Você está na página 1de 6

ID Task Name Duration Start Finish 2018

Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
1 NEW PASIG ARENA 763 days? Sun 10/15/17
Mon 3/23/20
2 PROJECT GEN. INFO 1 day Sun 10/15/17Mon 10/16/17
3 NOTICE TO PROCEED (NTP) 0 days Sun 10/15/17 Sun 10/15/17 Oct 15 '17

4 PROJECT START OFF 1 day Mon 10/16/17


Mon 10/16/17 PROJECT START OFF

5 PROJECT SITE TURNOVER to PHESCO 0 days Sun 10/15/17 Sun 10/15/17 Oct 15 '17
6 PROJECT COMPLETION 0 days Sun 10/15/17 Sun 10/15/17 Oct 15 '17
7 PROJECT PERMITS ACQUISITION 0 days Sun 10/15/17Sun 10/15/17 Oct 15 '17

8 BUILDING PERMITS - by client 0 days Sun 10/15/17 Sun 10/15/17 Oct 15 '17
9 CIVIL & STRUCTURE WORKS 0 days Sun 10/15/17 Sun 10/15/17 Oct 15 '17

10 SITE HANDING OVER - by client 0 days Sun 10/15/17 Sun 10/15/17 Oct 15 '17
11 PROJECT PRELIMINARIES 60 days Mon 10/16/17Sat 12/23/17
12 Temporary Fence 30 days Mon 10/16/17 Sat 11/18/17 Temporary Fence

13 Bunkhouse/Bodega 30 days Mon 10/16/17 Sat 11/18/17 Bunkhouse/Bodega


14 Clearing & Grubbing 60 days Mon 10/16/17
Sat 12/23/17 Clearing & Grubbing

15 Lay-out & Staking 30 days Thu 11/2/17Wed 12/6/17 Lay-out & Staking
16 PROJECT CONSTRUCTION WORKS 763 days? Mon 10/16/17Mon 3/23/20
17 MOBILIZATION & DEMOBILIZATION 699 days Mon 10/16/17
Wed 1/8/20
18 Mobilization 45 days Mon 10/16/17
Wed 12/6/17 Mobilization
19 Demobilization 15 days Mon 12/23/19
Wed 1/8/20
20 DEMOLITION WORKS 639 days Thu 12/7/17 Sat 12/21/19
21 Dismantling of Old Existing Light Tower 14 days Thu 12/7/17Fri 12/22/17 Dismantling of Old Existing Light Tower
22 Demolition of Ext'g Bldgs 42 days Mon 11/4/19Sat 12/21/19
23 DEWATERING WORKS 400 days Thu 12/7/17 Mon 3/18/19
24 Dewatering 400 days Thu 12/7/17Mon 3/18/19
25 EARTHWORKS 561 days Thu 12/7/17 Sat 9/21/19
26 Excavation for pile cap 45 days Thu 12/7/17Sat 1/27/18 Excavation for pile cap

27 Soil Poisoning 91 days Fri 2/22/19 Fri 6/7/19


28 Damp Proofing Polyethylene Sheet (6 mills) 90 days Sat 6/8/19 Fri 9/20/19
29 Escombro 30 days Mon 8/19/19Sat 9/21/19
30 CIVIL & STRUCTURE WORKS 763 days? Mon 10/16/17 Mon 3/23/20

31 REBAR FABRICATION 200 days Mon 12/25/17


T ue 8/14/18

32 Fabrication of rebar for pile cap & tie beam 200 days Mon 12/25/17
Tue 8/14/18
33 SUBSTRUCTURE 394 days Mon 12/25/17
T hu 3/28/19

