Background
Brief
The Company can enter into a direct supply agreement with customers which
belong to the contestable market, i.e., those who have monthly average usage of one
MW (1 MW) or 750kW by June 2017. However, the Company will not be allowed
to directly supply those customers which belong to the non-contestable or captive
market. In this regard, the Company may enter into a lease-to-own arrangement
with the captive market customers, who shall be the recognized RE Developers.
Our discussion in this memo is premised on the assumption that the Company will
service those who belong to the captive market. Thus, our advice herein is limited
to the legal and regulatory framework governing a lease-to-own arrangement
between the Company and a consumer which belongs to the captive market.
This arrangement though has certain challenges and issues, as discussed below.
Discussion
The development, exploitation and utilization of solar energy within the Philippine
jurisdiction was governed primarily by Executive Order No. 462, otherwise known
as Enabling Private Sector Participation in the Exploration, Development, Utilization
and Commercialization of Ocean, Solar and Wind Energy Resources for Power
Generation and Other Energy Uses. This law was amended and expanded by the
enactment of Republic Act No. 9513, otherwise known as the Renewable Energy Act
of 2008 (RA 9513 or the RE Act). This law, in turn, is enabled by its
Implementing Rules and Regulations under Department of Energy (DOE) Circular
2009-05-0008 (RA 9513 IRR).
It is important to note that under the RA 9513 IRR, the development, exploitation
and utilization of solar energy in the Philippines can only be undertaken through a
joint venture or co-production sharing agreements between the State and Filipino
citizens or juridical entities whose capital is at least 60%-owned by Filipinos. This
restriction echoes Section 2 of Article XII of the 1987 Philippine Constitution on
National Economy and Patrimony, to wit:
2
supervision of the State. The State may directly undertake such activities, or
it may enter into co-production, joint venture, or production-sharing
agreements with Filipino citizens, or corporations or associations at least
sixty per centum of whose capital is owned by such citizens. Such
agreements may be for a period not exceeding twenty-five years, renewable
for not more than twenty-five years, and under such terms and conditions as
may be provided by law. In cases of water rights for irrigation, water supply,
fisheries, or industrial uses other than the development of water power,
beneficial use may be the measure and limit of the grant. 1
The phrase all forces of potential energy has been interpreted by the enabling
statutory laws, such as the RA 9513 IRR, to include all sources of energy which
include thermal energy generated through solar means. Thus, the development,
exploitation and utilization of solar energy is limited to Filipino citizens or entities
whose capital is at least 60%-owned by Filipino citizens. Pursuant to this
requirement, Renewable Energy (Systems) Developers or RE Developers3 should be
Filipino citizens or owned by Filipinos to the extent of 60% of its outstanding capital
stock. However, RE Developers For Own Use need not comply with this
requirement, if they do not supply energy to third parties.4
1
Emphasis supplied.
2
Emphasis supplied.
3
RE Developers refers to individuals or a group of individuals formed in accordance with existing
Philippines Laws engaged in the exploration, development and utilization of RE resources and actual
operation of RE systems/facilities. RE Act, sec. 4(pp).
4
This was conformed by Mr. Peter Sablay, Science and Research Specialist of the Wind ans Solar
Division of the Department of Energy.
5
Part 1 (Application Requirements), Section 6 of DC 09-07-0011 provides the qualification of those
who may apply for RE contracts, as follows:
a. Who may apply Any person, natural or juridical, local or foreign, may, subject to the
limits herein set, apply for RE contracts:
XXX
ii. In the case of the exploration, development or utilization of geothermal resources,
the applicant may either be a Filipino, natural or juridical, or a foreign corporation.
3
B. The Philippine Electric Power Industry
The main law governing the Philippine power industry is Republic Act No. 9136 6,
otherwise known as the Electric Power Industry Reform Act of 2001 (EPIRA).
