vertical uplift (SLS) = 690 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.4 m
Height of stump above grd = 0.15 m
Earth thickness = 1.95 m
Base length, l = 4.3 m
Base width, b = 4.3 m
Base depth, h = 0.45 m
Stump length = 2.1 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 6.004 m
Length of tie Beam = 1.704 m

(b) Maximum earth pressure(SLS)

Weight of base = 199.7 kN


Weight of soil above = 696.2 kN
Weight of stump = 32.3 kN
Weight of tie beam = 7.4 kN
Total axial load- soil = 1018.3 kN
Total axial load = 1714.5 kN
Total moment = 176.4 kNm
Base area, A = 18.5 m2
Modulus, Z = 13.25 m3
Maximum Pressure, Pmax = 68.4 kN/m2 O.K
Minimun Pressure, Pmin = 41.8 kN/m2

(c) Check for uplift

Uplift force = 690.000 kN


Length of sand with 35deg. = 7.03 m
Wt of sand with 35 incline = 1324.3 kN
Uplift resistance load = 1563.6 kN
F.O.S = 2.27 O.K
(d) Resistance to horizontal load

Passive resistance, R = 857.23 kN


Horizontal load = 84 kN
F.O.S = 10.21 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 95.7 kN/m2


Minimum pressure, Pmin = 58.5 kN/m2
Distance at face of col = 1.75 m
Pmax, at col face = 80.57 kN/m2
Shear at col face = 154.27 kN
Moment, at face of column = 135.0 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 380 mm

M/bd2fcu = 0.00870
z/d = 0.990 >0.95
As = M/0.87fyz = 1048.3 mm 2

Asmin = 0.13bh/100 = 2515.5 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 8.0
Number of bar provided = 21.0 NOS
bar spasing = 210 mm

provide21 Y20 at 210 c/c


Area, A = 6597.36 mm2

(f) Vertical shear(ULS)

1.5d = 570 mm
Pressure at 1.5d = 85.51 kN/m2
Distance at 1.5d = 1.180 m
Vertical shear F = 459.8 kN
Shear stress v = 0.281 N/mm2
100As/bd = 0.404
Design stress vc = 0.467 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 7.76 m
Area = 3.76 m2
Pav for punching sheer = 90.63 kN/m2
V = 1334.59 kN
v = 0.453 N/mm2
vc = 0.467 N/mm2 O.K

Pav for shear Max Vmax = 77.10 kN/m2


Vmax = 1376.29 kN
vmax = 1.13 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1168.5 KN
horizontal load = 126.0 KN
uplift load = 828.0 KN
bar size = 20 mm Area = 314.16 mm2
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 264.60 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 264.60 KN/m
N/bh = 1.82578125
M/bh2 = 0.51679688

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2019.51 mm2 O.K


RNRS/0832
CLIENT:
PERUNDING RNR SEPAKAT DESA BINA
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A Rumaizi

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-DESA BINA IND.

(a) Specification

Vertical dead load (SLS) = 1909 kN


Horizontal dead load (SLS) = 212 kN
Vertical uplift (SLS) = 1760 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 25 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.6 m
Height of stump above grd = 0.15 m
Earth thickness = 2.85 m
Base length, l = 5 m
Base width, b = 5 m
Base depth, h = 0.75 m
Stump length = 3 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 9.912 m
Length of tie Beam = 4.912 m

(b) Maximum earth pressure(SLS)

Weight of base = 450.0 kN


Weight of soil above = 1388.5 kN
Weight of stump = 46.1 kN
Weight of tie beam = 21.2 kN
Total axial load- soil = 2426.3 kN
Total axial load = 3814.8 kN
Total moment = 636 kNm
Base area, A = 25.0 m2
Modulus, Z = 20.83 m3
Maximum Pressure, Pmax = 127.6 kN/m2 O.K
Minimun Pressure, Pmin = 66.5 kN/m 2
(c) Check for uplift

Uplift force = 1760.000 kN


Length of sand with 35deg. = 8.99 m
Wt of sand with 35 incline = 3015.9 kN
Uplift resistance load = 3533.2 kN
F.O.S = 2.01 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1907.41 kN


Horizontal load = 212 kN
F.O.S = 9.00 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 178.6 kN/m2


Minimum pressure, Pmin = 93.1 kN/m2
Distance at face of col = 2.10 m
Pmax, at col face = 142.71 kN/m2
Shear at col face = 337.39 kN
Moment, at face of column = 354.3 kNm

Cover bar = 50 mm
Diameter bar = 20 mm
Effective depth, dav = 680 mm

M/bd2fcu = 0.00613
z/d = 0.993 >0.95
As = M/0.87fyz = 1537.4 mm 2

Asmin = 0.13bh/100 = 4875.0 mm2 >As

Adopt diameter bar = 20 mm


area A = 314.160 mm2
Number of bar required = 15.5
Number of bar provided = 28.0 NOS
bar spasing = 181 mm

provide28 Y16 at 181 c/c


Area, A = 8796.48

(f) Vertical shear(ULS)

1.5d = 1020 mm
Pressure at 1.5d = 160.15 kN/m2
Distance at 1.5d = 1.080 m
Vertical shear F = 914.7 kN
Shear stress v = 0.269 N/mm2
100As/bd = 0.259
Design stress vc = 0.403 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 11.36 m
Area = 8.07 m2
Pav for punching sheer = 169.38 kN/m2
V = 2868.35 kN
v = 0.371 N/mm2
vc = 0.403 N/mm2 O.K

Pav for shear Max Vmax = 135.87 kN/m2


Vmax = 3309.86 kN
vmax = 1.52 N/mm2
0.8x(fcu)0.25 = 4.00 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 2863.5 KN
horizontal load = 318.0 KN
uplift load = 2112.0 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 744 mm
d/h = 0.93

moment from horiz. load,M1 = 954.00 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 954.00 KN/m
N/bh = 4.47421875
M/bh2 = 1.86328125

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 20 NOS
USE 20Y20 Asc =

Area of bar req. due to uplift = 5151.22 mm2 O.K


JOB NO:
RNRS/0832
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
8 Y16 at 181 c/c
mm2
mm2

6283.2 mm2
CLIENT:
PERUNDING RNR SEPAKAT CELCOM
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/003A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1392 kN


Horizontal dead load (SLS) = 156 kN
Vertical uplift (SLS) = 1106 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.2 m
Height of stump above grd = 0.15 m
Earth thickness = 2.6 m
Base length, l = 4.1 m
Base width, b = 4.1 m
Base depth, h = 0.6 m
Stump length = 2.75 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 10 m
Length of tie Beam = 5.9 m

(b) Maximum earth pressure(SLS)

Weight of base = 242.1 kN


Weight of soil above = 832.0 kN
Weight of stump = 53.5 kN
Weight of tie beam = 25.5 kN
Total axial load- soil = 1713.0 kN
Total axial load = 2545.0 kN
Total moment = 429 kNm
Base area, A = 16.8 m2
Modulus, Z = 11.49 m3
Maximum Pressure, Pmax = 139.3 kN/m2 O.K
Minimun Pressure, Pmin = 64.6 kN/m 2
(c) Check for uplift

