This document was prepared for ABPR3 Project for first issue.
0 N/A Closed
1
Detailed project schedule has been revised based
on civil construction schedule except E&C
building construction schedule. E&C building
construction schedule is now re-scheduling based
1
5 on the latest site construction progress. E&C
building construction schedule in the details
schedule is HOLD until further update on civil
construction schedule for E&C building.
2
Page 21 of 54 & Page 47 of 54.
6 1
Typo error has been corrected.
No. Rev. CUSTOMER COMMENTS REPLIES AND EXPLANATIONS
Fire Gas Heater changed to Fuel Gas Heater.
2
Page 30 of 54
Gas Turbine On-Base date has changed as per
1
7 the contract program.
8 Feb-2017 to 9-Feb-2017.
2
Page 48 of 54
1 Typo error has been corrected.
8
DCS/UPS system to DC/UPS system.
2
For Information
OWNER
REV DATE
ISSUE
APPROVED CHECKED DESIGNED
TPSC (Thailand) Co., Ltd.
PURPOSE
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.1 PROFESSIONAL
PROFESSIO SERVICES 650 01-Dec-15 10-Sep-17 144
03PMS-BL00.1.1 PROJECT
PROJEC MANAGEMENT & CONTROL SERVICE 119 01-Dec-15 28-Mar-16 675
03PMS-BL00.1.1.3 Project
Projec Planning & Control 119 01-Dec-15 28-Mar-16 675
03PMS-BL00.1.1.3.01 Pr
Project Operation Establishment 20 01-Dec-15 20-Dec-15 536
03PMS-BL00.1.1.3.02 Project
Pr Basic Planning 20 01-Dec-15 20-Dec-15 536
03PMS-BL00.1.1.3.03 Pr
Project WBS Developing 20 01-Dec-15 20-Dec-15 536
03PMS-BL00.1.1.3.04 Sc
Schedule Control 119 01-Dec-15 28-Mar-16 675
03PMS-BL00.1.2.2.03 Plant
Pla Basic Design Concept 56 01-Dec-15 25-Jan-16 64
03PMS-BL00.1.2.2.04 Pla
Plant Plot Plan Study 85 01-Dec-15 23-Feb-16 169
03PMS-BL00.1.2.2.05 Heat
He Balance Diagram 110 26-Jan-16 14-May-16 64
03PMS-BL00.1.2.2.06 Wa
Water Balance Diagram 56 19-Mar-16 13-May-16 629
03PMS-BL00.1.2.2.07 Plant
Pla Performance Test work 50 26-May-17 14-Jul-17 160
03PMS-BL00.1.2.2.08 Equipment
Eq Redundancy Concept 56 23-Feb-16 18-Apr-16 165
03PMS-BL00.1.2.2.09 Equipment
Eq Design Concept 56 23-Feb-16 18-Apr-16 165
03PMS-BL00.1.2.2.11 General
Ge arrangement Study 92 01-Dec-15 01-Mar-16 588
03PMS-BL00.1.2.2.12 P&
P&ID 125 23-Jan-16 26-May-16 291
03PMS-BL00.1.2.2.13 System
Sy Design Description 424 20-Jan-16 18-Mar-17 320
03PMS-BL00.1.2.2.14 Eq
Equipment Design Determination (Capacity Calculation) 413 23-Jan-16 10-Mar-17 328
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-12215640 Plant Communication System, CCTV & Clock 56 30-Nov-16 24-Jan-17 373
03PMS-BL00.1.2.2.16 RFQ
RF (Request for Quotation) 335 01-Dec-15 30-Oct-16 459
XAC03-122164Z1 RFQ Preparation - Others System (CT Make Up Storage Water Tank) 30 01-Dec-15 30-Dec-15 218
XAC03-122164Z2 RFQ Preparation - Others System (Waste Water Treatment) 1 01-Dec-15 01-Dec-15 169
XAC03-122164Z3 RFQ Preparation - Others System (Service Water & Fire Water Storage Tank) 30 09-Dec-15 07-Jan-16 172
XAC03-122164Z4 RFQ Preparation - Others System (Raw Water Buffer Tank) 30 09-Dec-15 07-Jan-16 255
XAC03-122164Z5 RFQ Preparation - Others System (DM Water Storage Tank) 30 10-Dec-15 08-Jan-16 182
XAC03-122164Z6 RFQ Preparation - Others System (Cooling Tower) 30 16-Dec-15 14-Jan-16 182
XAC03-122164Z7 RFQ Preparation - Others System (STG Overhead Crane) 30 16-Dec-15 14-Jan-16 294
XAC03-122164Z9 RFQ Preparation - Others System (Raw Water Pump) 30 16-Jan-16 14-Feb-16 182
XAC03-122164ZA RFQ Preparation - Others System (CT Make UP Water Pump) 30 16-Jan-16 14-Feb-16 193
XAC03-122164ZB RFQ Preparation - Others System (Service Water Pump) 30 16-Jan-16 14-Feb-16 283
XAC03-122164ZC RFQ Preparation - Others System (DM Water Pump) 30 16-Jan-16 14-Feb-16 197
XAC03-122164ZD RFQ Preparation - Others System (Chemical Dosing for HRSG) 30 17-Mar-16 15-Apr-16 227
XAC03-122164ZE RFQ Preparation - Others System (Chemical Dosing for CT) 30 17-Mar-16 15-Apr-16 186
XAC03-122164ZF RFQ Preparation - Others System (Sump Pump) 30 01-Apr-16 30-Apr-16 205
XAC03-12216660 RFQ Preparation - Primary Energy Saving System 15 14-Apr-16 28-Apr-16 278
XAC03-12216630 RFQ Preparation - Steam and Water Analysis System 15 02-May-16 16-May-16 305
XAC03-12216620 RFQ Preparation - Continuous Emission Monitoring System 15 12-May-16 26-May-16 176
XAC03-12216640 RFQ Preparation - Plant Communication System, CCTV & Clock 15 25-Aug-16 08-Sep-16 131
XAC03-1221667B RFQ Preparation - Cabling Bulk for C&I Cable 15 16-Oct-16 30-Oct-16 100
XAC03-1221671B RFQ Preparation - Unit Aux Transformer with remote OLTC panel 5 10-Dec-15 14-Dec-15 285
03PMS-BL00.1.2.2.17 Te
Technical Evaluation of Vendor Quotation 367 01-Dec-15 01-Dec-16 313
XAC03-12217110 Technical Evaluation of Vendor Qutation - HVAC System 52 08-Jan-16 28-Feb-16 201
XAC03-12217120 Technical Evaluation of Vendor Qutation - Fire Protection System 52 08-Jan-16 28-Feb-16 164
XAC03-12217220 Technical Evaluation of Vendor Qutation - ST and Auxiliary 30 02-Dec-15 31-Dec-15 266
XAC03-12217430 Technical Evaluation of Vendor Qutation - Boiler(HRSG) and Auxiliary 1 01-Dec-15 01-Dec-15 0
XAC03-122174A0 Technical Evaluation of Vendor Qutation - Compressed Air System 60 02-Jan-16 01-Mar-16 281
XAC03-12217440 Technical Evaluation of Vendor Qutation - Condensate Water System 152 08-Jan-16 07-Jun-16 209
XAC03-12217470 Technical Evaluation of Vendor Qutation - Boiler Feedwater System 67 08-Jan-16 14-Mar-16 314
XAC03-12217480 Technical Evaluation of Vendor Qutation - Fuel Gas System 48 14-Jan-16 01-Mar-16 294
XAC03-12217460 Technical Evaluation of Vendor Qutation - CCCW System 81 14-Feb-16 04-May-16 186
XAC03-12217450 Technical Evaluation of Vendor Qutation - CW/ACW System 46 15-Feb-16 31-Mar-16 220
03PMS-BL00.1.2.2.17.4.Z Others
03PMS-BL00.1.2.2.17.4 213 02-Dec-15 01-Jul-16 205
XAC03-122174Z1 Technical Evaluation of Vendor Qutation - Others System (Water treatment Plant) 60 02-Dec-15 30-Jan-16 169
XAC03-122174Z2 Technical Evaluation of Vendor Qutation - Others System (CT Make Up Water Storage 40 31-Dec-15 08-Feb-16 218
Tank)
XAC03-122174Z3 Technical Evaluation of Vendor Qutation - Others System (Service and Fire Water 32 08-Jan-16 08-Feb-16 172
Storage Tank)
XAC03-122174Z4 Technical Evaluation of Vendor Qutation - Others System (Raw Water Buffer Tank) 32 08-Jan-16 08-Feb-16 255
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-122174Z6 Technical Evaluation of Vendor Qutation - Others System (Cooling Tower) 45 15-Jan-16 28-Feb-16 182
XAC03-122174Z7 Technical Evaluation of Vendor Qutation - Others System (STG Overhead Crane) 47 15-Jan-16 01-Mar-16 294
XAC03-122174Z8 Technical Evaluation of Vendor Qutation - Others System (Condenser Ball Cleaning) 121 31-Jan-16 30-May-16 183
XAC03-122174Z9 Technical Evaluation of Vendor Qutation - Others System (Raw Water Pump) 47 15-Feb-16 01-Apr-16 182
XAC03-122174ZA Technical Evaluation of Vendor Qutation - Others System (CT Make Up Water Pump) 46 15-Feb-16 31-Mar-16 193
XAC03-122174ZB Technical Evaluation of Vendor Qutation - Others System (Service Water Pump) 46 15-Feb-16 31-Mar-16 283
XAC03-122174ZC Technical Evaluation of Vendor Qutation - Others System (DM Water Pump) 46 15-Feb-16 31-Mar-16 197
XAC03-122174ZD Technical Evaluation of Vendor Qutation - Others System (Chemical Dosing for HRSG) 46 16-Apr-16 31-May-16 227
XAC03-122174ZE Technical Evaluation of Vendor Qutation - Others System (Chemical Dosing for CT) 46 16-Apr-16 31-May-16 186
XAC03-122174ZF Technical Evaluation of Vendor Qutation - Others System (Sump Pump) 62 01-May-16 01-Jul-16 205
XAC03-12217650 Technical Evaluation of Vendor Qutation - Chemical Laboratory 60 02-Dec-15 30-Jan-16 619
XAC03-12217660 Technical Evaluation of Vendor Qutation - Primary Energy Saving System 31 29-Apr-16 29-May-16 278
XAC03-1221768A Technical Evaluation of Vendor Qutation - Tur bine Bypass 46 02-May-16 16-Jun-16 110
XAC03-1221768B Technical Evaluation of Vendor Qutation - Control Valves 45 02-May-16 15-Jun-16 139
XAC03-12217630 Technical Evaluation of Vendor Qutation - Steam and Water Analysis System 62 17-May-16 17-Jul-16 305
XAC03-12217620 Technical Evaluation of Vendor Qutation - Continuous Emission Monitoring System 62 27-May-16 27-Jul-16 176
XAC03-12217640 Technical Evaluation of Vendor Qutation - Communication & Clock System 30 09-Sep-16 08-Oct-16 131
XAC03-1221767A Technical Evaluation of Vendor Qutation - C&I Bulk Materials 77 13-Sep-16 28-Nov-16 91
XAC03-1221767B Technical Evaluation of Vendor Qutation - Cabling Bulk for C&I Cable 32 31-Oct-16 01-Dec-16 100
XAC03-1221771B Technical Evaluation of Vendor Qutation - Unit Aux Transformer with remote OLTC panel 36 15-Dec-15 19-Jan-16 285
XAC03-1221771C Technical Evaluation of Vendor Qutation - Auxiliary Transformer 40 01-Feb-16 11-Mar-16 290
XAC03-1221772B Technical Evaluation of Vendor Qutation - HV/MV SWGR 37 22-Feb-16 29-Mar-16 205
XAC03-12217730 Technical Evaluation of Vendor Qutation - DC & UPS 61 28-Feb-16 28-Apr-16 106
XAC03-12217740 Technical Evaluation of Vendor Qutation - EDG / BSDG 61 28-Feb-16 28-Apr-16 264
XAC03-1221772C Technical Evaluation of Vendor Qutation - MCCs / DBs 36 31-Mar-16 05-May-16 189
XAC03-12217800 Technical Evaluation of Vendor Qutation - Electrical Bulk 154 15-Apr-16 15-Sep-16 162
03PMS-BL00.1.2.2.18 List
Lis 457 26-Jan-16 26-Apr-17 281
03PMS-BL00.1.2.2.19 Electrical
Ele Load List 300 31-Dec-15 25-Oct-16 464
03PMS-BL00.1.2.2.19.1 Draft Electrical Load List (70% accuracy) 204 05-Apr-16 25-Oct-16 464
03PMS-BL00.1.2.2.19.2 Update Electrical Load List (90% accuracy) 300 31-Dec-15 25-Oct-16 464
03PMS-BL00.1.2.2.19.3 Final Electrical Load List (Freez) 300 31-Dec-15 25-Oct-16 464
03PMS-BL00.1.2.2.20 Single
Sin Line Diagram 56 13-Feb-16 08-Apr-16 664
03PMS-BL00.1.2.3 Plant O
Operation Engineering 176 02-Feb-16 26-Jul-16 555
03PMS-BL00.1.2.3.01 Plant
Pla Operation philosophy 56 02-Feb-16 28-Mar-16 186
03PMS-BL00.1.2.3.02 Pla
Plant Automation Operation philosophy 56 13-Feb-16 08-Apr-16 197
03PMS-BL00.1.2.3.03 Ele
Electrical Operation Philosophy 56 01-Jun-16 26-Jul-16 555
03PMS-BL00.1.2.3.04 Ele
Electrical Plant Interlock 56 02-May-16 26-Jun-16 585
03PMS-BL00.1.3 DETAIL E
ENGINEERING DOCUMENT 649 02-Dec-15 10-Sep-17 144
03PMS-BL00.1.3.1 Arrang
Arrangement Detail Engineering 208 25-Mar-16 18-Oct-16 471
03PMS-BL00.1.3.1.01 HVAC
HV System 99 22-Apr-16 29-Jul-16 552
03PMS-BL00.1.3.1.02 Fire
Fir protection System 208 25-Mar-16 18-Oct-16 471
03PMS-BL00.1.3.2 Civil D
Detail Design 506 31-Jan-16 19-Jun-17 227
03PMS-BL00.1.3.2.01 Ci
Civil General 506 31-Jan-16 19-Jun-17 227
03PMS-BL00.1.3.2.02 Concrete
Co Structure 449 05-Mar-16 27-May-17 250
03PMS-BL00.1.3.2.03 Steel
St Structure 173 26-Mar-16 14-Sep-16 505
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.1.3.2.04 Bu
Building 270 06-Apr-16 31-Dec-16 397
03PMS-BL00.1.3.3 Mecha
Mechanical Equipment Detail Engineering 431 02-Dec-15 04-Feb-17 156
03PMS-BL00.1.3.3.01 Gas
Ga turbine & generator 379 02-Dec-15 15-Dec-16 40
XAC03-13301100 Drawing Review and Comments for Notice To Fabr icate (NTF) 247 02-Dec-15 05-Aug-16 0
03PMS-BL00.1.3.3.02 Bo
Boiler / HRSG & Auxilliary Equipment 351 02-Dec-15 16-Nov-16 0
XAC03-13302100 Drawing Review and Comments for Notice To Fabr icate (NTF) 282 02-Dec-15 08-Sep-16 0
03PMS-BL00.1.3.3.03 St
Steam Turbine & Generator 302 18-Mar-16 13-Jan-17 59
XAC03-13303100 Drawing Review and Comments for Notice To Fabr icate (NTF) 161 18-Mar-16 25-Aug-16 200
03PMS-BL00.1.3.3.05 Condenser
Co / Air cooled co ndenser 238 09-Jun-16 01-Feb-17 54
XAC03-13305100 Drawing Review and Comments for Notice To Fabr icate (NTF) 84 09-Jun-16 31-Aug-16 208
03PMS-BL00.1.3.3.06 Water
Wa Pumps 311 31-Mar-16 04-Feb-17 156
XAC03-13306A10 Drawing Review and Comments for Notice To Fabr icate (NTF) 103 16-Apr-16 27-Jul-16 276
XAC03-13306B10 Drawing Review and Comments for Notice To Fabr icate (NTF) 78 13-May-16 29-Jul-16 239
XAC03-13306C10 Drawing Review and Comments for Notice To Fabr icate (NTF) 85 04-May-16 27-Jul-16 241
XAC03-13306D10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 94
XAC03-13306E10 Drawing Review and Comments for Notice To Fabr icate (NTF) 114 20-Apr-16 11-Aug-16 170
XAC03-13306F10 Drawing Review and Comments for Notice To Fabr icate (NTF) 118 31-Mar-16 26-Jul-16 349
XAC03-13306G10 Drawing Review and Comments for Notice To Fabr icate (NTF) 134 04-May-16 14-Sep-16 150
XAC03-13306H10 Drawing Review and Comments for Notice To Fabr icate (NTF) 150 04-May-16 30-Sep-16 160
XAC03-13306I10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 157
XAC03-13306J10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 71
XAC03-13306K10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 05-Aug-16 09-Nov-16 94
XAC03-13306L10 Drawing Review and Comments for Notice To Fabr icate (NTF) 64 27-Sep-16 29-Nov-16 126
03PMS-BL00.1.3.3.07 Fu
Fuel Supply System 212 06-May-16 03-Dec-16 96
XAC03-13307100 Drawing Review and Comments for Notice To Fabr icate (NTF) 79 06-May-16 23-Jul-16 229
03PMS-BL00.1.3.3.08 Cooling
Co Tower 262 17-Mar-16 03-Dec-16 66
XAC03-13308100 Drawing Review and Comments for Notice To Fabr icate (NTF) 163 17-Mar-16 26-Aug-16 165
03PMS-BL00.1.3.3.09 Water
Wa Treatment System 141 15-May-16 02-Oct-16 64
XAC03-13309100 Drawing Review and Comments for Notice To Fabr icate (NTF) 141 15-May-16 02-Oct-16 64
03PMS-BL00.1.3.3.ZZ Others
O 326 29-Feb-16 19-Jan-17 109
XAC03-133ZZA10 Drawing Review and Comments for Notice To Fabr icate (NTF) 93 01-Oct-16 01-Jan-17 105
XAC03-133ZZB10 Drawing Review and Comments for Notice To Fabr icate (NTF) 106 01-Oct-16 14-Jan-17 64
XAC03-133ZZC10 Drawing Review and Comments for Notice To Fabr icate (NTF) 69 16-Jun-16 23-Aug-16 175
XAC03-133ZZD10 Drawing Review and Comments for Notice To Fabr icate (NTF) 44 31-May-16 14-Jul-16 106
XAC03-133ZZE10 Drawing Review and Comments for Notice To Fabr icate (NTF) 53 02-May-16 23-Jun-16 89
XAC03-133ZZF10 Drawing Review and Comments for Notice To Fabr icate (NTF) 53 02-May-16 23-Jun-16 100
XAC03-133ZZG10 Drawing Review and Comments for Notice To Fabr icate (NTF) 44 28-Jul-16 10-Sep-16 85
XAC03-133ZZH10 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 05-Aug-16 30-Sep-16 160
XAC03-133ZZI10 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 07-Jun-16 02-Aug-16 279
XAC03-133ZZJ10 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 07-Aug-16 02-Oct-16 136
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-133ZZK10 Drawing Review and Comments for Notice To Fabr icate (NTF) 97 06-Aug-16 10-Nov-16 116
XAC03-133ZZL10 Drawing Review and Comments for Notice To Fabr icate (NTF) 153 29-Feb-16 30-Jul-16 201
XAC03-133ZZM10 Drawing Review and Comments for Notice To Fabr icate (NTF) 164 29-Feb-16 10-Aug-16 164
03PMS-BL00.1.3.4.01 De
Design Input Review 110 08-Jan-16 26-Apr-16 646
03PMS-BL00.1.3.4.02 De
Design Calculation 330 22-Apr-16 17-Mar-17 321
03PMS-BL00.1.3.4.03 Pip
Piping Arrangement 120 16-Jul-16 12-Nov-16 446
XAC03-13404C10 BQ and Specification (RFQ) - Underground Piping Materials (Stainless) 7 18-Mar-16 24-Mar-16 234
XAC03-13404C20 BQ and Specification (RFQ) - Underground Piping Materials (PVC&ABS) 7 18-Mar-16 24-Mar-16 234
XAC03-13404D20 BQ and Specification (RFQ) - BOP Piping Materials Large Bore (Alloy) 7 07-May-16 13-May-16 72
XAC03-13404D10 BQ and Specification (RFQ) - BOP Piping Materials Large Bore (Carbon & Stainless) 7 07-May-16 13-May-16 103
XAC03-13404D30 BQ and Specification (RFQ) - Shop Fabrication Piping - BOP Piping Materials Small 7 15-Jun-16 21-Jun-16 115
Bore (Galvanized Materials)
XAC03-13404D50 BQ and Specification (RFQ) - Shop Fabrication Piping - BOP Piping Materials Small 7 29-Jul-16 04-Aug-16 69
Bore (Alloy Materials)
XAC03-13404D40 BQ and Specification (RFQ) - Shop Fabrication Piping - BOP Piping Materials Small 7 08-Aug-16 14-Aug-16 117
Bore (Carbon & Stainless Materials)
03PMS-BL00.1.3.4.04.E Valve 471 05-Jan-16 19-Apr-17 218
XAC03-13404E40 BQ and Specification (RFQ) - Valve - High Pressure Valve 7 05-Jan-16 11-Jan-16 86
XAC03-13404E60 BQ and Specification (RFQ) - Valve - MCW and Non Return Butterfly Valve 7 27-Feb-16 04-Mar-16 94
XAC03-13404E70 BQ and Specification (RFQ) - Valve - General Butterfly Valve 7 10-Mar-16 16-Mar-16 202
XAC03-13404E90 BQ and Specification (RFQ) - Valve - Auto Vent Valve 7 08-May-16 14-May-16 116
XAC03-13404E80 BQ and Specification (RFQ) - Valve - Temporary Valve for Steam Blow 7 13-Apr-17 19-Apr-17 218
XAC03-13404F10 BQ and Specification (RFQ) - Expansion & Flexible Joint 7 02-Jul-16 08-Jul-16 74
XAC03-13404F50 BQ and Specification (RFQ) - Tar get Plate for Steam Blow 7 08-Mar-17 14-Mar-17 221
XAC03-13404G30 BQ and Specification (RFQ) - Structural Beam & Plate (2nd Order) 7 16-Sep-16 22-Sep-16 90
XAC03-13404G40 BQ and Specification (RFQ) - Structural Beam & Plate (3rd Order) 7 26-Dec-16 01-Jan-17 6
XAC03-13404H10 BQ and Specification (RFQ) - Platform for Valve - HRSG Side Pipe Rack 7 25-Oct-16 31-Oct-16 52
XAC03-13404H30 BQ and Specification (RFQ) - Platform for Valve - STG Side Pipe Rack 7 25-Oct-16 31-Oct-16 150
XAC03-13404H40 BQ and Specification (RFQ) - Platform for Valve - GTG Side Pipe Rack 7 02-Dec-16 08-Dec-16 52
XAC03-13404H20 BQ and Specification (RFQ) - Platform for Valve - Deaerator Tower Valve 7 03-Jan-17 09-Jan-17 308
OperationStage
03PMS-BL00.1.3.4.04.I Insulation 7 30-Jan-17 05-Feb-17 237
XAC03-13404J10 BQ and Specification (RFQ) - Consumable Materials - Paint for Support structure 7 14-Dec-16 20-Dec-16 31
XAC03-13404J20 BQ and Specification (RFQ) - Consumable Materials - Paint for Piping 7 22-Mar-17 28-Mar-17 101
XAC03-13404K60 BQ and Specification (RFQ) - Bolt, Nut and Gasket 7 26-Aug-16 01-Sep-16 90
XAC03-13404K10 BQ and Specification (RFQ) - Shop Fabrication Piping - Orifice 7 30-Sep-16 06-Oct-16 90
XAC03-13404K30 BQ and Specification (RFQ) - Shop Fabrication Piping - Fuel Gas Condensate Tank 7 28-Oct-16 03-Nov-16 47
XAC03-13404K20 BQ and Specification (RFQ) - Shop Fabrication Piping - Funnel 7 08-Dec-16 14-Dec-16 304
XAC03-13404K50 BQ and Specification (RFQ) - Shop Fabrication Piping - CCCW Head Pipe / CCCW 7 08-Dec-16 14-Dec-16 304
Chemical Pot
XAC03-13404K40 BQ and Specification (RFQ) - Shop Fabrication - Drain Flash Pipe 7 18-Dec-16 24-Dec-16 159
XAC03-13404K80 BQ and Specification (RFQ) - Name Tag Plate for Replace 7 19-Jun-17 25-Jun-17 56
XAC03-13404K70 BQ and Specification (RFQ) - Shop Fabrication Piping - Water seal for Buili ng 7 17-Jul-17 23-Jul-17 63
penetration Rain Cover
03PMS-BL00.1.3.4.04.L Steam Blow Piping 7 13-Apr-17 19-Apr-17 202
XAC03-13404L00 BQ and Specification (RFQ) - Steam Blow Piping 7 13-Apr-17 19-Apr-17 202
XAC03-13404M00 BQ and Specification (RFQ) - BOP Yard Pipe Prefabrication 7 18-May-16 24-May-16 174
03PMS-BL00.1.3.4.05 Dr
Drawing 312 05-Jul-16 12-May-17 265
XAC03-13405200 Drawing Preparation for Shop Raw & CT Make Up System (1st) 29 23-Sep-16* 21-Oct-16 90
XAC03-13405300 Drawing Preparation for Shop Condensate Water,MCW Blow & SW System (2nd) 29 21-Oct-16* 18-Nov-16 81
XAC03-13405400 Drawing Preparation for Shop DM Water, IA/SA Air (3rd) 29 18-Nov-16* 16-Dec-16 113
XAC03-13405500 Drawing Preparation for Shop Ext. Steam, HP/LP Feed & Fuel Gas (4th) 28 16-Dec-16* 12-Jan-17 47
XAC03-13405600 Drawing Preparation for Shop HP/LP Steam (5th) 28 12-Jan-17* 08-Feb-17 58
XAC03-13405700 Drawing Preparation for Shop CCCW, Condensate Drain & Vacuum System (6th) 28 08-Feb-17* 07-Mar-17 175
03PMS-BL00.1.3.4.06 Pr
Procurement Support 608 12-Jan-16 10-Sep-17 144
XAC03-13406A20 Procurement & Manufacturing - MCW Material Piping 151 16-Aug-16 13-Jan-17 81
XAC03-13406C10 Technical Clarification - Underground Piping Materials (Stainless) 29 25-Mar-16 22-Apr-16 234
XAC03-13406C20 Technical Clarification - Underground Piping Materials (PVC&ABS) 29 25-Mar-16 22-Apr-16 234
XAC03-13406C30 Procurement & Manufacturing - Underground Piping Materials (Stainless) 41 23-Apr-16 02-Jun-16 234
XAC03-13406C40 Procurement & Manufacturing - Underground Piping Materials (PVC / ABS) 41 23-Apr-16 02-Jun-16 234
XAC03-13406D20 Technical Clarification - BOP Pipin g Materials Large Bore (Alloy) 13 14-May-16 26-May-16 72
XAC03-13406D10 Technical Clarification - BOP Pipin g Materials Large Bore(Carbon & Stainles s) 37 14-May-16 19-Jun-16 103
XAC03-13406D70 Procurement & Manufacturing - Large Bore (Alloy) 210 27-May-16 22-Dec-16 72
XAC03-13406D60 Procurement & Manufacturing - Large Bore (Carbon & Stainless) 74 20-Jun-16 01-Sep-16 103
XAC03-13406D30 Technical Clarification - BOP Yard Piping Small Bore (Galvanized Materials) 30 22-Jun-16 21-Jul-16 115
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-13406D40 Technical Clarification - BOP Yard Piping Small Bore (Car bon & Stainless Materials) 43 15-Aug-16 26-Sep-16 117
XAC03-13406DA0 Procurement & Manufacturing - BOP Yard Piping Procurement - Small Bore (Alloy 126 17-Sep-16 20-Jan-17 69
Materials)
XAC03-13406D90 Procurement & Manufacturing - Small Bore (Carbon & Stainless Materials) 84 27-Sep-16 19-Dec-16 117
XAC03-13406ED0 Procurement & Manufacturing - High Pressure Valve 327 12-Feb-16 03-Jan-17 86
XAC03-13406E60 Technical Clarification - MCW and Non Return Butterfly Valve 44 05-Mar-16 17-Apr-16 94
XAC03-13406EF0 Procurement & Manufacturing - MCW and Non Return Butterfly Valve 221 18-Apr-16 24-Nov-16 94
XAC03-13406EG0 Procurement & Manufacturing - General Butterfly Valve 5 01-May-16 05-May-16 254
XAC03-13406EE0 Procurement & Manufacturing - High Temp (Alloy Mtrls.) Valve 207 26-Jun-16 18-Jan-17 19
XAC03-13406EI0 Procurement & Manufacturing - Auto Vent and Hoot Valve 188 28-Jun-16 01-Jan-17 116
XAC03-13406E80 Technical Clarification - Temporary valve for Steam Blow 19 20-Apr-17 08-May-17 218
XAC03-13406EH0 Procurement & Manufacturing - Temporary Valve, Pipe & Fitting for Steam Blow 14 09-May-17 22-May-17 218
XAC03-13406F10 Technical Clarification -Special Product - Expansion & Flexible Joint 44 09-Jul-16 21-Aug-16 74
XAC03-13406F60 Procurement & Manufacturing - Expansion & Flexible Joint 81 05-Sep-16 24-Nov-16 74
XAC03-13406F50 Technical Clarification -Special Product - Target Plate for Steam Blow 16 15-Mar-17 30-Mar-17 221
XAC03-13406FA0 Procurement & Manufacturing - Target Plate for Steam Blow 50 31-Mar-17 19-May-17 221
XAC03-13406G30 Technical Clarification - Structural Beam & Plate (2nd Order) 43 23-Sep-16 04-Nov-16 90
XAC03-13406G70 Procurement & Manufacturing - Structural Beam & Plate (2nd Order) 41 05-Nov-16 15-Dec-16 90
XAC03-13406G40 Technical Clarification - Structural Beam & Plate (3rd Order) 29 02-Jan-17 30-Jan-17 6