34 PILE CAP 348 days Mon 12/25/17


Sat 2/2/19

35 Crew 1 348 days Mon 12/25/17


Sat 2/2/19
36 Pile Hacking (32 Piles) 96 days Mon 12/25/17
Sat 4/14/18 Pile Hacking (32 Piles)
37 Removal & Disposal of debris 32 days Mon 4/16/18Tue 5/22/18 Removal & Disposal of debris
38 Compaction and testing of foundation bed 64 days Fri 5/4/18 Tue 7/17/18 Compaction and testing of foundation bed
39 Blinding of concrete 10 days Thu 7/12/18Mon 7/23/18 Blinding of concrete
40 Installation of pile cap rebar & dowels 32 days Tue 7/24/18Wed 8/29/18
41 Shuttering works 10 days Fri 8/24/18 Tue 9/4/18
42 Concreting 10 days Wed 9/5/18 Sat 9/15/18
43 Installation of column stump formworks 30 days Tue 9/25/18Mon 10/29/18
44 Concreting of column stump 7 days Tue 10/30/18Tue 11/6/18
45 Deshuttering works 10 days Thu 11/15/18
Mon 11/26/18
46 Backfilling & Compaction 64 days Wed 11/21/18
Sat 2/2/19
47 GROUND BEAM 186 days Fri 8/24/18 Thu 3/28/19
48 Excavation 30 days Fri 8/24/18 Thu 9/27/18
49 Installation of rebars 60 days Wed 9/5/18 Tue 11/13/18
50 Shuttering works 60 days Wed 10/10/18
Tue 12/18/18
51 Concreting 10 days Wed 12/19/18
Sat 12/29/18
52 Deshuttering works 10 days Tue 1/8/19 Fri 1/18/19
53 Backfilling & Compaction 64 days Mon 1/14/19Thu 3/28/19
54 SUPERSTRUCTURE 763 days? Mon 10/16/17
Mon 3/23/20

55 MAIN STRUCTURE 415 days Mon 11/26/18


Mon 3/23/20

56 1st FLOOR 50 days Mon 11/26/18


Tue 1/22/19
57 COLUMN 50 days Mon 11/26/18
Tue 1/22/19
58 Installation of rebars 30 days Mon 11/26/18
Sat 12/29/18
59 Shuttering works 30 days Fri 12/7/18 Thu 1/10/19
60 Concreting 10 days Thu 1/3/19 Mon 1/14/19
61 Deshuttering works 10 days Fri 1/11/19 Tue 1/22/19
62 1ST FLOOR MEZZANINE 52 days Fri 1/11/19 Tue 3/12/19
63 BEAM,GIRDERS & SLABS 52 days Fri 1/11/19 Tue 3/12/19
64 Erecting Scaffoldings 10 days Fri 1/11/19 Tue 1/22/19
65 Shuttering works 10 days Tue 1/15/19Fri 1/25/19
66 Installation of rebars for beam & girders 20 days Fri 1/18/19 Sat 2/9/19
67 Installation of rebar for slab 20 days Thu 1/24/19Fri 2/15/19
68 Concreting 7 days Sat 2/16/19 Sat 2/23/19
69 Deshuttering works 7 days Mon 2/25/19Mon 3/4/19
70 Removal of Scaffoldings 7 days Tue 3/5/19 Tue 3/12/19
71 2nd FLOOR 118 days Mon 2/25/19Thu 7/11/19
72 COLUMN 46 days Mon 2/25/19Thu 4/18/19
73 Installation of rebars 30 days Mon 2/25/19Sat 3/30/19
74 Shuttering works 20 days Thu 3/14/19Fri 4/5/19
75 Concreting 7 days Tue 3/26/19Tue 4/2/19
76 Deshuttering works 7 days Thu 4/11/19Thu 4/18/19
77 BEAM,GIRDERS & SLABS 72 days Fri 4/19/19 Thu 7/11/19
78 Erecting Scaffoldings 20 days Fri 4/19/19 Sat 5/11/19

Task Summary Path Driving Predecessor Summary Task Critical Split Baseline Summary Inactive Task Manual Task Manual Summary External Tasks Slippage

PASIG SPORTS ARENA BASELINE REV.00 (8hrs Mon-Sat).m Split Project Summary Path Driving Predecessor Normal Task Baseline Progress Inactive Milestone Duration-only Start-only External Milestone
Milestone Path Driving Predecessor Milestone Task Critical Baseline Milestone Deadline Inactive Summary Manual Summary Rollup Finish-only Manual Progress