Uplift force = 1106.000 kN


Length of sand with 35deg. = 7.74 m
Wt of sand with 35 incline = 1994.7 kN
Uplift resistance load = 2315.7 kN
F.O.S = 2.09 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1272.51 kN


Horizontal load = 156 kN
F.O.S = 8.16 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 208.9 kN/m2


Minimum pressure, Pmin = 96.8 kN/m2
Distance at face of col = 1.60 m
Pmax, at col face = 165.15 kN/m2
Shear at col face = 299.22 kN
Moment, at face of column = 239.4 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00682
z/d = 0.992 >0.95
As = M/0.87fyz = 1322.9 mm 2

Asmin = 0.15bh/100 = 3690.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 18.4
Number of bar provided = 23.0 NOS
bar spasing = 182 mm

provide23 Y16 at 182 c/c


Area, A = 4624.435

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 187.04 kN/m2
Distance at 1.5d = 0.799 m
Vertical shear F = 648.5 kN
Shear stress v = 0.296 N/mm2
100As/bd = 0.211
Design stress vc = 0.400 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 197.96 kN/m2
V = 2088.48 kN
v = 0.391 N/mm2
vc = 0.400 N/mm2 O.K

Pav for shear Max Vmax = 152.86 kN/m2


Vmax = 2445.70 kN
vmax = 1.27 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 2088 KN
horizontal load = 234.0 KN
uplift load = 1327.2 KN
bar size = 20 mm Area = 314.16
link size = 6 mm
cover = 40 mm
Eff. Depth, d = 844 mm
d/h = 0.94

moment from horiz. load,M1 = 643.50 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 643.50 KN/m
N/bh = 2.57777778
M/bh2 = 0.88271605

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 3237.07 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
1.0
DATE:
24/9/9/6
CHECKED BY:
Ir. Rosli
3 Y16 at 182 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (75 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1230 kN


Horizontal dead load (SLS) = 128 kN
Vertical uplift (SLS) = 966 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.1 m
Height of stump above grd = 0.15 m
Earth thickness = 2.55 m
Base length, l = 3.8 m
Base width, b = 3.8 m
Base depth, h = 0.55 m
Stump length = 2.7 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 4.2 m

(b) Maximum earth pressure(SLS)

Weight of base = 190.6 kN


Weight of soil above = 695.1 kN
Weight of stump = 52.5 kN
Weight of tie beam = 18.1 kN
Total axial load- soil = 1491.2 kN
Total axial load = 2186.4 kN
Total moment = 345.6 kNm
Base area, A = 14.4 m2
Modulus, Z = 9.15 m3
Maximum Pressure, Pmax = 141.1 kN/m2 O.K
Minimun Pressure, Pmin = 65.5 kN/m 2
(c) Check for uplift

Uplift force = 966.000 kN


Length of sand with 35deg. = 7.37 m
Wt of sand with 35 incline = 1753.3 kN
Uplift resistance load = 2014.5 kN
F.O.S = 2.09 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1093.19 kN


Horizontal load = 128 kN
F.O.S = 8.54 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 211.6 kN/m2


Minimum pressure, Pmin = 98.2 kN/m2
Distance at face of col = 1.45 m
Pmax, at col face = 168.33 kN/m2
Shear at col face = 275.45 kN
Moment, at face of column = 199.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 484 mm

M/bd2fcu = 0.00748
z/d = 0.992 >0.95
As = M/0.87fyz = 1217.6 mm 2

Asmin = 0.15bh/100 = 3135.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 15.6
Number of bar provided = 20.0 NOS
bar spasing = 195 mm

provide19 Y16 at 211 c/c


Area, A = 4021.248

(f) Vertical shear(ULS)

1.5d = 726 mm
Pressure at 1.5d = 189.99 kN/m2
Distance at 1.5d = 0.724 m
Vertical shear F = 552.4 kN
Shear stress v = 0.300 N/mm2
100As/bd = 0.219
Design stress vc = 0.405 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 200.79 kN/m2
V = 1788.67 kN
v = 0.393 N/mm2
vc = 0.405 N/mm2 O.K

Pav for shear Max Vmax = 154.91 kN/m2


Vmax = 2111.39 kN
vmax = 1.21 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1845 KN
horizontal load = 192.0 KN
uplift load = 1159.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 518.40 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 518.40 KN/m
N/bh = 2.27777778
M/bh2 = 0.71111111

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2827.32 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
9 Y16 at 211 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (75 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 75KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1230 kN


Horizontal dead load (SLS) = 128 kN
Vertical uplift (SLS) = 966 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3.1 m
Height of stump above grd = 0.15 m
Earth thickness = 2.45 m
Base length, l = 4.8 m
Base width, b = 4.8 m
Base depth, h = 0.65 m
Stump length = 2.6 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 3.2 m

(b) Maximum earth pressure(SLS)

Weight of base = 359.4 kN


Weight of soil above = 1089.3 kN
Weight of stump = 50.5 kN
Weight of tie beam = 13.8 kN
Total axial load- soil = 1653.8 kN
Total axial load = 2743.1 kN
Total moment = 332.8 kNm
Base area, A = 23.0 m2
Modulus, Z = 18.43 m3
Maximum Pressure, Pmax = 89.8 kN/m2 O.K
Minimun Pressure, Pmin = 53.7 kN/m 2
(c) Check for uplift

Uplift force = 966.000 kN


Length of sand with 35deg. = 8.23 m
Wt of sand with 35 incline = 2223.9 kN
Uplift resistance load = 2647.7 kN
F.O.S = 2.74 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1371.53 kN


Horizontal load = 128 kN
F.O.S = 10.72 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 134.8 kN/m2


Minimum pressure, Pmin = 80.6 kN/m2
Distance at face of col = 1.95 m
Pmax, at col face = 112.75 kN/m2
Shear at col face = 241.31 kN
Moment, at face of column = 235.3 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 584 mm

M/bd2fcu = 0.00479
z/d = 0.995 >0.95
As = M/0.87fyz = 1188.9 mm 2

Asmin = 0.15bh/100 = 4680.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 23.3
Number of bar provided = 24.0 NOS
bar spasing = 204 mm

provide26 Y16 at 200 c/c


Area, A = 4825.498

(f) Vertical shear(ULS)

1.5d = 876 mm
Pressure at 1.5d = 122.63 kN/m2
Distance at 1.5d = 1.074 m
Vertical shear F = 663.4 kN
Shear stress v = 0.237 N/mm2
100As/bd = 0.172
Design stress vc = 0.374 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.608 m
Area = 7.03 m2
Pav for punching sheer = 128.69 kN/m2
V = 2059.96 kN
v = 0.333 N/mm2
vc = 0.374 N/mm2 O.K

Pav for shear Max Vmax = 107.67 kN/m2


Vmax = 2393.48 kN
vmax = 1.14 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1845 KN
horizontal load = 192.0 KN
uplift load = 1159.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 499.20 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 499.20 KN/m
N/bh = 2.27777778
M/bh2 = 0.68477366

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2827.32 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
6 Y16 at 200 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (75 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 75KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1230 kN