XAC03-13406G80 Procurement & Manufacturing - Structural Beam & Plate (3rd Order) 38 31-Jan-17 09-Mar-17 6
XAC03-13406H10 Technical Clarification - Platform for Valve - HRSG Side Pipe Rack 25 01-Nov-16 25-Nov-16 52
XAC03-13406H30 Technical Clarification - Platform for Valve - STG Side Pipe Rack 25 01-Nov-16 25-Nov-16 150
XAC03-13406H50 Procurement & Manufacturing - Platform for Valve - HRSG Side Pipe Rack 79 26-Nov-16 12-Feb-17 52
XAC03-13406H40 Technical Clarification - Platform for Valve - GTG Side Pipe Rack 15 09-Dec-16 23-Dec-16 52
XAC03-13406H80 Procurement & Manufacturing - Platform for Valve - GTG Side Pipe Rack 67 24-Dec-16 28-Feb-17 52
XAC03-13406H20 Technical Clarification - Platform for Valve - Deaerator Tower Valve OperationStage 17 10-Jan-17 26-Jan-17 308
XAC03-13406H60 Procurement & Manufacturing - Platform for Valve - Deaerator Tower Valve 63 27-Jan-17 30-Mar-17 308
OperationStage
XAC03-13406H70 Procurement & Manufacturing - Platform for Valve - STG Side Pipe Rack 41 28-Feb-17 09-Apr-17 56
XAC03-13406J10 Technical Clarification - Consumable Materials - Paint for Support structure 21 21-Dec-16 10-Jan-17 31
XAC03-13406J30 Procurement & Manufacturing - Consumable Materials - Paint for Support structure 33 11-Jan-17 12-Feb-17 31
XAC03-13406J12 Technical Clarification - Consumable Materials - Paint for Piping 14 29-Mar-17 11-Apr-17 101
XAC03-13406J40 Procurement & Manufacturing - Consumable Materials - Paint for Piping 39 12-Apr-17 20-May-17 101
XAC03-13406KE0 Procurement & Manufacturing - Bolt Nut and Gasket 62 15-Oct-16 15-Dec-16 90
XAC03-13406KB0 Procurement & Manufacturing - Fuel Gas Condensate Tank 82 03-Dec-16 22-Feb-17 47
XAC03-13406K50 Technical Clarification - CCCW Head Pipe / CCCW Chemical Pot 28 15-Dec-16 11-Jan-17 304
XAC03-13406KD0 Procurement & Manufacturing - CCCW Head Pipe / CCCW Chemical Pot 82 12-Jan-17 03-Apr-17 304
XAC03-13406KC0 Procurement & Manufacturing - Drain Flash Pipe 82 27-Jan-17 18-Apr-17 159
XAC03-13406K70 Technical Clarification - Water seal for Builing penetration Rain Cover 29 25-Jun-17 24-Jul-17 63
XAC03-13406K80 Technical Clarification - Name Tag Plate for Replace 20 26-Jun-17 15-Jul-17 56
XAC03-13406KG0 Procurement & Manufacturing - Name Tag Plate for Replace 36 16-Jul-17 20-Aug-17 56
XAC03-13406KF0 Procurement & Manufacturing - Water seal for Buili ng penetration Rain Cover 21 21-Aug-17 10-Sep-17 35
XAC03-13406L20 Procurement & Manufacturing - Support material / Steam Blow Piping 41 19-May-17 28-Jun-17 218
XAC03-13406M20 Procurement & Pre-fabrication Raw & CT Make Up System (1st) 55 22-Oct-16 15-Dec-16 90
XAC03-13406M30 Procurement & Pre-fabrication Condensate Water,MCW Blow & SW System (2nd) 56 19-Nov-16 13-Jan-17 81
XAC03-13406M40 Procurement & Pre-fabrication DM Water, IA/SA Air (3rd) 51 17-Dec-16 05-Feb-17 113
XAC03-13406M05 Procurement & Pre-fabrication Ext. Steam, HP/LP Feed & Fuel Gas (4th) 41 13-Jan-17 22-Feb-17 47
XAC03-13406M70 Procurement & Pre-fabrication CCCW, Condensate Drain & Vacuum System (6th) 26 08-Mar-17 02-Apr-17 175
03PMS-BL00.1.3.4.07 Er
Erection Support 148 16-Dec-16 12-May-17 265
03PMS-BL00.1.3.5.01 DCS
DC 298 02-Mar-16 24-Dec-16 52
XAC03-13501100 Drawing Review and Comments for Notice To Fabr icate (NTF) 222 02-Mar-16 09-Oct-16 52
03PMS-BL00.1.3.5.02 Co
Continuous Emission Monitoring System 244 17-Aug-16 17-Apr-17 4
XAC03-13502100 Drawing Review and Comments for Notice To Fabr icate (NTF) 92 17-Aug-16 16-Nov-16 156
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.1.3.5.03 Steam
St and Water Analysis System 129 07-Oct-16 12-Feb-17 153
XAC03-13503100 Drawing Review and Comments for Notice To Fabr icate (NTF) 58 07-Oct-16 03-Dec-16 224
03PMS-BL00.1.3.5.04 Pla
Plant Communication System, CCTV & Clock 136 29-Nov-16 13-Apr-17 25
XAC03-13504100 Drawing Review and Comments for Notice To Fabr icate (NTF) 81 29-Nov-16 17-Feb-17 80
03PMS-BL00.1.3.5.05 Ch
Chemical Laboratory 142 19-Nov-16 09-Apr-17 273
XAC03-13505100 Drawing Review and Comments for Notice To Fabr icate (NTF) 57 19-Nov-16 14-Jan-17 358
03PMS-BL00.1.3.5.06 Primary
Pr Emergency Saving System 106 26-Oct-16 08-Feb-17 89
XAC03-13506100 Drawing Review and Comments for Notice To Fabr icate (NTF) 66 26-Oct-16 30-Dec-16 129
03PMS-BL00.1.3.5.07 C&
C&I Bulk Material 14 29-Nov-16 12-Dec-16 78
XAC03-13507100 Drawing Review and Comments for Notice To Fabr icate (NTF) 1 29-Nov-16 29-Nov-16 91
03PMS-BL00.1.3.5.08 Turbine
Tu Bypass Control 206 16-Jun-16 07-Jan-17 85
XAC03-135081B0 Drawing Review and Comments for Notice To Fabr icate (NTF) - Control 126 16-Jun-16 19-Oct-16 139
XAC03-135081A0 Drawing Review and Comments for Notice To Fabr icate (NTF) - Turbine Bypass 180 17-Jun-16 13-Dec-16 110
03PMS-BL00.1.3.5.ZZ Others
O 21 02-Dec-16 22-Dec-16 89
XAC03-135ZZ100 Drawing Review and Comments for Notice To Fabr icate (NTF) - Cabling Bulk For C&I 10 02-Dec-16 11-Dec-16 100
Cable
XAC03-135ZZ300 Factory Test - C abling Bulk For C&I Cable 0 22-Dec-16 89
03PMS-BL00.1.3.6 Electrical
Electri system Detail Engineering 360 18-Feb-16 11-Feb-17 80
03PMS-BL00.1.3.6.01 Ge
Generator Step Up Transformer 291 23-Mar-16 07-Jan-17 9
XAC03-13601100 Drawing Review and Comments for Notice To Fabr icate (NTF) 125 23-Mar-16 25-Jul-16 175
03PMS-BL00.1.3.6.02 Un
Unit Aux Transformer with remote OLTC panel 360 18-Feb-16 11-Feb-17 54
XAC03-13602100 Drawing Review and Comments for Notice To Fabr icate (NTF) 158 18-Feb-16 24-Jul-16 256
03PMS-BL00.1.3.6.05 HV
HV/MV SWGR 250 30-Mar-16 04-Dec-16 116
XAC03-13605100 Drawing Review and Comments for Notice To Fabr icate (NTF) 161 30-Mar-16 06-Sep-16 205
03PMS-BL00.1.3.6.06 Auxiliary
Au Transformer 242 08-May-16 04-Jan-17 93
XAC03-13606100 Drawing Review and Comments for Notice To Fabr icate (NTF) 102 08-May-16 17-Aug-16 233
XAC03-136071B0 Drawing Review and Comments for Notice To Fabr icate (NTF) - MCC /DB 156 08-Jun-16 10-Nov-16 156
XAC03-136071A0 Drawing Review and Comments for Notice To Fabr icate (NTF) - LV SWGR 100 03-Aug-16 10-Nov-16 147
XAC03-13608100 Drawing Review and Comments for Notice To Fabr icate (NTF) 127 30-May-16 03-Oct-16 75
03PMS-BL00.1.3.6.09 Em
Emergency Diesel Engine Generator 161 16-Jul-16 23-Dec-16 130
XAC03-13609100 Drawing Review and Comments for Notice To Fabr icate (NTF) 105 16-Jul-16 28-Oct-16 186
03PMS-BL00.1.3.7 Electri
Electrical Bulk Material Detail Design 190 09-Apr-16 15-Oct-16 409
03PMS-BL00.1.3.7.05.1 BQ List and Technical Specification for RFQ 67 09-Apr-16 14-Jun-16 183
XAC03-13705170 BQ and Specification (RFQ) - Cable Tray & Accessories 6 09-Apr-16 14-Apr-16 148
XAC03-13705180 BQ and Specification (RFQ) - Cable Tray Support 6 09-Apr-16 14-Apr-16 148
XAC03-137051C0 BQ and Specification (RFQ) - Grounding Material (Underground) 4 11-Apr-16 14-Apr-16 162
XAC03-137051D0 BQ and Specification (RFQ) - Grounding Material (Above Ground) 4 11-Apr-16 14-Apr-16 162
XAC03-137051E0 BQ and Specification (RFQ) - Lightning Protection Material 4 11-Apr-16 14-Apr-16 162
XAC03-137051H0 BQ and Specification (RFQ) - Fire Sealing Material 4 11-Jun-16 14-Jun-16 183
03PMS-BL00.1.3.7.05.2 Manufacturer's Specification & Technical Data 154 15-May-16 15-Oct-16 409
XAC03-13705260 Manufacturer's Specification & Technical Data - Grounding System Material 20 15-May-16 03-Jun-16 352
XAC03-13705270 Manufacturer's Specification & Technical Data - Lightning System Material 60 15-May-16 13-Jul-16 198
XAC03-13705290 Manufacturer's Specification & Technical Data - Lighting & Small Power Supply System 30 15-May-16 13-Jun-16 533
Material
XAC03-13705220 Manufacturer's Specification & Technical Data - Cable Tray & Accessories 30 02-Jun-16 01-Jul-16 148
XAC03-13705240 Manufacturer's Specification & Technical Data - Secondary Rac eway Mater ial 30 02-Jun-16 01-Jul-16 148
XAC03-137052L0 Manufacturer's Specification & Technical Data - Fire Sealing Material 30 15-Jul-16 13-Aug-16 183
XAC03-13705210 Manufacturer's Specification & Technical Data - Power, Control & Instrument Cables 30 16-Sep-16 15-Oct-16 162
03PMS-BL00.1.3.7.06 Pr
Procurement Support 154 15-Apr-16 15-Sep-16 308
XAC03-13706700 Technical Clarification & Evaluation for Cable Tray & Accessorie s 78 15-Apr-16 01-Jul-16 148
XAC03-13706800 Technical Clarification & Evaluation for Cable Tray Support 78 15-Apr-16 01-Jul-16 148
XAC03-13706900 Technical Clarification & Evaluation for Secondary Raceway 78 15-Apr-16 01-Jul-16 148
XAC03-13706C00 Technical Clarification & Evaluation for Grounding Material (Underground) 30 15-Apr-16 14-May-16 262
XAC03-13706D00 Technical Clarification & Evaluation for Grounding Material (Above Ground) 30 15-Apr-16 14-May-16 262
XAC03-13706E00 Technical Clarification & Evaluation for Lightning Protection Material 30 15-Apr-16 14-May-16 196
XAC03-13706F00 Technical Clarification & Evaluation for Lighting & Small Power Supply System 30 15-Apr-16 14-May-16 432
XAC03-13706100 Technical Clarification & Evaluation for Power Cable 93 15-Jun-16 15-Sep-16 162
XAC03-13706200 Technical Clarification & Evaluation for Control Cable 93 15-Jun-16 15-Sep-16 162
XAC03-13706300 Technical Clarification & Evaluation for Instrumentation Cable 93 15-Jun-16 15-Sep-16 162
XAC03-13706H00 Technical Clarification & Evaluation for Fire Sealing Material 30 15-Jun-16 14-Jul-16 183
03PMS-BL00.1.3.8 Switchyard
Switch Detail Engineering 204 26-Mar-16 15-Oct-16 91
03PMS-BL00.1.3.8.06 Pr
Procurement Support 204 26-Mar-16 15-Oct-16 91
03PMS-BL00.2 PROCUREMENT
PROCUREM 649 01-Dec-15 10-Sep-17 144
03PMS-BL00.2.1 DIRECT M
MATERIALS (cost procured by ) 649 01-Dec-15 10-Sep-17 144
03PMS-BL00.2.1.1 Arrangement
Arrang 390 08-Jan-16 31-Jan-17 192
03PMS-BL00.2.1.1.01 Fir
Fire Fighting system 332 08-Jan-16 04-Dec-16 102
03PMS-BL00.2.1.1.02 HVAC
HV 390 08-Jan-16 31-Jan-17 192
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.2.1.3 Mechanical
Mecha Equipment 530 01-Dec-15 14-May-17 117
03PMS-BL00.2.1.3.01 Gas
Ga turbine & Generator #31&32 442 01-Dec-15 15-Feb-17 37
XAC03-213010-510C MHO : Lot-3 Auxiliary Equipments & Accessories/Shortage Materials - GTG 31&32 0 15-Feb-17 36
XAC03-213010-510D MHO : Lot-4 Auxiliary Equipments (from China) - GTG 31&32 0 15-Feb-17 36
03PMS-BL00.2.1.3.02 HRSG
HR #31&32 446 01-Dec-15 19-Feb-17 113
XAC03-213020-510 MHO : (Lot-1 Base Plate / Stack Template / Embedded Materials) 0 31-May-16 114
XAC03-213020-510A MHO : (Lot-2 Box Assembly / Module Header / Module Tubes) 0 15-Jan-17 12
XAC03-213020-510B MHO : (Lot-3 Blowdown Tank / Expansion Joint - Inlet duct / Bypass s tack Accessories 0 19-Jan-17 0
/ Diverter dumper)
XAC03-213020-510C MHO : (Lot-4 Inlet Duct / Field Connection / Bypass Stack) 0 22-Jan-17 10
XAC03-213020-510E MHO : (Lot-6 LP & HP Steam Drum / Platforms, Ladders, Stairs) 0 05-Feb-17 11
XAC03-213020-510G MHO : (Lot-8 Main Stacks / Expansion Joint - Outlet duct) 0 09-Feb-17 20
03PMS-BL00.2.1.3.03 St
Steam Turbine & Generator 530 01-Dec-15 14-May-17 21
03PMS-BL00.2.1.3.07 Condenser
Co 444 14-Jan-16 02-Apr-17 54
03PMS-BL00.2.1.3.09 Condensate
Co Extraction Pump 372 08-Jan-16 13-Jan-17 166
03PMS-BL00.2.1.3.10 Bo
Boiler Feed Water Pump 416 08-Jan-16 27-Feb-17 86
03PMS-BL00.2.1.3.12 CW
CW/ACW System Equipment 404 08-Jan-16 14-Feb-17 57
03PMS-BL00.2.1.3.13 CC
CCCW Pump 367 14-Feb-16 14-Feb-17 57
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.2.1.3.15 Condenser
Co Vacuum Pump 447 14-Jan-16 05-Apr-17 156
03PMS-BL00.2.1.3.16 Ge
General Water Service Pump 364 15-Feb-16 12-Feb-17 122
03PMS-BL00.2.1.3.17 Su
Sump Pump 276 01-May-16 31-Jan-17 59
03PMS-BL00.2.1.3.18 Ch
Chemical Dosing System 339 16-Apr-16 20-Mar-17 87
03PMS-BL00.2.1.3.19 Air
Ai Compressor System 377 01-Jan-16 12-Jan-17 93
03PMS-BL00.2.1.3.20 Fu
Fuel Gas Supply System 385 14-Jan-16 01-Feb-17 96
03PMS-BL00.2.1.3.23 Water
Wa Tank 371 30-Dec-15 04-Jan-17 109
03PMS-BL00.2.1.3.23.3 Service Water & Fire Water Storage Tank 262 08-Jan-16 25-Sep-16 165
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.2.1.3.26 Heat
He exchanger 397 14-Jan-16 14-Feb-17 143
03PMS-BL00.2.1.3.27 Cooling
Co Tower 384 15-Jan-16 01-Feb-17 66
03PMS-BL00.2.1.3.30 Waste
Wa Water Treatment System 366 01-Dec-15 01-Dec-16 64
03PMS-BL00.2.1.3.45 Overhead
Ov Crane 385 15-Jan-16 02-Feb-17 38
03PMS-BL00.2.1.3.ZZ Others
O 379 30-Jan-16 12-Feb-17 82
03PMS-BL00.2.1.4.03 BOP
BO Piping Material (Bear) 70 25-Mar-16 02-Jun-16 234
XAC03-214031-510 MHO : Under Ground pipe material (Stainless) - Arrive at Site 0 02-Jun-16* 234
03PMS-BL00.2.1.4.03.2 Under Ground pipe material (PVC / ABS) 70 25-Mar-16 02-Jun-16 234
XAC03-214032-510 MHO : Under Ground pipe material (PVC / ABS) - Arrive at Site 0 02-Jun-16* 234
03PMS-BL00.2.1.4.04 Sh
Shop Fabrication Piping 299 14-May-16 09-Mar-17 75
03PMS-BL00.2.1.4.04.1 Pipe Raw Material for BOP Yard Fabrication Large Bore (Carbon & Stainless Mater 160 14-May-16 21-Oct-16 91
XAC03-214041-501 Issue RFQ : Large Bore (Carbon & Stainless) 0 14-May-16* 103
XAC03-214041-508 FOB or ETD : Large Bore (Carbon & Stainless) 0 01-Sep-16 103
XAC03-214041-510 MHO : Large Bore (Carbon & Stainless) - Arrive at Prefabrication Vendor 0 21-Oct-16* 91
03PMS-BL00.2.1.4.04.2 Pipe Raw Material for BOP Yard Fabrication Large Bore (Alloy Materials) 270 14-May-16 08-Feb-17 62
03PMS-BL00.2.1.4.04.3 BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 176 22-Jun-16 15-Dec-16 91
XAC03-214043-501 Issue RFQ : BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 0 22-Jun-16* 115
XAC03-214043-502 Issue PO : BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 0 03-Aug-16* 103
XAC03-214043-508 FOB or ETD : BOP Yard Piping Procurement - Small Bore (Galvanized Materials) 0 26-Oct-16 103
XAC03-214043-510 MHO : BOP Yard Piping Procurement - Small Bore (Galvanized : RW/SW Materials) - 0 15-Dec-16* 91
Arrive at Site
03PMS-BL00.2.1.4.04.4 BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) 171 15-Aug-16 02-Feb-17 110
XAC03-214044-501 Issue RFQ : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) 0 15-Aug-16* 117
XAC03-214044-502 Issue PO : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) 0 26-Sep-16* 117
XAC03-214044-508 FOB or ETD : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless 0 19-Dec-16 117
Materials)
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-214044-510 MHO : BOP Yard Piping Procurement - Small Bore (Carbon & Stainless Materials) - 0 02-Feb-17* 110
Arrive at Site
03PMS-BL00.2.1.4.04.5 BOP Yard Piping Procurement - Small Bore (Alloy Materials) 216 05-Aug-16 09-Mar-17 59
XAC03-214045-501 Issue RFQ : BOP Yard Piping Procurement - Small Bore (Alloy Materials) 0 05-Aug-16* 69
XAC03-214045-502 Issue PO : BOP Yard Piping Procurement - Small Bore (Alloy Materials) 0 16-Sep-16* 69
XAC03-214045-508 FOB or ETD : BOP Yard Piping Procurement - Small Bore (Alloy Materials) 0 20-Jan-17 69
XAC03-214045-510 MHO : BOP Yard Piping Procurement - Small Bore (Alloy Materials : Aux Steam, HP/Ext 0 09-Mar-17* 59
Steam Drain) - Arrive at Site
03PMS-BL00.2.1.4.05 Va
Valve 534 11-Jan-16 28-Jun-17 218
03PMS-BL00.2.1.4.05.6 MCW Butterfly Valve & MCW Non Return Butterfly Valve 306 05-Mar-16 05-Jan-17 90
XAC03-214056-501 Issue RFQ MCW and Non Return Butterfly Valve 0 05-Mar-16* 94
XAC03-214058-501 Issue RFQ Temporar y Valve for Steam Blow 0 20-Apr-17* 218
XAC03-214059-501 Issue RFQ Auto Vent and Hoot Valve 0 15-May-16* 116
03PMS-BL00.2.1.4.06 Sp
Specialty Product 437 17-Apr-16 28-Jun-17 219
03PMS-BL00.2.1.4.06.5 Target Plate for Steam Blow 105 15-Mar-17 28-Jun-17 219
XAC03-214065-501 Issue RFQ Target Pla te for Steam Blow 0 15-Mar-17* 221
03PMS-BL00.2.1.4.07 Pip
Piping Support Materials 168 23-Sep-16 09-Mar-17 6
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.2.1.4.07.2 Structural Beam & Plate 1st Order (Pipe Chair, Clamp) 111 04-Nov-16 22-Feb-17 21
03PMS-BL00.2.1.4.07.3 Structural Beam & Plate 2nd Order (80% Qty Beam, Anchor Bolt, U-Bolt, Plate etc.) 84 23-Sep-16 15-Dec-16 90
XAC03-214073-510 MHO : Structural Beam & Plate (2nd Order) - Arrive at Site 0 15-Dec-16* 90
03PMS-BL00.2.1.4.07.4 Structural Beam & Plate 3rd Order (20% Qty Beam, Anchor Bolt, U-Bolt, Plate etc.) 67 02-Jan-17 09-Mar-17 6
XAC03-214074-510 MHO : Structural Beam & Plate (3rd Order) - Arrive at Site 0 09-Mar-17* 6
03PMS-BL00.2.1.4.08 Pla
Platform for Valve 160 01-Nov-16 09-Apr-17 298
03PMS-BL00.2.1.4.08.1 Platform for Valve - HRSG Side Pipe Rack 104 01-Nov-16 12-Feb-17 52
XAC03-214081-510 MHO : Platform for Valve - HRSG Side Pipe Rack - Arrive at Site 0 12-Feb-17* 52
03PMS-BL00.2.1.4.08.2 Platform for Valve - Deaerator Tower Valve OperationStage 80 10-Jan-17 30-Mar-17 308
XAC03-214082-510 MHO : Platform for Valve - Deaerator Tower Valve OperationStage - Arrive at Site 0 30-Mar-17* 308
03PMS-BL00.2.1.4.08.3 Platform for Valve - STG Side Pipe Rack 160 01-Nov-16 09-Apr-17 56
XAC03-214083-510 MHO : Platform for Valve - STG Side Pipe Rack - Arrive at Site 0 09-Apr-17* 56
03PMS-BL00.2.1.4.08.4 Platform for Valve - GTG Side Pipe Rack 82 09-Dec-16 28-Feb-17 52
XAC03-214084-510 MHO : Platform for Valve - GTG Side Pipe Rack - Arrive at Site 0 28-Feb-17* 52
03PMS-BL00.2.1.4.09 Insulation
Ins 124 06-Feb-17 09-Jun-17 237
03PMS-BL00.2.1.4.10 Consumable
Co Material 151 21-Dec-16 20-May-17 101
03PMS-BL00.2.1.4.11 Mi
Miscellaneous Material 374 02-Sep-16 10-Sep-17 144
03PMS-BL00.2.1.4.11.5 CCCW Head Pipe /Chemical Pot Procurement 110 15-Dec-16 03-Apr-17 304
XAC03-214115-501 Issue RFQ CCCW Head Pipe / CCCW Chemical Pot 0 15-Dec-16* 304
XAC03-214115-502 Issue PO CCCW Head Pipe / CCCW Chemical Pot 0 11-Jan-17* 304
XAC03-214115-510 MHO : CCCW Head Pipe / CCCW Chemical Pot - Arrive at Site 0 03-Apr-17* 304
03PMS-BL00.2.1.4.11.7 Water seal for Building penetration Rain Cover Procurement 49 24-Jul-17 10-Sep-17 35
XAC03-214117-501 Issue RFQ Water seal for Builing penetration Rain Cover Procurement 0 24-Jul-17* 63
XAC03-214117-502 Issue PO Water seal for Builing penetration Rain Cover 0 21-Aug-17* 35
XAC03-214117-510 MHO : Water seal for Builing penetration Rain Cover - Arrive at Site 0 10-Sep-17* 35
XAC03-214118-510 MHO : Name Tag Plate for Replace - Arrive at Site 0 20-Aug-17* 56
03PMS-BL00.2.1.4.12 St
Steam Blow Piping 70 20-Apr-17 28-Jun-17 218
XAC03-214120-501 Issue RFQ Support material / Steam Blow Piping 0 20-Apr-17* 202
03PMS-BL00.2.1.4.13 Shop
Sh Prefabricated Piping 313 25-May-16 03-Apr-17 175
XAC03-214131-510A MHO : Arrive at Site Raw & CT Make Up System (1st) 0 15-Dec-16* 90
XAC03-214131-510B MHO : Arrive at Site Condensate Water,MCW Blow & SW System (2nd) 0 13-Jan-17* 81
XAC03-214131-510C MHO : Arrive at Site DM Water, IA/SA Air (3rd) 0 05-Feb-17* 113
XAC03-214131-510D MHO : Arrive at Site Ext. Steam, HP/LP Feed & Fuel Gas (4th) 0 22-Feb-17* 47
XAC03-214131-510F MHO : Arrive at Site CCCW, Condensate Drain & Vacuum System (6th) 0 03-Apr-17* 175
03PMS-BL00.2.1.5.01 DCS
DC 406 14-Jan-16 22-Feb-17 52
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.2.1.5.02 Co
Continuous Emission Monitoring System 351 27-May-16 12-May-17 4
03PMS-BL00.2.1.5.03 Steam
St and Water Analysis System 297 17-May-16 09-Mar-17 153
XAC03-215030-510 MHO : Steam and Water Sampling System Rack 0 09-Mar-17 153
03PMS-BL00.2.1.5.04 Pla
Plant Communication System, CCTV & Clock 242 08-Sep-16 08-May-17 25
03PMS-BL00.2.1.5.05 Ch
Chemical Laboratory 520 01-Dec-15 05-May-17 273
03PMS-BL00.2.1.5.06 Pr
Primary Energy Saving System 311 29-Apr-16 06-Mar-17 89
03PMS-BL00.2.1.5.07 C&
C&I Bulk Material 137 13-Sep-16 28-Jan-17 78
03PMS-BL00.2.1.5.08 Turbine
Tu Bypass Valve 311 02-May-16 08-Mar-17 85
03PMS-BL00.2.1.5.09 Co
Control Valves 256 02-May-16 13-Jan-17 114
03PMS-BL00.2.1.5.ZZ Others
O 78 31-Oct-16 17-Jan-17 89
XAC03-215ZZ0-501 Issue RFQ - Cabling Bulk For C&I Cable 0 31-Oct-16* 100
03PMS-BL00.2.1.6 Electrical
Electri 450 15-Dec-15 08-Mar-17 115
03PMS-BL00.2.1.6.01 Generator
Ge Transformer 450 15-Dec-15 08-Mar-17 9
03PMS-BL00.2.1.6.02 Un
Unit Aux Transformer with remote OLTC panel 450 15-Dec-15 08-Mar-17 54
03PMS-BL00.2.1.6.05 HV
HV/MV SWGR 312 22-Feb-16 29-Dec-16 116
03PMS-BL00.2.1.6.06 Auxiliary
Au Transformer 364 01-Feb-16 29-Jan-17 93
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.2.1.6.08 MCC/AC
MC DB 288 31-Mar-16 12-Jan-17 118
03PMS-BL00.2.1.6.10 Em
Emergency Diesel Engine Generator 360 28-Feb-16 21-Feb-17 130
03PMS-BL00.2.1.7 Electrical
Electri bulk 377 15-Apr-16 26-Apr-17 245
03PMS-BL00.2.1.7.01 Cables
Ca 273 15-Jun-16 15-Mar-17 42
03PMS-BL00.2.1.7.02 Raceway
Ra 179 15-Apr-16 11-Oct-16 72
03PMS-BL00.2.1.7.03 Secondary
Se raceway 179 15-Apr-16 11-Oct-16 72
03PMS-BL00.2.1.7.04 Grounding
Gr 90 15-Apr-16 14-Jul-16 337
03PMS-BL00.2.1.7.05 Lightning
Lig Protection system 291 15-Apr-16 30-Jan-17 22
03PMS-BL00.2.1.7.06 Lighting
Lig System 377 15-Apr-16 26-Apr-17 245
03PMS-BL00.2.1.7.07 Sealing
Se Material 230 15-Jun-16 30-Jan-17 38
03PMS-BL00.2.1.8 Switchyard
Switch 374 06-Dec-15 14-Dec-16 308
03PMS-BL00.2.1.8.01 GI
GIS / AIS 374 06-Dec-15 14-Dec-16 308
03PMS-BL00.3 CONSTRUC
CONSTRUCTION & COMMISSIONING 762 01-Dec-15 01-Jan-18 32
03PMS-BL00.3.1 GENERA
GENERAL WORK 125 01-Dec-15 22-Apr-16 93
03PMS-BL00.3.1.1 Civil P
Preparation (Soil Investigation) Work 125 01-Dec-15 22-Apr-16 93
03PMS-BL00.3.1.1.1 Civ
Civil Preparation (Soil Investigation) 125 01-Dec-15 22-Apr-16 93
XAC03-31112000 Civil Preparation (Soil Investigation) Work - Permit for Site Access from Owner 5 01-Dec-15 05-Dec-15 45
XAC03-31113000 Civil Preparation (Soil Investigation) Work - Preparation for Soil Investigation 6 05-Dec-15 12-Dec-15 45
XAC03-31114000 Civil Preparation (Soil Investigation) Work - Soil Investigation 14 12-Dec-15 29-Dec-15 45
XAC03-31115000 Civil Preparation (Soil Investigation) Work - Documentation for Report 18 29-Dec-15 19-Jan-16 45
XAC03-31116000 Civil Preparation (Soil Investigation) Work - Preliminary Report from Site 1 19-Jan-16 20-Jan-16 45
XAC03-31117000 Civil Preparation (Soil Investigation) Work - Report submit to Owner 5 20-Jan-16 26-Jan-16 45
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-31119000 Civil Preparation (Soil Investigation) Work - Pile Load Test 36 12-Mar-16 22-Apr-16 93
03PMS-BL00.3.2.1.01 St
Steam Turbine / Generator #3 305 06-Jun-16 06-Apr-17 155
XAC03-32101225 CEP PIT - Pump area - slab - Install Reinforcement 2 18-Jul-16 19-Jul-16 61
XAC03-32101226 CEP PIT - Pump area - slab - Install side formwork 1 20-Jul-16 20-Jul-16 61
XAC03-32101227 CEP PIT - Pump area - Slab - Casting concrete foundation 1 22-Jul-16 22-Jul-16 61