The electric power industry in the Philippines is divided into four sectors, namely:
generation, transmission, distribution and supply. Generation and supply sectors are
not required to secure a national franchise because the law does not consider them
engaged in public utility operations.7 Transmission and distribution players on the
other hand are considered public utilities or common carrier business for public
service, and thus, are required to secure a national franchise.8
Although EPIRA contains provisions which preserve the exclusive nature of the DUs
legislative franchise over its franchise area, it allows and promotes open access11 and
retail competition.12 Thus, the EPIRA permits independent electricity generators,
retailers, and aggregators to deliver electricity to end-users without having to
construct and own the distribution infrastructure. 13 This is made possible by
allowing such entities to have open access to the DUs infrastructures subject to the
payment of wheeling and access charge to the DUs for the use of the distribution
network. The EPIRA likewise allows entities to generate electricity for own use,
subject to compliance with regulatory requirements.14
6
An Act Ordaining Reforms in the Electric Power Industry, Amending for the Purpose Certain Laws
and for Other Purposes.
7
Section 6 of the EPIRA; IDEALS, Inc. v. PSALM, 682 SCRA, October 9, 2012.
8
EPIRA, Sections 7 and 22.
9
Id., Section 4(q).
10
IRR of RA 9513, states:
(a) A Distribution Utility may enter into bilateral power supply contracts subject to the
provisions of Section 5 of Rule 30 on NPC Offer of Transition Supply Contracts and a
review by the ERC: Provided, That such review shall only be required for a Distribution
Utility whose level of Open Access has not reached household demand level.
11
EPIRA, Section 6.
12
Id., Section 2(c).
13
EPIRA, Section 4(hh) and Section 31.
14
ERC Resolution No. 16, series of 2014.
4
C. Open-Access and Retail Competition
Open Access is defined in the EPIRA as a system of allowing any qualified person
the use of transmission, and/or distribution system, and associated facilities subject
to the payment of transmission and/or distribution retail wheeling rates duly
approved by the ERC.15
The EPIRAs Open Access and Retail Competition program divided the end-users
into two primary markets for the supply of electricity, namely, the non-contestable
or captive market and the contestable market. The initial implementation of Open
Access is limited to those which belong to the contestable market.
Upon the initial implementation of Open Access, the ERC [Energy Regulatory
Commission] shall allow all electricity End-users with a monthly average peak
demand of at least one megawatt (1 MW) for the preceding twelve (12)
months to be the Contestable Market. Two (2) years thereafter, the threshold
level for the Contestable Market shall be reduced to seven hundred fifty
kilowatts (750 kW). At this level, Aggregators shall be allowed to supply
electricity to End-users whose aggregate monthly average peak demand within
a Contiguous Area is at least seven hundred fifty kilowatts (750 kW).
Subsequently and every year thereafter, the ERC shall evaluate the
performance of the market. On the basis of such evaluation, it shall gradually
reduce the threshold level until it reaches the household demand level. In the
case of ECs, Retail Competition and Open Access shall be implemented not
earlier than five (5) years from the effectivity of the Act.16
Contestable Market
15
EPIRA, Section 4(ll).
16
Bracket and words within brackets supplied.
17
Refers to the regulatory body created under Republic Act No. 9136 or the EPIRA, as an
independent, quasi-judicial regulatory body whose main function is to implement rules and regulations
under the EPIRA, enforce rules and regulations governing electricity spot market, establish and
enforce methodologies for setting transmission and distribution wheeling charges and retails rates for
the captive market of a DU, among others. EPIRA, Section 43.
18
EPIRA, Section 4(h).
19
Id., sec. 31.
20
Id., Section 4(c)
5
the contestable market.
Captive Market
The captive market end-users, on the other hand, cannot choose their supplier of
electricity. Pursuant to ERC Case No. 2005-10RM,21 otherwise known as the
Distribution Services and Open Access Rules, regular supply of electricity to the
captive market shall be provided by the DUs holding the legislative franchise over
the area. Thus:
Based on the foregoing, until the monthly average peak threshold for purposes of
defining who belongs to the contestable market is further reduced to what is called
household levels,22 end-users with average household level electricity usage
cannot participate in the open access and retail competition options of the EPIRA,
subject to the very narrow exception as an RE Developer for Own Use which will
be discussed further herein.