Horizontal dead load (SLS) = 128 kN
Vertical uplift (SLS) = 966 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 80 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.15 m
Base length, l = 5.1 m
Base width, b = 5.1 m
Base depth, h = 0.65 m
Stump length = 2.3 m
Stump width = 0.9 m
Depth of tie Beam = 0.65 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 2.9 m

(b) Maximum earth pressure(SLS)

Weight of base = 405.8 kN


Weight of soil above = 1083.6 kN
Weight of stump = 44.7 kN
Weight of tie beam = 13.6 kN
Total axial load- soil = 1694.0 kN
Total axial load = 2777.6 kN
Total moment = 294.4 kNm
Base area, A = 26.0 m2
Modulus, Z = 22.11 m3
Maximum Pressure, Pmax = 78.4 kN/m2 O.K
Minimun Pressure, Pmin = 51.8 kN/m 2
(c) Check for uplift

Uplift force = 966.000 kN


Length of sand with 35deg. = 8.11 m
Wt of sand with 35 incline = 1973.3 kN
Uplift resistance load = 2437.4 kN
F.O.S = 2.52 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1388.82 kN


Horizontal load = 128 kN
F.O.S = 10.85 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 117.7 kN/m2


Minimum pressure, Pmin = 77.7 kN/m2
Distance at face of col = 2.10 m
Pmax, at col face = 101.22 kN/m2
Shear at col face = 229.83 kN
Moment, at face of column = 241.3 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 584 mm

M/bd2fcu = 0.00462
z/d = 0.995 >0.95
As = M/0.87fyz = 1219.5 mm 2

Asmin = 0.15bh/100 = 4972.5 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 24.7
Number of bar provided = 26.0 NOS
bar spasing = 200 mm

provide26 Y16 at 200 c/c


Area, A = 5227.622

(f) Vertical shear(ULS)

1.5d = 876 mm
Pressure at 1.5d = 108.08 kN/m2
Distance at 1.5d = 1.224 m
Vertical shear F = 704.6 kN
Shear stress v = 0.237 N/mm2
100As/bd = 0.176
Design stress vc = 0.376 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.608 m
Area = 7.03 m2
Pav for punching sheer = 112.88 kN/m2
V = 2142.03 kN
v = 0.346 N/mm2
vc = 0.376 N/mm2 O.K

Pav for shear Max Vmax = 97.70 kN/m2


Vmax = 2461.93 kN
vmax = 1.17 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1845 KN
horizontal load = 192.0 KN
uplift load = 1159.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 441.60 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 441.60 KN/m
N/bh = 2.27777778
M/bh2 = 0.60576132

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2827.32 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
6 Y16 at 200 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (75 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 75KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 5 m
Base width, b = 5 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 3 m

(b) Maximum earth pressure(SLS)

Weight of base = 360.0 kN


Weight of soil above = 1161.1 kN
Weight of stump = 49.6 kN
Weight of tie beam = 13.0 kN
Total axial load- soil = 1487.5 kN
Total axial load = 2648.7 kN
Total moment = 293.25 kNm
Base area, A = 25.0 m2
Modulus, Z = 20.83 m3
Maximum Pressure, Pmax = 73.6 kN/m2 O.K
Minimun Pressure, Pmin = 45.4 kN/m 2
(c) Check for uplift

Uplift force = 851.000 kN


Length of sand with 35deg. = 8.36 m
Wt of sand with 35 incline = 2277.4 kN
Uplift resistance load = 2699.9 kN
F.O.S = 3.17 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1324.33 kN


Horizontal load = 115 kN
F.O.S = 11.52 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 110.4 kN/m2


Minimum pressure, Pmin = 68.1 kN/m2
Distance at face of col = 2.05 m
Pmax, at col face = 93.05 kN/m2
Shear at col face = 208.50 kN
Moment, at face of column = 213.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00500
z/d = 0.994 >0.95
As = M/0.87fyz = 1181.1 mm 2

Asmin = 0.15bh/100 = 4500.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 22.4
Number of bar provided = 24.0 NOS
bar spasing = 213 mm

provide24 Y16 at 213 c/c


Area, A = 4825.498

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 99.82 kN/m2
Distance at 1.5d = 1.249 m
Vertical shear F = 656.3 kN
Shear stress v = 0.246 N/mm2
100As/bd = 0.181
Design stress vc = 0.380 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 105.09 kN/m2
V = 1969.42 kN
v = 0.369 N/mm2
vc = 0.380 N/mm2 O.K

Pav for shear Max Vmax = 89.25 kN/m2


Vmax = 2159.00 kN
vmax = 1.12 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 439.88 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 439.88 KN/m
N/bh = 1.97222222
M/bh2 = 0.60339506

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2490.73 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
4 Y16 at 213 c/c
mm2
mm2

3769.92 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (130 KN/M2)
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 130KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 130 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.45 m
Base length, l = 4 m
Base width, b = 4 m
Base depth, h = 0.55 m
Stump length = 2.6 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 4 m

(b) Maximum earth pressure(SLS)

Weight of base = 211.2 kN


Weight of soil above = 669.9 kN
Weight of stump = 50.5 kN
Weight of tie beam = 17.3 kN
Total axial load- soil = 1344.0 kN
Total axial load = 2013.9 kN
Total moment = 299 kNm
Base area, A = 16.0 m2
Modulus, Z = 10.67 m3
Maximum Pressure, Pmax = 112.0 kN/m2 O.K
Minimun Pressure, Pmin = 56.0 kN/m 2

(c) Check for uplift


Uplift force = 851.000 kN
Length of sand with 35deg. = 7.43 m
Wt of sand with 35 incline = 1570.1 kN
Uplift resistance load = 1849.1 kN
F.O.S = 2.17 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1006.95 kN


Horizontal load = 115 kN
F.O.S = 8.76 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 168.0 kN/m2


Minimum pressure, Pmin = 84.0 kN/m2
Distance at face of col = 1.55 m
Pmax, at col face = 135.46 kN/m2
Shear at col face = 235.22 kN
Moment, at face of column = 182.3 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 484 mm

M/bd2fcu = 0.00648
z/d = 0.993 >0.95
As = M/0.87fyz = 1111.5 mm2
Asmin = 0.15bh/100 = 3300.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 16.4
Number of bar provided = 20.0 NOS
bar spasing = 205 mm

provide20 Y16 at 205 c/c


Area, A = 4021.248 mm2

(f) Vertical shear(ULS)

1.5d = 726 mm
Pressure at 1.5d = 150.73 kN/m2
Distance at 1.5d = 0.824 m
Vertical shear F = 525.3 kN
Shear stress v = 0.271 N/mm2
100As/bd = 0.208
Design stress vc = 0.398 N/mm2 O.K

(g) Punching shear and maximum shear


Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 159.39 kN/m2
V = 1668.48 kN
v = 0.366 N/mm2
vc = 0.398 N/mm2 O.K

Pav for shear Max Vmax = 126.00 kN/m2


Vmax = 1913.97 kN
vmax = 1.10 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 448.50 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 448.50 KN/m
N/bh = 1.97222222
M/bh2 = 0.61522634