XAC03-32101228 CEP PIT - Pump area - Wall - Install Reinforcement 1 25-Jul-16 26-Jul-16 61
XAC03-32101229 CEP PIT - Pump area - Install side formwork 2 27-Jul-16 28-Jul-16 61
XAC03-3210122A CEP PIT - Pump area - Wall - Casting concrete foundation 2 29-Jul-16 30-Jul-16 61
XAC03-3210122C CEP PIT - CEP Base Foundation - Lean concrete 2 13-Aug-16 15-Aug-16 61
XAC03-3210122D CEP PIT - CEP Base Foundation - Pile Cutting 2 16-Aug-16 17-Aug-16 61
XAC03-3210122E CEP PIT - CEP Base Foundation - Slab - Install Reinforcement 12 18-Aug-16 31-Aug-16 61
XAC03-3210122F CEP PIT - CEP Base Foundation - Slab - Install side formwork 3 30-Aug-16 02-Sep-16 70
XAC03-3210122G CEP PIT - CEP Base Foundation - Slab - Casting concrete foundation 1 03-Sep-16 05-Sep-16 61
XAC03-3210122H CEP PIT - CEP Base Foundation - Wall - Install Reinforcement 10 07-Sep-16 17-Sep-16 61
XAC03-3210122I CEP PIT - CEP Base Foundation - Wall - Install side formwork 5 13-Sep-16 17-Sep-16 70
XAC03-3210122J CEP PIT - CEP Base Foundation - Wall - Casting concrete foundation 2 19-Sep-16 20-Sep-16 70
XAC03-32101232 CVP Pump Foundation - Install side formwork 4 06-Dec-16 09-Dec-16 234
XAC03-32101233 CVP Pump Foundation - Casting concrete foundation 1 10-Dec-16 12-Dec-16 234
XAC03-32101242 Extraction Heater Foundation - Install side formwork 4 27-Feb-17 02-Mar-17 100
XAC03-32101243 Extraction Heater Foundation - Casting concrete foundation 1 03-Mar-17 04-Mar-17 100
XAC03-32101350 STG Building - Footing - Install Embeded part material 39 06-Oct-16 19-Nov-16 47
XAC03-321013A0 STG Building - Slab- Conrete Work - Install side formwork 11 05-Dec-16 16-Dec-16 79
03PMS-BL00.3.2.1.02 Co
Condenser Ball Cleaning Foundation 12 11-Jan-17 23-Jan-17 102
03PMS-BL00.3.2.1.03 Cl
Closed Cycle Cooling Water System 15 13-Jan-17 27-Jan-17 75
XAC03-32103210 Closed Cycle Cooling Water System - Civil Work 13 13-Jan-17* 27-Jan-17 64
03PMS-BL00.3.2.1.06 Pip
Pipe Rack RF (STG#30 / E&C Area) 47.5 m + 26.0 m. 191 07-Jun-16 14-Dec-16 91
03PMS-BL00.3.2.1.07 Ca
Cable Trench (STG#30 - Pipe Rack RB ) 60 07-Jun-16 15-Aug-16 444
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-32107250 Cable Trench - Slab - Install side formwork 9 14-Jul-16 23-Jul-16 254
XAC03-32107280 Cable Trench - Wall - Install side formwork 6 03-Aug-16 10-Aug-16 254
03PMS-BL00.3.2.1.08 Ca
Cable Trench (STG#30 - Pipe Rack RB Road Crossing ) 76 07-Jun-16 01-Sep-16 238
XAC03-32108250 Cable Trench - Slab - Install side formwork 10 02-Jul-16 13-Jul-16 238
XAC03-32108280 Cable Trench - Wall - Install side formwork 6 27-Jul-16 03-Aug-16 238
XAC03-321082A0 Cable Trench - Top Slab - Install Reinforcement 13 09-Aug-16 23-Aug-16 238
XAC03-321082B0 Cable Trench - Top Slab - Install side formwork 7 24-Aug-16 31-Aug-16 238
XAC03-321082C0 Cable Trench - Top Slab - Casting concrete 1 01-Sep-16 01-Sep-16 238
03PMS-BL00.3.2.1.09 Ca
Cable Trench (STG Building) 56 18-Jul-16 19-Sep-16 224
XAC03-32109210 Cable Trench - Excavation and Lean concrete 6 18-Jul-16 23-Jul-16 224
XAC03-32109230 Cable Trench - Formwork and Water Stop 4 30-Jul-16 04-Aug-16 224
XAC03-32109240 Cable Trench - Casting for Base Slab 1 05-Aug-16 05-Aug-16 224
XAC03-32109290 Cable Trench - Scaffolding for TOP Slab 1 03-Sep-16 05-Sep-16 224
XAC03-321092A0 Cable Trench - Top Slab - Form Work 4 06-Sep-16 09-Sep-16 224
XAC03-321092B0 Cable Trench - Rebar for Top Slab 3 10-Sep-16 13-Sep-16 224
XAC03-321092C0 Cable Trench - Casting Concrete TOP Slab 1 14-Sep-16 14-Sep-16 224
XAC03-32109280 Cable Trench - Remove Form work and Reparing Concrete 4 15-Sep-16 19-Sep-16 224
03PMS-BL00.3.2.1.10 Pipe
Pip Sleeper (STG #3 Area) 26 21-Dec-16 19-Jan-17 116
03PMS-BL00.3.2.1.ZZ O
Other Civil Work 50 13-Dec-16 08-Feb-17 100
03PMS-BL00.3.2.2 Civil (E
(E&C Bldg Area) 380 02-May-16 16-May-17 261
03PMS-BL00.3.2.2.01 Ele
Electrical & Control Building 330 02-May-16 27-Mar-17 311
XAC03-32201220 Foundation Work at E&C Bldg. - Lean concrete 50THK 7 27-May-16 04-Jun-16 1
XAC03-32201230 Foundation Work at E&C Bldg. - Pile cut off 11 06-Jun-16 17-Jun-16 1
XAC03-32201240 Foundation Work at E&C Bldg. - Extend dowel by coupler 1 17-Jun-16 18-Jun-16 1
XAC03-32201260 Foundation Work at E&C Bldg. - Install side formwork 11 21-Jun-16 02-Jul-16 1
XAC03-32201270 Foundation Work at E&C Bldg. - Casting concrete foundation (pile cap) 1 04-Jul-16 04-Jul-16 1
XAC03-32201280 Foundation Work at E&C Bldg. - Remove formwork and repair concrete 12 05-Jul-16 18-Jul-16 3
XAC03-32201313 Tie Beam - Install side formwork (block wall) 10 21-Jul-16 01-Aug-16 1
XAC03-32201332 Ground floor (Column) +0.20 m - Install side formwork 6 01-Sep-16 08-Sep-16 1
XAC03-32201335 Ground floor (Column) +0.20 m - Cable Celler Room - H/O to Mech 0 29-Oct-16 94
XAC03-32201341 1st Floor (SWGR) (Beam+Slab) +2.70m - Scaffolding Installation 8 09-Sep-16 19-Sep-16 1
XAC03-32201342 1st Floor (SWGR) (Beam+Slab) +2.70m - Install Reinforcement 10 19-Sep-16 30-Sep-16 1
XAC03-32201343 1st Floor (SWGR) (Beam+Slab) +2.70m - Install side formwork 10 19-Sep-16 30-Sep-16 1
XAC03-32201344 1st Floor (SWGR) (Beam+Slab) +2.70m - Casting concrete 1 30-Sep-16 01-Oct-16 1
XAC03-3220134B 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Survey Marking 1 01-Oct-16 03-Oct-16 1
XAC03-3220134C 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Scaffolding Installation 2 03-Oct-16 05-Oct-16 1
XAC03-32201345 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Install Reinforcement 7 06-Oct-16 14-Oct-16 1
XAC03-32201346 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Install side formwork 7 06-Oct-16 14-Oct-16 1
XAC03-32201347 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - Casting concrete 1 14-Oct-16 15-Oct-16 1
XAC03-3220134A 1st Floor (SWGR) (Beam+Slab) +2.70m - Column at 1st Floor - SWGR Room - H/O to 0 09-Dec-16 67
Mech
03PMS-BL00.3.2.2.01.3.5 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m
03PMS-BL00.3.2.2.01.3 77 15-Oct-16 12-Jan-17 29
XAC03-32201351 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Scaffolding Installation 5 15-Oct-16 21-Oct-16 1
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-32201353 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Install side formwork 8 25-Oct-16 03-Nov-16 1
XAC03-32201354 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Casting concrete 1 03-Nov-16 04-Nov-16 1
XAC03-3220135A 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Survey 1 05-Nov-16 07-Nov-16 1
Marking
XAC03-3220135B 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - 3 07-Nov-16 10-Nov-16 1
Scaffolding Installation
XAC03-32201355 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Install 5 10-Nov-16 16-Nov-16 1
Reinforcement
XAC03-32201356 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Install side 5 10-Nov-16 16-Nov-16 1
formwork
XAC03-32201357 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - Casting 3 16-Nov-16 19-Nov-16 1
concrete
XAC03-32201358 Block Wall with plastering 2F+Floor coating 12 29-Dec-16 12-Jan-17 1
XAC03-32201359 2nd Floor (Battery room,Havc) (Beam+Slab) +7.50m - Column at 2nd Floor - 0 12-Jan-17 29
Battery/HVAC Room - H/O to mech
03PMS-BL00.3.2.2.01.3.6 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m
03PMS-BL00.3.2.2.01.3 128 19-Nov-16 27-Mar-17 311
XAC03-32201361 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Scaffolding Installation 7 19-Nov-16 28-Nov-16 1
XAC03-32201362 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Install Reinforcement 10 01-Dec-16 13-Dec-16 1
XAC03-32201363 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Install side formwork 6 06-Dec-16 13-Dec-16 1
XAC03-32201364 3rd Floor (CCR,DCS,Office) (Beam+Slab) +12.00m - Casting concrete 1 13-Dec-16 14-Dec-16 1
XAC03-32202212 LV Transformer Foundation (south side) - Lean concrete 50THK 6 01-Nov-16 07-Nov-16 91
XAC03-32202213 LV Transformer Foundation (south side) - Pile cut off 8 08-Nov-16 16-Nov-16 91
XAC03-32202215 LV Transformer Foundation (south side) - Install sid e formwork 11 09-Dec-16 21-Dec-16 91
XAC03-32202216 LV Transformer Foundation (south side) - Casting c oncrete foundation 1 22-Dec-16 22-Dec-16 91
XAC03-32202222 LV Transformer Foundation (North side) - Lean concrete 50THK 6 08-Mar-17 14-Mar-17 37
XAC03-32202223 LV Transformer Foundation (North side) - Pile cut off 6 15-Mar-17 21-Mar-17 37
XAC03-32202225 LV Transformer Foundation (North side) - Install sid e formwork 10 23-Mar-17 04-Apr-17 37
XAC03-32202226 LV Transformer Foundation (North side) - Casting c oncrete foundation 1 05-Apr-17 05-Apr-17 37
03PMS-BL00.3.2.2.03 Ca
Cable Trench (E&C Building - Pipe Rack RE) 194 30-May-16 07-Jan-17 5
XAC03-32203210 Cable Trench (E&C Bldg. - Pipe Rack RE) - Excavation 3 21-Nov-16* 23-Nov-16 5
XAC03-32203220 Cable Trench (E&C Bldg. - Pipe Rack RE) - Lean concrete 2 24-Nov-16 25-Nov-16 5
XAC03-32203230 Cable Trench (E&C Bldg. - Pipe Rack RE) - Pile cut off 3 26-Nov-16 29-Nov-16 5
XAC03-32203240 Cable Trench (E&C Bldg. - Pipe Rack RE) - Slab - Install Reinforcement 3 30-Nov-16 02-Dec-16 5
XAC03-32203250 Cable Trench (E&C Bldg. - Pipe Rack RE) - Slab - Install side formwork 3 03-Dec-16 06-Dec-16 5
XAC03-32203260 Cable Trench (E&C Bldg. - Pipe Rack RE) - Casting concrete 1 07-Dec-16 07-Dec-16 5
XAC03-32203270 Cable Trench (E&C Bldg. - Pipe Rack RE) - Wall - Install Reinforcement 7 12-Dec-16 20-Dec-16 5
XAC03-32203280 Cable Trench (E&C Bldg. - Pipe Rack RE) - Wall - Install side formwork 2 21-Dec-16 22-Dec-16 5
XAC03-32203290 Cable Trench (E&C Bldg. - Pipe Rack RE) - Wall - Casting concrete 1 23-Dec-16 23-Dec-16 5
XAC03-322032A0 Cable Trench (E&C Bldg. - Pipe Rack RE) - Backfill 3 04-Jan-17 07-Jan-17 5
XAC03-322032B0 Cable Trench (E&C Bldg. - Pipe Rack RE) - H/O to Mech 0 07-Jan-17 5
03PMS-BL00.3.2.2.04 Pip
Pipe Sleeper E&C Building Area 131 22-Dec-16 01-May-17 43
XAC03-32204110 Pipe Sleeper (E&C Bldg.) - East Side - LV Trans. Drain Pit 19 22-Dec-16 18-Jan-17 75
XAC03-32204130 Pipe Sleeper (E&C Bldg.) - East Side -H/O to Mech 0 18-Jan-17 91
XAC03-32204120 Pipe Sleeper (E&C Bldg.) - North Side - LV Trans. Drain Pit 19 05-Apr-17 01-May-17 31
XAC03-32204140 Pipe Sleeper (E&C Bldg.) - North Side -H/O to Mech 0 01-May-17 37
03PMS-BL00.3.2.2.ZZ O
Other Civil Work 225 03-Oct-16 16-May-17 261
XAC03-322ZZ100 Civil (E&C Bldg Area) - South Side - LV Trans. Drain Pit 37 03-Oct-16* 23-Nov-16 108
XAC03-322ZZ400 Civil (E&C Bldg Area) - South Side - LV Trans. Drain Pit - H/O to Mech 0 01-Dec-16 131
XAC03-322ZZ300 Civil (E&C Bldg Area) - North Side - LV Trans. Drain Pit 38 14-Feb-17* 06-Apr-17 204
XAC03-322ZZ200 Civil (E&C Bldg Area) - Septic Tank and Sanitary System 54 01-Mar-17* 16-May-17 187
XAC03-322ZZ600 Civil (E&C Bldg Area) - North Side - LV Trans. Drain Pit - H/O to Mech 0 21-Apr-17 248
XAC03-322ZZ500 Civil (E&C Bldg Area) - Septic Tank and Sanitary System - H/O to Mech 0 16-May-17 226
03PMS-BL00.3.2.3.01 Ga
Gas Turbine / Generator #31 143 13-May-16 03-Oct-16 177
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-3230121F Foundation/Pedestal - Epoxy Injection under steel plate 3 23-Sep-16 26-Sep-16 101
03PMS-BL00.3.2.3.02 Ga
Gas Turbine / Generator #32 178 27-May-16 21-Nov-16 108
XAC03-3230221E Foundation/Pedestal - Epoxy Injection under steel plate 5 14-Oct-16 19-Oct-16 120
03PMS-BL00.3.2.3.03 HRSG
HR #31 / BDTP #31 167 27-Apr-16 12-Oct-16 478
XAC03-3230321H Blowdown Tank Pit #31 Foundatio n - H/O to Mech 0 08-Aug-16 136
XAC03-32303226 Stack - Install embedded material (Erection company scope) 7 03-Aug-16 10-Aug-16 29
XAC03-32303229 Foundation HRSG 31 - Install embedded material (Erection company scope) 7 03-Sep-16 10-Sep-16 31
03PMS-BL00.3.2.3.04 HRSG
HR #32 / BDTP #32 164 10-May-16 20-Oct-16 469
XAC03-3230421G Remove Formwork and Repairing concrete surface 5 23-Jul-16 28-Jul-16 134
XAC03-3230421K Water leak test, Monitoring and Repairing 7 29-Jul-16 05-Aug-16 134
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-3230421I Blowdown Tank Pit #32 Foundatio n - H/O to Mech 0 18-Aug-16 111
XAC03-332031490 Stack - Excavation, Lean and pile cutting 21 21-Jul-16* 13-Aug-16 104
XAC03-32304226 Stack - Install embedded material (Erection company scope) 7 15-Aug-16 22-Aug-16 104
XAC03-32304229 Foundation HRSG 32 - Install embedded material (Erection company scope) 15 13-Sep-16 29-Sep-16 80
03PMS-BL00.3.2.3.05 Deaerator/
De BFP #3 283 06-Jun-16 15-Mar-17 46
XAC03-32305250 Base Slab - Install embeded material and pocket 4 11-Oct-16 14-Oct-16 130
03PMS-BL00.3.2.3.06 CEMS
CE #3 34 18-Jan-17 25-Feb-17 69
03PMS-BL00.3.2.3.07 HR
HRSG Chemical Dosing Skid #3 81 05-Apr-17 06-Jul-17 33
03PMS-BL00.3.2.3.08 Sa
Sampling Rack #3 25 01-Oct-16 29-Oct-16 247
03PMS-BL00.3.2.3.09 HR
HRSG Local Control Building 44 30-Jan-17 14-Mar-17 52
03PMS-BL00.3.2.3.10 Fu
Fuel Gas Filter Foundation #3 13 21-Oct-16 05-Nov-16 392
XAC03-32310210 Fuel Gas Fillter - Foundation Work #31 7 21-Oct-16 29-Oct-16 137
XAC03-32310220 Fuel Gas Fillter - Foundation Work #32 7 28-Oct-16 05-Nov-16 137
XAC03-32310240 Foundation Work - H/O to Mech - Fuel Gas Fillter #31 0 29-Oct-16 398
XAC03-32310230 Foundation Work - H/O to Mech - Fuel Gas Fillter #32 0 05-Nov-16 137
03PMS-BL00.3.2.3.11 Pipe
Pip Rack ( Main - HRSG #31,#32 Area) 262 27-Jun-16 24-Apr-17 246
XAC03-32311210 Pipe Rack (HRSG #31,#32 Area) - Slab - Install Reinforcement 9 03-Oct-16 12-Oct-16 46
XAC03-32311220 Pipe Rack (HRSG #31,#32 Area) - Slab - Install formwork 4 10-Oct-16 13-Oct-16 64
XAC03-32311230 Pipe Rack (HRSG #31,#32 Area) - Slab - Casting concrete 1 14-Oct-16 14-Oct-16 64
XAC03-32311240 Pipe Rack (HRSG #31,#32 Area) - - H/O to Mech 0 14-Oct-16 117
XAC03-32311480 Structure Work - Pipe Rack RD (HRSG 32) 20 01-Apr-17* 24-Apr-17 246
03PMS-BL00.3.2.3.12 Pipe
Pip Rack (GTG #31 Area) 256 27-Jun-16 09-Mar-17 40
XAC03-32312240 Pipe rack ( GTG#31 ) - Slab - Install Reinforcement 3 17-Sep-16 20-Sep-16 114
XAC03-32312260 Pipe rack ( GTG#31 ) - Slab - Casting concrete 1 23-Sep-16 23-Sep-16 114
XAC03-32312270 Pipe rack ( GTG#31 ) - Pedestal - Install Reinforcement 3 24-Sep-16 27-Sep-16 114
XAC03-32312280 Pipe rack ( GTG#31 ) - Pedestal - Install anchor bolt 1 28-Sep-16 28-Sep-16 114
XAC03-32312290 Pipe rack ( GTG#31 ) - Pedestal - Install formwork 3 29-Sep-16 01-Oct-16 114
XAC03-323122A0 Pipe rack ( GTG#31 ) - Pedestal - Casting concrete 1 03-Oct-16 03-Oct-16 114
03PMS-BL00.3.2.3.13 Pipe
Pip Rack (GTG #32 Area) 89 22-Nov-16 04-Mar-17 15
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-32313280 Pipe rack ( GTG#32 ) - Pedestal - Install anchor bolt 2 20-Dec-16 21-Dec-16 49
03PMS-BL00.3.2.3.14 Cable
Ca Trench (GTG #31 Area) 33.00m 31 18-Aug-16 22-Sep-16 97
XAC03-32314510 Cable Trench (GTG 31 area ) - Excavation (Open cut) 2 18-Aug-16* 19-Aug-16 72
XAC03-32314530 Cable Trench (GTG 31 area ) - Pile cut off 3 23-Aug-16 25-Aug-16 72
XAC03-32314550 Cable Trench (GTG 31 area ) - Slab - Install Reinforcement 3 26-Aug-16 29-Aug-16 72
XAC03-32314540 Cable Trench (GTG 31 area ) - Slab - Install side formwork 5 30-Aug-16 03-Sep-16 72
XAC03-32314580 Cable Trench (GTG 31 area ) - Wall - Install side formwork 9 02-Sep-16 13-Sep-16 72
XAC03-32314570 Cable Trench (GTG 31 area ) - Wall - Install Reinforcement 8 06-Sep-16 14-Sep-16 72
XAC03-32314590 Cable Trench (GTG 31 area ) - Wall - Casting concrete 1 14-Sep-16 14-Sep-16 72
03PMS-BL00.3.2.3.15 Cable
Ca Trench (GTG #32 Area) 33.00m 41 12-Oct-16 28-Nov-16 122
XAC03-32315510 Cable Trench (GTG 32 area ) - Excavation (Open cut) 3 12-Oct-16* 14-Oct-16 49
XAC03-32315530 Cable Trench (GTG 32 area ) - Pile cut off 3 17-Oct-16 19-Oct-16 49
XAC03-32315540 Cable Trench (GTG 32 area ) - Slab - Install Reinforcement 3 20-Oct-16 22-Oct-16 49
XAC03-32315550 Cable Trench (GTG 32 area ) - Slab - Install side formwork 3 24-Oct-16 26-Oct-16 49
XAC03-32315560 Cable Trench (GTG 32 area ) - Slab - Casting concrete 1 27-Oct-16 27-Oct-16 49
XAC03-32315570 Cable Trench (GTG 32 area ) - Wall - Install Reinforcement 9 28-Oct-16 07-Nov-16 49
XAC03-32315580 Cable Trench (GTG 32 area ) - Wall - Install side formwork 9 08-Nov-16 17-Nov-16 49
XAC03-32315590 Cable Trench (GTG 32 area ) - Wall - Casting concrete 1 18-Nov-16 18-Nov-16 49
03PMS-BL00.3.2.3.16 Ca
Cable Trench (Road Crossing GTG 31 - SWYD ) 33.00 m. 59 01-Dec-16 28-Jan-17 79
XAC03-32316510 Cable Trench (Road Crossing GTG 31 - SWYD ) - Excavation (Open cut) 3 01-Dec-16* 03-Dec-16 67
XAC03-32316520 Cable Trench (Road Crossing GTG 31 - SWYD ) -Lean concrete 1 05-Dec-16 05-Dec-16 67
XAC03-32316530 Cable Trench (Road Crossing GTG 31 - SWYD ) - Pile cut off 3 06-Dec-16 08-Dec-16 67
XAC03-32316540 Cable Trench (Road Crossing GTG 31 - SWYD ) - Slab - Install Reinforcement 3 09-Dec-16 12-Dec-16 67
XAC03-32316550 Cable Trench (Road Crossing GTG 31 - SWYD ) - Slab - Install side formwork 3 13-Dec-16 15-Dec-16 67
XAC03-32316560 Cable Trench (Road Crossing GTG 31 - SWYD ) - Slab - Casting concrete 1 16-Dec-16 16-Dec-16 67
XAC03-32316570 Cable Trench (Road Crossing GTG 31 - SWYD ) - Wall - Install Reinforcement 16 17-Dec-16 04-Jan-17 67
XAC03-32316580 Cable Trench (Road Crossing GTG 31 - SWYD ) - Wall - Install side formwork 1 05-Jan-17 05-Jan-17 67
XAC03-32316590 Cable Trench (Road Crossing GTG 31 - SWYD ) - Wall - Casting concrete 1 06-Jan-17 06-Jan-17 67
XAC03-323165C0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Top - Install Scaffolding and 7 07-Jan-17 14-Jan-17 67
formwork
XAC03-323165D0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Top - Install Reinforcement and side 5 15-Jan-17 19-Jan-17 78
formwork
XAC03-323165E0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Top - Casting concrete 1 20-Jan-17 20-Jan-17 68
XAC03-323165A0 Cable Trench (Road Crossing GTG 31 - SWYD ) - Backfill 7 21-Jan-17 28-Jan-17 68
XAC03-323165B0 Cable Trench (Road Crossing GTG 31 - SWYD ) - H/O to Mech 0 28-Jan-17 68
03PMS-BL00.3.2.3.17 Ca
Cable Trench (Road Crossing GTG 32 - SWYD 2) 33.00 m. 111 02-Feb-17 09-Jun-17 205
XAC03-32317510 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Excavation (Open cut) 8 02-Feb-17* 10-Feb-17 205
XAC03-32317520 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Lean concrete 4 11-Feb-17 15-Feb-17 205
XAC03-32317530 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Pile cut off 6 16-Feb-17 22-Feb-17 205
XAC03-32317540 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Slab - Install Reinforcement 6 23-Feb-17 01-Mar-17 205
XAC03-32317550 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Slab - Install side formwork 6 02-Mar-17 08-Mar-17 205
XAC03-32317560 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Slab - Casting concrete 4 09-Mar-17 13-Mar-17 205
XAC03-32317570 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Wall - Install Reinforcement 14 14-Mar-17 29-Mar-17 205
XAC03-32317580 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Wall - Install side formwork 20 30-Mar-17 21-Apr-17 205
XAC03-32317590 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Wall - Casting concrete 4 22-Apr-17 26-Apr-17 205
XAC03-323175C0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Top - Install Scaffolding and 12 27-Apr-17 10-May-17 205
formwork
XAC03-323175D0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Top - Install Reinforcement and 10 11-May-17 22-May-17 205
side formwork
XAC03-323175E0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Top - Casting concrete 4 23-May-17 26-May-17 205
XAC03-323175A0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - Backfill 12 27-May-17 09-Jun-17 205
XAC03-323175B0 Cable Trench (Road Crossing GTG 32 - SWYD 2) - H/O to Mech 0 09-Jun-17 205
03PMS-BL00.3.2.3.18 Ca
Cable Trench (Road Crossing GTG 32 - E&C Building ) 33.00 m. 61 01-Dec-16 30-Jan-17 367
XAC03-32318510 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Excavation (Open cut) 3 01-Dec-16* 03-Dec-16 91
XAC03-32318520 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Lean concrete 1 05-Dec-16 05-Dec-16 318
XAC03-32318530 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Pile cut off 3 06-Dec-16 08-Dec-16 318
XAC03-32318540 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install Reinforcement 3 09-Dec-16 12-Dec-16 318
XAC03-32318550 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install side formwork 3 13-Dec-16 15-Dec-16 318
XAC03-32318560 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Casting concrete 1 16-Dec-16 16-Dec-16 318
XAC03-32318570 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install Reinforcement 16 17-Dec-16 04-Jan-17 318
XAC03-32318580 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install side formwork 2 05-Jan-17 06-Jan-17 318
XAC03-32318590 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Casting concrete 1 07-Jan-17 07-Jan-17 318
XAC03-323185C0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Top - Install Scaffolding and 7 09-Jan-17 15-Jan-17 367
formwork
XAC03-323185D0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Top - Install Reinforcement 5 16-Jan-17 20-Jan-17 318
and side formwork
XAC03-323185E0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Top - Casting concrete 1 21-Jan-17 21-Jan-17 318
XAC03-323185A0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Backfill 7 23-Jan-17 30-Jan-17 318
XAC03-323185B0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - H/O to Mech 0 30-Jan-17 318
03PMS-BL00.3.2.3.19 Ca
Cable Trench (Road Crossing STG #30 - SWYD) 33.00 m. 29 05-Dec-16 03-Jan-17 105
XAC03-32319510 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Excavation (Open cut) 3 05-Dec-16* 07-Dec-16 75
XAC03-32319520 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Lean concrete 1 08-Dec-16 08-Dec-16 91
XAC03-32319530 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Pile cut off 3 09-Dec-16 12-Dec-16 91
XAC03-32319540 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install Reinforcement 3 13-Dec-16 16-Dec-16 91
XAC03-32319550 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Slab - Install side formwork 3 13-Dec-16 16-Dec-16 91
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-32319570 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install Reinforcement 9 17-Dec-16 28-Dec-16 91
XAC03-32319580 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Install side formwork 9 20-Dec-16 30-Dec-16 91
XAC03-32319590 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Wall - Casting concrete 1 30-Dec-16 31-Dec-16 91
XAC03-323195A0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - Backfill 2 31-Dec-16 03-Jan-17 91