The Transitory Rules also mandated that contestable customers enter into an RSC
contract with an RES on or before May 20, 2013.25 This mandatory migration was
extended in ERC Resolution No. 10, Series of 2016 as amended by ERC Resolution
No. 28 Series of 2016 providing for a February 2017 timeline for mandatory
migration to an RSC system.
21
Dated January 18, 2006.
22
refers to end users with average monthly consumption below 500kW.
23
EPIRA, Section 2(c).
24
A Resolution Adopting the Transitory Rules for the Implementation of Open Access and Retail
Competition. December 17, 2012,
25
Section 6, Transitory Rules
6
However, on February 21, 2017,26 the Supreme Court issued a Temporary
Restraining Order (TRO) against the implementation of the following various rules
and regulations promulgated by the ERC for the implementation of Open Access to
the contestable market. 27
Although the issue is limited to the mandatory migration, the TRO was issued
against the body of rules. A TRO issued by the Supreme Court, unlike those issued
by the lower courts, shall be effective until further orders.28 As of date of writing,
the Supreme Court has not lifted the TRO hence the implementation of the
enumerated rules and regulations is effectively suspended.
We were advised that because of the TRO, the ERC in the meantime has withheld
the granting of authority or renewals of registrations of RES or Renewable Energy
Suppliers.
The legal framework for the development and utilization of renewable energy is
further implemented by DC 2009-07-0011,29 which sets out the policy of the DOE30
to implement a transparent and competitive system of awarding Renewable Energy
Contracts (REC) or Operating Contracts. DC 09-07-0011 also provides for two
frameworks, namely (a) renewable energy generation through the application and
26
Upon petition of the Philippine Chamber of Commerce and Industry, San Beda College Alabang Inc.,
Ateneo De Manila University, and Riverbanks Development Corp.
27
Supreme Court issues TRO against contestable-customer power scheme, retrieved from
https://www.doe.gov.ph/energist/index.php/2-uncategorised/11846-supreme-court-issues-tro-against-
contestable-customer-power-scheme on May 24, 2017. The rules are as follows:
a. DOE Circular No. DC2015-06-0010 (Providing Policies to Facilitate the Full Implementation
of Retail Competition and Open Access in the Philippine Electric Power Industry);
b. ERC Resolution No. 05 (Series of 2016) (A Resolution Adopting the 2016 Rules Governing
the Issuances of the Licenses to Retail Electricity Suppliers (RES) and Prescribing the
Requirements and Conditions Therefore);
c. ERC Resolution No. 10 (Series of 2016) (Adopting the Revised Rules for Contestability);
d. ERC Resolution No. 11 (Series of 2016) (Imposing Restrictions on the Operations of
Distribution Utilities and Retail Electricity Suppliers in the Competitive Retail Electricity
Market); and
e. ERC Resolution No. 28 (Series of 2016) (Revised Timeframe for Mandatory Contestability,
Amending Resolution No. 10)
28
Rules of Court, Section 5, Rule 58.
29
Guidelines Governing a Transparent and Competitive System of Awarding Renewable Energy
Service/Operating Contracts and Providing for the Registration Process of Renewable Energy
Developers
30
The DOE refers to the government agency created pursuant to Republic Act No. 7638, which is
tasked to implement the Governments policies and empowered to prepare, integrate, coordinate,
supervise, and control all plans, programs, projects, and activities of the Government relative to
energy exploration, development, utilization, distribution, and conservation.
7
award of REC to renewable energy developers; and, (b) generation of renewable
energy for own use, which we discuss further below.
An RE Developer may also generate power for its own use and own self-generating Commented [FS1]: EMP/SLP DC 09-07-0011 does not
facilities (SGF), in which case it will be considered an RE Developer for Own Use. define RE Developer for Own Use. Neither is such concept
defined under the EPIRA, the RE Law, and other similar
issuances. The closest definition I can get is that of a Self
Said developer will also be entitled to incentives under the RE Act, provided it Generation Facility (SGF) under ERC Resolution No. 16-
registers with the DOE. The users of the solar panels under a lease-to-own 2014. Such concept is however already defined in the
discussion below.
arrangement structure fall under this category.