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92

Area of bar req. due to uplift = 2490.73 mm2 O.K


RNRS/0639
3-Jan
19/9/6
Ir. Rosli
mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (100 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 4.3 m
Base width, b = 4.3 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 3.7 m

(b) Maximum earth pressure(SLS)

Weight of base = 266.3 kN


Weight of soil above = 848.6 kN
Weight of stump = 49.6 kN
Weight of tie beam = 16.0 kN
Total axial load- soil = 1396.8 kN
Total axial load = 2245.5 kN
Total moment = 293.25 kNm
Base area, A = 18.5 m2
Modulus, Z = 13.25 m3
Maximum Pressure, Pmax = 97.7 kN/m2 O.K
Minimun Pressure, Pmin = 53.4 kN/m 2
(c) Check for uplift

Uplift force = 851.000 kN


Length of sand with 35deg. = 7.66 m
Wt of sand with 35 incline = 1852.0 kN
Uplift resistance load = 2183.8 kN
F.O.S = 2.57 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1122.73 kN


Horizontal load = 115 kN
F.O.S = 9.76 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 146.5 kN/m2


Minimum pressure, Pmin = 80.1 kN/m2
Distance at face of col = 1.70 m
Pmax, at col face = 120.26 kN/m2
Shear at col face = 226.76 kN
Moment, at face of column = 192.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00524
z/d = 0.994 >0.95
As = M/0.87fyz = 1065.2 mm 2

Asmin = 0.15bh/100 = 3870.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 19.2
Number of bar provided = 20.0 NOS
bar spasing = 221 mm

provide20 Y16 at 221 c/c


Area, A = 4021.248

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 132.63 kN/m2
Distance at 1.5d = 0.899 m
Vertical shear F = 539.5 kN
Shear stress v = 0.235 N/mm2
100As/bd = 0.175
Design stress vc = 0.376 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 139.57 kN/m2
V = 1706.96 kN
v = 0.319 N/mm2
vc = 0.376 N/mm2 O.K

Pav for shear Max Vmax = 113.32 kN/m2


Vmax = 2003.43 kN
vmax = 1.04 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 439.88 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 439.88 KN/m
N/bh = 1.97222222
M/bh2 = 0.60339506

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2490.73 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
0 Y16 at 221 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1001 kN


Horizontal dead load (SLS) = 109 kN
Vertical uplift (SLS) = 739 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.45 m
Base length, l = 3.6 m
Base width, b = 3.6 m
Base depth, h = 0.55 m
Stump length = 2.6 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 4.4 m

(b) Maximum earth pressure(SLS)

Weight of base = 171.1 kN


Weight of soil above = 595.4 kN
Weight of stump = 50.5 kN
Weight of tie beam = 19.0 kN
Total axial load- soil = 1241.6 kN
Total axial load = 1837.0 kN
Total moment = 283.4 kNm
Base area, A = 13.0 m2
Modulus, Z = 7.78 m3
Maximum Pressure, Pmax = 132.2 kN/m2 O.K
Minimun Pressure, Pmin = 59.4 kN/m 2
(c) Check for uplift

Uplift force = 739.000 kN


Length of sand with 35deg. = 7.03 m
Wt of sand with 35 incline = 1528.3 kN
Uplift resistance load = 1769.0 kN
F.O.S = 2.39 O.K

(d) Resistance to horizontal load

Passive resistance, R = 918.49 kN


Horizontal load = 109 kN
F.O.S = 8.43 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 198.4 kN/m2


Minimum pressure, Pmin = 89.0 kN/m2
Distance at face of col = 1.35 m
Pmax, at col face = 157.37 kN/m2
Shear at col face = 240.13 kN
Moment, at face of column = 162.1 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 484 mm

M/bd2fcu = 0.00641
z/d = 0.993 >0.95
As = M/0.87fyz = 988.3 mm 2

Asmin = 0.15bh/100 = 2970.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 14.8
Number of bar provided = 18.0 NOS
bar spasing = 206 mm

provide18 Y16 at 206 c/c


Area, A = 3619.123

(f) Vertical shear(ULS)

1.5d = 726 mm
Pressure at 1.5d = 179.42 kN/m2
Distance at 1.5d = 0.624 m
Vertical shear F = 424.3 kN
Shear stress v = 0.244 N/mm2
100As/bd = 0.208
Design stress vc = 0.398 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 188.90 kN/m2
V = 1403.16 kN
v = 0.308 N/mm2
vc = 0.398 N/mm2 O.K

Pav for shear Max Vmax = 143.71 kN/m2


Vmax = 1746.03 kN
vmax = 1.00 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1501.5 KN
horizontal load = 163.5 KN
uplift load = 886.8 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 425.10 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 425.10 KN/m
N/bh = 1.8537037
M/bh2 = 0.58312757

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2162.93 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
8 Y16 at 206 c/c
mm2
mm2

3769.92 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (175 KN/M2) 20/7/2009
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 S6 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 175KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 788 kN


Horizontal dead load (SLS) = 87 kN
Vertical uplift (SLS) = 609 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 175 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.35 m
Base length, l = 3 m
Base width, b = 3 m
Base depth, h = 0.45 m
Stump length = 2.5 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 5 m

(b) Maximum earth pressure(SLS)

Weight of base = 97.2 kN


Weight of soil above = 353.6 kN
Weight of stump = 38.4 kN
Weight of tie beam = 21.6 kN
Total axial load- soil = 945.2 kN
Total axial load = 1298.8 kN
Total moment = 217.5 kNm
Base area, A = 9.0 m2
Modulus, Z = 4.50 m3
Maximum Pressure, Pmax = 153.4 kN/m2 O.K
Minimun Pressure, Pmin = 56.7 kN/m 2

(c) Check for uplift

Uplift force = 609.000 kN


Length of sand with 35deg. = 6.29 m
Wt of sand with 35 incline = 1027.1 kN
Area of slab within beam area = 10.7 m2
Select thickness of slab ,h = 0.900 m
Load from slab with thickness,h = 230.4 kN
Actual weight of sand effect = 855.6 kN
Uplift resistance load = 1243.2 kN
F.O.S = 2.041 O.K
(d) Resistance to horizontal load

Passive resistance, R = 649.41 kN


Horizontal load = 87 kN
F.O.S = 7.46 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 230.0 kN/m2


Minimum pressure, Pmin = 85.0 kN/m2
Distance at face of col = 1.10 m
Pmax, at col face = 176.87 kN/m2
Shear at col face = 223.80 kN
Moment, at face of column = 123.1 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 384 mm

M/bd2fcu = 0.00927
z/d = 0.990 >0.95
As = M/0.87fyz = 945.9 mm 2

Asmin = 0.15bh/100 = 2025.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 10.1
Number of bar provided = 14.0 NOS
bar spasing = 223 mm

provide14 Y16 at 223 c/c


Area, A = 2814.874 mm2

(f) Vertical shear(ULS)

1.5d = 576 mm
Pressure at 1.5d = 204.71 kN/m2
Distance at 1.5d = 0.524 m
Vertical shear F = 341.7 kN
Shear stress v = 0.297 N/mm2
100As/bd = 0.244
Design stress vc = 0.420 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 7.808 m
Area = 3.81 m2
Pav for punching sheer = 217.37 kN/m2
V = 1128.08 kN
v = 0.376 N/mm2
vc = 0.420 N/mm2 O.K

