ID Task Name Duration Start Finish April 2014 May 2014 June 2014 July 2014

30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14
2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14 /1 4/2
3 Array Area and General Works 110 days Sat 4/5/14 Wed 7/23/14
4 Civil Works 93 days Sat 4/5/14 Sun 7/6/14
5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14 4/5 4/19
6 Marking and Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14 4/15 5/14
7 Foundation and Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14 4/18 4/22
8 Foundation and Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14 4/18 4/22
9 Construction of Internal Roads 5 days Tue 4/22/14 Sat 4/26/14 4/22 4/26
10 Foundation Marking for Structures 5 days Mon 4/21/14 Fri 4/25/14 4/21 4/25
11 Excavation for Structure Foundation 20 days Tue 4/22/14 Sun 5/11/14 4/22 5/11
12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu 5/22/14 4/23 5/22
13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14 5/3 5/7
14 Cable trench 7 days Fri 5/23/14 Thu 5/29/14 5/23 5/29
15 Construction of Water Collection Tank 10 days Fri 5/23/14 Sun 6/1/14 5/23 6/1
16 Construction of Drainage system 30 days Tue 5/27/14 Wed 6/25/14 5/27 6/25
17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14 5/23 5/25
18 Lightening Arrester Foundation 5 days Sun 6/22/14 Thu 6/26/14 6/22 6/26
19 External Lighting Foundation 15 days Sun 6/22/14 Sun 7/6/14 6/22 7/6
20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14 6/22 6/26
21 Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14 6/12 6/16
22 Electrical Works 97 days Thu 4/17/14 Wed 7/23/14
23 Structure 57 days Thu 4/17/14 Fri 6/13/14
24 Purchase Order for Structure 0 days Thu 4/17/14 Thu 4/17/14 4/17
25 Payment for Structure 0 days Thu 4/24/14 Thu 4/24/14 4/24
26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14 4/25 5/19
27 Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14 5/30 6/13
28 PV Module 52 days Fri 4/25/14 Sun 6/15/14
29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14 4/25
30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14 4/25 5/2
31 Receiving of PV Module 30 days Fri 5/2/14 Sun 6/1/14 5/2 6/1
32 Installation of PV Module 15 days Sun 6/1/14 Sun 6/15/14 6/1 6/15
33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14
34 Purchase Order for SMB 0 days Mon 4/21/14 Mon 4/21/14 4/21
35 Payment for SMB 7 days Mon 4/21/14 Mon 4/28/14 4/21 4/28
36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14 4/28 5/28
37 Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14 5/28 5/31
38 Inverter 69 days Sat 4/19/14 Thu 6/26/14
39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat 4/19/14 4/19
40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14 4/19 4/26
41 Receiving of Inverter 60 days Sat 4/26/14 Wed 6/25/14 4/26 6/25
42 Installation of Inverter 2 days Wed 6/25/14 Thu 6/26/14 6/25 6/26
43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14
44 Purchase Order for DC Cable 0 days Tue 4/29/14 Tue 4/29/14 4/29
45 Payment for DC Cable 7 days Tue 4/29/14 Tue 5/6/14 4/29 5/6
46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14 5/6 6/20
47 Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14 6/20 6/27
48 Termination of DC Cable 5 days Fri 6/27/14 Tue 7/1/14 6/27 7/1
49 OFC 60 days Thu 5/1/14 Sun 6/29/14
50 Purchase Order for OFC 0 days Thu 5/1/14 Thu 5/1/14 5/1
51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14 5/1 5/8
52 Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14 5/8 6/22
53 Laying of OFC 5 days Sun 6/22/14 Fri 6/27/14 6/22 6/27
54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14 6/27 6/29
55 CCTV SYSTEM 40 days Sat 5/31/14 Wed 7/9/14
56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat 5/31/14 5/31
57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14 5/31 6/7
58 Receiving of CCTV 30 days Sat 6/7/14 Mon 7/7/14 6/7 7/7
59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14 7/7 7/9
60 Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14
61 Purchase order for Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14 5/31
62 Payment for Lightening Arrestor 7 days Sat 5/31/14 Sat 6/7/14 5/31 6/7
63 Receiving of Lightening Arrestor 30 days Sat 6/7/14 Mon 7/7/14 6/7 7/7
64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu 7/10/14 7/7 7/10
65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14
66 Purchase Order for SCADA System 0 days Tue 5/13/14 Tue 5/13/14 5/13
67 Payment for SCADA System 7 days Tue 5/13/14 Tue 5/20/14 5/13 5/20
68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14 5/20 7/19