An RE Developer for Own Use may either be part of the contestable or non-
contestable market. In any case, by becoming RE Developers for Own Use, small
and medium-sized enterprises, as well as residential houses forming part of the
captive market, have the option to choose their source of electricity supply.
It is clear from the foregoing that the Company will not be permitted to supply
those who belong to the captive or non-contestable market. Thus, another
arrangement, such as a lease-to-own arrangement, can be explored with respect to
customers belonging to said market. However, under this arrangement the user or
lessee is the one required to register as an RE Developer for Own Use. It should be
noted that the DOE prescribes less stringent requirements for RE Developers for
Own Use as compared to an RE Developer applying for an REC.
As a requisite to operate its chosen RE system, the RE Developer for Own Use,
regardless of whether it belongs to the contestable or non-contestable market, is
required to get a certificate of compliance (COC) from the ERC.
31
Id., Section 4
8
the generation of electricity.32 ERC Resolution 16 series of 2014 issued on
September 15, 2014 (ERC Resolution No. 16-2014) also states as follows:
General
The COC is valid for a period of five years, with the option to renew. ERC must be
notified of any transfer or change of ownership of the SGF within three days from
the date of change in ownership. 34
Pending the issuance of the COC, the ERC may issue provisional authority to
operate (PAO).35 Prior to the issuance of the COC, the ERC is also mandated to
inspect the SGF or SPV facilities.36
32
EPIRA, Section 6; Section 1, Rule 5 of the EPIRA IRR; ERC Resolution No. 16, series of 2014,
September 15, 2014 also states:
33
ERC Resolution 16 series of 2014 issued on September 15, 2014 (ERC Resolution No. 16-2014),
Article III, Sections 1 and 2; underscoring supplied.
34
Attached as Annex A and B are the COC Form 1: Self-Generating Facilities and Checklist of
Requirements for SGF below 1MW, respectively.
35
ERC Resolution No. 16, Article VI, Section. 3 provides.
Article VI, Section 3. Provisional Authority to Operate (PAO). - Pending the approval
of the COC application, no Generation Company shall operate its Generation Facility
unless a PAO is issued by the ERC. The PAO shall be issued in the form of a
notification to the applicant and shall be valid for a period of six (6) months from
issuance thereof. The six (6)-month validity period shall be included in the five (5) year
term of the COC that may be issued by the ERC for such Generation Facility/ies
31
Id., Article III, Section 7. The conduct of the technical inspection may be waived by the ERC due to
force majeure, safety and security concerns of the ERC technical personnel, and other conditions as
the ERC may deem fit.
9
To avail of the incentives granted under the RE Act, owners, or even operators
thereof the SGFs must secure a Certificate of Registration (COR) from the DOE as
an RE Developer in order to avail of incentives under RE Act, such as the duty-free
importation.37 To avail of duty-free importation, the RE Developer has to apply for a
DOE endorsement which shall be submitted to the Board of Investments (BOI). Said
endorsement and clearance must be obtained prior to the purchase and importation
of the equipment for any importation made to be duty-free.38 The RE Act exempts
the importation of machinery and equipment, and materials and parts thereof,
including control and communication equipment, from import duties within the first
ten (10) years upon the issuance of a certification of an RE Developer.
It should be noted that one of the requirements is for the importation to be covered
by shipping documents in the name of the duly registered RE Developer or operator
to whom the shipment will be directly delivered by customs authorities.39 The
checklist of the requirements for the application and issuance of COR is attached
herein.40
c. Proof of Ownership
37
DC 2009-07-2011, Section 26.
38
RE Act, Section 15.