XAC03-323195B0 Cable Trench (Road Crossing GTG 32 - E&C Building ) - H/O to Mech 0 03-Jan-17 91
03PMS-BL00.3.2.3.20 Pip
Pipe Sleeper (HRSG #31 & #32 Area) 18 02-Mar-17 22-Mar-17 71
03PMS-BL00.3.2.3.21 Emergency
Em Diesel Generator 22 09-Jan-17 30-Jan-17 123
03PMS-BL00.3.2.3.22 E&C
E& - EDG Pipe Sleeper 14 01-Mar-17 16-Mar-17 80
03PMS-BL00.3.2.3.23 Fu
Fuel Gas Heater Foundation 8 04-Nov-16 12-Nov-16 223
XAC03-32323220 Foundation Work - H/O to Mech - Fuel Gas Heater 0 12-Nov-16 193
03PMS-BL00.3.2.3.24 Pip
Pipe Rack RE 168 27-Jun-16 05-Jan-17 60
03PMS-BL00.3.2.3.ZZ O
Other Civil Work 175 28-Sep-16 22-Mar-17 72
XAC03-323ZZ111 Water Wash Pit #31 - GT Water Wash Pit Work 15 28-Sep-16 13-Oct-16 151
XAC03-323ZZ112 Water Wash Pit #31 - Chemical Coating 5 14-Oct-16 20-Oct-16 141
XAC03-323ZZ121 Water Wash Pit #32 - GT Water Wash Pit Work 14 10-Oct-16 25-Oct-16 131
XAC03-323ZZ122 Water Wash Pit #32 - Chemical Coating 6 26-Oct-16 01-Nov-16 131
03PMS-BL00.3.2.4.01 Water
Wa Treatment System 234 20-Jun-16 08-Feb-17 358
XAC03-32401217 WTP Shed plint - Install side formwork 25 28-Sep-16 26-Oct-16 400
XAC03-3240121G WTP Shed Column - Group 1 - Install side formwork 5 14-Oct-16 19-Oct-16 52
XAC03-3240121I WTP Shed Column - Group 1 - Casting concrete foundation 1 20-Oct-16 20-Oct-16 52
XAC03-3240121J WTP Shed Column - Group 2 - Install side formwork 5 26-Oct-16 31-Oct-16 47
XAC03-3240121D WTP Shed plint - Casting concrete foundation 1 27-Oct-16 27-Oct-16 400
XAC03-3240121K WTP Shed Column - Group 2 - Casting concrete foundation 1 01-Nov-16 01-Nov-16 47
XAC03-32401219 WTP Shed wall - Install side formwork 7 08-Nov-16 15-Nov-16 110
XAC03-3240121E WTP Shed wall - Casting concrete foundation 1 16-Nov-16 16-Nov-16 110
XAC03-32401228 Wall - Install embedded material (Pipe N1-N6 Supply and Install by M&E) 2 29-Sep-16 30-Sep-16 98
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.2.4.01.2.3 Neutralization
03PMS-BL00.3.2.4.01.2 107 04-Oct-16 03-Feb-17 52
XAC03-32401241 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Excavation 2 31-Aug-16* 01-Sep-16 72
XAC03-32401242 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Lean Concrete 1 02-Sep-16 02-Sep-16 72
XAC03-32401243 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Pile Cut off 1 03-Sep-16 03-Sep-16 72
XAC03-32401244 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Install Reinforcement 5 05-Sep-16 09-Sep-16 72
XAC03-32401245 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Install formwork 4 10-Sep-16 14-Sep-16 72
XAC03-32401246 1st Floor-WTP Belt Press Shed FND+Tie beam -0.20 m - Casting concrete 1 15-Sep-16 15-Sep-16 72
XAC03-32401247 WTP Belt Press Shed Column 1st floor - Scafolding installation 5 16-Sep-16 21-Sep-16 72
XAC03-32401248 WTP Belt Press Shed Column 1st floor - Install Reinforcement 6 22-Sep-16 28-Sep-16 72
XAC03-32401249 WTP Belt Press Shed Column 1st floor - Install formwork 3 27-Sep-16 30-Sep-16 83
XAC03-3240124A WTP Belt Press Shed Column 1st floor - Casting concrete 1 01-Oct-16 01-Oct-16 72
XAC03-3240124B 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Scafolding installation 7 03-Oct-16 10-Oct-16 72
XAC03-3240124D 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Install Reinforcement 6 11-Oct-16 17-Oct-16 72
XAC03-3240124C 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Install formwork 7 13-Oct-16 20-Oct-16 72
XAC03-3240124F 2nd Floor + 5.80m - WTP Belt Press Shed (Beam+Slab) - Casting concrete 1 21-Oct-16 21-Oct-16 72
XAC03-3240124I WTP Belt Press Shed Column 2nd floor - Scafolding installation 2 24-Oct-16 25-Oct-16 72
XAC03-3240124G WTP Belt Press Shed Column 2nd floor - Install Reinforcement 5 26-Oct-16 31-Oct-16 72
XAC03-3240124H WTP Belt Press Shed Column 2nd floor - Install formwork 6 01-Nov-16 07-Nov-16 72
XAC03-3240124J WTP Belt Press Shed Column 2nd floor - Casting concrete 1 08-Nov-16 08-Nov-16 72
XAC03-3240124K WTP Belt Press Shed Roof Beam - Scafolding installation 7 09-Nov-16 16-Nov-16 72
XAC03-3240124L WTP Belt Press Shed Roof Beam - Install Reinforcement 5 17-Nov-16 22-Nov-16 72
XAC03-3240124M WTP Belt Press Shed Roof Beam - Install formwork 3 21-Nov-16 24-Nov-16 72
XAC03-3240124N WTP Belt Press Shed Roof Beam - Casting concrete 1 25-Nov-16 25-Nov-16 72
XAC03-3240124O WTP Belt Press Shed Stair - Scafolding installation 7 26-Nov-16 03-Dec-16 72
XAC03-3240124P WTP Belt Press Shed Roof Structure 22 26-Nov-16 22-Dec-16 353
XAC03-3240124Q WTP Belt Press Shed Stair - Install Reinforcement 7 05-Dec-16 12-Dec-16 72
XAC03-3240124R WTP Belt Press Shed Stair - Install formwork 7 13-Dec-16 20-Dec-16 72
XAC03-3240124S WTP Belt Press Shed Stair - Casting concrete 1 21-Dec-16 21-Dec-16 72
XAC03-32401255 Base Slab - Slab - Install side formwork 5 12-Sep-16 16-Sep-16 102
XAC03-32401257 Base Slab - Slab - Concrete work - Casting concrete foundation 1 17-Sep-16 17-Sep-16 102
XAC03-3240125A Base Slab - Wall - Install side formwork 7 01-Oct-16 08-Oct-16 102
XAC03-3240125C Base Slab - Wall - Casting concrete foundation 4 10-Oct-16 13-Oct-16 102
XAC03-32401256 Sludge Thickner - Leak test and finishing 20 01-Nov-16 23-Nov-16 102
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.2.4.01.2.7 Clarifier
03PMS-BL00.3.2.4.01.2 162 01-Jul-16 09-Dec-16 102
XAC03-3240127A Clarifier Wall -Slab - Install Reinforcement and scaffolding 7 12-Oct-16 19-Oct-16 88
XAC03-324012Z5 Foundation for Backwash / RO Feed / Regeneration Pump - H/O to Mech 0 20-Dec-16 79
XAC03-324012Z4 Foundation for Filtering / Clarifier water / Belt Press Washing Pump 6 03-Jan-17 10-Jan-17 78
XAC03-324012Z8 Foundation for Filtering / Clarifier water / Belt Press Washing Pump - H/O to Mech 0 10-Jan-17 64
03PMS-BL00.3.2.4.02 Fir
Fire Fighting Pump Station 49 09-Nov-16 03-Jan-17 63
XAC03-32402240 Fire Fighting Shed Foundation (Footing+Tie Beam+Slab) - Install Reinforcement 10 12-Nov-16 23-Nov-16 56
XAC03-32402250 Fire Fighting Shed Foundation (Footing+Tie Beam+Slab) - Install formwork 6 17-Nov-16 23-Nov-16 56
XAC03-32402260 Fire Fighting Shed Foundation (Footing+Tie Beam+Slab) - Casting concrete 1 24-Nov-16 24-Nov-16 56
XAC03-32402270 Fire Fighting Shed concrete plinth - Install Reinforcement 3 25-Nov-16 28-Nov-16 65
XAC03-32402280 Fire Fighting Shed concrete plinth - Install formwork 2 26-Nov-16 28-Nov-16 65
XAC03-32402290 Fire Fighting Shed concrete plinth - Casting concrete 1 29-Nov-16 29-Nov-16 65
03PMS-BL00.3.2.5.01 Cooling
Co Tower #3 301 08-Jun-16 04-Apr-17 303
XAC03-32501215 Foundation Work - Install side formwork & Water Stop 5 13-Aug-16 18-Aug-16 30
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-325012CB Roof Slab Zone 1 - Remove Scaffolding and formwork 7 11-Feb-17 18-Feb-17 287
XAC03-325012CC Roof Slab Zone 1 - Repair concrete inside 14 20-Feb-17 07-Mar-17 287
XAC03-325012CD Roof Slab Zone 2 - Remove Scaffolding and formwork 7 20-Feb-17 27-Feb-17 30
XAC03-325012E6 Over flow guter - Remove inside formwork & Repair concrete 14 22-Feb-17 09-Mar-17 285
03PMS-BL00.3.2.5.02 Re
Retention/Emergency (Pit & Pump Foundation) 211 20-Jun-16 16-Jan-17 381
XAC03-32502215 Base Slab - Slab - Install side formwork 13 30-Sep-16 15-Oct-16 131
XAC03-32502216 Base Slab - Slab - Casting concrete foundation 1 17-Oct-16 17-Oct-16 131
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.2.5.04 MC
MCWP #3 Foundation 162 20-Jun-16 28-Nov-16 141
03PMS-BL00.3.2.5.05 MCW
MC Pipe Sleeper FDN (CT #3 Area) 72 07-Nov-16 17-Jan-17 71
XAC03-32505240 CW Sleeper Foundation - Base Slab - Slab - Install Reinforcement 7 21-Nov-16 28-Nov-16 62
XAC03-32505250 CW Sleeper Foundation - Base Slab - Slab - Install formwork 6 29-Nov-16 05-Dec-16 62
XAC03-32505260 CW Sleeper Foundation - Base Slab - Slab - Casting concrete foundation 1 06-Dec-16 06-Dec-16 62
XAC03-32505270 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Install Reinforcement 7 07-Dec-16 14-Dec-16 62
XAC03-32505280 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Install side formwork 7 15-Dec-16 22-Dec-16 62
XAC03-32505290 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Casting concrete 1 23-Dec-16 23-Dec-16 62
XAC03-325052A0 CW Sleeper Foundation - Concrete plint P5, P5 + wall - Remove formwork 12 24-Dec-16 06-Jan-17 62
03PMS-BL00.3.2.5.06 Instrument
Ins Air System 63 30-Nov-16 31-Jan-17 307
03PMS-BL00.3.2.5.06.2 Compressor Shed/ Receiver Tank Foundation Work 37 30-Nov-16 05-Jan-17 102
XAC03-32506220 Compressor Shed/ Receiver Tank Foundation Work - H/O to Mech 0 05-Jan-17 72
03PMS-BL00.3.2.5.08 Oi
Oily Water Separator 184 27-Jun-16 24-Jan-17 112
XAC03-32508260 Base Slab - Casting concrete foundation (slab) 1 18-Nov-16 18-Nov-16 112
03PMS-BL00.3.2.5.10 Au
Auxiliary Cooling Water System 23 01-Oct-16 24-Oct-16 157
XAC03-32510210 AUX Cooling Water System - Pump Foundation 10 01-Oct-16* 12-Oct-16 137
XAC03-32510220 AUX Cooling Water System - Pipe Supoort Foundation 9 13-Oct-16 22-Oct-16 137
03PMS-BL00.3.2.6.01 Service
Se Water System 138 28-May-16 12-Oct-16 160
XAC03-32601230 Service Water Tank - Foundation - Pile Cut off 6 28-Jun-16 04-Jul-16 70
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.2.6.04 Pip
Pipe Trench (Tank - Fire Fighting Pump Station) 157 20-Jun-16 23-Nov-16 81
XAC03-32604220 Pipe Trench (Tank - FF Pump Sta.) - Lean concrete 1 25-Aug-16 26-Aug-16 70
XAC03-32604230 Pipe Trench (Tank - FF Pump Sta.) - Slab - Install Reinforcement 6 27-Aug-16 02-Sep-16 70
XAC03-32604240 Pipe Trench (Tank - FF Pump Sta.) - Slab - Install side formwork 6 03-Sep-16 09-Sep-16 70
XAC03-32604250 Pipe Trench (Tank - FF Pump Sta.) - Slab - Casting concrete 6 10-Sep-16 16-Sep-16 70
XAC03-32604260 Pipe Trench (Tank - FF Pump Sta.) - Wall - Install Reinforcement 12 17-Sep-16 30-Sep-16 70
XAC03-32604270 Pipe Trench (Tank - FF Pump Sta.) - Wall - Install side formwork 6 01-Oct-16 07-Oct-16 70
XAC03-32604280 Pipe Trench (Tank - FF Pump Sta.) - Wall - Casting concrete 1 08-Oct-16 08-Oct-16 70
XAC03-32604290 Pipe Trench (Tank - FF Pump Sta.) - Top Slab - Install Reinforcement 12 10-Oct-16 22-Oct-16 70
XAC03-326042A0 Pipe Trench (Tank - FF Pump Sta.) - Top Slab - Install side formwork 6 24-Oct-16 29-Oct-16 70
XAC03-326042B0 Pipe Trench (Tank - FF Pump Sta.) - Top Slab - Casting concrete 1 31-Oct-16 31-Oct-16 70
03PMS-BL00.3.2.6.05 Pipe
Pip Trench (Tank - WTP) 164 30-Jul-16 04-Feb-17 82
XAC03-32605230 Pipe Trench (Tank - WTP) - Slab - Install Reinforcement 6 05-Nov-16 11-Nov-16 82
XAC03-32605240 Pipe Trench (Tank - WTP) - Slab - Install side formwork 6 12-Nov-16 18-Nov-16 82
XAC03-32605250 Pipe Trench (Tank - WTP) - Slab - Casting concrete 1 19-Nov-16 19-Nov-16 82
XAC03-32605260 Pipe Trench (Tank - WTP) - Wall - Install Reinforcement 12 21-Nov-16 03-Dec-16 82
XAC03-32605270 Pipe Trench (Tank - WTP) - Wall - Install side formwork 6 05-Dec-16 10-Dec-16 82
XAC03-32605280 Pipe Trench (Tank - WTP) - Wall - Casting concrete 1 12-Dec-16 12-Dec-16 82
XAC03-32605290 Pipe Trench (Tank - WTP) - Top Slab - Install Reinforcement 19 13-Dec-16 03-Jan-17 82
XAC03-326052A0 Pipe Trench (Tank - WTP) - Top Slab - Install side formwork 6 04-Jan-17 10-Jan-17 82
XAC03-326052B0 Pipe Trench (Tank - WTP) - Top Slab - Casting concrete 1 11-Jan-17 11-Jan-17 82
03PMS-BL00.3.2.6.06 Pipe
Pip Sleeper (Tank Area) 23 02-Mar-17 24-Mar-17 70
XAC03-32606610 Civil (Tank Area) - Pipe Sleeper (Tank Area) 20 02-Mar-17* 24-Mar-17 61
XAC03-32606620 Civil (Tank Area) - Pipe Sleeper (Tank Area) - H/O to Mech 0 24-Mar-17 50
03PMS-BL00.3.2.7.01 GSUT
GS #31 & #32 & ST #30 & Unit Aux. #31 & #32 Transformer 254 06-Jun-16 14-Feb-17 352
XAC03-32701110 Pile Work - GTG#31 / 32 / ST / UAT Tr. Pile Work 9 06-Jun-16* 16-Jun-16 126
XAC03-32701212 Foundation Work - Base slab - Lean concrete 5 05-Aug-16 10-Aug-16 113
XAC03-32701213 Foundation Work - Base slab - Pile cut off 7 06-Aug-16 13-Aug-16 113
XAC03-32701214 Foundation Work - Base slab - Repair PC piles and Dowel 2 13-Aug-16 16-Aug-16 113
XAC03-32701215 Foundation Work - Base slab - Rebar work 10 17-Aug-16 27-Aug-16 113
XAC03-32701218 Foundation Work - Base slab - Concrete base slab 1 31-Aug-16 31-Aug-16 113
XAC03-32701222 GTG GSUT Unit 1 - Wall - Rebar work 4 03-Sep-16 07-Sep-16 130
XAC03-32701224 GTG GSUT Unit 1 - Wall - Concrete wall 1 15-Sep-16 15-Sep-16 130
XAC03-32701225 GTG GSUT Unit 1 - Wall - Remove formwork and repair concrete 3 16-Sep-16 19-Sep-16 130
XAC03-32701226 GTG GSUT Unit 1 - Pedestal and kerb- Rebar work 3 17-Sep-16 20-Sep-16 147
XAC03-32701227 GTG GSUT Unit 1 - Pedestal and kerb - Formwork 4 21-Sep-16 24-Sep-16 147
XAC03-32701228 GTG GSUT Unit 1 - Pedestal and kerb - concrete 1 26-Sep-16 26-Sep-16 147
XAC03-32701232 GTG GSUT Unit 2 - Wall - Rebar work 4 07-Sep-16 10-Sep-16 142
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-32701234 GTG GSUT Unit 2 - Wall - Concrete wall 1 19-Sep-16 19-Sep-16 142
XAC03-32701235 GTG GSUT Unit 2 - Wall - Remove formwork and repair concrete 5 20-Sep-16 24-Sep-16 142
XAC03-32701236 GTG GSUT Unit 2 - Pedestal and kerb- Rebar work 2 23-Sep-16 26-Sep-16 142
XAC03-32701237 GTG GSUT Unit 2 - Pedestal and kerb - Formwork 4 27-Sep-16 30-Sep-16 142
XAC03-32701238 GTG GSUT Unit 2 - Pedestal and kerb - concrete 1 01-Oct-16 01-Oct-16 142
XAC03-32701245 STG GSUT - Wall - Remove formwork and repair concrete 3 04-Oct-16 06-Oct-16 130
XAC03-32701246 STG GSUT - Pedestal and kerb- Rebar work 3 07-Oct-16 10-Oct-16 130
XAC03-32701247 STG GSUT - Pedestal and kerb - Formwork 4 11-Oct-16 14-Oct-16 130
XAC03-32701248 STG GSUT - Pedestal and kerb - concrete 1 15-Oct-16 15-Oct-16 130
XAC03-32701255 UAT Unit 1 - Wall - Remove formwork and repair concrete 3 28-Sep-16 30-Sep-16 113
XAC03-32701256 UAT Unit 1 - Pedestal and kerb- Rebar work 3 01-Oct-16 04-Oct-16 113
XAC03-32701257 UAT Unit 1 - Pedestal and kerb - Formwork 4 05-Oct-16 08-Oct-16 113
XAC03-32701258 UAT Unit 1 - Pedestal and kerb - concrete 1 10-Oct-16 10-Oct-16 113
XAC03-32701261 UAT Unit 2 - Pedestal and kerb- Rebar work 3 11-Oct-16 13-Oct-16 113
XAC03-32701262 UAT Unit 2 - Pedestal and kerb - Formwork 3 14-Oct-16 17-Oct-16 113
XAC03-32701263 UAT Unit 2 - Pedestal and kerb - concrete 1 18-Oct-16 18-Oct-16 113
XAC03-32701273 Oil Drain Pit - Base slab - Rebar work 5 20-Jun-16 24-Jun-16 196
XAC03-32701274 Oil Drain Pit - Base slab - Formwork and water stop 3 25-Jun-16 28-Jun-16 196
XAC03-32701275 Oil Drain Pit - Base slab - Concrete base slab 1 29-Jun-16 29-Jun-16 196
XAC03-32701277 Oil Drain Pit - Wall - Rebar work 4 02-Jul-16 06-Jul-16 196
XAC03-32701278 Oil Drain Pit - Wall - Formwork and Embedded 7 07-Jul-16 14-Jul-16 196
XAC03-32701279 Oil Drain Pit - Wall - Concrete wall 1 15-Jul-16 15-Jul-16 196
XAC03-3270127A Oil Drain Pit - Wall - Remove formwork and repai concrete 2 16-Jul-16 18-Jul-16 196
XAC03-3270127B Oil Drain Pit - Wall - Water Leak test and repairing 10 19-Jul-16 29-Jul-16 196
03PMS-BL00.3.2.7.02 Cable
Ca Trench 6 (GSU Transformer area) 42 21-Jun-16 08-Aug-16 470
XAC03-32702512 Cable Trench - First section 20 meter - Lean concrete 3 29-Jun-16 01-Jul-16 470
XAC03-32702513 Cable Trench - First section 20 meter - Base slab - Rebar work 7 02-Jul-16 09-Jul-16 470
XAC03-32702514 Cable Trench - First section 20 meter - Base slab - Formwork and water stop 6 06-Jul-16 12-Jul-16 477
XAC03-32702515 Cable Trench - First section 20 meter - Base slab - Concrete base slab 1 13-Jul-16 13-Jul-16 477
XAC03-32702516 Cable Trench - First section 20 meter - wall - Scaffolding 2 14-Jul-16 15-Jul-16 477
XAC03-32702517 Cable Trench - First section 20 meter - wall - Rebar work 5 14-Jul-16 19-Jul-16 477
XAC03-32702518 Cable Trench - First section 20 meter - wall - Formwork and Embedded 7 15-Jul-16 22-Jul-16 477
XAC03-32702519 Cable Trench - First section 20 meter - wall - Concrete wall 1 22-Jul-16 23-Jul-16 477
XAC03-3270251A Cable Trench - First section 20 meter - wall - Remove formwork and repair concrete 3 25-Jul-16 27-Jul-16 477
XAC03-3270251B Cable Trench - First section 20 meter - wall - Backfill for GSUT area 3 28-Jul-16 30-Jul-16 477
XAC03-32702521 Cable Trench - Second section 20 meter - Lean concrete 3 06-Jul-16 08-Jul-16 471
XAC03-32702522 Cable Trench - Second section 20 meter - Base slab - Rebar work 7 11-Jul-16 18-Jul-16 470
XAC03-32702523 Cable Trench - Second section 20 meter - Base slab - Formwork and water stop 6 14-Jul-16 20-Jul-16 470
XAC03-32702524 Cable Trench - Second section 20 meter - Base slab - Concrete base slab 1 21-Jul-16 21-Jul-16 470
XAC03-32702525 Cable Trench - Second section 20 meter - wall - Scaffolding 2 22-Jul-16 23-Jul-16 470
XAC03-32702526 Cable Trench - Second section 20 meter - wall - Rebar work 5 22-Jul-16 27-Jul-16 470
XAC03-32702527 Cable Trench - Second section 20 meter - wall - Formwork and Embedded 7 23-Jul-16 30-Jul-16 470
XAC03-32702528 Cable Trench - Second section 20 meter - wall - Concrete wall 1 30-Jul-16 01-Aug-16 470
XAC03-32702529 Cable Trench - Second section 20 meter - wall - Remove formwork and repair concrete 3 02-Aug-16 04-Aug-16 470
XAC03-3270252A Cable Trench - Second section 20 meter - wall - Backfill for GSUT area 3 05-Aug-16 08-Aug-16 470
03PMS-BL00.3.2.7.ZZ O
Other Civil Work 7 01-Apr-17 10-Apr-17 34
03PMS-BL00.3.2.8.01 Raw
Ra Water System 60 06-Jun-16 04-Aug-16 176
03PMS-BL00.3.2.8.02 Inspection
Ins Pit 124 08-Jun-16 10-Oct-16 249
XAC03-32802290 Wall +Column C1 (6 number) - Install embedded material 5 27-Aug-16 01-Sep-16 223
XAC03-32802280 Wall +Column C1 (6 number) - Install side formwork 7 27-Aug-16 03-Sep-16 216
XAC03-328022A0 Wall +Column C1 (6 number) - Casting concrete foundation 1 05-Sep-16 05-Sep-16 216
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-328022C0 Roof Beam (+2.275) - Wall - Install Reinforcement 4 13-Sep-16 16-Sep-16 216
XAC03-328022D0 Roof Beam (+2.275) - Wall - Install side formwork 4 17-Sep-16 21-Sep-16 216
XAC03-328022E0 Roof Beam (+2.275) - Wall - Casting concrete 1 22-Sep-16 22-Sep-16 216
03PMS-BL00.3.2.8.06 Pip
Pipe Rack RA (BOP Area Road Crossing) 95 29-Jun-16 08-Nov-16 129
03PMS-BL00.3.2.8.07 Pip
Pipe Rack RB (BOP Area Road Crossing) 106 01-Jul-16 25-Nov-16 78
03PMS-BL00.3.2.8.08 Pip
Pipe Sleeper (BOP Area) 272 01-Jul-16 30-Mar-17 40
XAC03-32808110 Sleeper FDN for Gas Metering - WTP 31 01-Jul-16* 05-Aug-16 138
XAC03-32808120 Sleeper FDN for WTP area to Tank area 18 01-Aug-16 20-Aug-16 138
XAC03-32808180 Sleeper FDN for Gas Metering - WTP - H/O to Mech 0 05-Aug-16 162
XAC03-32808190 Sleeper FDN for WTP area to Tank area - H/O to Mech 0 22-Aug-16 152
XAC03-32808140 Sleeper FDN for SWYD - Pipe Rack RA 11 01-Sep-16 14-Sep-16 143
XAC03-328081E0 Sleeper FDN for SWYD - Pipe Rack RA - H/O to Mech 0 14-Sep-16 168
XAC03-328081A0 Sleeper FDN for WTP - Retention - H/O to Mech 0 19-Sep-16 166
XAC03-32808150 Sleeper FDN for Pipe Rack RF - Retention 18 01-Nov-16* 21-Nov-16 103
XAC03-328081B0 Sleeper FDN for Pipe Rack RF - Retention - H/O to Mech 0 21-Nov-16 102
XAC03-32808170 Sleeper FDN for Retention Basin Around (Oily Separator) 9 02-Mar-17* 11-Mar-17 50
XAC03-328081C0 Sleeper FDN for Retention Basin Around (Oily Separator) - H/O to Mech 0 13-Mar-17 41
03PMS-BL00.3.2.9.2 ABPR3
ABP Zone-1 76 01-Aug-16 27-Oct-16 401
03PMS-BL00.3.2.9.2.1 ABPR3
A Equipment Foundation Zone-1 66 01-Aug-16 15-Oct-16 411
03PMS-BL00.3.2.9.2.2 ABPR3
A Cable Trench Zone-1 41 22-Aug-16 08-Oct-16 417
03PMS-BL00.3.2.9.2.3 A
ABPR3 Backfill Zone-1 18 06-Oct-16 27-Oct-16 309
03PMS-BL00.3.2.9.3 ABPR3
ABP Zone-2 76 09-Aug-16 04-Nov-16 394
03PMS-BL00.3.2.9.3.1 ABPR3
A Equipment Foundation Zone-2 66 09-Aug-16 24-Oct-16 404
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.2.9.3.3 A
ABPR3 Backfill Zone-2 18 14-Oct-16 04-Nov-16 302
03PMS-BL00.3.2.9.4 ABPR3
ABP Zone-3 76 16-Aug-16 12-Nov-16 387
03PMS-BL00.3.2.9.4.1 ABPR3
A Equipment Foundation Zone-3 66 16-Aug-16 01-Nov-16 397
03PMS-BL00.3.2.9.4.2 ABPR3
A Cable Trench Zone-3 41 07-Sep-16 25-Oct-16 403
03PMS-BL00.3.2.9.4.3 A
ABPR3 Backfill Zone-3 18 22-Oct-16 12-Nov-16 295
03PMS-BL00.3.2.9.5 ABPR3
ABP Zone-4 76 03-Sep-16 30-Nov-16 371
03PMS-BL00.3.2.9.5.1 ABPR3
A Equipment Foundation Zone-4 66 03-Sep-16 19-Nov-16 381
03PMS-BL00.3.2.9.5.2 ABPR3
A Cable Trench Zone-4 41 26-Sep-16 12-Nov-16 387
03PMS-BL00.3.2.9.5.3 A
ABPR3 Backfill Zone-4 18 10-Nov-16 30-Nov-16 258
03PMS-BL00.3.2.A.01 La
Landscape / Road / Stormwater / Soil Backfilling 361 18-Jul-16 06-Sep-17 128
XAC03-32A01210 Soil Backfilling (600mm THK) - E&C Bldg. Area 311 18-Jul-16* 11-Jul-17 178
XAC03-32A01220 Soil Backfilling (600mm THK) - Raw Water & WTP Area 207 09-Aug-16 05-Apr-17 31
XAC03-32A01230 Soil Backfilling (600mm THK) - ST & CT Area 314 06-Sep-16* 02-Sep-17 131
XAC03-32A01240 Soil Backfilling (600mm THK) - GTG & HRSG Area 225 31-Oct-16* 17-Jul-17 13
XAC03-32A01250 Soil Backfilling (600mm THK) - Switchyard Area 47 02-Dec-16* 25-Jan-17 322
XAC03-32A01260 Soil Backfilling (600mm THK) - Tank Area 57 24-Feb-17* 01-May-17 240
03PMS-BL00.3.3.1.01 Ga
Gas turbine & Generator #31 (Siemens) 368 02-Jun-16 01-Aug-17 0
XAC03-33101110 Mechanical Work - Foundation Chipping and Packer Setting 9 23-Jan-17* 01-Feb-17 0
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33101150 Mechanical Work - Remove the On Base Lifting Devise 1 11-Feb-17 11-Feb-17 0
XAC03-33101160 Mechanical Work - Gas Turbine Alignment to Center Line 2 11-Feb-17 13-Feb-17 0
XAC03-33101210 Overhead Crane - Rail Girder and Rail Installation 7 17-Mar-17 25-Mar-17 46
XAC03-33101220 Overhead Crane - Outdoor Rail and Sructure Installation 9 19-Apr-17 28-Apr-17 25
XAC03-33101240 Overhead Crane - Conduits Installaton and Cable Pulling 6 02-May-17 08-May-17 25
XAC03-33101250 Overhead Crane - Function Check and Overload Test 3 09-May-17 11-May-17 25
XAC03-33101310 Intake Air Filter System - Support Structure Installation 8 24-Mar-17 01-Apr-17 25
XAC03-33101330 Intake Air Filter System - Intake Air Filter House Assembly and Installation 13 18-Apr-17 02-May-17 27
XAC03-33101410 Water Wash and Drain System - Water Wash Equipment Installation 1 22-Apr-17 22-Apr-17 17
XAC03-33101420 Water Wash and Drain System - Water Wash Piping Installation 13 24-Apr-17 08-May-17 17
XAC03-33101430 Water Wash and Drain System - Line Check 2 09-May-17 10-May-17 17
XAC03-33101440 Water Wash and Drain System - Punch Clear 4 11-May-17 15-May-17 17
XAC03-33101450 Water Wash and Drain System - Hydro Test 3 16-May-17 18-May-17 17
XAC03-33101510 Fuel Gas System - Fuel Gas Piping Work 25 24-Mar-17 21-Apr-17 17