Pav for shear Max Vmax = 157.53 kN/m2


Vmax = 1316.98 kN
vmax = 1.07 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1182 KN
horizontal load = 130.5 KN
uplift load = 730.8 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 326.25 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 326.25 KN/m
N/bh = 1.846875
M/bh2 = 0.63720703

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 1782.44 mm2 O.K


CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 20/8/2009
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3-13 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 788 kN


Horizontal dead load (SLS) = 87 kN
Vertical uplift (SLS) = 609 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.3 m
Base length, l = 3.5 m
Base width, b = 3.5 m
Base depth, h = 0.5 m
Stump length = 2.45 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 4.5 m

(b) Maximum earth pressure(SLS)

Weight of base = 147.0 kN


Weight of soil above = 480.7 kN
Weight of stump = 37.6 kN
Weight of tie beam = 19.4 kN
Total axial load- soil = 992.1 kN
Total axial load = 1472.7 kN
Total moment = 213.15 kNm
Base area, A = 12.3 m2
Modulus, Z = 7.15 m3
Maximum Pressure, Pmax = 110.8 kN/m2 O.K
Minimun Pressure, Pmin = 51.2 kN/m2

(c) Check for uplift

Uplift force = 609.000 kN


Length of sand with 35deg. = 6.72 m
Wt of sand with 35 incline = 1188.4 kN
Uplift resistance load = 1392.4 kN
F.O.S = 2.29 O.K
(d) Resistance to horizontal load

Passive resistance, R = 736.36 kN


Horizontal load = 87 kN
F.O.S = 8.46 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 166.2 kN/m2


Minimum pressure, Pmin = 76.7 kN/m2
Distance at face of col = 1.35 m
Pmax, at col face = 131.71 kN/m2
Shear at col face = 201.10 kN
Moment, at face of column = 135.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 434 mm

M/bd2fcu = 0.00686
z/d = 0.992 >0.95
As = M/0.87fyz = 923.0 mm 2

Asmin = 0.15bh/100 = 2625.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 13.1
Number of bar provided = 18.0 NOS
bar spasing = 200 mm

provide18 Y16 at 200 c/c


Area, A = 3619.123 mm2

(f) Vertical shear(ULS)

1.5d = 651 mm
Pressure at 1.5d = 148.35 kN/m2
Distance at 1.5d = 0.699 m
Vertical shear F = 384.8 kN
Shear stress v = 0.253 N/mm2
100As/bd = 0.238
Design stress vc = 0.416 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 8.408 m
Area = 4.42 m2
Pav for punching sheer = 157.29 kN/m2
V = 1231.79 kN
v = 0.338 N/mm2
vc = 0.416 N/mm2 O.K

Pav for shear Max Vmax = 121.48 kN/m2


Vmax = 1410.36 kN
vmax = 1.02 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1182 KN
horizontal load = 130.5 KN
uplift load = 730.8 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 319.73 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 319.73 KN/m
N/bh = 1.846875
M/bh2 = 0.62446289

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 1782.44 mm2 O.K


CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 20/7/2009
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 FDN/01 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1049.4 kN


Horizontal dead load (SLS) = 119.21 kN
Vertical uplift (SLS) = 809.4 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.45 m
Base length, l = 3.7 m
Base width, b = 3.7 m
Base depth, h = 0.55 m
Stump length = 2.6 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 10 m
Length of tie Beam = 6.3 m

(b) Maximum earth pressure(SLS)

Weight of base = 180.7 kN


Weight of soil above = 575.5 kN
Weight of stump = 39.9 kN
Weight of tie beam = 27.2 kN
Total axial load- soil = 1297.3 kN
Total axial load = 1872.8 kN
Total moment = 309.946 kNm
Base area, A = 13.7 m2
Modulus, Z = 8.44 m3
Maximum Pressure, Pmax = 131.5 kN/m2 O.K
Minimun Pressure, Pmin = 58.0 kN/m2

(c) Check for uplift

Uplift force = 809.400 kN


Length of sand with 35deg. = 7.13 m
Wt of sand with 35 incline = 1422.8 kN
Uplift resistance load = 1670.7 kN
F.O.S = 2.06 O.K
(d) Resistance to horizontal load

Passive resistance, R = 936.38 kN


Horizontal load = 119.21 kN
F.O.S = 7.85 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 197.2 kN/m2


Minimum pressure, Pmin = 87.1 kN/m2
Distance at face of col = 1.45 m
Pmax, at col face = 154.05 kN/m2
Shear at col face = 254.66 kN
Moment, at face of column = 184.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 484 mm

M/bd2fcu = 0.00710
z/d = 0.992 >0.95
As = M/0.87fyz = 1125.7 mm 2

Asmin = 0.15bh/100 = 3052.5 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 15.2
Number of bar provided = 19.0 NOS
bar spasing = 200 mm

provide19 Y16 at 200 c/c


Area, A = 3820.186 mm2

(f) Vertical shear(ULS)

1.5d = 726 mm
Pressure at 1.5d = 175.66 kN/m2
Distance at 1.5d = 0.724 m
Vertical shear F = 499.4 kN
Shear stress v = 0.279 N/mm2
100As/bd = 0.213
Design stress vc = 0.401 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.008 m
Area = 5.07 m2
Pav for punching sheer = 186.43 kN/m2
V = 1606.79 kN
v = 0.369 N/mm2
vc = 0.401 N/mm2 O.K

Pav for shear Max Vmax = 142.14 kN/m2


Vmax = 1854.92 kN
vmax = 1.20 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1574.1 KN
horizontal load = 178.8 KN
uplift load = 971.3 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 464.92 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 464.92 KN/m
N/bh = 2.45953125
M/bh2 = 0.90804492

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2368.98 mm2 O.K


CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS/0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 76M 3-LEGGED TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 24/7/09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3-2 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

76m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 940 kN


Horizontal dead load (SLS) = 113 kN
Vertical uplift (SLS) = 757 kN
Soil Density = 18 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.45 m
Base length, l = 3.7 m
Base width, b = 3.7 m
Base depth, h = 0.55 m
Stump length = 2.6 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 10 m
Length of tie Beam = 6.3 m

(b) Maximum earth pressure(SLS)

Weight of base = 180.7 kN


Weight of soil above = 575.5 kN
Weight of stump = 39.9 kN
Weight of tie beam = 27.2 kN
Total axial load- soil = 1187.9 kN
Total axial load = 1763.4 kN
Total moment = 293.8 kNm
Base area, A = 13.7 m2
Modulus, Z = 8.44 m3
Maximum Pressure, Pmax = 121.6 kN/m2 O.K
Minimun Pressure, Pmin = 52.0 kN/m2

(c) Check for uplift

Uplift force = 757.000 kN


Length of sand with 35deg. = 7.13 m
Wt of sand with 35 incline = 1422.8 kN
Uplift resistance load = 1670.7 kN
F.O.S = 2.21 O.K
(d) Resistance to horizontal load

Passive resistance, R = 881.68 kN


Horizontal load = 113 kN
F.O.S = 7.80 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 182.4 kN/m2


