Você está na página 1de 17

Cockatiel Relocation Define Care Requirements

Start: 10/1/17 ID: 1 Start: 10/1/17 ID: 2


Finish: 11/23/17 Dur: 40 days Finish: 10/9/17 Dur: 7 days
Comp: 0% Comp: 0%

Page 1
Page 2
Read MSPCA-ANGELL Information Create Summary to Share with Stakeholders
Start: Sun 10/1/17 ID: 3 Start: Mon 10/2/17 ID: 4
Finish: Sun 10/1/17 Dur: 1 day Finish: Mon 10/2/17Dur: 1 day
Res: Res:

Research Potential Solutions/Relocation Locations


Start: 10/10/17 ID: 6
Finish: 10/19/17 Dur: 8 days
Comp: 0%

Page 3
Diseminate Information and Solicit Stakeholder Input
Start: 10/20/17 ID: 13
Finish: 11/10/17 Dur: 15.5 days
Comp: 0%

Page 4
Seek Input
Start: Tue 10/3/17 ID: 5
Finish: Mon 10/9/17Dur: 5 days
Res:

Contact Nancy's Leasing Company


Start: Tue 10/10/17 ID: 7
Finish: Tue 10/10/17Dur: 1 day
Res:

Contact Humane Society


Start: Tue 10/10/17 ID: 8
Finish: Tue 10/10/17Dur: 1 day
Res:

Contact Omaha's Henry Doorly Zoo


Start: Tue 10/10/17 ID: 9
Finish: Tue 10/10/17Dur: 1 day
Res:

Look Into Service Animal Exemptions for Angel or one of Nancy's Other Animals
Start: Tue 10/10/17 ID: 10
Finish: Wed 10/11/17Dur: 2 days
Res:

Page 5
Locate Online Posting Opportunities (Facebook, Craigslist, ReHomeYourPet.com, etc.)
Start: Tue 10/10/17 ID: 11
Finish: Mon 10/16/17Dur: 5 days
Res:

Create Google Spreadsheet to Track Possible Relocation Options


Start: Fri 10/20/17 ID: 14
Finish: Mon 10/23/17Dur: 2 days
Res:

Relocation
Start: 11/10/17 ID: 20
Finish: 11/23/17 Dur: 9.5 days
Comp: 0%

Page 6
Page 7
Create and Publish Postings on Applicable Online Options
Start: Tue 10/17/17 ID: 12
Finish: Thu 10/19/17Dur: 3 days
Res:

Invite Stakeholders to Google Spreadsheet Determine When Search has Received Enough Viable Options
Start: Tue 10/24/17 ID: 15 Start: Tue 10/24/17 ID: 16
Finish: Tue 10/24/17Dur: 0.5 days Finish: Wed 10/25/17Dur: 1 day
Res: Res:

Page 8
Page 9
Contact Stakeholders and Set Week Deadline to Provide Feedback
Create SWOT Analysis of Relocation Opportunities Based on Feedback
Start: Wed 10/25/17ID: 17 Start: Fri 11/3/17 ID: 18
Finish: Fri 11/3/17 Dur: 7 days Finish: Tue 11/7/17 Dur: 2 days
Res: Res:

Page 10
Page 11
Stakeholders Rank Their Respective Top Three Placements
Start: Tue 11/7/17 ID: 19
Finish: Fri 11/10/17 Dur: 3 days
Res:

Contact Preferred New Caretaker in Rank Order Until One Confirms Willingness
Start: Fri 11/10/17 ID: 21
Finish: Mon 11/13/17Dur: 1 day
Res:

Page 12
Page 13
Inquire Date Availability of New Caretaker to Assume Care ofShare
AngelRelocation Plan with All Stakeholders at least 7 Days Prior to Move
Start: Mon 11/13/17ID: 22 Start: Tue 11/14/17 ID: 23
Finish: Mon 11/13/17Dur: 0.5 days Finish: Wed 11/22/17Dur: 7 days
Res: Res:

Page 14
Page 15
Pack up Angel and Her Items for Relocation
Start: Thu 11/23/17ID: 24
Finish: Thu 11/23/17Dur: 1 day
Res:

Page 16
Critical Summary Critical External

Noncritical Critical Inserted External

Project: Christensen- Week 6 N


Critical Milestone Inserted Project Summary
Date: Tue 9/26/17
Milestone Critical Marked Highlighted Critical

Critical Summary Marked Highlighted Noncritical

Page 17