XAC03-33101600 Lube Oil / Control Oil System - Delivery Lube Oil Skid 0 18-Feb-17* 40
XAC03-33101610 Lube Oil / Control Oil System - Lube Oil Tank Installation 2 28-Feb-17 01-Mar-17 31
XAC03-33101620 Lube Oil / Control Oil System - Lube Oil Cooler Installation 3 02-Mar-17 04-Mar-17 31
XAC03-33101630 Lube Oil / Control Oil System - Lube Oil Piping Work 25 24-Mar-17 21-Apr-17 15
XAC03-33101640 Lube Oil / Control Oil System - Control Oil Tubing Work 13 22-Apr-17 06-May-17 15
XAC03-33101650 Lube Oil / Control Oil System - RT of Lube Oil Piping (10%) 2 22-Apr-17 24-Apr-17 26
XAC03-33101660 Lube Oil / Control Oil System - Line Check 1 08-May-17 08-May-17 15
XAC03-33101670 Lube Oil / Control Oil System - Punch Clear 5 09-May-17 13-May-17 15
XAC03-33101680 Lube Oil / Control Oil System - Pressure Test 2 15-May-17 16-May-17 15
XAC03-33101690 Lube Oil / Control Oil System - Preparation of Oil Flushing 6 17-May-17 23-May-17 15
XAC03-33101710 Cooling and Sealing Air System - Bleed Air Piping Work 8 24-Mar-17 01-Apr-17 22
XAC03-33101720 Cooling and Sealing Air System - Line Check 1 03-Apr-17 03-Apr-17 54
XAC03-33101730 Cooling and Sealing Air System - Punch Clear 5 04-Apr-17 08-Apr-17 54
XAC03-33101810 Instrument Air System - Instrument Air Tubing Work 16 03-Apr-17 20-Apr-17 22
XAC03-33101B10 Fire Alarm System - Conduit Work and Fire Alarm Installation 8 24-Mar-17 01-Apr-17 0
XAC03-33101F10 Conduit & Cable Tray Installation - Outside Enclosure 21 24-Mar-17 18-Apr-17 0
XAC03-33101F20 Conduit & Cable Tray Installation - Inside Enclosure 17 06-Apr-17 25-Apr-17 26
XAC03-33101G10 Cabling Work - Cable Pulling and Termination Work 26 22-Apr-17 22-May-17 3
03PMS-BL00.3.3.1.02 Ga
Gas turbine & Generator #32 (Siemens) 381 02-Jun-16 17-Aug-17 5
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33102110 Mechanical Work - Foundation Chipping and Packer Setting 9 30-Jan-17* 08-Feb-17 33
XAC03-33102150 Mechanical Work - Remove the On Base Lifting Devise 1 18-Feb-17 18-Feb-17 49
XAC03-33102160 Mechanical Work - Gas Turbine Alignment to Center Line 3 28-Feb-17 02-Mar-17 25
XAC03-33102210 Overhead Crane - Rail Girder and Rail Installation 15 03-Apr-17 20-Apr-17 87
XAC03-33102220 Overhead Crane - Outdoor Rail and Sructure Installation 8 05-May-17 13-May-17 75
XAC03-33102240 Overhead Crane - Conduits Installaton and Cable Pulling 6 18-May-17 24-May-17 75
XAC03-33102250 Overhead Crane - Function Check and Overload Test 3 25-May-17 27-May-17 75
XAC03-33102300 Intake Air Filter System - Delivery Filter House/Diffuser 0 14-Jan-17* 156
XAC03-33102310 Intake Air Filter System - Support Structure Installation 9 18-Apr-17 27-Apr-17 75
XAC03-33102330 Intake Air Filter System - Intake Air Filter House Assembly and Installation 12 05-May-17 19-May-17 76
XAC03-33102410 Water Wash and Drain System - Water Wash Equipment Installation 2 09-May-17 10-May-17 68
XAC03-33102420 Water Wash and Drain System - Water Wash Piping Installation 13 11-May-17 25-May-17 68
XAC03-33102430 Water Wash and Drain System - Line Check 2 26-May-17 27-May-17 68
XAC03-33102440 Water Wash and Drain System - Punch Clear 4 29-May-17 01-Jun-17 68
XAC03-33102450 Water Wash and Drain System - Hydro Test 2 02-Jun-17 03-Jun-17 68
XAC03-33102510 Fuel Gas System - Fuel Gas Piping Work 18 18-Apr-17 08-May-17 68
XAC03-33102600 Lube Oil / Control Oil System - Delivery Lube Oil Skid 0 25-Feb-17* 104
XAC03-33102610 Lube Oil / Control Oil System - Lube Oil Tank Installation 2 17-Mar-17 18-Mar-17 87
XAC03-33102620 Lube Oil / Control Oil System - Lube Oil Cooler Installation 2 20-Mar-17 21-Mar-17 87
XAC03-33102630 Lube Oil / Control Oil System - Lube Oil Piping Work 18 18-Apr-17 08-May-17 64
XAC03-33102640 Lube Oil / Control Oil System - Control Oil Tubing Work 13 09-May-17 23-May-17 64
XAC03-33102650 Lube Oil / Control Oil System - RT of Lube Oil Piping (10%) 3 09-May-17 11-May-17 74
XAC03-33102660 Lube Oil / Control Oil System - Line Check 2 24-May-17 25-May-17 64
XAC03-33102670 Lube Oil / Control Oil System - Punch Clear 4 26-May-17 30-May-17 64
XAC03-33102680 Lube Oil / Control Oil System - Pressure Test 3 31-May-17 02-Jun-17 64
XAC03-33102690 Lube Oil / Control Oil System - Preparation of Oil Flushing 6 03-Jun-17 09-Jun-17 64
XAC03-33102710 Cooling and Sealing Air System - Bleed Air Piping Work 9 18-Apr-17 27-Apr-17 71
XAC03-33102720 Cooling and Sealing Air System - Line Check 1 28-Apr-17 28-Apr-17 96
XAC03-33102730 Cooling and Sealing Air System - Punch Clear 4 29-Apr-17 03-May-17 96
XAC03-33102810 Instrument Air System - Instrument Air Tubing Work 8 28-Apr-17 06-May-17 71
XAC03-33102B10 Fire Alarm System - Conduit Work and Fire Alarm Installation 9 18-Apr-17 27-Apr-17 25
XAC03-33102E10 Start Transformer - Foundation Work of Start Transformer 9 18-Apr-17 27-Apr-17 100
XAC03-33102F10 Conduit & Cable Tray Installation - Outside Enclosure 16 18-Apr-17 05-May-17 25
XAC03-33102F20 Conduit & Cable Tray Installation - Inside Enclosure 11 01-May-17 12-May-17 48
XAC03-33102G10 Cabling Work - Cable Pulling and Termination Work 27 09-May-17 08-Jun-17 25
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.3.1.03 HRSG
HR #31 (Vogt Power) 394 01-Jun-16 29-Aug-17 0
XAC03-3310301B Interface - MHO- Lot-2 (Box Assembly / Module Header / Module Tubes) 0 16-Jan-17* 104
XAC03-3310301C Interface - MHO- Lot-3 (Blowdown Tank / Expansion Joint - Inlet duct / Bypass stack 0 20-Jan-17* 18
Accessories / Diverter dumper)
XAC03-3310301D Interface - MHO- Lot-4 (Inlet Duct / Spool Duct / Field Connection / Bypass Stack / 0 23-Jan-17* 20
Bypass Damper)
XAC03-3310301E Interface - MHO- Lot-5 (Steam Silencers) 0 01-Feb-17* 132
XAC03-3310301F Interface - MHO- Lot-6 (LP & HP Steam Drum / Platforms, Ladders, Stairs) 0 06-Feb-17* 13
XAC03-3310301H Interface - MHO- Lot-8 (Main Stacks / Expansion Joint - Outlet duct) 0 10-Feb-17* 18
XAC03-33103111 Tube Blocks & Duct Assemble - Heavy Lifting - Heavy Lifting 0 01-Dec-16* 20
XAC03-33103112 Tube Blocks & Duct Assemble - Heavy Lifting - Crane Parts Delivery and assembly 9 01-Dec-16 10-Dec-16 20
250ton
XAC03-33103113 Tube Blocks & Duct Assemble - Heavy Lifting - Load Test 250ton 1 12-Dec-16 12-Dec-16 20
XAC03-33103114 Tube Blocks & Duct Assemble - Heavy Lifting - Crane Parts Delivery and assembly 6 12-Dec-16 17-Dec-16 20
750ton
XAC03-33103115 Tube Blocks & Duct Assemble - Heavy Lifting - Load Test 750ton 1 19-Dec-16 19-Dec-16 20
XAC03-33103116 Tube Blocks & Duct Assemble - Heavy Lifting - Preparation 6 09-Jan-17 16-Jan-17 20
XAC03-33103117 Tube Blocks & Duct Assemble - Heavy Lifting - Heavy Lifting 0 16-Jan-17 104
XAC03-33103118 Tube Blocks & Duct Assemble - Heavy Lifting - Paker Plate boxout grouting and curing 1 17-Jan-17 17-Jan-17 103
XAC03-33103119 Tube Blocks & Duct Assemble - Heavy Lifting - Setting center line and elevation of base 1 17-Jan-17 17-Jan-17 103
plates
XAC03-3310311A Tube Blocks & Duct Assemble - Heavy Lifting - Packer Plate Setting 1 17-Jan-17* 17-Jan-17 103
XAC03-3310311B Tube Blocks & Duct Assemble - Heavy Lifting - Formwork setting for grouting 1 17-Jan-17 17-Jan-17 103
XAC03-33103121 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Module Box Alignment 1 16-Jan-17* 16-Jan-17 104
XAC03-33103122 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Module Box#1,2,3 1 16-Jan-17 16-Jan-17 104
Installation and alignment
XAC03-33103123 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Welding base plates of 1 16-Jan-17 16-Jan-17 104
Column HRSG Module
XAC03-33103124 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - PT Check welding joint of 1 16-Jan-17 16-Jan-17 104
Column HRSG Module
XAC03-33103125 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes - Grouting Base plates of 1 16-Jan-17 16-Jan-17 104
Column HRSG Module
03PMS-BL00.3.3.1.03.1.3 Spool Duct Installation
03PMS-BL00.3.3.1.03.1 7 23-Jan-17 30-Jan-17 99
XAC03-33103131 Tube Blocks & Duct Assemble - Spool Duct Installation - Spool Duct Box 1-2 installation 1 23-Jan-17* 23-Jan-17 99
XAC03-33103132 Tube Blocks & Duct Assemble - Spool Duct Installation - Spool Duct Box 2-3 installation 1 24-Jan-17 24-Jan-17 99
XAC03-33103133 Tube Blocks & Duct Assemble - Spool Duct Installation - Scaffolding setting Left & Right 1 25-Jan-17 25-Jan-17 99
side
XAC03-33103134 Tube Blocks & Duct Assemble - Spool Duct Installation - Spool Duct Alignment 1 26-Jan-17 26-Jan-17 99
XAC03-33103135 Tube Blocks & Duct Assemble - Module Box Grout 3 27-Jan-17 30-Jan-17 99
XAC03-33103141 Tube Blocks & Duct Assemble - Complete Module Box/Panel Seal Welding - Welding 1 31-Jan-17 31-Jan-17 99
joint connect spool duct for HRSG Module
XAC03-33103142 Tube Blocks & Duct Assemble - Complete Module Box/Panel Seal Welding - Insulation 24 08-Mar-17 04-Apr-17 77
and liners
03PMS-BL00.3.3.1.03.1.5 Install HP/LP Drums
03PMS-BL00.3.3.1.03.1 20 05-Apr-17 27-Apr-17 77
XAC03-33103151 Tube Blocks & Duct Assemble - Install HP/LP Drums - Support Installation of HP/LP 13 05-Apr-17 19-Apr-17 77
Drum
XAC03-33103152 Tube Blocks & Duct Assemble - Install HP/LP Drums - Install HP/LP Drums 6 20-Apr-17 26-Apr-17 77
XAC03-33103153 Tube Blocks & Duct Assemble - Install HP/LP Drums - HP/LP Drum alignment 1 27-Apr-17 27-Apr-17 77
XAC03-33103161 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation 1 27-Apr-17 28-Apr-17 77
XAC03-33103162 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation - Welding of 2 28-Apr-17 01-May-17 77
column structure silencers
XAC03-33103163 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation - Install and 1 01-May-17 02-May-17 77
alignment Silencers
03PMS-BL00.3.3.1.03.1.7 Platform & Stairway
03PMS-BL00.3.3.1.03.1 16 06-Feb-17 23-Feb-17 112
XAC03-33103171 Tube Blocks & Duct Assemble - Platform & Stairway - Packer Plates setting for Base 1 06-Feb-17 06-Feb-17 13
Plate Stair Tower
XAC03-33103172 Tube Blocks & Duct Assemble - Platform & Stairway - Setting center line and elevation 2 07-Feb-17 08-Feb-17 112
of base plates
XAC03-33103173 Tube Blocks & Duct Assemble - Platform & Stairway - Assembly Stair Tower Structure 4 09-Feb-17 13-Feb-17 112
XAC03-33103174 Tube Blocks & Duct Assemble - Platform & Stairway - Install Stair Tow er Structure 3 13-Feb-17 16-Feb-17 112
XAC03-33103175 Tube Blocks & Duct Assemble - Platform & Stairway - Stair Tower Str ucture Alignment 1 16-Feb-17 17-Feb-17 112
XAC03-33103176 Tube Blocks & Duct Assemble - Platform & Stairway - Grouting Base plates of Column 2 17-Feb-17 20-Feb-17 112
Stair Tower
XAC03-33103177 Tube Blocks & Duct Assemble - Platform & Stairway - Install Main Deck Platform, 3 20-Feb-17 23-Feb-17 112
Handrail and ladder
03PMS-BL00.3.3.1.03.2 Blowdown Tank 5 26-Jan-17 31-Jan-17 18
XAC03-33103310 Bypass Damper and Bypass Stack - Foundation Preparation 4 17-Jan-17 20-Jan-17 20
XAC03-33103320 Bypass Damper and Bypass Stack - Diverter Damper On-Base 4 23-Jan-17 26-Jan-17 20
XAC03-33103330 Bypass Damper and Bypass Stack - Bypass Stack Painting & Platform installation 8 26-Jan-17 04-Feb-17 21
XAC03-33103340 Bypass Damper and Bypass Stack - Erect Bypass Stack steel structure 8 27-Jan-17 04-Feb-17 20
XAC03-33103350 Bypass Damper and Bypass Stack - Install Stack Exp.Joint 1 06-Feb-17 06-Feb-17 20
XAC03-33103360 Bypass Damper and Bypass Stack - Bypass Stack On-base 1 07-Feb-17 07-Feb-17 20
XAC03-33103370 Bypass Damper and Bypass Stack - Seal Air Fan/Diverter ancillaries Installation 14 08-Feb-17 23-Feb-17 125
XAC03-33103380 Bypass Damper and Bypass Stack - Bypass Damper Tes t 11 24-Feb-17 08-Mar-17 125
XAC03-33103410 Inlet Duct and Expansion Joint - Bottom Panels 2 27-Jan-17 30-Jan-17 77
XAC03-33103420 Inlet Duct and Expansion Joint - Siding Panels 10 31-Jan-17 10-Feb-17 77
XAC03-33103430 Inlet Duct and Expansion Joint - Top Panels 7 11-Feb-17 18-Feb-17 77
XAC03-33103440 Inlet Duct and Expansion Joint - Seal Welding 14 20-Feb-17 07-Mar-17 77
XAC03-33103450 Inlet Duct and Expansion Joint - Insulation and liners 24 08-Mar-17 04-Apr-17 77
XAC03-33103510 Outlet Duct and Stack - Main Stack (Lower Parts) On Base 1 10-Feb-17 10-Feb-17 18
XAC03-33103520 Outlet Duct and Stack - Main Stack (Upper Parts) Assembly & Painting 10 11-Feb-17 22-Feb-17 18
XAC03-33103530 Outlet Duct and Stack - Main Stack (Upper Parts) On Base & Welding 3 23-Feb-17 25-Feb-17 18
XAC03-33103540 Outlet Duct and Stack - Outlet Duct Install 12 27-Feb-17 11-Mar-17 18
XAC03-33103610 Internal Piping - Large Bore Piping & Support 48 07-Feb-17 01-Apr-17 13
XAC03-33103620 Internal Piping - Small Bore Piping & Support 37 14-Mar-17 25-Apr-17 50
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33103Z50 Access Platform - Isolation Valve Access - Installation 8 13-Mar-17 21-Mar-17 104
XAC03-33103Z60 Access Platform - HRSG#31 Flow Nozzle - Installation 9 22-Mar-17 31-Mar-17 104
03PMS-BL00.3.3.1.04 HRSG
HR #32 (Vogt Power) 391 05-Jul-16 29-Sep-17 109
XAC03-3310401A Interface - MHO - Lot-1 (Base Plate / Stack Template / Embedded Material) 0 05-Jul-16* 126
XAC03-3310401B Interface - MHO - Lot-2 (Box Assembly / Module Header / Module Tubes) 0 23-Jan-17* 5
XAC03-3310401D Interface - MHO - Lot-4 (Inlet Duct / Spool Duct / Field Connection / Bypass Stack / 0 26-Jan-17* 6
Bypass Damper)
XAC03-3310401C Interface -MHO - Lot-3 (Blowdown Tank / Expansion Joint - Inlet duct / Bypass stack 0 04-Feb-17* 0
Accessories / Diverter dumper)
XAC03-3310401F Interface - MHO - Lot-6 (LP & HP Steam Drum / Platforms, Ladders, Stairs) 0 08-Feb-17* 8
XAC03-3310401H Interface - MHO - Lot-8 (Main Stacks / Expansion Joint - Outlet duct) 0 17-Feb-17* 264
XAC03-3310401G Interface - MHO - Lot-7 (Pipe & Supports & Vent) 0 20-Feb-17* 14
XAC03-33104120 Tube Blocks & Duct Assemble - Lift and Install Tube Boxes 2 23-Jan-17 24-Jan-17 5
XAC03-33104130 Tube Blocks & Duct Assemble - Module Box Alignment 3 25-Jan-17 27-Jan-17 5
XAC03-33104140 Tube Blocks & Duct Assemble - Spool Duct Installation 2 28-Jan-17 30-Jan-17 5
XAC03-33104150 Tube Blocks & Duct Assemble - Module Box Grout 5 31-Jan-17 04-Feb-17 91
XAC03-33104160 Tube Blocks & Duct Assemble - Complete Module Box/Panel Seal Welding 13 06-Feb-17 20-Feb-17 91
XAC03-33104170 Tube Blocks & Duct Assemble - Platform & Stairway 16 08-Feb-17 25-Feb-17 8
XAC03-33104180 Tube Blocks & Duct Assemble - Support Installation of HP/LP Drum 6 21-Feb-17 27-Feb-17 91
XAC03-33104190 Tube Blocks & Duct Assemble - Install HP/LP Drums 6 28-Feb-17 06-Mar-17 91
XAC03-331041A0 Tube Blocks & Duct Assemble - Support Structure & Silencers Installation 4 07-Mar-17 10-Mar-17 91
XAC03-331041B0 Tube Blocks & Duct Assemble - Insulation and liners 31 17-Mar-17 21-Apr-17 85
XAC03-33104310 Bypass Damper and Bypass Stack - Foundation Preparation 4 23-Jan-17 26-Jan-17 5
XAC03-33104320 Bypass Damper and Bypass Stack - Diverter Damper On-Base 3 27-Jan-17 30-Jan-17 5
XAC03-33104330 Bypass Damper and Bypass Stack - Erect Bypass Stack steel structure 9 31-Jan-17 09-Feb-17 121
XAC03-33104340 Bypass Damper and Bypass Stack - Bypass Stack Painting & Platform installation 9 31-Jan-17 10-Feb-17 121
XAC03-33104350 Bypass Damper and Bypass Stack - Install Stack Exp.Joint 1 10-Feb-17 10-Feb-17 121
XAC03-33104360 Bypass Damper and Bypass Stack - Bypass Stack On-base 1 11-Feb-17 11-Feb-17 121
XAC03-33104370 Bypass Damper and Bypass Stack - Seal Air Fan/Diverter ancillaries Installation 13 13-Feb-17 27-Feb-17 121
XAC03-33104380 Bypass Damper and Bypass Stack - Bypass Damper Tes t 11 28-Feb-17 11-Mar-17 121
XAC03-33104410 Inlet Duct and Expension Joint - Bottom Panels 3 06-Feb-17 08-Feb-17 0
XAC03-33104420 Inlet Duct and Expension Joint - Siding Panels 9 09-Feb-17 18-Feb-17 0
XAC03-33104430 Inlet Duct and Expension Joint - Top Panels 7 20-Feb-17 27-Feb-17 0
XAC03-33104440 Inlet Duct and Expension Joint - Seal Welding 15 28-Feb-17 16-Mar-17 85
XAC03-33104450 Inlet Duct and Expension Joint - Insulation and liners 31 17-Mar-17 21-Apr-17 85
XAC03-33104510 Outlet Duct and Stack - Main Stack (Lower Parts) On Base 1 17-Feb-17 17-Feb-17 264
XAC03-33104520 Outlet Duct and Stack - Main Stack (Upper Parts) Assembly & Painting 10 18-Feb-17 01-Mar-17 264
XAC03-33104530 Outlet Duct and Stack - Main Stack (Upper Parts) On Base & Welding 3 02-Mar-17 04-Mar-17 264
XAC03-33104540 Outlet Duct and Stack - Outlet Duct Install 12 06-Mar-17 18-Mar-17 264
XAC03-33104550 Outlet Duct and Stack - Expansion Install 13 20-Mar-17 03-Apr-17 264
XAC03-33104610 Internal Piping - Large Bore Piping & Support 55 27-Feb-17 29-Apr-17 8
XAC03-33104620 Internal Piping - Small Bore Piping & Support 37 03-Apr-17 15-May-17 65
XAC03-331046A0 Internal Piping - Final Inspection Application to MOI 6 03-Aug-17 09-Aug-17 153
XAC03-33104Z50 Access Platform - Isolation Valve Access - Installation 8 27-Mar-17 04-Apr-17 119
XAC03-33104Z60 Access Platform - HRSG#31 Flow Nozzle - Installation 9 05-Apr-17 14-Apr-17 119
03PMS-BL00.3.3.1.05 St
Steam Turbine & Generator (Siemens) 174 15-Mar-17 30-Sep-17 107
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33105230 Electrical Work - Megger Check & Continuity Cable 1 28-Aug-17 28-Aug-17 17
XAC03-33105Z10 Access Platform - Access & Maintenance Platform for O/H Crane - Delivery 0 26-Aug-17 107
XAC03-33105Z30 Access Platform - Access & Maintenance Platform for ST - Delivery 0 26-Aug-17 117
XAC03-33105Z50 Access Platform - Platform for CEP Pit - Delivery 0 26-Aug-17 127
XAC03-33105Z20 Access Platform - Access & Maintenance Platform for O/H Crane - Installation 10 28-Aug-17 07-Sep-17 107
XAC03-33105Z40 Access Platform - Access & Maintenance Platform for ST - Installation 10 07-Sep-17 19-Sep-17 107
XAC03-33105Z60 Access Platform - Platform for CEP Pit - Installation 10 19-Sep-17 30-Sep-17 107
XAC03-33201120 DM Water Tank - Erection & Fit-up Annular Plate 3 09-Sep-16 13-Sep-16 76
XAC03-33201140 DM Water Tank - NDE (RT) Annular Plate Before Shell Erection 2 16-Sep-16 19-Sep-16 76
XAC03-33201170 DM Water Tank - Shell Plate Erection and Fit-up Course-1 2 30-Sep-16 01-Oct-16 73
XAC03-33201180 DM Water Tank - Shell Course-1 Inspection (Fit-up, Roundness, Levelness, 2 03-Oct-16 04-Oct-16 73
Plumbness)
XAC03-33201190 DM Water Tank - Shell Course-1 Vertical Join t Welding 2 06-Oct-16 07-Oct-16 73
XAC03-332011A0 DM Water Tank - Shell Course-2 Erection & Fit-up 1 10-Oct-16 11-Oct-16 73
XAC03-332011C0 DM Water Tank - Shell Course-2 Vertical Join t Welding 2 14-Oct-16 15-Oct-16 73
XAC03-332011D0 DM Water Tank - Shell Course 1&2 Horizontal Joint Fit-up 3 17-Oct-16 19-Oct-16 73
XAC03-332011E0 DM Water Tank - Shell Course 1&2 Horizontal Joint Fit-up Inspection 1 20-Oct-16 20-Oct-16 73
XAC03-332011F0 DM Water Tank - Shell Course 1&2 Horizontal Joint Welding 7 21-Oct-16 28-Oct-16 73
XAC03-332011G0 DM Water Tank - Shell Course-2 Peaking, Banding & Plumbness Inspection 6 24-Oct-16 29-Oct-16 73
XAC03-332011H0 DM Water Tank - Shell Course-3 Erection & Fit-up 2 26-Oct-16 27-Oct-16 73
XAC03-332011J0 DM Water Tank - Shell Course-3 Vertical Join t Welding 1 29-Oct-16 29-Oct-16 73
XAC03-332011K0 DM Water Tank - Shell Course 2&3 Horizontal Joint Fit-up 3 31-Oct-16 02-Nov-16 73
XAC03-332011L0 DM Water Tank - Shell Course 2&3 Horizontal Joint Fit-up Inspection 2 02-Nov-16 03-Nov-16 73
XAC03-332011M0 DM Water Tank - Shell Course 2&3 Horizontal Joint Welding 2 03-Nov-16 05-Nov-16 73
XAC03-332011N0 DM Water Tank - Shell Course 1&2 Welding Seam NDE (RT) 3 03-Nov-16 07-Nov-16 73
XAC03-332011O0 DM Water Tank - Shell Course-3 Peaking, Banding, Plumbness Inspection 1 07-Nov-16 07-Nov-16 73
XAC03-332011P0 DM Water Tank - Annular Plate & Bottom Plate Welding 2 07-Nov-16 08-Nov-16 73
XAC03-332011Q0 DM Water Tank - Shell Course-1 & Annular Plate Fit-up & Inspection 2 07-Nov-16 08-Nov-16 73
XAC03-332011R0 DM Water Tank - Draw-off Sump Installation & Welding 2 08-Nov-16 10-Nov-16 73
XAC03-332011S0 DM Water Tank - Internal Structure Erection (Column, Grider, Internal Rafter) 2 08-Nov-16 10-Nov-16 73
XAC03-332011T0 DM Water Tank - Shell Course-1 & Annular Plate Welding 2 09-Nov-16 11-Nov-16 73
XAC03-332011U0 DM Water Tank - Bottom Plate Welding Seam Vacuum Test 2 09-Nov-16 11-Nov-16 73
XAC03-332011V0 DM Water Tank - Shell Course-4 Erection & Fit-up 1 10-Nov-16 11-Nov-16 73
XAC03-332011W0 DM Water Tank - Shell Course-1 & Annular Plate Welding Seam NDE (PT) 1 11-Nov-16 12-Nov-16 73
XAC03-332011Y0 DM Water Tank - Shell Course-4 Vertical Join t Welding 2 12-Nov-16 14-Nov-16 73
XAC03-332011Z0 DM Water Tank - Shell Course 3&4 Horizontal Joint Fit-up 2 14-Nov-16 15-Nov-16 73
XAC03-33201111 DM Water Tank - Shell Course 3&4 Horizontal Joint Fit-up Inspection 2 16-Nov-16 17-Nov-16 73
XAC03-33201112 DM Water Tank - Shell Course 3&4 Horizontal Joint Welding 2 17-Nov-16 19-Nov-16 73
XAC03-33201113 DM Water Tank - Shell Course 3&4 Welding Seam NDE (RT) 2 19-Nov-16 22-Nov-16 73
XAC03-33201114 DM Water Tank - Shell Course-5 Erection & Fit-up 3 21-Nov-16 23-Nov-16 73
XAC03-33201115 DM Water Tank - Shell Course-4 Peaking, Banding, Plumbness Inspection 1 21-Nov-16 21-Nov-16 73
XAC03-33201117 DM Water Tank - Shell Course-5 Vertical Join t Welding 3 24-Nov-16 26-Nov-16 73
XAC03-33201118 DM Water Tank - Shell Course 4&5 Horizontal Joint Fit-up 1 26-Nov-16 26-Nov-16 73
XAC03-33201119 DM Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Inspection 1 26-Nov-16 28-Nov-16 73
XAC03-3320111B DM Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Welding 4 28-Nov-16 01-Dec-16 73
XAC03-3320111C DM Water Tank - Shell Course-5 Peaking, Banding, Plumbness Inspection 2 01-Dec-16 02-Dec-16 73
XAC03-3320111D DM Water Tank - Shell Course-6 Erection & Fit-up 1 02-Dec-16 03-Dec-16 73
XAC03-3320111F DM Water Tank - Shell Course-6 Vertical Join t Welding 1 05-Dec-16 06-Dec-16 73
XAC03-3320111G DM Water Tank - Shell Course 5&6 Horizontal Joint Fit-up 2 07-Dec-16 08-Dec-16 73
XAC03-3320111H DM Water Tank - Shell Course 5&6 Horizontal Joint Fit-up Inspection 2 08-Dec-16 09-Dec-16 73
XAC03-3320111I DM Water Tank - Shell Course 5&6 Horizontal Joint Welding 3 09-Dec-16 12-Dec-16 73
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-3320111K DM Water Tank - Nozzles & Manhole Installation & Welding 5 12-Dec-16 16-Dec-16 73
XAC03-3320111L DM Water Tank - Shell Course-7 Erection & Fit-up 2 13-Dec-16 14-Dec-16 73
XAC03-3320111O DM Water Tank - Shell Course-7 Vertical Join t Welding 2 15-Dec-16 16-Dec-16 73
XAC03-3320111P DM Water Tank - Nozzle & Manhole Welding Seam NDE 3 15-Dec-16 17-Dec-16 73