Minimum pressure, Pmin = 78.0 kN/m2
Distance at face of col = 1.45 m
Pmax, at col face = 141.44 kN/m2
Shear at col face = 234.75 kN
Moment, at face of column = 170.2 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 484 mm

M/bd2fcu = 0.00655
z/d = 0.993 >0.95
As = M/0.87fyz = 1037.7 mm2
Asmin = 0.15bh/100 = 3052.5 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 15.2
Number of bar provided = 19.0 NOS
bar spasing = 200 mm

provide19 Y16 at 200 c/c


Area, A = 3820.186 mm2

(f) Vertical shear(ULS)

1.5d = 726 mm
Pressure at 1.5d = 161.93 kN/m2
Distance at 1.5d = 0.724 m
Vertical shear F = 461.1 kN
Shear stress v = 0.257 N/mm2
100As/bd = 0.213
Design stress vc = 0.401 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.008 m
Area = 5.07 m2
Pav for punching sheer = 172.14 kN/m2
V = 1483.59 kN
v = 0.340 N/mm2
vc = 0.401 N/mm2 O.K

Pav for shear Max Vmax = 130.15 kN/m2


Vmax = 1698.49 kN
vmax = 1.10 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1410 KN
horizontal load = 169.5 KN
uplift load = 908.4 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 440.70 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 440.70 KN/m
N/bh = 2.203125
M/bh2 = 0.86074219

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2215.61 mm2 O.K


CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS/0945
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 1
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 24/7/09
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 T3-5 Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 691 kN


Horizontal dead load (SLS) = 81 kN
Vertical uplift (SLS) = 562 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.3 m
Base length, l = 3.5 m
Base width, b = 3.5 m
Base depth, h = 0.5 m
Stump length = 2.45 m
Stump width = 0.8 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 4.5 m

(b) Maximum earth pressure(SLS)

Weight of base = 147.0 kN


Weight of soil above = 534.1 kN
Weight of stump = 37.6 kN
Weight of tie beam = 19.4 kN
Total axial load- soil = 895.1 kN
Total axial load = 1429.1 kN
Total moment = 198.45 kNm
Base area, A = 12.3 m2
Modulus, Z = 7.15 m3
Maximum Pressure, Pmax = 100.8 kN/m2 O.K
Minimun Pressure, Pmin = 45.3 kN/m2

(c) Check for uplift

Uplift force = 562.000 kN


Length of sand with 35deg. = 6.72 m
Wt of sand with 35 incline = 1320.4 kN
Uplift resistance load = 1524.5 kN
F.O.S = 2.71 O.K

(d) Resistance to horizontal load

Passive resistance, R = 714.57 kN


Horizontal load = 81 kN
F.O.S = 8.82 O.K
(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 151.3 kN/m2


Minimum pressure, Pmin = 67.9 kN/m2
Distance at face of col = 1.35 m
Pmax, at col face = 119.12 kN/m2
Shear at col face = 182.51 kN
Moment, at face of column = 123.2 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 434 mm

M/bd2fcu = 0.00623
z/d = 0.993 >0.95
As = M/0.87fyz = 837.7 mm2
Asmin = 0.15bh/100 = 2625.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 13.1
Number of bar provided = 18.0 NOS
bar spasing = 200 mm

provide18 Y16 at 200 c/c


Area, A = 3619.123 mm2

(f) Vertical shear(ULS)

1.5d = 651 mm
Pressure at 1.5d = 134.62 kN/m2
Distance at 1.5d = 0.699 m
Vertical shear F = 349.7 kN
Shear stress v = 0.230 N/mm2
100As/bd = 0.238
Design stress vc = 0.416 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 8.408 m
Area = 4.42 m2
Pav for punching sheer = 142.94 kN/m2
V = 1119.43 kN
v = 0.307 N/mm2
vc = 0.416 N/mm2 O.K

Pav for shear Max Vmax = 109.60 kN/m2


Vmax = 1272.46 kN
vmax = 0.92 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K
(h) Stump design(ULS)

stump size,h = 800 mm


stump size,b = 800 mm
compression load,N = 1036.5 KN
horizontal load = 121.5 KN
uplift load = 674.4 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 740 mm
d/h = 0.93

moment from horiz. load,M1 = 297.68 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 297.68 KN/m
N/bh = 1.61953125
M/bh2 = 0.58139648

from chart, 100Asc/bh = 0.4


Asc = 2560 mm2
Asmin = 2560 mm2
number of bar req. = 8.15
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 1644.88 mm2 O.K


RNRS/0945
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS/0639
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 3-Jan
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2) 19/9/6
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 150KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 3.8 m
Base width, b = 3.8 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 4.2 m

(b) Maximum earth pressure(SLS)

Weight of base = 207.9 kN


Weight of soil above = 654.2 kN
Weight of stump = 49.6 kN
Weight of tie beam = 18.1 kN
Total axial load- soil = 1340.7 kN
Total axial load = 1994.9 kN
Total moment = 293.25 kNm
Base area, A = 14.4 m2
Modulus, Z = 9.15 m3
Maximum Pressure, Pmax = 124.9 kN/m2 O.K
Minimun Pressure, Pmin = 60.8 kN/m 2

(c) Check for uplift

Uplift force = 851.000 kN


Length of sand with 35deg. = 7.16 m
Wt of sand with 35 incline = 1576.9 kN
Uplift resistance load = 1852.6 kN
F.O.S = 2.18 O.K

(d) Resistance to horizontal load

Passive resistance, R = 997.45 kN


Horizontal load = 115 kN
F.O.S = 8.67 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 187.4 kN/m2


Minimum pressure, Pmin = 91.2 kN/m2
Distance at face of col = 1.45 m
Pmax, at col face = 150.66 kN/m2
Shear at col face = 245.06 kN
Moment, at face of column = 177.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00547
z/d = 0.994 >0.95
As = M/0.87fyz = 981.9 mm 2

Asmin = 0.15bh/100 = 3420.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 17.0
Number of bar provided = 19.0 NOS
bar spasing = 206 mm

provide19 Y16 at 206 c/c


Area, A = 3820.186 mm2

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 170.93 kN/m2
Distance at 1.5d = 0.649 m
Vertical shear F = 441.8 kN
Shear stress v = 0.218 N/mm2
100As/bd = 0.188
Design stress vc = 0.385 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 179.15 kN/m2
V = 1465.43 kN
v = 0.274 N/mm2
vc = 0.385 N/mm2 O.K
Pav for shear Max Vmax = 139.26 kN/m2
Vmax = 1898.17 kN
vmax = 0.99 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 439.88 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 439.88 KN/m
N/bh = 1.97222222
M/bh2 = 0.60339506

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2490.73 mm2 O.K


RNRS/0639
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (75 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 75KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 75 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 5 m
Base width, b = 5 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 3 m

(b) Maximum earth pressure(SLS)