39
DOE Department Circular No. DC2009-05-0008, May 25, 2009. The list of requirements is as
follows:
1. That the said machinery, equipment, materials and parts are directly and actually needed and
used exclusively in the RE facilities for transformation into energy and delivery of energy to
the point of use;
2. The importation of materials and spare parts shall be restricted only to component materials
and parts for the specific machinery and/or equipment authorized to be imported;
3. The kind of capital machinery and equipment to be imported must be in accordance with the
approved work and financial program of the RE facilities
4. Such importation shall be covered by shipping documents in the name of the duly registered
RE Developer/operator to whom the shipment will be directly delivered by customs
authorities; and
5. Covered by shipping documents in the name of the duly registered RE Developer/operator
to whom the shipment will be directly delivered by customs authorities.
40
Attached as Annex C is the Checklist for Certificate of Registration of Renewable Energy
Developer for Own Use.
41
ERC Resolution No. 16-2014, Section 4(ddd); underscoring supplied.
10
availment of incentives under the RE Act, Section 26 of DC2009-07-2011 requires
the submission of proof of ownership of the facilities, as follows:
a. Letter of Intent;
b. Project Description; and
c. Proof of ownership of the RE facilities.43
From the foregoing, it can be gathered that an RE Developer for Own Use must
own the RE facilities, in this case, the SPVs. However, it is also recognized that if the
generation facility is operated by a person or entity other than the owner, to the
extent that the former controls the output of the facility, enters into supply
agreements with energy off-takers, or enters into such other similar arrangements,
the ERC reserves the authority to determine in whose name the application for the
issuance of a COC should be made. It thus follows that an operator of the SPVs,,
not an owner, can be the applicant and be the holder of a COC. In this regard, ERC
Resolution No. 16-2014 states:
ii. The application for a COC shall be in the name of the person or
entity owning the Generation Facilities used in the Generation of
Electricity. For purposes of this Section, the person or entity owning
the Generation Facility is understood to be the person or entity
having legal title to the same. In such case, the person or entity shall
apply for, and the COC shall be issued in its name, Provided: That, in
case the Generation Facility is operated by a person or entity other
than the owner, to the extent that the former controls the output of
the facility, enters into supply agreements with energy off-takers, or
enters into such other similar arrangements, the ERC reserves the
authority to determine in whose name the application for the
issuance of a COC should be made.44
Mr. Peter Sablay, Science Research Specialist of the Wind and Solar Division of the
DOE, confirmed to us that a lease-to-own agreement, wherein the RE Developer for
Own Use is granted the right to acquire the leased SPV, is sufficient to comply with
the ownership requirement. He mentioned that there has been several lease-to-
own arrangements which were allowed by DOE. Such arrangements involve at least
42
Referring to the Renewable Energy Act of 2008.
43
Underscoring supplied.
44
Underscoring supplied.
11
three schools in Metro Manila (and thus, within the MERALCO franchise area).45
d. Operation
We also note that in this project, the Company might have to undertake the
operation and management of the SPV system installed in the premises of the end
user.
There are no laws or regulations which prescribe as to who should operate and
maintain the SPV of an RE Developer for Own Use. We were advised by DOE that
they do not regulator operations and maintenance contracts of SGFs.
Although the generation of solar power of subject to our nationality laws, we believe
that an operator of a solar-powered SGF will not have to be owned by Filipinos to
the extent of not less than 60% of its outstanding capital stock, provided it is not the
one to whom the COC or the COR is issued, or is not the recognized generator of
the facility.
e. Net Metering
45
Mr. Sablay mentioned that lease-to-own arrangements have been allowed for St. Scholasticas
Academy and Manuel L. Quezon University (MLQU).
46
RE Act, Section 10.
47
IRR of the RE Act, Section 7.
12
facilities with a maximum capacity of 100 kWp to the DUs distribution system per
qualified end-user account.48 Thus, if the RE facilities have a higher maximum
capacity, net-metering will not be allowed.
f. DU Approval
The DU which has the exclusive franchise over the location of the RE Developer for
Own Use must approve the design, installations, operations and maintenance of the
solar panels, which at the minimum must be compliant with industry standard, as
well as the Philippine Distribution Code.49
If the Companys lease customers are part of the captive market, they are still
required to be connected to the local DU. Thus, any RE facility or SPV which such
customers may establish is subject to the standards, requirements and impact studies
promulgated and conducted by the local DU to ascertain that the installed SPV
adheres to safety standards for the protection of the DUs surrounding customers
and linesmen. In other words, while the SPV transmits power directly to the RE
Developer for Own Use without need of any interconnection to the DU, the DU
has a significant stake in ensuring that the proposed system is compliant and will not
affect any of its nearby distribution system assets.