XAC03-3320111Q DM Water Tank - Shell Course 6&7 Horizontal Joint Fit-up 1 16-Dec-16 17-Dec-16 73
XAC03-3320111R DM Water Tank - Shell Course 6&7 Horizontal Joint Fit-up Inspection 1 16-Dec-16 17-Dec-16 73
XAC03-3320111S DM Water Tank - Shell Course 5&6 Welding Seam NDE (RT) 4 19-Dec-16 22-Dec-16 73
XAC03-3320111T DM Water Tank - Top Angle Erection & Welding 4 19-Dec-16 22-Dec-16 73
XAC03-3320111U DM Water Tank - Platform & Handrail Erection & Welding 6 19-Dec-16 24-Dec-16 73
XAC03-3320111V DM Water Tank - Shell Course 6&7 Horizontal Joint Welding 3 19-Dec-16 21-Dec-16 73
XAC03-3320111W DM Water Tank - Rafter Clip Support Fit-up & Welding 3 20-Dec-16 22-Dec-16 73
XAC03-3320111X DM Water Tank - Shell Course-7 Peaking, Banding, Plumbness Inspection 2 21-Dec-16 22-Dec-16 73
XAC03-3320111Z DM Water Tank - Internal Structure Alignment & Bolt Tightening 3 21-Dec-16 23-Dec-16 73
XAC03-332011110 DM Water Tank - Anc hor Chair Installation & Welding 3 21-Dec-16 23-Dec-16 73
XAC03-332011120 DM Water Tank - Anc hor Bolts Installation & G routing 12 23-Dec-16 05-Jan-17 73
XAC03-332011130 DM Water Tank - Roof Plate Erection & Fit-up 11 23-Dec-16 05-Jan-17 73
XAC03-332011140 DM Water Tank - Roof Plate Fit-up Inspection & Welding 4 05-Jan-17 09-Jan-17 73
XAC03-332011150 DM Water Tank - Roof Plate Welding Seam NDE (PT) 2 05-Jan-17 06-Jan-17 73
XAC03-332011170 DM Water Tank - Final Inspection Before Water Filling Test 2 05-Jan-17 06-Jan-17 73
XAC03-332011190 DM Water Tank - Full Water Test & Holding Time 7 05-Jan-17 12-Jan-17 73
XAC03-3320111B0 DM Water Tank - Drain Water & Internal Cleaning 3 07-Jan-17 10-Jan-17 73
XAC03-3320111D0 DM Water Tank - Internal Painting Shell & Roof 25 09-Jan-17 06-Feb-17 88
XAC03-3320111H0 DM Water Tank - Internal Painting Inspection for Shell & Roof 2 08-Feb-17 10-Feb-17 73
03PMS-BL00.3.3.2.02 Se
Service Water & Fire Water Storage Tank (Common) 158 26-Aug-16 24-Feb-17 118
XAC03-33202110 Service Water Tank - Shell Course-3 Erection & Fit-up 2 01-Sep-16 02-Sep-16 70
XAC03-33202130 Service Water Tank - Erection & Fit-up Annular Plate 3 09-Sep-16 13-Sep-16 70
XAC03-33202150 Service Water Tank - NDE (RT) Annular Plate Before Shell Erection 1 19-Sep-16 20-Sep-16 70
XAC03-33202170 Service Water Tank - Shell Plate Erection and Fit-up Course-1 2 29-Sep-16 01-Oct-16 70
XAC03-33202180 Service Water Tank - Shell Course-1 Inspection (Fit-up, Roundness, Levelness, 1 05-Oct-16 06-Oct-16 70
Plumbness)
XAC03-33202190 Service Water Tank - Shell Course-1 Vertical Joint Welding 5 07-Oct-16 13-Oct-16 70
XAC03-332021A0 Service Water Tank - Shell Course-2 Fit-up Inspection 2 12-Oct-16 14-Oct-16 70
XAC03-332021B0 Service Water Tank - Shell Course-2 Erection & Fit-up 2 14-Oct-16 17-Oct-16 71
XAC03-332021C0 Service Water Tank - Shell Course-2 Vertical Joint Welding 3 14-Oct-16 18-Oct-16 70
XAC03-332021D0 Service Water Tank - Shell Course 1&2 Horizontal Joint Fit-up 1 18-Oct-16 19-Oct-16 70
XAC03-332021E0 Service Water Tank - Shell Course 1&2 Horizontal Joint Fit-up Inspection 1 19-Oct-16 20-Oct-16 70
XAC03-332021F0 Service Water Tank - Shell Course 1&2 Horizontal Joint Welding 5 20-Oct-16 26-Oct-16 70
XAC03-332021G0 Service Water Tank - Shell Course-2 Peaking, Banding & Plumbness Inspection 1 24-Oct-16 25-Oct-16 70
XAC03-332021I0 Service Water Tank - Shell Course-3 Fit-up Inspection 1 26-Oct-16 27-Oct-16 70
XAC03-332021J0 Service Water Tank - Shell Course-3 Vertical Joint Welding 4 28-Oct-16 02-Nov-16 70
XAC03-332021K0 Service Water Tank - Shell Course 2&3 Horizontal Joint Fit-up 3 29-Oct-16 02-Nov-16 70
XAC03-332021L0 Service Water Tank - Shell Course 2&3 Horizontal Joint Fit-up Inspection 1 01-Nov-16 02-Nov-16 70
XAC03-332021M0 Service Water Tank - Shell Course 2&3 Horizontal Joint Welding 5 02-Nov-16 08-Nov-16 70
XAC03-332021N0 Service Water Tank - Shell Course-3 Peaking, Banding, Plumbness Inspection 2 04-Nov-16 07-Nov-16 70
XAC03-332021O0 Service Water Tank - Shell Course 1&2 Welding Seam NDE (RT) 3 04-Nov-16 08-Nov-16 70
XAC03-332021P0 Service Water Tank - Annular Plate & Bottom Plate Welding 2 05-Nov-16 08-Nov-16 70
XAC03-332021Q0 Service Water Tank - Shell Course-1 & Annular Plate Fit-up & Inspection 2 05-Nov-16 08-Nov-16 70
XAC03-332021R0 Service Water Tank - Internal Structure Erection (Column, Grider, Internal R after) 3 05-Nov-16 09-Nov-16 70
XAC03-332021S0 Service Water Tank - Shell Course-4 Erection & Fit-up 3 05-Nov-16 09-Nov-16 70
XAC03-332021U0 Service Water Tank - Bottom Plate Welding Seam Vacuum Test 2 07-Nov-16 09-Nov-16 70
XAC03-332021V0 Service Water Tank - Draw-off Sump Installation & Welding 2 07-Nov-16 09-Nov-16 70
XAC03-332021T0 Service Water Tank - Shell Course-1 & Annular Plate Welding 1 08-Nov-16 09-Nov-16 70
XAC03-332021W0 Service Water Tank - Shell Course-1 & Annular Plate Welding Seam NDE (PT) 1 08-Nov-16 09-Nov-16 70
XAC03-332021X0 Service Water Tank - Shell Course-4 Fit-up Inspection 1 08-Nov-16 09-Nov-16 70
XAC03-332021Y0 Service Water Tank - Shell Course-4 Vertical Joint Welding 2 09-Nov-16 11-Nov-16 70
XAC03-332021Z0 Service Water Tank - Shell Course 3&4 Horizontal Joint Fit-up 3 09-Nov-16 12-Nov-16 70
XAC03-33202111 Service Water Tank - Shell Course 3&4 Horizontal Joint Fit-up Inspection 2 10-Nov-16 12-Nov-16 70
XAC03-33202112 Service Water Tank - Shell Course 3&4 Horizontal Joint Welding 4 11-Nov-16 16-Nov-16 70
XAC03-33202113 Service Water Tank - Shell Course 3&4 Welding Seam NDE (RT) 3 12-Nov-16 16-Nov-16 70
XAC03-33202114 Service Water Tank - Shell Course-4 Peaking, Banding, Plumbness Inspection 1 15-Nov-16 16-Nov-16 70
XAC03-33202115 Service Water Tank - Shell Course-5 Erection & Fit-up 2 16-Nov-16 18-Nov-16 70
XAC03-33202116 Service Water Tank - Shell Course-5 Fit-up Inspection 2 18-Nov-16 21-Nov-16 70
XAC03-33202117 Service Water Tank - Shell Course-5 Vertical Joint Welding 3 18-Nov-16 22-Nov-16 70
XAC03-33202118 Service Water Tank - Shell Course 4&5 Horizontal Joint Fit-up 1 22-Nov-16 23-Nov-16 70
XAC03-33202119 Service Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Inspection 1 23-Nov-16 24-Nov-16 70
XAC03-3320211A Service Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Welding 4 23-Nov-16 28-Nov-16 70
XAC03-3320211C Service Water Tank - Shell Course-5 Peaking, Banding, Plumbness Inspection 2 28-Nov-16 30-Nov-16 70
XAC03-3320211D Service Water Tank - Shell Course-6 Erection & Fit-up 2 29-Nov-16 01-Dec-16 70
XAC03-3320211E Service Water Tank - Shell Course-6 Fit-up Inspection 2 30-Nov-16 02-Dec-16 70
XAC03-3320211F Service Water Tank - Shell Course-6 Vertical Joint Welding 2 01-Dec-16 03-Dec-16 70
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-3320211H Service Water Tank - Shell Course 5&6 Horizontal Joint Fit-up Inspection 2 05-Dec-16 07-Dec-16 70
XAC03-3320211I Service Water Tank - Shell Course 5&6 Horizontal Joint Welding 3 06-Dec-16 09-Dec-16 70
XAC03-3320211J Service Water Tank - Shell Course-6 Peaking, Banding, Plumbness Inspection 2 09-Dec-16 12-Dec-16 70
XAC03-3320211K Service Water Tank - Nozzles & Manhole Installation & Welding 4 09-Dec-16 14-Dec-16 70
XAC03-3320211L Service Water Tank - Platform & Handrail Erection & Welding 6 09-Dec-16 16-Dec-16 70
XAC03-3320211M Service Water Tank - Shell Course-7 Erection & Fit-up 3 10-Dec-16 14-Dec-16 70
XAC03-3320211N Service Water Tank - Shell Course-7 Fit-up Inspection 1 13-Dec-16 14-Dec-16 70
XAC03-3320211O Service Water Tank - Shell Course-7 Vertical Joint Welding 1 14-Dec-16 15-Dec-16 70
XAC03-3320211P Service Water Tank - Shell Course 6&7 Horizontal Joint Fit-up 3 14-Dec-16 17-Dec-16 70
XAC03-3320211Q Service Water Tank - Top Angle Erection & Welding 4 14-Dec-16 19-Dec-16 70
XAC03-3320211R Service Water Tank - Nozzle & Manhole Welding Seam NDE 3 14-Dec-16 17-Dec-16 70
XAC03-3320211S Service Water Tank - Shell Course 6&7 Horizontal Joint Fit-up Inspection 1 16-Dec-16 17-Dec-16 70
XAC03-3320211T Service Water Tank - Shell Course 6&7 Horizontal Joint Welding 4 16-Dec-16 21-Dec-16 70
XAC03-3320211U Service Water Tank - Shell Course-7 Peaking, Banding, Plumbness Inspection 2 16-Dec-16 19-Dec-16 70
XAC03-3320211V Service Water Tank - Shell Course 5&6 Welding Seam NDE (RT) 4 16-Dec-16 21-Dec-16 70
XAC03-3320211W Service Water Tank - Rafter Clip Support Fit-up & Welding 3 16-Dec-16 20-Dec-16 70
XAC03-3320211X Service Water Tank - Anchor Chair Installation & Welding 3 16-Dec-16 20-Dec-16 70
XAC03-3320211Z Service Water Tank - Internal Structure Alignment & Bolt Tightening 1 20-Dec-16 21-Dec-16 70
XAC03-332021110 Service Water Tank - Roof Plate Erection & Fit-up 1 20-Dec-16 21-Dec-16 70
XAC03-332021120 Service Water Tank - Anchor Bolts Installation & Gr outing 1 20-Dec-16 21-Dec-16 70
XAC03-332021130 Service Water Tank - Roof Plate Fit-up Inspection & Welding 4 21-Dec-16 26-Dec-16 70
XAC03-332021150 Service Water Tank - Roof Plate Welding Seam NDE (PT) 2 23-Dec-16 26-Dec-16 70
XAC03-332021160 Service Water Tank - Final Inspection Before Water Filling Test 1 24-Dec-16 26-Dec-16 70
XAC03-332021170 Service Water Tank - Water Filling Test Preparation 2 24-Dec-16 27-Dec-16 70
XAC03-332021180 Service Water Tank - Full Water Test & Holding Time 16 27-Dec-16 14-Jan-17 70
XAC03-3320211A0 Service Water Tank - Drain Water & Internal Cleaning 2 09-Jan-17 11-Jan-17 70
XAC03-3320211C0 Service Water Tank - Internal Painting Shell & Roof 25 09-Jan-17 06-Feb-17 95
XAC03-3320211F0 Service Water Tank - Internal Painting Inspection for Shell & Roof 2 08-Feb-17 09-Feb-17 70
XAC03-3320211G0 Service Water Tank - Internal Scaffolding Removal Work 3 08-Feb-17 10-Feb-17 70
XAC03-3320211H0 Service Water Tank - Internal Bottom Plate Painting 4 09-Feb-17 13-Feb-17 70
XAC03-3320211I0 Service Water Tank - External Scaffolding Removal Work 4 09-Feb-17 14-Feb-17 70
XAC03-3320211J0 Service Water Tank - Final Inspection (Including Painting) 2 15-Feb-17 17-Feb-17 70
XAC03-33203120 CT Make Up Water Tank - Erection & Fit-up Annular Plate 3 26-Sep-16 28-Sep-16 92
XAC03-33203140 CT Make Up Water Tank - NDE (RT) Annular Plate Before Shell Erection 2 03-Oct-16 04-Oct-16 92
XAC03-33203170 CT Make Up Water Tank - Shell Plate Erection and Fit-up Course-1 3 07-Oct-16 11-Oct-16 92
XAC03-33203180 CT Make Up Water Tank - Shell Course-1 Inspection (Fit-up, Roundness, Levelness, 2 12-Oct-16 13-Oct-16 92
Plumbness)
XAC03-33203190 CT Make Up Water Tank - Shell Course-1 Vertical Joint Welding 3 13-Oct-16 17-Oct-16 92
XAC03-332031A0 CT Make Up Water Tank - Shell Course-2 Erection & Fit-up 1 20-Oct-16 21-Oct-16 92
XAC03-332031B0 CT Make Up Water Tank - Shell Course-2 Fit-up Inspection 1 21-Oct-16 22-Oct-16 92
XAC03-332031C0 CT Make Up Water Tank - Shell Course-2 Vertical Joint Welding 2 24-Oct-16 25-Oct-16 92
XAC03-332031D0 CT Make Up Water Tank - Shell Course 1&2 Horizontal Joint Fit-up 2 26-Oct-16 27-Oct-16 92
XAC03-332031E0 CT Make Up Water Tank - Shell Course 1&2 Horizontal Joint Fit-up Inspection 1 27-Oct-16 28-Oct-16 92
XAC03-332031F0 CT Make Up Water Tank - Shell Course 1&2 Horizontal Joint Welding 7 28-Oct-16 05-Nov-16 92
XAC03-332031G0 CT Make Up Water Tank - Shell Course-2 Peaking, Banding & Plumbness Inspection 1 02-Nov-16 02-Nov-16 92
XAC03-332031H0 CT Make Up Water Tank - Shell Course-3 Erection & Fit-up 1 02-Nov-16 02-Nov-16 92
XAC03-332031I0 CT Make Up Water Tank - Shell Course-3 Fit-up Inspection 1 03-Nov-16 03-Nov-16 92
XAC03-332031J0 CT Make Up Water Tank - Shell Course-3 Vertical Joint Welding 1 03-Nov-16 04-Nov-16 92
XAC03-332031K0 CT Make Up Water Tank - Shell Course 2&3 Horizontal Joint Fit-up 3 05-Nov-16 08-Nov-16 92
XAC03-332031L0 CT Make Up Water Tank - Shell Course 2&3 Horizontal Joint Fit-up Inspection 1 09-Nov-16 09-Nov-16 92
XAC03-332031M0 CT Make Up Water Tank - Shell Course 2&3 Horizontal Joint Welding 2 10-Nov-16 11-Nov-16 92
XAC03-332031N0 CT Make Up Water Tank - Shell Course 1&2 Welding Seam NDE (RT) 2 10-Nov-16 11-Nov-16 92
XAC03-332031O0 CT Make Up Water Tank - Annular Plate & Bottom Plate Welding 1 10-Nov-16 10-Nov-16 92
XAC03-332031P0 CT Make Up Water Tank - Shell Course-1 & Annular Plate Fit-up & Inspection 2 10-Nov-16 11-Nov-16 92
XAC03-332031Q0 CT Make Up Water Tank - Shell Course-3 Peaking, Banding, Plumbness Inspection 2 10-Nov-16 12-Nov-16 92
XAC03-332031R0 CT Make Up Water Tank - Shell Course-1 & Annular Plate Welding 3 10-Nov-16 14-Nov-16 92
XAC03-332031S0 CT Make Up Water Tank - Bottom Plate Welding Seam Vacuum Test 3 10-Nov-16 14-Nov-16 92
XAC03-332031T0 CT Make Up Water Tank - Draw-off Sump Installation & Welding 3 10-Nov-16 14-Nov-16 92
XAC03-332031U0 CT Make Up Water Tank - Internal Structure Erection (Column, Grider, Internal Rafter) 3 10-Nov-16 14-Nov-16 92
XAC03-332031V0 CT Make Up Water Tank - Shell Course-1 & Annular Plate Welding Seam NDE (PT) 2 14-Nov-16 15-Nov-16 92
XAC03-332031W0 CT Make Up Water Tank - Shell Course-4 Erection & Fit-up 2 14-Nov-16 15-Nov-16 92
XAC03-332031X0 CT Make Up Water Tank - Shell Course-4 Fit-up Inspection 1 14-Nov-16 15-Nov-16 92
XAC03-332031Y0 CT Make Up Water Tank - Shell Course-4 Vertical Joint Welding 2 15-Nov-16 17-Nov-16 92
XAC03-332031Z0 CT Make Up Water Tank - Shell Course 3&4 Horizontal Joint Fit-up 2 17-Nov-16 19-Nov-16 92
XAC03-33203111 CT Make Up Water Tank - Shell Course 3&4 Horizontal Joint Fit-up Inspection 1 19-Nov-16 21-Nov-16 92
XAC03-33203112 CT Make Up Water Tank - Shell Course 3&4 Horizontal Joint Welding 2 21-Nov-16 23-Nov-16 92
XAC03-33203113 CT Make Up Water Tank - Shell Course-4 Peaking, Banding, Plumbness Inspection 2 23-Nov-16 24-Nov-16 92
XAC03-33203114 CT Make Up Water Tank - Shell Course 3&4 Welding Seam NDE (RT) 3 23-Nov-16 25-Nov-16 92
XAC03-33203115 CT Make Up Water Tank - Shell Course-5 Erection & Fit-up 2 24-Nov-16 26-Nov-16 92
XAC03-33203116 CT Make Up Water Tank - Shell Course-5 Fit-up Inspection 1 26-Nov-16 28-Nov-16 92
XAC03-33203117 CT Make Up Water Tank - Shell Course-5 Vertical Joint Welding 2 28-Nov-16 29-Nov-16 92
XAC03-33203118 CT Make Up Water Tank - Shell Course 4&5 Horizontal Joint Fit-up 1 30-Nov-16 30-Nov-16 92
XAC03-33203119 CT Make Up Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Inspection 2 30-Nov-16 01-Dec-16 92
XAC03-3320311A CT Make Up Water Tank - Shell Course 4&5 Horizontal Joint Fit-up Welding 4 01-Dec-16 05-Dec-16 92
XAC03-3320311C CT Make Up Water Tank - Shell Course-5 Peaking, Banding, Plumbness Inspection 1 05-Dec-16 06-Dec-16 92
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-3320311E CT Make Up Water Tank - Shell Course-6 Fit-up Inspection 2 06-Dec-16 08-Dec-16 92
XAC03-3320311F CT Make Up Water Tank - Shell Course-6 Vertical Joint Welding 2 08-Dec-16 10-Dec-16 92
XAC03-3320311G CT Make Up Water Tank - Shell Course 5&6 Horizontal Joint Fit-up 2 09-Dec-16 12-Dec-16 92
XAC03-3320311H CT Make Up Water Tank - Shell Course 5&6 Horizontal Joint Fit-up Inspection 2 12-Dec-16 13-Dec-16 92
XAC03-3320311I CT Make Up Water Tank - Shell Course 5&6 Horizontal Joint Welding 3 13-Dec-16 15-Dec-16 92
XAC03-3320311J CT Make Up Water Tank - Shell Course-6 Peaking, Banding, Plumbness Inspection 2 15-Dec-16 16-Dec-16 92
XAC03-3320311K CT Make Up Water Tank - Shell Course-7 Erection & Fit-up 2 15-Dec-16 17-Dec-16 92
XAC03-3320311L CT Make Up Water Tank - Shell Course-7 Fit-up Inspection 2 16-Dec-16 19-Dec-16 92
XAC03-3320311N CT Make Up Water Tank - Nozzles & Manhole Installation & Welding 4 19-Dec-16 22-Dec-16 92
XAC03-3320311M CT Make Up Water Tank - Shell Course-7 Vertical Joint Welding 2 19-Dec-16 20-Dec-16 92
XAC03-3320311O CT Make Up Water Tank - Shell Course 6&7 Horizontal Joint Fit-up 1 20-Dec-16 20-Dec-16 92
XAC03-3320311P CT Make Up Water Tank - Shell Course 6&7 Horizontal Joint Fit-up Inspection 1 21-Dec-16 21-Dec-16 92
XAC03-3320311Q CT Make Up Water Tank - Shell Course 6&7 Horizontal Joint Welding 4 21-Dec-16 24-Dec-16 92
XAC03-3320311R CT Make Up Water Tank - Nozzle & Manhole Welding Seam NDE 2 21-Dec-16 22-Dec-16 92
XAC03-3320311S CT Make Up Water Tank - Shell Course 5&6 Welding Seam NDE (RT) 4 22-Dec-16 26-Dec-16 92
XAC03-3320311T CT Make Up Water Tank - Platform & Handrail Erection & Welding 16 22-Dec-16 10-Jan-17 92
XAC03-3320311U CT Make Up Water Tank - Shell Course-7 Peaking, Banding, Plumbness Inspection 2 23-Dec-16 26-Dec-16 92
XAC03-3320311V CT Make Up Water Tank - Top Angle Erection & Welding 13 23-Dec-16 07-Jan-17 92
XAC03-3320311W CT Make Up Water Tank - Rafter Clip Support Fit-up & Welding 3 06-Jan-17 10-Jan-17 92
XAC03-3320311Y CT Make Up Water Tank - Internal Structure Alignment & Bolt Tightening 3 06-Jan-17 10-Jan-17 92
XAC03-3320311Z CT Make Up Water Tank - Roof Plate Erection & Fit-up 3 06-Jan-17 10-Jan-17 92
XAC03-332031110 CT Make Up Water Tank - Roof Plate Fit-up Inspection & Welding 4 06-Jan-17 11-Jan-17 92
XAC03-332031120 CT Make Up Water Tank - Roof Plate Welding Seam NDE (PT) 2 06-Jan-17 09-Jan-17 92
XAC03-332031130 CT Make Up Water Tank - Anchor Chair Installation & Welding 3 06-Jan-17 10-Jan-17 92
XAC03-332031140 CT Make Up Water Tank - Anchor Bolts Installation & Grouting 3 06-Jan-17 10-Jan-17 92
XAC03-332031160 CT Make Up Water Tank - Final Inspection Before Water Filling Test 1 10-Jan-17 10-Jan-17 92
XAC03-332031170 CT Make Up Water Tank - Water Filling Test Preparation 1 10-Jan-17 10-Jan-17 92
XAC03-332031180 CT Make Up Water Tank - Full Water Test & Holding Time 6 11-Jan-17 17-Jan-17 92
XAC03-3320311A0 CT Make Up Water Tank - Drain Water & Internal C leanin g 3 18-Jan-17 20-Jan-17 92
XAC03-3320311C0 CT Make Up Water Tank - Internal Painting Shell & Roof 25 19-Jan-17 17-Feb-17 92
XAC03-3320311E0 CT Make Up Water Tank - Internal Painting Inspection for Shell & Roof 1 16-Feb-17 17-Feb-17 92
XAC03-3320311F0 CT Make Up Water Tank - Internal Scaffolding Removal Work 3 17-Feb-17 21-Feb-17 92
XAC03-3320311H0 CT Make Up Water Tank - Internal Bottom Plate Welding 5 20-Feb-17 25-Feb-17 92
XAC03-3320311I0 CT Make Up Water Tank - External Scaffolding Removal Work 4 20-Feb-17 24-Feb-17 92
XAC03-3320311J0 CT Make Up Water Tank - Final Inspection (Including Painting) 2 27-Feb-17 01-Mar-17 92
03PMS-BL00.3.3.2.04 Water
Wa Treatment Plant (Common) 158 01-Nov-16 03-May-17 13
XAC03-33204140 Clarifier Installation - Drive Unit and Agitator Installation 8 19-Jan-17 27-Jan-17 83
03PMS-BL00.3.3.2.04.2 Filtering Pump, Clarified Water Pump, Belt Press Washing Pump, Air Blowers 20 13-Jan-17 04-Feb-17 83
XAC03-33204210 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 6 13-Jan-17 19-Jan-17 66
Chipping and Packer Setting
XAC03-33204220 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 2 20-Jan-17 21-Jan-17 66
Equipment on the Foundation
XAC03-33204230 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 6 23-Jan-17 28-Jan-17 66
Equipment Alignment
XAC03-33204240 Filtering Pumps, Clarifier Water Pump, Belt Press Washing Pump, Air Blowers - 6 30-Jan-17 04-Feb-17 83
Grouting
03PMS-BL00.3.3.2.04.3 Multi Media Filter (2 pcs) 12 06-Jan-17 20-Jan-17 96
XAC03-33204310 Multi Media Filter (2 pcs) - Chipping and Packer Setting 5 06-Jan-17 12-Jan-17 66
XAC03-33204320 Multi Media Filter (2 pcs) - Equipment on the Foundation 2 13-Jan-17 14-Jan-17 66
XAC03-33204410 Sludge Shute / Sludge Thickner / Sludge Container - Chipping and Packer Setting 4 03-Feb-17 08-Feb-17 52
XAC03-33204420 Sludge Shute / Sludge Thickner / Sludge Container - Installation and Alignment 5 08-Feb-17 14-Feb-17 73
XAC03-33204430 Sludge Shute / Sludge Thickner / Sludge Container - Grouting 2 14-Feb-17 16-Feb-17 73
XAC03-33204510 Belt Press Unit - Chipping and Packer Setting 4 08-Feb-17* 13-Feb-17 52
XAC03-33204610 Chemical Tanks / Chemical Pumps - Chipping and Packer Setting 6 21-Feb-17 28-Feb-17 52
XAC03-33204620 Chemical Tanks / Chemical Pumps - Installation and Alignment 6 28-Feb-17 07-Mar-17 52
XAC03-33204810 WTP Area Electrical Work - Cable Tray installation 26 11-Jan-17* 09-Feb-17 21
XAC03-33204820 WTP Area Electrical Work - Cabling and Termination Work 38 10-Feb-17 25-Mar-17 21
XAC03-33204830 WTP Area Electrical Work - Instrument and Tubing Installation 12 25-Feb-17 11-Mar-17 35
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33204920 WTP Electrical Room - Control Panel Installation 6 02-Dec-16 08-Dec-16 106
03PMS-BL00.3.3.2.05 Condenser
Co 287 19-Sep-16 16-Aug-17 53
XAC03-33205110 Mechanical Work - Base Plate / Sliding Plate Setting 13 09-Mar-17 23-Mar-17 44
03PMS-BL00.3.3.2.06 Cooling
Co Tower 244 21-Sep-16 28-Jun-17 2
XAC03-33206140 Mechanical Work - Fan / Motor / Gear Box / Reducer Installation 9 16-Mar-17 27-Mar-17 30
XAC03-33206220 Electrical Work - Megger Check & Continuity Cable 4 27-Apr-17 01-May-17 30
03PMS-BL00.3.3.2.07 Air
Ai Compressor System 134 13-Jan-17 16-Jun-17 199
XAC03-33207310 Air Reciever Tank - Chipping and Packer Setting 4 18-Jan-17 23-Jan-17 73
XAC03-33207320 Air Reciever Tank - Air Receiver Tank Installation 1 23-Jan-17 24-Jan-17 73
03PMS-BL00.3.3.2.09 Co
Condenser Ball Cleaning System 169 23-Jan-17 07-Aug-17 61
XAC03-33209320 Electrical / C&I Work - Cabling & Termination Works 3 10-Jul-17 12-Jul-17 72
XAC03-33209330 Electrical / C&I Work - Megger Check & Continuity Cable 2 13-Jul-17 14-Jul-17 72
03PMS-BL00.3.3.2.10 Ch
Chemical dosing system for HRSG Unit #30 109 20-Mar-17 24-Jul-17 33
XAC03-33210110 Mechianical Workv - HRSG Chemical Dosing Skid Installation 3 10-May-17 12-May-17 33
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.3.2.11 Ch
Chemical dosing system for CT Unit #30 142 16-Jan-17 28-Jun-17 2
03PMS-BL00.3.3.2.13 HVAC
HV 163 05-Dec-16 10-Jun-17 205
XAC03-33213710 HRSG Local Control Compartment - HVAC System - Install AC Unit 6 10-Dec-16 17-Dec-16 170
03PMS-BL00.3.3.2.14 Fir
Fire Fighting System 272 05-Sep-16 15-Jul-17 175
XAC03-3321401A Interface - MHO for Fire Fighting Ring Main & Others 0 05-Sep-16* 143
XAC03-3321402C Interface - CTO for E&C Biulding For Ground Floor 0 17-Dec-16* 72
XAC03-33214110 Fire Alarm System - Devices, Conduit, Cabling Installation 22 02-Nov-16* 26-Nov-16 359
03PMS-BL00.3.3.2.14.2.1 GT 31 GSUT
03PMS-BL00.3.3.2.14.2 38 31-Mar-17 15-May-17 8
03PMS-BL00.3.3.2.14.2.2 GT 32 GSUT
03PMS-BL00.3.3.2.14.2 38 31-Mar-17 15-May-17 68
03PMS-BL00.3.3.2.14.2.3 ST 3 GSUT
03PMS-BL00.3.3.2.14.2 39 01-Apr-17 17-May-17 66
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33214241 Unit Auxilliary Trans. 31 & 32 - Scaffolding Work Including Inspction 3 11-Jan-17* 13-Jan-17 77
XAC03-33214242 Unit Auxilliary Trans. 31 & 32 - Support Installation & Piping Work 21 14-Jan-17 07-Feb-17 77