Weight of base = 360.0 kN


Weight of soil above = 1161.1 kN
Weight of stump = 49.6 kN
Weight of tie beam = 13.0 kN
Total axial load- soil = 1487.5 kN
Total axial load = 2648.7 kN
Total moment = 293.25 kNm
Base area, A = 25.0 m2
Modulus, Z = 20.83 m3
Maximum Pressure, Pmax = 73.6 kN/m2 O.K
Minimun Pressure, Pmin = 45.4 kN/m 2
(c) Check for uplift

Uplift force = 851.000 kN


Length of sand with 35deg. = 8.36 m
Wt of sand with 35 incline = 2277.4 kN
Uplift resistance load = 2699.9 kN
F.O.S = 3.17 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1324.33 kN


Horizontal load = 115 kN
F.O.S = 11.52 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 110.4 kN/m2


Minimum pressure, Pmin = 68.1 kN/m2
Distance at face of col = 2.05 m
Pmax, at col face = 93.05 kN/m2
Shear at col face = 208.50 kN
Moment, at face of column = 213.7 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00500
z/d = 0.994 >0.95
As = M/0.87fyz = 1181.1 mm 2

Asmin = 0.15bh/100 = 4500.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 22.4
Number of bar provided = 25.0 NOS
bar spasing = 204 mm

provide 22 Y16 at 200 c/c


Area, A = 5026.56

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 99.82 kN/m2
Distance at 1.5d = 1.249 m
Vertical shear F = 656.3 kN
Shear stress v = 0.246 N/mm2
100As/bd = 0.188
Design stress vc = 0.385 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 105.09 kN/m2
V = 1969.42 kN
v = 0.369 N/mm2
vc = 0.385 N/mm2 O.K

Pav for shear Max Vmax = 89.25 kN/m2


Vmax = 2159.00 kN
vmax = 1.12 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 439.88 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 439.88 KN/m
N/bh = 1.97222222
M/bh2 = 0.60339506

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2490.73 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
3-Jan
DATE:
19/9/6
CHECKED BY:
Ir. Rosli
22 Y16 at 200 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 45M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 924.4 kN


Horizontal dead load (SLS) = 96.3 kN
Vertical uplift (SLS) = 740.9 kN

Pre. Factor of safety for Vert. Load = 2.5


Pre. Factor of safety for Uplft Load = 2

Factored Vert. Load = 2311 kN


Factored Uplift. Load = 1481.8 kN

(b)Result From Mayerhof Equation

Size of pile = 200 SQ


Pile Length = 24 m
Ultimate Load = 578 kN
Total Pile Skin Friction = 365 kN

Nos Of Pile Req. Due To Vert. Load = 4.00 NOS


Nos Of Pile Req. Due To Uplift Load = 4.06 NOS
Nos Of Pile Provided = 5 NOS

Pile Cap Length = 1448 mm


Pile Cap Width = 1448 mm
Pile Cap Depth = 900 mm
Stump width = 900 mm
Stump Height = 800 mm

Weight Of Pile Cap = 45.29 kN


Weight Of Stump = 15.55 m

Total Uplift Resistance Force = 1885.84


Actual Factor Of Safety Againt Uplift = 2.5

Pile Working Load = 231.2 kN


Adopt Pile Working Load = 230.0 kN
JOB NO:
RNRS/0639
CALC SHEET:
31-Dec
DATE:
Jun-06
CHECKED BY:
Ir. Rosli
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 45M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 924.4 kN


Horizontal dead load (SLS) = 96.3 kN
Vertical uplift (SLS) = 740.9 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.5 m
Height of stump above grd = 0.15 m
Earth thickness = 1.95 m
Base length, l = 4.1 m
Base width, b = 4.1 m
Base depth, h = 0.55 m
Stump length = 2.1 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 6.125 m
Length of tie Beam = 2.025 m

(b) Maximum earth pressure(SLS)

Weight of base = 221.9 kN


Weight of soil above = 624.0 kN
Weight of stump = 40.8 kN
Weight of tie beam = 8.7 kN
Total axial load- soil = 1195.9 kN
Total axial load = 1819.9 kN
Total moment = 202.23 kNm
Base area, A = 16.8 m2
Modulus, Z = 11.49 m3
Maximum Pressure, Pmax = 88.7 kN/m2 O.K
Minimun Pressure, Pmin = 53.5 kN/m 2
(c) Check for uplift

Uplift force = 740.900 kN


Length of sand with 35deg. = 6.83 m
Wt of sand with 35 incline = 1237.4 kN
Uplift resistance load = 1508.9 kN
F.O.S = 2.04 O.K

(d) Resistance to horizontal load

Passive resistance, R = 909.93 kN


Horizontal load = 96.3 kN
F.O.S = 9.45 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 133.1 kN/m2


Minimum pressure, Pmin = 80.3 kN/m2
Distance at face of col = 1.60 m
Pmax, at col face = 112.51 kN/m2
Shear at col face = 196.50 kN
Moment, at face of column = 157.2 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 484 mm

M/bd2fcu = 0.00546
z/d = 0.994 >0.95
As = M/0.87fyz = 958.5 mm 2

Asmin = 0.15bh/100 = 3382.5 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 16.8
Number of bar provided = 17.0 NOS
bar spasing = 250 mm

provide 17 Y16 at 213 c/c


Area, A = 3418.061

(f) Vertical shear(ULS)

1.5d = 726 mm
Pressure at 1.5d = 121.86 kN/m2
Distance at 1.5d = 0.874 m
Vertical shear F = 456.8 kN
Shear stress v = 0.230 N/mm2
100As/bd = 0.172
Design stress vc = 0.374 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 9.408 m
Area = 5.53 m2
Pav for punching sheer = 127.49 kN/m2
V = 1437.83 kN
v = 0.316 N/mm2
vc = 0.374 N/mm2 O.K

Pav for shear Max Vmax = 106.71 kN/m2


Vmax = 1707.36 kN
vmax = 0.98 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1386.6 KN
horizontal load = 144.5 KN
uplift load = 889.1 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 303.35 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 303.35 KN/m
N/bh = 1.71185185
M/bh2 = 0.41611111

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2168.49 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
31-Dec
DATE:
Jun-06
CHECKED BY:
Ir. Rosli
17 Y16 at 213 c/c
mm2
mm2

3769.92 mm2
CLIENT:
PERUNDING RNR SEPAKAT INFRA QUEST
PROJECT:
Lot 2564, Taman Adabi, Kota Kubang Labu, 45M 3-LEGGED TOWER
STRUCTURE:
16250 Tumpat, Kelantan Darul Naim FOOTING (150 KN/M2)
DRG. REF: CALC BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 924.4 kN


Horizontal dead load (SLS) = 96.3 kN
Vertical uplift (SLS) = 740.9 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 150 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 3 m
Height of stump above grd = 0.15 m
Earth thickness = 2.4 m
Base length, l = 3.5 m
Base width, b = 3.5 m
Base depth, h = 0.6 m
Stump length = 2.55 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 6.125 m
Length of tie Beam = 2.625 m

(b) Maximum earth pressure(SLS)

Weight of base = 176.4 kN


Weight of soil above = 549.1 kN
Weight of stump = 49.6 kN
Weight of tie beam = 11.3 kN
Total axial load- soil = 1161.7 kN
Total axial load = 1710.8 kN
Total moment = 245.565 kNm
Base area, A = 12.3 m2
Modulus, Z = 7.15 m3
Maximum Pressure, Pmax = 129.2 kN/m2 O.K
Minimun Pressure, Pmin = 60.5 kN/m 2
(c) Check for uplift