The other importance of ensuring that the end-user owns or will own the SPV is to
prevent possible infringement on the exclusive nature of the local DUs franchise.
This will be discussed in a subsequent section.
In this regard, it is required that the DU conduct a Distribution Impact Study (DIS)
to gauge the impact of the proposed system and to evaluate significant incidents. A
DIS refers to a set of technical studies which are used to assess the possible effects
of a Distribution System or a User Development and to evaluate Significant
Incidents.50 While the requirement for the DIS is found in the Guidelines on the net-
metering system, we were advised by the DOE that both DIS (and Distribution
Asset Study (DAS) discussed below) are mandatorily conducted to all self-generating
facilities, regardless if they qualify for the net-metering system.
The DUs thus primarily determine the scope of the study, estimated time of
completion and fees payable of the DIS. The DIS must be conducted prior to the
actual construction of the facilities.51 The requirements for the DIS will also be
provided by the DU concerned.
48
ERC Resolution 09, Series of 2013 Under ERC Resolution 09, Series of 2013.
49
Section 4.3.1 of the Philippine Distribution Code, 2016 Edition.
50
Annex A-1 (Net Metering Interconnection Standards) of ERC Resolution No. 09, series of 2013.
51
This was confirmed by Mr. Peter Sablay, the Science Research Specialist of the Solar and Wind
Energy Management Division of the DOE.
13
g. Distribution Assets Study (DAS)
After the completion of the DIS as discussed above, the DU forwards to the
applicant the results of the study and the DUs findings. Such findings would include
a determination on whether a subsequent stage of a DAS is necessary.
h. Universal Charges
Under the EPIRA, universal charges are imposed for the recovery of the Stranded
Debts, Stranded Contract Costs of the National Power Corporation, and Stranded
Contract Costs of Eligible Contracts of Distribution Utilities and other mandated
purposes. It is a non-by passable charge, which shall be passed on and collected from
all end-users on a monthly basis by the distribution utilities.
Payment for the stranded debts and stranded contract costs of NPC as well
as qualified stranded contract cost of distribution utilities;
Missionary electrification;
Equalization of taxes and royalties between indigenous or renewable sources
of energy vis-a-vis imported energy fuels;
An environmental charge of PhP 0.0025 per kilowatt-hour, which shall accrue
to an environmental fund to be used solely for watershed rehabilitation and
management; and 5. A charge to account for all forms of cross-subsidies for a
period not exceeding three (3) years.
Under the Primer on Universal Charges52 the following persons shall bear the cost of
the Universal Charges:
14
The Universal Charges are collected by the DU, and in cases of SGFs not connected
to the DU, the same shall be collected by the Transmission Corporation
(TRANSCO).
For this purpose, the ERC is given the authority to look into the books of account of
the DU for purposes of monitoring, verifying and accounting of amounts collected
from the universal charge and remitted.
Generally, all LGUs require the application for electrical permits as part of the
procedure for application of a Building Permit with the Office of the Building Official
(OBO) of the LGU. The electrical permit is issued upon OBOs finding of compliance
with the standards and requirements on electrical safety in the Philippine Electrical
Code (PEC), the Electrical Engineering Law, and the concerned LGU.
Upon submission of the required administrative and technical documents/forms and
all the electrical systems have been installed, the applicant is usually required to
submit a request for inspection addressed to the Electrical Division of the concerned
LGU. If satisfied upon inspection, the Electrical Division thereafter issues a
Certificate of Final Electrical Inspection.