XAC03-33214244 Unit Auxilliary Trans. 31 & 32 - Line Check & Punch Clearing 4 08-Feb-17 11-Feb-17 77
XAC03-33214247 Unit Auxilliary Trans. 31 & 32 - Painting Inspection & Remove Scaffolding 3 22-Feb-17 24-Feb-17 77
XAC03-33214243 Unit Auxilliary Trans. 31 & 32 - Conduit and Cabling Work 39 05-Apr-17 20-May-17 63
03PMS-BL00.3.3.2.14.2.5 LV Transformer
03PMS-BL00.3.3.2.14.2 62 21-Dec-16 01-Mar-17 73
XAC03-33214251 LV Transformer - Fire Fighting System - Scaffolding Work Including Inspction 14 21-Dec-16* 05-Jan-17 73
XAC03-33214252 LV Transformer - Fire Fighting System - Support Installation & Piping Work 26 06-Jan-17 04-Feb-17 73
XAC03-33214253 LV Transformer - Fire Fighting System - Line Check & Punch Clearing 6 06-Feb-17 11-Feb-17 73
XAC03-33214256 LV Transformer - Fire Fighting System - Painting Inspection & Remove Scaffolding 3 27-Feb-17 01-Mar-17 73
XAC03-33214311 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Support Installation & Piping Work 27 30-Jan-17 02-Mar-17 34
XAC03-33214312 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Line Check & Punch Clearing 6 02-Mar-17 09-Mar-17 34
XAC03-33214313 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Hydro-Test 3 09-Mar-17 13-Mar-17 34
XAC03-33214314 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Painting Work 6 13-Mar-17 20-Mar-17 34
XAC03-33214315 Fire Fighting / Fire Alarm - GF Sprinkle Installation - Painting Inspection 1 20-Mar-17 21-Mar-17 34
XAC03-33214321 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Support Installation & 61 30-Jan-17* 10-Apr-17 19
Piping Work
XAC03-33214322 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Line Check & Punch 2 10-Apr-17 12-Apr-17 19
Clearing
XAC03-33214323 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Hydro-Test 3 12-Apr-17 15-Apr-17 19
XAC03-33214324 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Painting Work 2 15-Apr-17 18-Apr-17 19
XAC03-33214325 Fire Fighting / Fire Alarm - Hydrant installation (1st FL-3rd FL) - Painting Inspection 2 18-Apr-17 20-Apr-17 19
XAC03-33214412 Indoor Hydrant - Support Installation & Piping Work 18 17-May-17 06-Jun-17 99
XAC03-33214413 Indoor Hydrant - Line Check & Punch Clearing 3 07-Jun-17 09-Jun-17 99
XAC03-33214416 Indoor Hydrant - Painting Inspection & Remove Scaffolding 3 20-Jun-17 22-Jun-17 99
XAC03-33214422 Fire Alarm Install - STG Building (Lube Oil & Transfer) 26 22-May-17 20-Jun-17 101
XAC03-33214612 Mechanical Work - On Base Diesel/Electric/Jucky Pump/Fuel Oil Tank 3 05-Dec-16 07-Dec-16 121
XAC03-33214621 FF Pumps Suction, Discharge & Recirculation Line - Scaffolding Work Including 3 30-Nov-16 02-Dec-16 65
Inspection
XAC03-33214622 FF Pumps Suction, Discharge & Recirculation Line - Support Installation & Piping Work 25 06-Dec-16 03-Jan-17 63
XAC03-33214623 FF Pumps Suction, Discharge & Recirculation Line - Line Check & Punch Clearing 6 04-Jan-17 10-Jan-17 63
XAC03-33214624 FF Pumps Suction, Discharge & Recirculation Line - Hydro-Test 3 11-Jan-17 13-Jan-17 63
XAC03-33214625 FF Pumps Suction, Discharge & Recirculation Line - Painting Work 6 13-Jan-17 20-Jan-17 93
XAC03-33214626 FF Pumps Suction, Discharge & Recirculation Line - Painting Inspection & Remove 3 20-Jan-17 24-Jan-17 93
Scaffolding
03PMS-BL00.3.3.2.14.6 Electrical / C&I Work
03PMS-BL00.3.3.2.14.6.3 32 13-Jan-17 20-Feb-17 63
XAC03-33214631 Electrical / C&I Work - Cable Tray & Support 3 13-Jan-17 17-Jan-17 63
XAC03-33214711 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - Excavation & Sand Bedding Including 6 05-Sep-16* 10-Sep-16 160
Density Test (by TPSC)
XAC03-33214712 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - HDPE Pipe Line-up & Welding Work 4 12-Sep-16 15-Sep-16 160
XAC03-33214713 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - Hydro-Test 2 16-Sep-16 17-Sep-16 160
XAC03-33214714 U/G HDPE Pipe - Ret. Pit & HRSG 32 Area - Backfilling Including Density Test (by 6 19-Sep-16 24-Sep-16 160
TPSC)
XAC03-33214715 U/G HDPE Pipe - HRGS 31 to STG Bldg Area - Excavation & Sand Bedding Including 6 26-Sep-16 01-Oct-16 160
Density Test (by TPSC)
XAC03-33214716 U/G HDPE Pipe - HRGS 31 to STG Bldg Area - HDPE Pipe Line-up & Welding Work 4 03-Oct-16 06-Oct-16 160
XAC03-33214717 U/G HDPE Pipe - HRGS 31 to STG Bldg Area - Hydro-Test 3 07-Oct-16 10-Oct-16 160
XAC03-33214718 U/G HDPE Pipe Installation - HRGS 31 to STG Bldg Area - Backfilling Including Density 6 11-Oct-16 17-Oct-16 160
Test (by TPSC)
XAC03-33214719 U/G HDPE Pipe - GSUT & UAT Area - Excavation & Sand Bedding Including Density 6 18-Oct-16 24-Oct-16 160
Test (by TPSC)
XAC03-3321471A U/G HDPE Pipe - GSUT & UAT Area - HDPE Pipe Line-up & Welding Work 4 25-Oct-16 28-Oct-16 160
XAC03-3321471B U/G HDPE Pipe - GSUT & UAT Area - Hydro-Test 3 29-Oct-16 01-Nov-16 160
XAC03-3321471C U/G HDPE Pipe - GSUT & UAT Area - Backfilling Including Density Test (by TPSC) 6 02-Nov-16 09-Nov-16 160
XAC03-33214721 A/G Steel Pipe - A/G Pipe on Pipe Sleeper (WTP Area) 12 12-Oct-16* 25-Oct-16 160
XAC03-33214722 A/G Steel Pipe - A/G Pipe on Pipe Sleeper (Tank Ar ea) 12 12-Oct-16* 25-Oct-16 160
XAC03-33214723 A/G Steel Pipe - A/G Pipe on Pipe Rack (South-2 Area 13.5m) 6 02-Nov-16* 08-Nov-16 154
XAC03-33214724 A/G Steel Pipe - A/G Pipe on Pipe Rack (South-1 Area 18m) 6 10-Nov-16* 16-Nov-16 153
XAC03-33214810 EDG - Sprinkler System - Marking and Check Location 1 25-Feb-17* 25-Feb-17 284
XAC03-33214820 EDG - Sprinkler System - Piping and Support Fabrication 2 27-Feb-17 28-Feb-17 284
XAC03-33214830 EDG - Sprinkler System - Support Installation & Piping Work 4 01-Mar-17 04-Mar-17 284
XAC03-33214840 EDG - Sprinkler System - Line Check before Hydro Test 1 06-Mar-17 06-Mar-17 284
XAC03-33214870 EDG - Sprinkler System - Painting Inspection and Punch Clearing 1 10-Mar-17 10-Mar-17 284
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33214910 Fire Alarm System - Devices, Conduit, Cabling Installation 22 02-Nov-16* 26-Nov-16 360
03PMS-BL00.3.3.2.15 11
115kV Switch Yard 216 30-Sep-16 08-Jun-17 207
XAC03-3321501C Interface - ABPR3 SWYD MHO-3 (Main Equipment & AC/DC Panel) 0 15-Dec-16* 79
XAC03-33215311 Lifting Steel Support For Main Bus No.1 1 24-Dec-16 26-Dec-16 258
XAC03-33215312 Install Steel Support For Main Bus No.1 5 26-Dec-16 31-Dec-16 308
XAC03-33215313 Lifting Steel Support For CVT -Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258
XAC03-33215314 Lifting Steel Support For Main Bus No.1-Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258
XAC03-33215315 Install Steel Support For Main Bus No.1-Pile Deviated FDN. 5 02-Jan-17 07-Jan-17 302
XAC03-33215316 Install Steel Support For CVT Main Bus No.1-Pile Deviated 5 02-Jan-17 07-Jan-17 258
XAC03-33215318 Install CVT 115 kV included Junction Box 15 07-Jan-17 25-Jan-17 302
XAC03-3321531A AL Tube - Lifting AL tube and Fixing-(After lifting PASS M00) 1 16-Feb-17 17-Feb-17 302
XAC03-33215321 Lifting Steel Support For Main Bus No.2 1 24-Dec-16 26-Dec-16 258
XAC03-33215322 Install Steel Support For Main Bus No.2 5 26-Dec-16 31-Dec-16 258
XAC03-33215323 Lifting Steel Support For Main Bus No.2-Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258
XAC03-33215324 Lifting Steel Support For CVT -Pile Deviated Foundation 1 31-Dec-16 02-Jan-17 258
XAC03-33215325 Install Steel Support For Main Bus No.2-Pile Deviated FDN. 5 02-Jan-17 07-Jan-17 307
XAC03-33215326 Install Steel Support For CVT Main Bus No.2-Pile Deviated 5 02-Jan-17 07-Jan-17 258
XAC03-33215328 Install CVT 115 kV included Junction Box 15 07-Jan-17 25-Jan-17 302
XAC03-3321532A AL Tube - Lifting AL tube and Fixing-(After lifting PASS M00) 1 16-Feb-17 17-Feb-17 302
XAC03-33215363 Install Steel Support Junction Box CVT 5 20-Feb-17 25-Feb-17 270
XAC03-33215373 Install Steel Support Junction Box CVT 5 27-Feb-17 04-Mar-17 268
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33215383 Install Steel Support Junction Box CVT 5 06-Mar-17 11-Mar-17 272
03PMS-BL00.3.3.2.16 Lig
Lightning Protection 124 12-Jan-17 05-Jun-17 210
03PMS-BL00.3.3.2.17 Earthing
Ea 223 14-Jul-16 28-Mar-17 269
XAC03-3321702B Interface - Earthing - CTO for Power Plant Area 0 10-Aug-16 269
XAC03-33217110 Erection - Earthing - Power Plant Area 200 10-Aug-16 28-Mar-17 269
03PMS-BL00.3.3.2.18 Lig
Lighting 211 12-Jan-17 13-Sep-17 122
XAC03-33218310 Lighting for Other - Lighting System 120 28-Apr-17 13-Sep-17 122
XAC03-33219150 ST Over Head Crane 5 ton - Conduit and Internal Cabling 14 05-Apr-17 21-Apr-17 33
03PMS-BL00.3.3.3 Process
Proces Package 298 01-Oct-16 11-Sep-17 125
XAC03-33301110 HP Main Steam System - HP Turbine Bypass Valve Installation 1 25-Mar-17 25-Mar-17 271
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33302110 Bypass Valve - LP Turbine Bypass Valve Installation 1 09-Mar-17 09-Mar-17 285
XAC03-33302290 Additonal Chemical Clean for Steam Line - Preparation for Steam Pipe Chemical Clean 4 20-Jul-17 24-Jul-17 25
XAC03-333022A0 Additonal Chemical Clean for Steam Line - Steam Pipe Chemical Clean 5 25-Jul-17 29-Jul-17 25
XAC03-333022B0 Additonal Chemical Clean for Steam Line - Restoration 2 31-Jul-17 01-Aug-17 25
03PMS-BL00.3.3.3.03 Extraction
Ex Steam System 185 08-Feb-17 11-Sep-17 125
XAC03-33303110 Equipment - Silencer Structure Fabrication and Installation 7 09-Mar-17 16-Mar-17 265
XAC03-33303130 Equipment - Extraction Steam Bypass Valve Installation 7 24-Mar-17 01-Apr-17 265
03PMS-BL00.3.3.3.04 Aux
Au Steam System 150 09-Mar-17 30-Aug-17 0
03PMS-BL00.3.3.3.05 Condensate
Co Water System 146 13-Jan-17 01-Jul-17 91
XAC03-33305211 From CEP to Pipe Rack - On Pipe Rack to Deaerator 21 27-Mar-17 20-Apr-17 136
XAC03-33305223 Piping Work - CEP Suction Line Check with Owner 1 08-Apr-17 10-Apr-17 133
XAC03-33305224 Piping Work - CEP Suction Line Punch A, B Clear 2 10-Apr-17 12-Apr-17 133
XAC03-33305227 Piping Work - Bearing Sealing/Vacuum Seal Line 10 19-Apr-17 01-May-17 103
XAC03-3330522B Piping Work - Gland Seal Steam Spray Line 5 22-Apr-17 28-Apr-17 105
XAC03-3330522D Piping Work - CEP Discharge Line Check with Owner 7 15-May-17 23-May-17 91
XAC03-3330601A Interface - MHO for FW Heat Exchanger - HP Feedwater System 0 08-Feb-17* 131
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33306110 HP Feed Water Pump - HP Feed Water Pump Installation 9 15-Mar-17 25-Mar-17 60
XAC03-33306Z20 Access Platform - Dearator Tower Access - Installation 9 16-Mar-17 25-Mar-17 271
XAC03-33306Z30 Access Platform - FWHE Outlet Isolation Valve Acc ess - Delivery 0 25-Mar-17* 114
XAC03-33306Z40 Access Platform - FWHE Outlet Isolation Valve Acc ess - Installation 8 27-Mar-17 04-Apr-17 114
03PMS-BL00.3.3.3.08 Main
Ma Cooling Water System 197 10-Dec-16 25-Jul-17 71
XAC03-33308010 Interface - Main Cooling Water System - MHO lot 2 (MCW Pump) 0 10-Dec-16* 95
XAC03-33308030 Interface - Main Cooling Water System - MHO lot 1 (Pipe) 0 13-Jan-17* 69
XAC03-33308020 Interface - Main Cooling Water System - CTO for Pump 0 17-Jan-17* 79
XAC03-33308040 Interface - Main Cooling Water System - CTO for Piping 0 30-Mar-17* 71
XAC03-33308320 Electrical Work - Megger Check & Continuity Cable 4 24-May-17 27-May-17 94
03PMS-BL00.3.3.3.09 Au
Auxiliary Cooling Water System 176 10-Dec-16 30-Jun-17 0
XAC03-33309110 Auxiliary Cooling Water Pump - Auxiliary Cooling Water Pump Intallatio n 4 18-Jan-17 23-Jan-17 62
XAC03-33309420 Electrical / C&I Work - Cabling & Termination Works 3 10-Mar-17 14-Mar-17 62
XAC03-33309430 Electrical / C&I Work - Megger Check & Continuity Cable 2 21-Mar-17 23-Mar-17 62
XAC03-33309470 Electrical / C&I Work - System Handover Walk Down 1 23-Mar-17 24-Mar-17 62
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33310220 Piping Work - BOP Pipe Sleeper line, Tank - Pump 6 20-Mar-17 25-Mar-17 50
XAC03-33310230 Piping Work - BOP Pipe Sleeper line, Pump - Cooling Tower 9 27-Mar-17 06-Apr-17 50
XAC03-33310210 Piping Work - BOP Pipe Sleeper line, WTP - Tank 6 29-Mar-17 04-Apr-17 51
XAC03-33310260 Piping Work - CT MU Water System Handover to commissioning walkdown 1 12-Apr-17 12-Apr-17 50
03PMS-BL00.3.3.3.11 Clo
Closed Cycle Cooling Water System 199 14-Nov-16 30-Jun-17 0
XAC03-3331101A Interface - MHO (CCCW Head Tank) - Closed Cycle Cooling Water System 0 14-Nov-16* 134
XAC03-3331101B Interface - MHO (CCCW pump) - Closed Cycle Cooling Water System 0 15-Feb-17* 49
XAC03-3331101C Interface - MHO (Heat Exchanger) - Closed Cycle Cooling Water System 0 15-Feb-17* 72
XAC03-3331101D Interface - MHO (Pipe) - Closed Cycle Cooling Water System 0 15-Feb-17* 26
XAC03-33311210 CCCW Heat Exchanger - Chipping and Packer Setting 4 15-Feb-17 18-Feb-17 72
XAC03-33311220 CCCW Heat Exchanger - CCCW Heat Exchanger Installation 1 20-Feb-17 21-Feb-17 72
XAC03-33311410 Piping Work - At CCCW Pump area to Pipe Rack 17 16-Mar-17 05-Apr-17 44
XAC03-33311480 Piping Work - Temporary Bypass Piping for Flushing 4 29-Apr-17 04-May-17 23
XAC03-33311Z10 Access Platform - Platform for Process Steam Header - Delivery 0 25-Apr-17 41
XAC03-33311Z20 Access Platform - Platform for Process Steam Header - Installation 1 26-Apr-17 26-Apr-17 41
03PMS-BL00.3.3.3.12 Condenser
Co Vacuum System 115 10-Feb-17 23-Jun-17 99
XAC03-3331201B Interface - MHO for Pipe - Condenser Vacuum System 0 18-Apr-17* 138
03PMS-BL00.3.3.3.13 Ra
Raw Water Distribution System (Common) 169 01-Oct-16 13-Apr-17 24
XAC03-33313020 Interface - CTO Raw Water Pump, Buffa Tank 0 01-Oct-16* 103
XAC03-33313110 Raw Water Buffer tank - Chipping and Packer Setting 4 30-Dec-16 04-Jan-17 24
XAC03-33313120 Raw Water Buffer tank - Raw Water Buffer Tank On Base 3 05-Jan-17 07-Jan-17 24
XAC03-33313210 Raw Water Pump - Chipping and Packer Setting 4 31-Dec-16 04-Jan-17 85
XAC03-33313220 Raw Water Pump - Raw Water Pump On Base 2 05-Jan-17 06-Jan-17 85
XAC03-33313410 Piping Work - Buffer Tank and Pump Area 35 12-Jan-17 21-Feb-17 24
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.3.3.14 Service
Se water Distribution System 112 13-Feb-17 21-Jun-17 36
XAC03-3331401B Interface - Service Water Distribution System - MHO for SWP 0 13-Feb-17* 106
XAC03-3331401C Interface - Service Water Distribution System - MHO for Pipe Lot-1 (Around Tank) 0 20-Feb-17* 113
XAC03-3331401A Interface - Service Water Distribution System - MHO for Pipe Lot-2 0 20-Feb-17* 92
XAC03-33314230 Piping Work - BOP Pipe Sleeper line, Tank - Pump 5 14-Mar-17 20-Mar-17 90
XAC03-33314220 Piping Work - BOP Pipe Sleeper line, WTP - Tank 7 15-Mar-17 23-Mar-17 92
XAC03-33314240 Piping Work - BOP Pipe Sleeper line, Pump - Fire Pump 6 20-Mar-17 27-Mar-17 90
XAC03-33314250 Piping Work - BOP Pipe Sleeper line, Pump - other 6 25-Mar-17 31-Mar-17 85
XAC03-33314290 Piping Work - Sirvice Water System Handover to commissioning walkdown 1 06-Apr-17 07-Apr-17 85
XAC03-333142B0 Piping Work - Sirvice Water System Handover to comissioing 1 14-Apr-17 15-Apr-17 85
03PMS-BL00.3.3.3.15 De
Demineralized water Distribution System 118 06-Feb-17 21-Jun-17 0
XAC03-3331501A Interface - Demineralized Water Distribution System - MHO for Pipe Lot-1 (Around 0 06-Feb-17* 98
Tank)
XAC03-3331501B Interface - Demineralized Water Distribution System - MHO Pump 0 13-Feb-17* 31
XAC03-3331501C Interface - Demineralized Water Distribution System - MHO for Pipe Lot-2 0 20-Feb-17* 92
XAC03-33315230 Piping Work - BOP Pipe Sleeper line, WTP - Tank 6 06-Feb-17 11-Feb-17 98
XAC03-33315240 Piping Work - BOP Pipe Sleeper line, Tank - Pump 5 14-Mar-17 20-Mar-17 55
XAC03-33315250 Piping Work - BOP Pipe Sleeper line, Pump - Sleeper 11 20-Mar-17 01-Apr-17 55
XAC03-33315340 Electrical Work - CT Make up / SW / DM Water System Handover to commissioning 1 18-May-17 18-May-17 14
walkdown
XAC03-33315350 Electrical Work - Punch Clear 6 18-May-17 25-May-17 14
XAC03-33315360 Electrical Work - CT Make up / SW / DM Water System Handover to comissioing 1 25-May-17 26-May-17 14
03PMS-BL00.3.3.3.16 Waste
Wa water collection System 138 09-Jan-17 17-Jun-17 199
XAC03-3331601B Interface - Waste Water Collection System - MHO for Retention Pump 0 01-Feb-17* 117
XAC03-3331601C Interface - Waste Water Collection System - MHO for Sump Pump 0 01-Feb-17* 52
XAC03-33316211 Electrical Work - Retention Pit / Emergency Pit - Consuit / Support 4 28-Mar-17 01-Apr-17 74
XAC03-33316212 Electrical Work - Retention Pit / Emergency Pit - Cabling / Termination 10 14-Apr-17 26-Apr-17 63
XAC03-33316213 Electrical Work - Retention Pit / Emergency Pit - Instrument Installation 2 26-Apr-17 28-Apr-17 63
XAC03-33316214 Electrical Work - Retention Pit / Emergency Pit - Handover to Commissioning Walkdown 1 28-Apr-17 29-Apr-17 63
XAC03-33316215 Electrical Work - Retention Pit / Emergency Pit - Punch Clear 4 29-Apr-17 04-May-17 63
XAC03-33316216 Electrical Work - Retention Pit / Emergency Pit - Handover to Commissioning 1 04-May-17 05-May-17 63
XAC03-33316221 Electrical Work - Oily Water Separator - Consuit / Support 3 01-Mar-17 04-Mar-17 98
XAC03-33316222 Electrical Work - Oily Water Separator - Cabling / Termination 4 04-Mar-17 09-Mar-17 98
XAC03-33316223 Electrical Work - Oily Water Separator - Instrument Installation 1 09-Mar-17 10-Mar-17 98
XAC03-33316224 Electrical Work - Oily Water Separator - Handover to Commissioning Walkdown 1 10-Mar-17 11-Mar-17 98
XAC03-33316225 Electrical Work - Oily Water Separator - Punch Clear 5 11-Mar-17 17-Mar-17 98
XAC03-33316226 Electrical Work - Oily Water Separator - Handover to Commissioning 1 25-Mar-17 25-Mar-17 98
XAC03-33316231 Electrical Work - Oily Water Separator - Consuit / Support 3 04-Mar-17 07-Mar-17 103
XAC03-33316232 Electrical Work - Oily Water Separator - Cabling / Termination 4 08-Mar-17 11-Mar-17 103
XAC03-33316233 Electrical Work - Oily Water Separator - Instrument Installation 1 13-Mar-17 13-Mar-17 103
XAC03-33316234 Electrical Work - Oily Water Separator - Handover to Commissioning Walkdown 1 14-Mar-17 14-Mar-17 103
XAC03-33316235 Electrical Work - Oily Water Separator - Punch Clear 4 15-Mar-17 18-Mar-17 103
XAC03-33316236 Electrical Work - Oily Water Separator - Handover to Commissioning 1 20-Mar-17 20-Mar-17 103
XAC03-33316310 Retention Pit - Piping Retention Basin Pit Piping Installation 26 20-Feb-17* 22-Mar-17 79
XAC03-33316320 Retention Pit - Mechanical Retention Pit / Emergency Pump Installation 5 22-Mar-17 28-Mar-17 74
XAC03-33316410 Auxiliary Transformer Area Drain Pit - Sump Pump for pit 1 & 2 Installation 5 09-Mar-17 14-Mar-17 60
XAC03-33316420 Auxiliary Transformer Area Drain Pit - Piping to Oil Water Separator Sump Pit 14 14-Mar-17 30-Mar-17 60
XAC03-33316430 Auxiliary Transformer Area Drain Pit - Handover to Comm. prior to Tr pre-commissioning 0 30-Mar-17 60
XAC03-33316510 Step Up / UAT Transformer Area Drain Pit - Sump Pump Installation 5 01-Feb-17 06-Feb-17 52
XAC03-33316520 Step Up / UAT Transformer Area Drain Pit - Piping to Oil Water Seperator Sump Pit 36 06-Feb-17 20-Mar-17 52
XAC03-33316530 Step Up / UAT Transformer Area Drain Pit - Handover to Comm. prior to Tr 0 20-Mar-17 52
pre-commissioning
03PMS-BL00.3.3.3.16.6 GTG Oily Drain Pit 67 01-Feb-17 19-Apr-17 77
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33316620 GTG Oily Drain Pit - Piping to Oil Water Separator Sump Pit 30 16-Mar-17 19-Apr-17 77
XAC03-33316630 GTG Oily Drain Pit - Handover to Comm. prior to Tr pre-commissioning 0 19-Apr-17 77
XAC03-33316720 Oil Water Separator Sump Pit - Retention Basin Pit Piping Installation 24 02-Feb-17* 01-Mar-17 50
XAC03-33316710 Oil Water Separator Sump Pit - Mechanical Retention Pit Pump Installation 2 27-Feb-17 01-Mar-17 98
XAC03-33316810 HRSG Blowdown Tank Pit Sump - Sump Pump for pit 1 & 2 Installation 10 22-Mar-17 03-Apr-17 71
XAC03-33316820 HRSG Blowdown Tank Pit Sump - Piping to CT Area basin 31 03-Apr-17 09-May-17 71
XAC03-33316830 HRSG Blowdown Tank Pit Sump - Handover to Comm. prior to Simple Cycle opreration 0 09-May-17 71
XAC03-33316A10 CEP Pit Sump - Sump Pump Installation 5 27-Mar-17 01-Apr-17 136
XAC03-33316A20 CEP Pit Sump - Piping to Oil Water Separator Sump Pit 24 01-Apr-17 29-Apr-17 136
XAC03-33316A30 CEP Pit Sump - Handover to Comm. prior to CEP commissioning 0 29-Apr-17 136
XAC03-33316B10 CT/CWP Area Pit - Sump Pump Installation 2 02-Mar-17* 03-Mar-17 103
XAC03-33316C10 STG Area Pit - Sump Pump Installation 5 07-Apr-17 12-Apr-17 106
XAC03-33316C20 STG Area Pit - Piping to Retention Pit 30 13-Apr-17 17-May-17 106
XAC03-33316C30 STG Area Pit - Handover to Comm. prior to Combined Cycle 0 17-May-17 106
XAC03-33316D10 EDG Oily Drain Pit Sump - Sump Pump Installation 5 03-Apr-17 08-Apr-17 61
XAC03-33316D20 EDG Oily Drain Pit Sump - Piping to Oil Water Separator 30 08-Apr-17 12-May-17 61
XAC03-33316D30 EDG Oily Drain Pit Sump - Handover to Comm. prior to EDG Commissioning 0 13-May-17 61
XAC03-33316E30 GT Water Wash Pit - Handover to Comm. prior to Combined Cycle 0 13-Mar-17 52
03PMS-BL00.3.3.3.17 Instrument
Ins & Service Air System (Common) 164 06-Feb-17 12-Aug-17 150
XAC03-33317010 Interface - Instrument & Service Air System - MHO Pipe 0 06-Feb-17* 285
XAC03-33317020 Interface - Instrument & Service Air System - CTO 0 31-Mar-17* 214
03PMS-BL00.3.3.3.18 Fu
Fuel Gas Distribution System 153 02-Feb-17 28-Jul-17 0
XAC03-3331801A Interface - MHO Fuel Gas Filter - Fuel Gas Distribution System 0 02-Feb-17* 83
XAC03-3331801B Interface - MHO Fuel Gas Pipe - Fuel Gas Distribution System 0 22-Feb-17* 41
03PMS-BL00.3.3.3.19 Fuel
Fu Gas Heater System 153 02-Feb-17 27-Jul-17 4
03PMS-BL00.3.3.4 Electrical
Electri Package 341 08-Aug-16 06-Sep-17 129
03PMS-BL00.3.3.4.01 Generator
Ge Transformer 133 07-Jan-17 12-Jun-17 109
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.3.4.02 Un
Unit Auxiliary Transformer 81 09-Mar-17 10-Jun-17 0
XAC03-3340204B Interface - TOP - Unit Auxiliary Transformer (Ready for Power Receiving) 0 10-Jun-17 0
XAC03-33402130 Unit Axiliary Transformer - Insulation Oil Treatment and Filling 7 25-Apr-17 03-May-17 27
XAC03-33403120 6.6kV Switchgear - Electrical Work - channel base setting & on base 2 30-Dec-16 31-Dec-16 100
XAC03-33403110 6.6kV Switchgear - Electrical Work - Cabling (Power & Control/Panel to Panel) 55 30-Dec-16 02-Mar-17 50
XAC03-33403130 6.6kV Switchgear - Electrical Work - 6.6kV SWGR Install 9 02-Jan-17 12-Jan-17 100
XAC03-33403140 6.6kV Switchgear - Electrical Work - busbar connection 8 12-Jan-17 20-Jan-17 100
XAC03-33403150 6.6kV Switchgear - Electrical Work - busbar torque check (RFI) 1 21-Jan-17 21-Jan-17 100
XAC03-33403160 6.6kV Switchgear - Electrical Work - Hipot Test Busbar 2 23-Jan-17 24-Jan-17 100