Project: Template PIS Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Date: Wed 3/19/14 Progress Summary Rolled Up Milestone Split Project Summary Deadline

Page 1
ID Task Name Duration Start Finish April 2014 May 2014 June 2014 July 2014
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14 7/19 7/23
70 External Lighting 57 days Wed 5/21/14 Wed 7/16/14
71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14 5/21
72 Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14 5/21 5/28
73 Receiving of Lighting System 40 days Wed 5/28/14 Mon 7/7/14 5/28 7/7
74 Installation and Termination of Lighting System 10 days Mon 7/7/14 Wed 7/16/14 7/7 7/16
75 Array Earthing 57 days Sun 5/18/14 Sun 7/13/14
76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14 5/18
77 Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14 5/18 5/25
78 Receiving of Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14 5/25 7/4
79 Array Earthing Installation and Connection 10 days Fri 7/4/14 Sun 7/13/14 7/4 7/13
80 Main Control Room & Substation 86 days Thu 4/24/14 Fri 7/18/14
81 Civil Work in MCR & Substation 60 days Sat 4/26/14 Tue 6/24/14
82 Marking 2 days Sat 4/26/14 Sun 4/27/14 4/26 4/27
83 Excavation 3 days Mon 4/28/14 Wed 4/30/14 4/28 4/30
84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14 5/1 5/20
85 Brick work 15 days Wed 5/21/14 Wed 6/4/14 5/21 6/4
86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14 6/5 6/11
87 Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14 6/12 6/18
88 Windows & Doors Fixing 7 days Thu 6/12/14 Wed 6/18/14 6/12 6/18
89 Painting work 7 days Thu 6/12/14 Wed 6/18/14 6/12 6/18
90 Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14 6/15 6/24
91 Power and Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14 5/6 5/20
92 Switch Yard Earthing Mat Construction 7 days Fri 5/16/14 Thu 5/22/14 5/16 5/22
93 Switch Yard Equipment Foundation 15 days Fri 5/23/14 Fri 6/6/14 5/23 6/6
94 Foundation for Transmission Towers 30 days Fri 5/23/14 Sat 6/21/14 5/23 6/21
95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14
96 Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14
97 Purchase Order for Transformer 0 days Thu 4/24/14 Thu 4/24/14 4/24
98 Payment for Transformer 7 days Thu 4/24/14 Thu 5/1/14 4/24 5/1
99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14 5/1 6/30
100 Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14 6/30 7/4
101 33 kV bay station 73 days Tue 4/29/14 Thu 7/10/14
102 Purchase Order for VCB,Conductors,Isolator,CT,PT,Structure
2 days Tue 4/29/14 Thu 5/1/14 4/29 5/1
103 Payment for VCB,Conductors,Isolator,CT,PT,Structure
7 days Thu 5/1/14 Thu 5/8/14 5/1 5/8
104 Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14 5/8 6/27
105 Installation of Equipments 7 days Fri 6/27/14 Thu 7/3/14 6/27 7/3
106 Termination of Conductors 7 days Fri 7/4/14 Thu 7/10/14 7/4 7/10
107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14
108 Purchase Order for HT Panels 0 days Fri 5/9/14 Fri 5/9/14 5/9
109 Payment for HT Panels 7 days Fri 5/9/14 Fri 5/16/14 5/9 5/16
110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14 5/16 7/5
111 Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14 7/5 7/8
112 LT Panels 61 days Fri 5/9/14 Tue 7/8/14
113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14 5/9
114 Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14 5/9 5/16
115 Receiving of LT Panels 50 days Fri 5/16/14 Sat 7/5/14 5/16 7/5
116 Installation of LT Panels 4 days Sat 7/5/14 Tue 7/8/14 7/5 7/8
117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14
118 Purchase Order for LT Cable 0 days Sat 5/3/14 Sat 5/3/14 5/3
119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14 5/3 5/10
120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14 5/10 6/29
121 Laying of LT Cable 5 days Sun 6/29/14 Thu 7/3/14 6/29 7/3
122 Terination of LT Cable 5 days Wed 7/9/14 Sun 7/13/14 7/9 7/13
123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14
124 Purchase Order for HT Cable 0 days Mon 5/5/14 Mon 5/5/14 5/5
125 Payment for HT Cable 7 days Mon 5/5/14 Mon 5/12/14 5/5 5/12
126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14 5/12 7/1
127 Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14 7/1 7/5
128 Termination of HT Cable 5 days Wed 7/9/14 Sun 7/13/14 7/9 7/13
129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14
130 Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14 5/10
131 Payment for Control Cable 7 days Sat 5/10/14 Sat 5/17/14 5/10 5/17
132 Receiving of Control Cables 45 days Sat 5/17/14 Tue 7/1/14 5/17 7/1
133 Laying of Control Cable 4 days Tue 7/1/14 Fri 7/4/14 7/1 7/4
134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14 7/9 7/11
135 Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14
136 Purchase Order for LA 0 days Wed 5/21/14 Wed 5/21/14 5/21