In this situation, where an existing building will host another electrical system, such
as the SPV, certain requirements53 have to be submitted.54
F. Procedure
We identify the following as the four major phases and milestones in the
development of solar panel projects in the Philippines:
1. Project Preparation
53
As prescribed by the Local Government Unit of Makati City. Different LGUs prescribe different
requirements which can be obtained from the respective offices.
54
These requirements include the following: Land Title/Contract of Lease
1. Realty Tax Receipt
2. Duly Notarized Affidavit of the owner authorizing use of the property to separate,
reconnect, remodel, relocate the kWh meter and repair of service entrance.
3. Accomplished Application Form (DPWH Form No. 96-001-E) to be signed by a licensed
engineer/master electrician with PTR No. for the current year.
4. Floor Lay-out with lighting and power lay-out
5. Riser Diagram
6. For a load of 4kW or 20 outlets or more, 5 sets of plans, signed & sealed by a PEE with
PTR No. for the current year
7. Barangay Clearance
15
b. Notification to the relevant DU over the area of the project and
intention to apply for DIS.
2. Pre-Development
3. Development
a. Contract Issue
We believe that there is always a risk that the lease-to-own arrangement may be
viewed as a power supply arrangement in disguise.
As mentioned above, the DOE officials we had discussions with opined that a lease-
to-own arrangement is permissible, and that even a purely variable rent based on
generation is acceptable. They said that they generally leave the commercial terms
of the arrangement to the parties of the contract.
However, certain BOI officials are of the took the view that such an arrangement
may be considered a supply arrangement in disguise especially if the rentals are
variable based on usage. The BOI officials acknowledge though that ultimately it is
the DOE and the ERC which have final say on this matter. Officers of the Philippine
Economic Zone Authorities (PEZA), on the other hand, believe that the rent should
be based on rental space and not usage.55
Unfortunately, the officials of the Wind and Solar Division of the DOE refused to give us
copies of existing lease-to-own contracts. However, based on our review of available
information on several solar power companies in the internet, we learned that a lease-
to-own arrangement has been adopted with the requisite approvals by an RE systems
55
As informally discussed with Mr. Tereso O. Panga, Deputy Director General for Policy and Planning
of the PEZA.
16
provider called Cebu Solar Incorporated (CSI) operating in Cebu, a metropolis located
in a province of the same name within the Visayas region. 56 We note the following
significant provisions in the arrangement:
(a) The first tranche of payment to cover the first four or five years is fixed and paid
upon the signing of the agreement;
(b) The remaining payments are based on the customers projected usage and not
the actual generated electricity; 57
56
http://www.cebusolar.com/solar-power-leasing accessed on June 6, 2017.
57The relevant provisions which we noted in said lease-to-own agreement are the
following:
After the initial period, a per Kw charge of p__ (sic) (identical to the initial
estimated amount- p2 less than initial utility billing amount) is the basis of
billing, never to increase. After initial block of energy is consumed a yearly
payment will be required in advance for the Kws expected to be consumed
that year, or a quarterly breakdown payment of the annual payment can be
made with prior notice from customer and written approval from CSI.
At the end of the lease/payment period (after the final required block of power is
used) the equipment is turned over to the homeowner, in good functioning
condition and with new batteries.
17
(c) There is a guarantee for the turn-over of the system to the customer at the end
of the lease period; and
(d) CSI only made provisions for compliance with DOE and ERC requirements
should the customer decide to avail of the net-metering program.
In view of the foregoing, we have the following comments on the terms of the draft
lease-to-own arrangement:
1. Rental We suggest that the rent should not entirely be variable based on
energy output; thus, a fixed rental should be provided such that it can be
shown that even if the systems do not generate energy, the Lessee still has
obligations to the Lessor.
3. Purchase Option Based on our discussions with the ERC and DOE officers,
the transfer of ownership to the lessee at the end of the lease is mandatory.
A pure purchase option may not satisfy the ownership requirement
discussed above. Thus, while there may be a purchase option which may be
exercised during the period of the lease, at the lessees choice, there should
be a mandatory transfer of the ownership of the system after the end of the
lease. In other words, there should be no possibility that the Lessee will not
own the system after the expiration of the lease.