Uplift force = 740.900 kN


Length of sand with 35deg. = 6.86 m
Wt of sand with 35 incline = 1423.4 kN
Uplift resistance load = 1660.7 kN
F.O.S = 2.24 O.K

(d) Resistance to horizontal load

Passive resistance, R = 855.42 kN


Horizontal load = 96.3 kN
F.O.S = 8.88 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 193.8 kN/m2


Minimum pressure, Pmin = 90.7 kN/m2
Distance at face of col = 1.30 m
Pmax, at col face = 155.51 kN/m2
Shear at col face = 227.05 kN
Moment, at face of column = 147.6 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00493
z/d = 0.994 >0.95
As = M/0.87fyz = 815.6 mm 2

Asmin = 0.15bh/100 = 3150.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 15.7
Number of bar provided = 17.0 NOS
bar spasing = 213 mm

provide 17 Y16 at 213 c/c


Area, A = 3418.061

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 179.10 kN/m2
Distance at 1.5d = 0.499 m
Vertical shear F = 325.6 kN
Shear stress v = 0.174 N/mm2
100As/bd = 0.183
Design stress vc = 0.381 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 186.45 kN/m2
V = 1116.83 kN
v = 0.209 N/mm2
vc = 0.381 N/mm2 O.K

Pav for shear Max Vmax = 142.25 kN/m2


Vmax = 1627.35 kN
vmax = 0.85 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1386.6 KN
horizontal load = 144.5 KN
uplift load = 889.1 KN
bar size = 20 mm Area = 314.16
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 368.35 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 368.35 KN/m
N/bh = 1.71185185
M/bh2 = 0.50527778

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc =

Area of bar req. due to uplift = 2168.49 mm2 O.K


JOB NO:
RNRS/0639
CALC SHEET:
31-Dec
DATE:
Jun-06
CHECKED BY:
Ir. Rosli
17 Y16 at 213 c/c
mm2
mm2

3769.92 mm2
CLIENT: JOB NO:
PERUNDING RNR SEPAKAT INFRA QUEST RNRS/0639
PROJECT: CALC SHEET:
Lot 2564, Taman Adabi, Kota Kubang Labu, 60M 3-LEGGED TOWER 3-Jan
STRUCTURE: DATE:
16250 Tumpat, Kelantan Darul Naim FOOTING (100 KN/M2) 19/9/6
DRG. REF: CALC BY: CHECKED BY:
Tel : 609-7185070 / 71 Fax No: 609-7185072 C&S/002A Rumaizi Ir. Rosli

FOUNDATION CALCULATION

60m Tower 3-leg-(soil bearing = 100KN/M2)-INFRA QUEST

(a) Specification

Vertical dead load (SLS) = 1065 kN


Horizontal dead load (SLS) = 115 kN
Vertical uplift (SLS) = 851 kN
Soil Density = 20 kN/m3
Safe bearing pressure, pb = 100 kN/m2
Cohesion, c = 60 kN/m2
Concrete strength, fcu = 30 N/mm2
Reinforcement strength, fy = 410 N/mm2
Soffit Depth of Excavation = 2.8 m
Height of stump above grd = 0.15 m
Earth thickness = 2.2 m
Base length, l = 4.3 m
Base width, b = 4.3 m
Base depth, h = 0.6 m
Stump length = 2.35 m
Stump width = 0.9 m
Depth of tie Beam = 0.6 m
Width of tie Beam = 0.3 m
Length between ftg = 8 m
Length of tie Beam = 3.7 m

(b) Maximum earth pressure(SLS)

Weight of base = 266.3 kN


Weight of soil above = 777.9 kN
Weight of stump = 45.7 kN
Weight of tie beam = 16.0 kN
Total axial load- soil = 1392.9 kN
Total axial load = 2170.8 kN
Total moment = 270.25 kNm
Base area, A = 18.5 m2
Modulus, Z = 13.25 m3
Maximum Pressure, Pmax = 95.7 kN/m2 O.K
Minimun Pressure, Pmin = 54.9 kN/m 2

(c) Check for uplift

Uplift force = 851.000 kN


Length of sand with 35deg. = 7.38 m
Wt of sand with 35 incline = 1605.0 kN
Uplift resistance load = 1932.9 kN
F.O.S = 2.27 O.K

(d) Resistance to horizontal load

Passive resistance, R = 1085.42 kN


Horizontal load = 115 kN
F.O.S = 9.44 O.K

(e) Design of the moment reinforcement(ULS)

Maximum pressure, Pmax = 143.6 kN/m2


Minimum pressure, Pmin = 82.4 kN/m2
Distance at face of col = 1.70 m
Pmax, at col face = 119.40 kN/m2
Shear at col face = 223.55 kN
Moment, at face of column = 190.0 kNm

Cover bar = 50 mm
Diameter bar = 16 mm
Effective depth, dav = 534 mm

M/bd2fcu = 0.00517
z/d = 0.994 >0.95
As = M/0.87fyz = 1050.1 mm 2

Asmin = 0.15bh/100 = 3870.0 mm2 >As

Adopt diameter bar = 16 mm


area A = 201.062 mm2
Number of bar required = 19.2
Number of bar provided = 22.0 NOS
bar spasing = 200 mm

provide 22 Y16 at 200 c/c


Area, A = 4423.373 mm2

(f) Vertical shear(ULS)

1.5d = 801 mm
Pressure at 1.5d = 130.80 kN/m2
Distance at 1.5d = 0.899 m
Vertical shear F = 530.4 kN
Shear stress v = 0.231 N/mm2
100As/bd = 0.193
Design stress vc = 0.388 N/mm2 O.K

(g) Punching shear and maximum shear

Perimeter = 10.008 m
Area = 6.26 m2
Pav for punching sheer = 137.20 kN/m2
V = 1677.92 kN
v = 0.314 N/mm2
vc = 0.388 N/mm2 O.K
Pav for shear Max Vmax = 113.00 kN/m2
Vmax = 1997.86 kN
vmax = 1.04 N/mm2
0.8x(fcu)0.25 = 4.38 N/mm2 O.K

(h) Stump design(ULS)

stump size,h = 900 mm


stump size,b = 900 mm
compression load,N = 1597.5 KN
horizontal load = 172.5 KN
uplift load = 1021.2 KN
bar size = 20 mm Area = 314.16 mm2
link size = 10 mm
cover = 40 mm
Eff. Depth, d = 840 mm
d/h = 0.93

moment from horiz. load,M1 = 405.38 KN/m


applied moment,M2 = 0.00 KN/m
Total moment,M = 405.38 KN/m
N/bh = 1.97222222
M/bh2 = 0.55606996

from chart, 100Asc/bh = 0.4


Asc = 3240 mm2
Asmin = 3240 mm2
number of bar req. = 10.31
number of bar prov. = 12 NOS
USE 12Y20 Asc = 3769.92 mm2

Area of bar req. due to uplift = 2490.73 mm2 O.K