ENGR. ROBERT C. BULAN Sun 10/15/17


Project Manager Mon 3/23/20
ID Task Name Duration Start Finish 2018
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
79 Shuttering works 30 days Thu 4/25/19Wed 5/29/19
80 Installation of rebars for beam & girders 30 days Tue 5/7/19 Mon 6/10/19
81 Installation of rebar for slab 30 days Sat 5/18/19 Fri 6/21/19
82 Concreting 10 days Tue 6/11/19Fri 6/21/19
83 Deshuttering works 10 days Mon 7/1/19 Thu 7/11/19
84 Removal of Scaffoldings 10 days Mon 7/1/19 Thu 7/11/19
85 2nd FLOOR MEZZANINE 151 days Fri 7/12/19 Fri 1/3/20
86 BEAM,GIRDERS & SLABS 86 days Fri 7/12/19 Sat 10/19/19
87 Erecting Scaffoldings 20 days Fri 7/12/19 Sat 8/3/19
88 Shuttering works 20 days Wed 7/24/19Thu 8/15/19
89 Installation of rebars for beam & girders 30 days Mon 8/5/19 Sat 9/7/19
90 Installation of rebar for slab 30 days Thu 8/22/19Wed 9/25/19
91 Concreting 7 days Thu 9/26/19Thu 10/3/19
92 Deshuttering works 7 days Sat 10/12/19Sat 10/19/19
93 Removal of Scaffoldings 7 days Sat 10/12/19Sat 10/19/19
94 COLUMN 72 days Sat 10/12/19Fri 1/3/20
95 Installation of rebars 40 days Sat 10/12/19Wed 11/27/19
96 Shuttering works 40 days Wed 10/30/19
Sat 12/14/19
97 Concreting 10 days Tue 12/10/19Fri 12/20/19
98 Deshuttering works 10 days Tue 12/24/19Fri 1/3/20
99 3RD FLOOR 80 days Sat 12/21/19Mon 3/23/20
100 STEEL GIRDER & STEEL DECK 80 days Sat 12/21/19Mon 3/23/20
101 Erecting Sccaffoldings 40 days Sat 12/21/19Wed 2/5/20
102 Installation of steel girder 40 days Tue 1/14/20Fri 2/28/20
103 Installation of steel deck 40 days Tue 1/14/20Fri 2/28/20
104 Removal of Sccaffoldings 20 days Sat 2/29/20 Mon 3/23/20
105 TOWER & SPIRAL 1 day? Mon 10/16/17
Mon 10/16/17

106 1ST FLOOR MEZZANINE 1 day? Mon 10/16/17


Mon 10/16/17 1ST FLOOR MEZZANINE

107 1 day? Mon 10/16/17


Mon 10/16/17
108 1 day? Mon 10/16/17
Mon 10/16/17
109 1 day? Mon 10/16/17
Mon 10/16/17
110 ELECTRICAL WORKS 350 days Wed 1/23/19 Thu 3/5/20

111 ROUGH-INS 350 days Wed 1/23/19Thu 3/5/20


112 15 mm PVC, Neltex or Atlanta, sch.40 350 days Wed 1/23/19Thu 3/5/20
113 15 mm IMC, MATSUSHITA, PANASONIC 350 days Wed 1/23/19Thu 3/5/20
114 65 mm PVC, Neltex or Atlanta, sch.40 350 days Wed 1/23/19Thu 3/5/20
115 110 mm PVC, Neltex or Atlanta, sch.40 350 days Wed 1/23/19Thu 3/5/20
116 Chipping and restoration 317 days Wed 1/23/19Mon 1/27/20
117 Service Entrance Concrete Pedestal to DPG inside 90 days Wed 8/21/19Tue 12/3/19
118 Other accessories ( pulling compound, pull wires, h317
supports,
days Wed
electrical
1/23/19
tape,
MonEntrance
1/27/20 caps, expansion junction box, utility box, etc.)
119 GRINDING SYSTEM 350 days Wed 1/23/19Thu 3/5/20
120 Ground Rod, 20mm x 3000mm Copper Clad 105 days Wed 1/23/19Fri 5/24/19
121 Bare wire 80mm2 350 days Wed 1/23/19Thu 3/5/20
122 25 mm PVC, sch 40 180 days Wed 1/23/19Tue 8/20/19
123 MECHANICAL WORKS 360 days Wed 1/23/19 Tue 3/17/20