XAC03-33403170 6.6kV Switchgear - Electrical Work - Handover to Commissioning Walkdown 1 03-Mar-17 03-Mar-17 68
XAC03-33404120 LV Switchgear (CCB 1F) - Electrical Work - Channel Base setting 2 06-Jan-17 07-Jan-17 100
XAC03-33404130 LV Switchgear (CCB 1F) - Electrical Work - 400V Main Switchgear Install 5 09-Jan-17 13-Jan-17 100
XAC03-33404140 LV Switchgear (CCB 1F) - Electrical Work - 400V Sub Switchgear Install 5 14-Jan-17 19-Jan-17 100
XAC03-33404110 LV Switchgear (CCB 1F) - Electrical Work - Cabling (Power & Control/Panel to Panel) 60 16-Jan-17 25-Mar-17 50
XAC03-33404150 LV Switchgear (CCB 1F) - Electrical Work - 400V Essential Switchgear Install 6 20-Jan-17 27-Jan-17 100
XAC03-33404160 LV Switchgear (CCB 1F) - Electrical Work - Handover to Commissioning Walkdown 1 27-Mar-17 27-Mar-17 50
XAC03-33404170 LV Switchgear (CCB 1F) - Electrical Work - Punch Clear 5 28-Mar-17 01-Apr-17 50
XAC03-33404180 LV Switchgear (CCB 1F) - Electrical Work - Handover to Commissioning 1 03-Apr-17 03-Apr-17 50
XAC03-33405120 LV Transformer - Electrical Works - Installation (cable tray, cables) 27 31-Jan-17 02-Mar-17 81
03PMS-BL00.3.3.4.06 Mo
Motor Control Center /Distribution Panel 163 09-Dec-16 16-Jun-17 14
XAC03-33406110 Electrical Work - Install MCC & DCS Panel 5 13-Jan-17 18-Jan-17 102
XAC03-33406130 Electrical Work - Devices, Conduit & Cabling Install 12 15-Mar-17 29-Mar-17 76
XAC03-33406210 Electrical Work - Install MCC & DCS Panel 5 15-Mar-17 20-Mar-17 45
XAC03-33406230 Electrical Work - Devices, Conduit & Cabling Install 12 27-Apr-17 11-May-17 45
XAC03-33407250 Electrical Work - Cable Megger & Continuity Check (RFI) 2 16-Mar-17 17-Mar-17 12
03PMS-BL00.3.3.4.08 Emergency
Em DG System 133 30-Jan-17 04-Jul-17 25
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-33408320 Electrical Work - Handover Walk Down to Commissioning 1 07-Mar-17 07-Mar-17 113
03PMS-BL00.3.3.4.09 Cable
Ca & Raceway 341 08-Aug-16 06-Sep-17 129
XAC03-3340902I Interface - CTO - Cable Trench 6 (GSU Transformer area) 0 08-Aug-16 470
XAC03-3340902J Interface - CTO - Cable Trench (STG#30 - Pipe Rack RB) 0 15-Aug-16 465
XAC03-3340902A Interface - CTO - Cable & Raceway - E&C Building Ground Floor 0 27-Aug-16 100
XAC03-3340902K Interface - CTO - Cable Trench (STG#30 - Pipe Rack RB Road Crossing) 0 01-Sep-16 449
XAC03-3340902R Interface - CTO - Sleeper FDN for SWYD - Pipe Rack RB 0 14-Sep-16 438
XAC03-3340902M Interface - CTO - Cable Trench (GTG #31 Area) 33.00m 0 22-Sep-16 430
XAC03-3340901A Interface - MHO - Cable & Raceway - lot 1(ABPR3 Power Received) 0 11-Oct-16* 63
XAC03-3340902S Interface - CTO - Pipe Rack RB (BOP Area Road Crossing) 0 25-Nov-16 375
XAC03-3340902N Interface - CTO - Cable Trench (GTG #32 Area) 33.00m 0 28-Nov-16 374
XAC03-3340901B Interface - MHO - Cable & Raceway - lot 2 (Initial Fire) 0 15-Dec-16* 154
XAC03-3340902H Interface - CTO - Cable Trench (Road Crossing STG #30 - SWYD) 33.00 m. 0 03-Jan-17 343
XAC03-3340902D Interface - CTO - Cable & Raceway - E&C Building 1st Floor 0 07-Jan-17 8
XAC03-3340902C Interface - CTO - Cable & Raceway - (ABPR3 P/R btwn SWYD and ECB) 0 07-Jan-17* 14
XAC03-3340902G Interface - CTO - Cable Trench (E&C Building - Pipe Rack RE) 0 07-Jan-17 338
XAC03-3340902E Interface - CTO - Cable & Raceway - E&C Building 2nd Floor 0 12-Jan-17 1
XAC03-3340901C Interface - MHO - Cable & Raceway - lot 3 (ABPR3 Combined) 0 13-Jan-17* 54
XAC03-3340902B Interface - CTO - Cable & Raceway - E&C Building 3rd Floor 0 24-Jan-17 31
XAC03-3340902O Interface - CTO - Cable Trench (Road Crossing GTG 31 - SWYD ) 33.00 m. 0 28-Jan-17 319
XAC03-3340902Q Interface - CTO - Cable Trench (Road Crossing GTG 32 - E&C Building ) 33.00 m. 0 30-Jan-17 318
XAC03-3340902F Interface - CTO - Cable & Raceway - All Pipe Rack (ABPR3 Area) 0 10-Apr-17* 219
XAC03-3340903B Interface - MC - Cable & Raceway - (ABPR3 Power Receive) 0 18-Apr-17* 252
XAC03-3340902P Interface - CTO - Cable Trench (Road Crossing GTG 32 - SWYD ) 33.00 m. 0 09-Jun-17 205
03PMS-BL00.3.3.5.01 DCS
DC 177 08-Feb-17 31-Aug-17 134
XAC03-3350102B Interface - CTO (HRSG Control Building Panel Installation) 0 14-Mar-17 281
XAC03-33501130 Electrical Wok - DCS (3F) - DCS Cable Pulling & Termination for Power Receiving Area 33 08-Feb-17 17-Mar-17 31
XAC03-33501110 Electrical Wok - DCS (3F) - Channel Base Material at Site 0 23-Feb-17 36
XAC03-33501120 Electrical Wok - DCS (3F) - Channel Base Setting 9 23-Feb-17 04-Mar-17 36
XAC03-33501150 Electrical Wok - DCS (3F) - Comissioning Handover Walk Down 1 18-Mar-17 18-Mar-17 31
03PMS-BL00.3.3.5.02 St
Steam and Water Sampling System 126 02-Feb-17 28-Jun-17 55
03PMS-BL00.3.3.5.03 Co
Continuous Emission Monitoring System 122 10-Mar-17 28-Jul-17 3
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.3.5.04 Clock
Cl System 44 09-May-17 28-Jun-17 23
03PMS-BL00.3.3.5.05 Co
Communication System (Common) 141 12-Jan-17 24-Jun-17 33
03PMS-BL00.3.3.5.06 Primary
Pr Energy System 114 23-Feb-17 04-Jul-17 128
03PMS-BL00.3.4 COLD CO
COMMISSIONING WORK 169 01-Apr-17 14-Oct-17 2
03PMS-BL00.3.4.1.01 Ga
Gas turbine & Generator #31 (Siemens) 40 16-Jun-17 01-Aug-17 0
XAC03-34101300 GT #31 Cold Commissioning - Lube Oil / Control Oil Flushing 6 17-Jul-17 24-Jul-17 0
03PMS-BL00.3.4.1.02 Ga
Gas turbine & Generator #32 (Siemens) 23 26-Jul-17 22-Aug-17 0
XAC03-34102300 GT #32 Cold Commissioning - Lube Oil / Control Oil Flushing 5 04-Aug-17 10-Aug-17 2
03PMS-BL00.3.4.1.05 St
Steam Turbine & Generator (Siemens) 54 12-Aug-17 14-Oct-17 2
XAC03-34105110 Pre-Commissioning - Checking & Readiness for Operation - Oil-pumps Power-supply 0 12-Aug-17 45
XAC03-34105120 Pre-Commissioning - Checking & Readiness for Operation - Preparingof oil system 1 14-Aug-17 14-Aug-17 45
flushing
XAC03-34105130 Pre-Commissioning - Checking & Readiness for Operation - Oilsystemflushing 3 15-Aug-17 18-Aug-17 45
XAC03-34105140 Pre-Commissioning - Checking & Readiness for Operation - Blowingof steam 0 29-Sep-17 9
piping-Finished
XAC03-34105150 Pre-Commissioning - Checking & Readiness for Operation - Checking of main piping 1 29-Sep-17 30-Sep-17 9
connection
XAC03-34105160 Pre-Commissioning - Checking & Readiness for Operation - Checking of insulation 1 30-Sep-17 02-Oct-17 9
resistance of generator
XAC03-34105170 Pre-Commissioning - Checking & Readiness for Operation - Connection of turbine and 1 30-Sep-17 02-Oct-17 9
generator coupling
XAC03-34105180 Pre-Commissioning - Checking & Readiness for Operation - Close of bearing pedestals 3 30-Sep-17 04-Oct-17 9
XAC03-34105190 Pre-Commissioning - Checking & Readiness for Operation - Installationof turbine and 3 30-Sep-17 04-Oct-17 9
piping insulation
XAC03-341051A0 Pre-Commissioning - Checking & Readiness for Operation - Installation of turbine and 1 03-Oct-17 04-Oct-17 9
piping sensors
XAC03-341051B0 Pre-Commissioning - Checking & Readiness for Operation - Turbine ready for the test 0 04-Oct-17 9
XAC03-34105210 Cold tests Commissioning - Electronic control system activation 3 02-Sep-17 07-Sep-17 12
XAC03-34105230 Cold tests Commissioning - Instrument ation activation & Loop test 10 04-Sep-17 16-Sep-17 17
XAC03-34105240 Cold tests Commissioning - Turbine special measurement adjustment 3 07-Sep-17 11-Sep-17 12
XAC03-34105250 Cold tests Commissioning - Putting of eletric consumers into operation 3 11-Sep-17 14-Sep-17 12
XAC03-34105260 Cold tests Commissioning - Puttingof pneumatically driven valves/check valve into 2 14-Sep-17 16-Sep-17 12
operation
XAC03-34105270 Cold tests Commissioning - Adjustment of switches 1 16-Sep-17 18-Sep-17 12
XAC03-34105290 Cold tests Commissioning - Preliminary oil system preparation 2 29-Sep-17 02-Oct-17 2
XAC03-341052A0 Cold tests Commissioning - Test of HP control oil unit 2 29-Sep-17 02-Oct-17 2
XAC03-341052B0 Cold tests Commissioning - Turning gear put into operation 1 02-Oct-17 03-Oct-17 2
XAC03-341052D0 Cold tests Commissioning - Test of safety block - SAT 1 04-Oct-17 05-Oct-17 2
XAC03-341052F0 Cold tests Commissioning - Adjustingof turbine control valves/adaptive stage actuators 1 05-Oct-17 06-Oct-17 2
XAC03-341052H0 Cold tests Commissioning - Checkof alarm signals and protections 1 05-Oct-17 06-Oct-17 2
XAC03-341052K0 Cold tests Commissioning - Measurement of levels, pressures and temperatures - SAT 1 06-Oct-17 07-Oct-17 2
XAC03-341052N0 Cold tests Commissioning - Preparationof Gen. protections and AVR for primary tests 3 07-Oct-17 11-Oct-17 2
03PMS-BL00.3.4.2.04 Water
Wa Treatment Plant (Common) 23 06-Apr-17 03-May-17 8
03PMS-BL00.3.4.2.10 Ch
Chemical dosing system for HRSG Unit #30 1 14-Jul-17 15-Jul-17 33
03PMS-BL00.3.4.2.11 Ch
Chemical dosing system for CT Unit #30 20 01-Apr-17 25-Apr-17 52
03PMS-BL00.3.4.2.15 11
115kV Switch Yard 38 05-Apr-17 18-May-17 18
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-34215230 Pre-Commissioning - SWYD Auxiliary System Substation Ground Continuity Test 1 18-Apr-17 19-Apr-17 42
XAC03-34215240 Pre-Commissioning - SWYD Auxiliary System Substation Grounding System 1 19-Apr-17 20-Apr-17 42
XAC03-34215410 Pre-Commissioning - Control Protection and Metering Equip. - Distance Relay (REL670) 3 06-Apr-17 10-Apr-17 1
XAC03-34215420 Pre-Commissioning - Control Protection and Metering Equip. - Line Differential Relay 4 10-Apr-17 14-Apr-17 1
(RED670)
XAC03-34215430 Pre-Commissioning - Control Protection and Metering Equip. - Bus Differential Relay 1 14-Apr-17 15-Apr-17 1
(REB670)
XAC03-34215440 Pre-Commissioning - Control Protection and Metering Equip. - Transformer Differential 3 15-Apr-17 19-Apr-17 1
Relay (RET650)
XAC03-34215450 Pre-Commissioning - Control Protection and Metering Equip. - Transformer Differential 3 20-Apr-17 22-Apr-17 1
Relay (RET630)
XAC03-34215460 Pre-Commissioning - Control Protection and Metering Equip. - Combine Relay (REF630) 3 22-Apr-17 26-Apr-17 1
XAC03-34215470 Pre-Commissioning - Control Protection and Metering Equip. - Revenue Meter 1 26-Apr-17 27-Apr-17 1
XAC03-34215480 Pre-Commissioning - Control Protection and Metering Equip. - Universal Meter 1 27-Apr-17 28-Apr-17 1
XAC03-34215490 Pre-Commissioning - Control Protection and Metering Equip. - Transducer 1 28-Apr-17 29-Apr-17 1
03PMS-BL00.3.4.5.01 DCS
DC 17 13-Apr-17 02-May-17 12
XAC03-34501300 Pre-Commissioning - DCS (3F) - Loop Check for Power Receiving Area 12 19-Apr-17 02-May-17 12
03PMS-BL00.3.5.1.01 Ga
Gas turbine & Generator #31 (Siemens) 8 01-Aug-17 10-Aug-17 0
XAC03-35101200 GT #31 Commissioning - FSNL Test and Over Speed Test 2 03-Aug-17 04-Aug-17 0
XAC03-35101500 GT #31 Commissioning - Unit Load Up Test and Water Injection Test 3 07-Aug-17 10-Aug-17 0
03PMS-BL00.3.5.1.02 Ga
Gas turbine & Generator #32 (Siemens) 7 23-Aug-17 31-Aug-17 0
XAC03-35102200 GT #32 Commissioning - FSNL Test and Over Speed Test 1 24-Aug-17 24-Aug-17 0
XAC03-35102500 GT #32 Commissioning - Unit Load Up Test and Water Injection Test 2 29-Aug-17 31-Aug-17 0
03PMS-BL00.3.5.1.03 HRSG
HR #31 (Vogt Power) 32 31-Jul-17 05-Sep-17 0
XAC03-35103110 Commissioning for Simple Cycle - Bypass Damper Operation Check 8 31-Jul-17 08-Aug-17 19
XAC03-35103210 Combined for Combined Cycle - Sequence / Loop Check 14 31-Jul-17 15-Aug-17 0
XAC03-35103220 Combined for Combined Cycle - Valve Function Check 12 15-Aug-17 29-Aug-17 0
XAC03-35103230 Combined for Combined Cycle - #31 Blowing Out 6 30-Aug-17 05-Sep-17 0
03PMS-BL00.3.5.1.04 HRSG
HR #32 (Vogt Power) 70 21-Jul-17 29-Sep-17 0
XAC03-35104110 Commissioning for Simple Cycle - Bypass Damper Operation Check 7 21-Jul-17 28-Jul-17 8
XAC03-35104210 Commissioning for Combined Cycle - Sequence / Loop Check 14 28-Jul-17 14-Aug-17 8
XAC03-35104220 Commissioning for Combined Cycle - Valve Function Check 12 14-Aug-17 28-Aug-17 8
XAC03-35104230 Commissioning for Combined Cycle - #32 Blowing Out 5 06-Sep-17 12-Sep-17 0
XAC03-35104240 Commissioning for Combined Cycle - #31 & 32 Blowing Out 3 12-Sep-17 15-Sep-17 0
03PMS-BL00.3.5.1.05 St
Steam Turbine & Generator (Siemens) 93 30-Sep-17 01-Jan-18 0
XAC03-35105110 Condenser Hotwell Vacuum-up & ST Start-up - Turbine Bypass Restoration 3 30-Sep-17 04-Oct-17 0
XAC03-35105120 Condenser Hotwell Vacuum-up & ST Start-up - Turbine Bypass Cont - Valve Simulation 2 04-Oct-17 06-Oct-17 0
Test
XAC03-35105130 Condenser Hotwell Vacuum-up & ST Start-up - Gland Steam Supply & Tuning, 2 06-Oct-17 09-Oct-17 0
Condenser Hotwell Vacuum-up
XAC03-35105150 Condenser Hotwell Vacuum-up & ST Start-up - HRSG Drum Level Tuning & DSH 3 09-Oct-17 12-Oct-17 1
Control Tuning
XAC03-35105140 Condenser Hotwell Vacuum-up & ST Start-up - Tuning for Steam Purity 6 09-Oct-17 16-Oct-17 0
XAC03-35105160 Condenser Hotwell Vacuum-up & ST Start-up - HRSG Safety Valve Test 2 12-Oct-17 14-Oct-17 1
XAC03-35105170 Condenser Hotwell Vacuum-up & ST Start-up - Turbine Full Byapass operation 3 12-Oct-17 16-Oct-17 0
XAC03-35105180 Condenser Hotwell Vacuum-up & ST Start-up - ST Initial Start-up, FSNL, Mechanical 1 16-Oct-17 17-Oct-17 0
Check, Over speed test
XAC03-35105190 Condenser Hotwell Vacuum-up & ST Start-up - STG Electrical Primary protection Test 4 17-Oct-17 21-Oct-17 0
XAC03-351051A0 Condenser Hotwell Vacuum-up & ST Start-up - STG AVR Tuning, Dummy Syn Test 2 17-Oct-17 19-Oct-17 2
XAC03-351051B0 Condenser Hotwell Vacuum-up & ST Start-up - STG Initial-Syn, Loading by 1-1-1 1 21-Oct-17 23-Oct-17 0
XAC03-351051C0 Condenser Hotwell Vacuum-up & ST Start-up - Loading by 2-2-1 & Load rejection test 2 23-Oct-17 25-Oct-17 0
XAC03-351051D0 Condenser Hotwell Vacuum-up & ST Start-up - Condenser Hotwell Cleaning 3 25-Oct-17 28-Oct-17 0
XAC03-351051E0 Condenser Hotwell Vacuum-up & ST Start-up - Extraction steam tuning & Back-up 1 28-Oct-17 30-Oct-17 0
system testing
03PMS-BL00.3.5.1.05.2 Overall Commissioning 63 30-Oct-17 01-Jan-18 0
XAC03-35105210 Overall Combined Cycle Operation - ASC Start-up & Shutdown Tuning 7 30-Oct-17 07-Nov-17 0
XAC03-35105230 Overall Combined Cycle Operation - ASC Start-up & Shutdown Test 12 07-Nov-17 21-Nov-17 0
XAC03-35105240 Overall Combined Cycle Operation - 2-2-1 Full block 1-1-1 Half block operation tuning 3 14-Nov-17 17-Nov-17 0
& test
XAC03-35105250 Overall Combined Cycle Operation - GT-ST Capability operation test 4 17-Nov-17 22-Nov-17 0
XAC03-35105260 Overall Combined Cycle Operation - Extraction Change-over Test, Capacity test, ST trip 2 22-Nov-17 24-Nov-17 0
Back-up test
XAC03-35105270 Overall Combined Cycle Operation - IMO Response Test 2 24-Nov-17 27-Nov-17 0
XAC03-35105290 Overall Combined Cycle Operation - Preparation for Performance Test & 3 29-Nov-17 02-Dec-17 0
Pre-performance check
XAC03-351052A0 Overall Combined Cycle Operation - RATA test 4 02-Dec-17 06-Dec-17 0
XAC03-351052D0 Overall Combined Cycle Operation - PEA 24h RTR 2 12-Dec-17 14-Dec-17 0
03PMS-BL00.3.5.2.04 Water
Wa Treatment Plant (Common) 31 03-May-17 08-Jun-17 8
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
03PMS-BL00.3.5.2.06 Cooling
Co Tower 40 09-May-17 24-Jun-17 5
XAC03-35206200 Commissioning - Fan Motor No Loading Test / Heat Run 7 16-Jun-17 24-Jun-17 5
03PMS-BL00.3.5.2.09 Co
Condenser Ball Cleaning System 8 17-Jul-17 25-Jul-17 71
03PMS-BL00.3.5.2.10 Ch
Chemical dosing system for HRSG Unit #30 5 18-Jul-17 24-Jul-17 33
03PMS-BL00.3.5.2.11 Ch
Chemical dosing system for CT Unit #30 6 16-Jun-17 23-Jun-17 6
03PMS-BL00.3.5.2.14 Fir
Fire Fighting System 67 10-Mar-17 26-May-17 218
XAC03-35214110 Commissioning - Fire Pupmp Station - Pump Station Temporary Power Supply 1 22-Apr-17* 22-Apr-17 10
Preparation
XAC03-35214120 Commissioning - Fire Pupmp Station - Pump Station-Sequence/Function Check 3 24-Apr-17 26-Apr-17 10
XAC03-35214130 Commissioning - Fire Pupmp Station - Pump Station & Ring Main Pipe Water Filling 1 27-Apr-17 27-Apr-17 10
XAC03-35214140 Commissioning - Fire Pupmp Station - Pumps Suction & Recirculation Line Water 2 27-Apr-17 28-Apr-17 10
Flushing
XAC03-35214150 Commissioning - Fire Pupmp Station - Jockey Pump Motor No-Load Test 1 29-Apr-17 29-Apr-17 10
XAC03-35214160 Commissioning - Fire Pupmp Station - Jockey Pump Heat Run 1 01-May-17 01-May-17 10
XAC03-35214170 Commissioning - Fire Pupmp Station - Engine Fire Pump Heat Run 1 02-May-17 02-May-17 10
XAC03-35214180 Commissioning - Fire Pupmp Station - Motor Fire Pump Motor No-Load Tes t (After 1 03-May-17 03-May-17 10
Power Receiving)
XAC03-35214190 Commissioning - Fire Pupmp Station - Motor Fire Pump Heat Run (After Power 1 04-May-17 04-May-17 10
Receiving)
03PMS-BL00.3.5.2.14.2 Commissioning - Each Transformer Water Flushing & Spray Test 22 02-May-17 26-May-17 8
XAC03-35214220 Commissioning - Each Transformer Water Flushing & Spray Test - Ring Main Pipe 1 02-May-17 02-May-17 19
Water Flushing
XAC03-35214230 Comm. - Each Trans Water Flushing & Spray Test - Water Flushing Each Transformer 6 03-May-17 09-May-17 19
(Spray Nozzle & Detector Installation)
XAC03-35214210 Commissioning - Each Transformer Water Flushing & Spray Test - Function/Sequence 6 15-May-17 22-May-17* 8
Check All Transformers
XAC03-35214240 Commissioning - Each Transformer Water Flushing & Spray Test - Spray Test in Each 4 22-May-17 26-May-17 8
Transformers
03PMS-BL00.3.5.2.14.3 Commissioning - Sprinkler System 23 27-Mar-17 21-Apr-17 20
XAC03-35214310 Commissioning - Sprinkler System - E&C Bldg Cable Cellar 2 27-Mar-17* 28-Mar-17 29
XAC03-35214510 Commissioning - Outdoor Hydrant - Around Plant (ABPR3) 2 10-Mar-17* 11-Mar-17 274
XAC03-35214610 Commissioning - Fire Alarm System - Function/Sequence Check All Area ABPR3 Plant 9 17-Apr-17* 26-Apr-17 244
03PMS-BL00.3.5.2.15 11
115kV Switch Yard 34 29-Apr-17 08-Jun-17 0
03PMS-BL00.3.5.3 Process
Proces Package 174 09-Mar-17 30-Aug-17 47
03PMS-BL00.3.5.3.04 Aux
Au Steam System 7 22-Aug-17 30-Aug-17 0
03PMS-BL00.3.5.3.05 Condensate
Co Water System 18 12-Jun-17 01-Jul-17 91
XAC03-35305500 Commissioning - Condensate Water System Operation Check / Flushing 7 24-Jun-17 01-Jul-17 91
XAC03-35306100 Commissioning - HP Boiler Feed Water System Sequence Check 6 10-May-17 16-May-17 83
XAC03-35306500 Commissioning - HP Boiler Feed Water System Operation Check / Flushing 3 17-Jun-17 21-Jun-17 60
XAC03-35307100 Commissioning - LP Boiler Feed Water System Sequence Check 6 06-Jun-17 13-Jun-17 60
XAC03-35307500 Commissioning - LP Boiler Feed Water System Operation Check / Flushing 3 21-Jun-17 24-Jun-17 57
03PMS-BL00.3.5.3.08 Main
Ma Cooling Water System 19 03-Jul-17 25-Jul-17 71
XAC03-35308100 Commissioning - Main Cooling Water System Sequence Check 6 03-Jul-17 10-Jul-17 71
XAC03-35308300 Commissioning - MCW Pump - Motor Alignment and Coupling 1 11-Jul-17 12-Jul-17 71
XAC03-35308500 Commissioning - Main Cooling Water System Operation Check / Flushing 5 15-Jul-17 21-Jul-17 71
03PMS-BL00.3.5.3.09 Au
Auxiliary Cooling Water System 18 09-Jun-17 30-Jun-17 0
XAC03-35309300 Commissioning - ACW Pump - Motor Alignment and Coupling 1 19-Jun-17 19-Jun-17 0
XAC03-35310100 Commissioning - CT Make-up System Sequence Check / Loop Check 6 26-May-17 02-Jun-17 18
XAC03-35310200 Commissioning - CT Make-up Pump - Motor Test Run & Pump Heat Run 1 16-Jun-17 17-Jun-17 6
03PMS-BL00.3.5.3.11 Clo
Closed Cycle Cooling Water System 39 17-May-17 30-Jun-17 0
XAC03-35311100 Commissioning - CCCW System Sequence Check / Loop Check 6 17-May-17 23-May-17 23
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary
Amata B. Grimm Power (Rayong) 3 Limited ABPR3 CCCP-EPC Detailed Project Schedule NTP : 1-Dec-2015 / Project Completion : 1-Feb-2018
XAC03-35311300 Commissioning - CCCW Pump - Motor Alignment and Coupling 1 17-Jun-17 19-Jun-17 3
03PMS-BL00.3.5.3.12 Condenser
Co Vacuum System 21 31-May-17 23-Jun-17 99
03PMS-BL00.3.5.3.13 Ra
Raw Water Distribution System (Common) 8 05-Apr-17 13-Apr-17 24
XAC03-35313200 Commissioning - Raw Water Pump - Motor Test Run & Pump Heat Run (by Temp. 2 08-Apr-17 11-Apr-17 24
Power)
XAC03-35313300 Commissioning - Raw Water System - Operation Check / Flushing 2 11-Apr-17 13-Apr-17 24
03PMS-BL00.3.5.3.14 Service
Se water Distribution System 22 26-May-17 21-Jun-17 36
XAC03-35314200 Commissioning - SW Pump - Motor Tes t Run & Pump Heat Run 2 16-Jun-17 19-Jun-17 36
03PMS-BL00.3.5.3.15 De
Demineralized water Distribution System 26 26-May-17 21-Jun-17 0
XAC03-35315200 Commissioning - DM Pump - Motor Test Run & Pump Heat Run 3 16-Jun-17 19-Jun-17 0
03PMS-BL00.3.5.3.16 Waste
Wa water collection System 54 20-Mar-17 20-May-17 63
XAC03-35316110 Commissioning - Retention Pit / Emergency Pit - Sequence Check 8 05-May-17 15-May-17 63
XAC03-35316120 Commissioning - Retention Pit / Emergency Pit - Pump Heat Run 5 15-May-17 20-May-17 63
XAC03-35316210 Commissioning - CT/CWP Area Pit - Sequence Check 9 20-Mar-17 30-Mar-17 103
XAC03-35316220 Commissioning - CT/CWP Area Pit - Pump Heat Run 4 30-Mar-17 04-Apr-17 103
XAC03-35316320 Commissioning - Oily Water Separator - Pump Heat Run 4 05-Apr-17 10-Apr-17 98
03PMS-BL00.3.5.3.17 Instrument
Ins & Service Air System (Common) 86 09-Mar-17 16-Jun-17 0
03PMS-BL00.3.5.3.18 Fu
Fuel Gas Distribution System 14 17-Jul-17 01-Aug-17 0
03PMS-BL00.3.5.3.19 Fuel
Fu Gas Heater 10 17-Jul-17 27-Jul-17 4
03PMS-BL00.3.5.4 Electrical
Electri Package 99 10-Mar-17 16-Jun-17 121
03PMS-BL00.3.5.4.01 Generator
Ge Transformer 47 18-Apr-17 10-Jun-17 110
03PMS-BL00.3.5.4.02 Un
Unit Auxiliary Transformer 33 03-May-17 10-Jun-17 0
XAC03-35403200 6.6kV Switchgear - Commissioning - Energize (Station Power Receiving) 3 10-Jun-17 12-Jun-17 0
XAC03-35405200 Commissioning - Power Receiving from 6.6kV MV SWGR & Soaking 1 13-Jun-17* 13-Jun-17 0
XAC03-35407200 Commissioning - DC & UPS Charging & Load Test 6 05-Apr-17 11-Apr-17 12
03PMS-BL00.3.5.4.08 Emergency
Em DG System 9 13-May-17 24-May-17 61
03PMS-BL00.3.5.5.02 St
Steam and Water Sampling System 3 29-May-17 31-May-17 78
XAC03-35502100 Commissioning - Steam and Water Sampling System Commissioning 2 29-May-17 30-May-17 78
XAC03-35502200 Commissioning - Steam and Water Sampling System Sampling System In-service 1 31-May-17 31-May-17 78
03PMS-BL00.3.5.5.03 Co
Continuous Emission Monitoring System 26 29-Jun-17 28-Jul-17 3
03PMS-BL00.3.5.5.04 Clock
Cl System 7 28-Jun-17 06-Jul-17 23
03PMS-BL00.3.5.5.05 Communication
Co System 7 16-Jun-17 24-Jun-17 33
03PMS-BL00.3.5.5.06 Primary
Pr Energy System 7 26-Jun-17 04-Jul-17 128
Remaining Work Actual Work Actual Milestone Date Revision Checked Approved
09-Jul-16 First Issue Y. Miyasaka M. Kainuma
Critical Work Milestone Summary