In the end, the Company will have to submit a copy of the lease-to-own contract to
the DOE and ERC, for their approval and clearance.
Also, both the application and issuance of the COR in order to avail of the duty-free
importation incentive occur at the beginning of the projects timeline. Yet, at this
point, the Company as lessor remains to be the owner of the SPV, and not the RE
Developer for Own Use. Based on discussions with the BOI, in granting the import
clearance, they require that all import documents be in the name of the RE
Developer, and they assume that such entity will be the owner of the facilities
imported.
We nonetheless believe that even if the import documents are in the name of the RE
Developer, the RE Developer for Own Use may be-considered the legal title
holder of the equipment. It can be proven that the Company is the beneficial
owner of the properties imported. Article 427 of the Civil Code provides that,
18
beneficial ownership is distinguished from naked ownership, which is the enjoyment
of all the benefits and privileges of ownership, as against possession of the bare title
to property.58 The Supreme Court defined beneficial ownership as the ownership
recognized by law and capable of being enforced in the courts at the suit of the
beneficial owner.59 Beneficial use, ownership or interest in property means right to
its enjoyment in one person where the legal title is in another.60 Legal title denotes
registered ownership, while equitable title means beneficial ownership.61 Thus, legal
title or ownership can be separate from beneficial ownership. In this regard, we
recommend that documents or agreements confirming the Companys beneficial
ownership be entered into to avoid questions. DOE officials also confirmed that the
beneficial ownership issue should be a matter that can be addressed in the
contract between the parties.
c. DU involvement
We have discussed in a previous section why the DU is allowed to interfere with the
structure of the project. From a legal standpoint, the average consumption of the
Companys prospective customers places them within the captive market range and
are thus required to source their energy requirement from the relevant DU. This is
pursuant to the exclusive franchise of the DU.
1. The DU may take the view the lease-to-own arrangement is a disguised supply
arrangement; or
2. The DU will accept the arrangement but require the payment of distribution or
wheeling charges during the life of the lease prior to the execution of the
purchase option.
58
Residents of Lower Atab & Teacher's Village, Barangay Sto. Tomas Proper, Baguio City vs. Sta.
Monica Industrial & Development Corporation, 738 SCRA 450, G.R. No. 198878 October 15, 2014
59
Ibid.
60
Id.
61
Mananquil v. Moico, G.R. No. 180076, November 21, 2012, 686 SCRA 123, 124.
19
We wish to mention though that MERALCO has issued a press release that it
supports the installation of SPVs by its end-users subject to the conformity of the
SPV with their distribution system.62
d. Timing Issue
With the present numerous regulatory requirements in place, we wish to advise the
Company to manage their expectations on the length of time that it will take for the
project to commence operation. The DOE advised that particularly with the DIS and
the DAS, the Company is expected to wait between one to two months for the
procedures to complete.
Note that after the completion of the DIS as discussed above, the DU forwards to
the applicant the results of the study and the DUs findings on whether a subsequent
stage of a DAS is necessary. At this point, the Company may commence the physical
construction of the facilities. Thus, simultaneous to the physical construction of the
facilities, we recommend that the Company notify and engage the DU again to
determine if a DAS is necessary.
e. Technical Design
We were advised by the DOE that one requirement for securing the COR by an RE
Project for Own-Use is the technical design of the project. This is an important
requirement because the technical design will serve as the exclusive basis for the
items endorsed by DOE as necessary and material for the construction of the SGF.
Concomitantly, only the items endorsed can be subject of the duty-free importation.
The DOE strongly urges the accurate and thorough preparation of the technical
design to be submitted by the Company. We were informed that this is a common
issue encountered by many applicants and they are often asked to re-do the entire
technical design which will entail costs and time.
62
Meralco Shines the Light on Renewable Energy, retrieved from http://corporate-downloadables-
services-tools.s3.amazonaws.com/1436941603.5b4d36d72ef9633be2fead66f4e54fe8.pdf on May 25,
2017.