Project: Template PIS Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Date: Wed 3/19/14 Progress Summary Rolled Up Milestone Split Project Summary Deadline

Page 2
ID Task Name Duration Start Finish April 2014 May 2014 June 2014 July 2014
30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
137 Payment for LA 7 days Wed 5/21/14 Wed 5/28/14 5/21 5/28
138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14 5/28 6/17
139 Installation of LA 5 days Tue 6/17/14 Sat 6/21/14 6/17 6/21
140 Battery System 57 days Fri 5/9/14 Fri 7/4/14
141 Purchase Order for Battery Bank 0 days Fri 5/9/14 Fri 5/9/14 5/9
142 Payment for Battery Bank 7 days Fri 5/9/14 Fri 5/16/14 5/9 5/16
143 Receiving of Battery Bank 45 days Fri 5/16/14 Mon 6/30/14 5/16 6/30
144 Installation of Battery Bank 5 days Mon 6/30/14 Fri 7/4/14 6/30 7/4
145 Switch Yard Earthing 30 days Sat 4/26/14 Sun 5/25/14
146 Purchase Order for Earthing Equipments 0 days Sat 4/26/14 Sat 4/26/14 4/26
147 Payment for Earthing Equipments 7 days Sat 4/26/14 Sat 5/3/14 4/26 5/3
148 Receiving of Earthing Equipments 20 days Sat 5/3/14 Fri 5/23/14 5/3 5/23
149 Installation and Connection 3 days Fri 5/23/14 Sun 5/25/14 5/23 5/25
150 Internal Lightning System 42 days Mon 5/26/14 Sun 7/6/14
151 Purchase Order for Poles and Lights 0 days Mon 5/26/14 Mon 5/26/14 5/26
152 Payment for Lighting System 7 days Mon 5/26/14 Mon 6/2/14 5/26 6/2
153 Receiving of Lighting System 30 days Mon 6/2/14 Wed 7/2/14 6/2 7/2
154 Installation and Termination of Lighting System 5 days Wed 7/2/14 Sun 7/6/14 7/2 7/6
155 Misc. Items(SDB,Feeders,ACDB,Industrial Socket) 67 days Tue 4/29/14 Fri 7/4/14
156 Purchase Order for Misc.Items 0 days Tue 4/29/14 Tue 4/29/14 4/29
157 Payment for Misc.Items 7 days Tue 4/29/14 Tue 5/6/14 4/29 5/6
158 Receiving of Misc.Items 50 days Tue 5/6/14 Wed 6/25/14 5/6 6/25
159 Installation and Termination of Misc.Items 10 days Wed 6/25/14 Fri 7/4/14 6/25 7/4
160 Weather monitoring system 42 days Sat 6/7/14 Fri 7/18/14
161 Purchase Order for WMS 0 days Sat 6/7/14 Sat 6/7/14 6/7
162 Payment for WMS 7 days Sat 6/7/14 Sat 6/14/14 6/7 6/14
163 Receiving of WMS 30 days Sat 6/14/14 Mon 7/14/14 6/14 7/14
164 Installation of WMS 5 days Mon 7/14/14 Fri 7/18/14 7/14 7/18
165 Transmission Line 57 days Fri 5/16/14 Fri 7/11/14
166 Purchase Order for Transmission Line Structures & 0Equipments
days Fri 5/16/14 Fri 5/16/14 5/16
167 Payment for Transmission Line Structures & Equipments
7 days Fri 5/16/14 Fri 5/23/14 5/16 5/23
168 Receiving of Structures and Equipments 30 days Fri 5/23/14 Sun 6/22/14 5/23 6/22
169 Installation and Stringing of Equipments 20 days Sun 6/22/14 Fri 7/11/14 6/22 7/11
170 Fire alarm system works 5 days Wed 7/9/14 Sun 7/13/14 7/9 7/13
171 Testing and commissioning 10 days Sat 7/19/14 Mon 7/28/14 7/19 7/2
172 Proposed Commercial Operation Date 1 day Tue 7/29/14 Tue 7/29/14 7/29 7

Project: Template PIS Task Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary
Date: Wed 3/19/14 Progress Summary Rolled Up Milestone Split Project Summary Deadline