124 ROUGH-INS 360 days Wed 1/23/19Tue 3/17/20


125 Drainage Line & Collector Pipe (Catch Basin) 330 days Wed 1/23/19Tue 2/11/20
126 Collector of Perforated Pipe @ Mezzanine Area 300 days Wed 1/23/19Tue 1/7/20
127 Threaded Plug for Clean-out 54 days Wed 1/23/19Tue 3/26/19
128 Pipe Hangers 318 days Mon 2/11/19Sat 2/15/20
129 Sanitary Soil Stack 360 days Wed 1/23/19Tue 3/17/20
130 Water Supply 348 days Wed 1/23/19Tue 3/3/20
131 PROJECT CLOSED-OUT 7 days Mon 10/16/17 Mon 10/23/17

132 AS-BUILT SHOP DRAWINGS 7 days Mon 10/16/17 Mon 10/23/17


133 Civil/Architectural As-built 7 days Mon 10/16/17
Mon 10/23/17 Civil/Architectural As-built
134 Electrical As-built 7 days Mon 10/16/17 Mon 10/23/17 Electrical As-built

135 Mechanical As-Built 7 days Mon 10/16/17 Mon 10/23/17 Mechanical As-Built
136 O & M MANUALS 7 days Mon 10/16/17 Mon 10/23/17
137 Civil and Architectural Works 7 days Mon 10/16/17 Mon 10/23/17 Civil and Architectural Works
138 Electrical Works 7 days Mon 10/16/17 Mon 10/23/17 Electrical Works

139 Mechanical Works 7 days Mon 10/16/17 Mon 10/23/17 Mechanical Works
140 SNAG AND DISNAG 7 days Mon 10/16/17 Mon 10/23/17
141 Civil and Architectural Works 7 days Mon 10/16/17 Mon 10/23/17 Civil and Architectural Works
142 Electrical Works 7 days Mon 10/16/17 Mon 10/23/17 Electrical Works

143 Mechanical Works 7 days Mon 10/16/17 Mon 10/23/17 Mechanical Works
144 CLOSURE PROJECT 1 day Mon 10/16/17 Mon 10/16/17
145 Handing Over Project 1 day Mon 10/16/17 Mon 10/16/17 Handing Over Project

Task Summary Path Driving Predecessor Summary Task Critical Split Baseline Summary Inactive Task Manual Task Manual Summary External Tasks Slippage

PASIG SPORTS ARENA BASELINE REV.00 (8hrs Mon-Sat).m Split Project Summary Path Driving Predecessor Normal Task Baseline Progress Inactive Milestone Duration-only Start-only External Milestone
Milestone Path Driving Predecessor Milestone Task Critical Baseline Milestone Deadline Inactive Summary Manual Summary Rollup Finish-only Manual Progress

ENGR. ROBERT C. BULAN Sun 10/15/17


Project Manager Mon 3/23/20
2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

Dewatering

Soil Poisoning
Damp Proofing Polyethylene
Escombro

Fabrication of rebar for pile cap & tie beam

Compaction and testing of foundation bed


Blinding of concrete
Installation of pile cap rebar & dowels
Shuttering works
Concreting
Installation of column stump formworks
Concreting of column stump
Deshuttering works
Backfilling & Compaction

Excavation
Installation of rebars
Shuttering works
Concreting
Deshuttering works
Backfilling & Compaction

Installation of rebars
Shuttering works
Concreting
Deshuttering works

Erecting Scaffoldings
Shuttering works
Installation of rebars for beam & girders
Installation of rebar for slab
Concreting
Deshuttering works
Removal of Scaffoldings

Installation of rebars
Shuttering works
Concreting
Deshuttering works

Erecting Scaffoldings

Task Summary Path Driving Predecessor Summary Task Critical Split Baseline Summary Inactive Task Manual Task Manual Summary External Tasks Slippage

PASIG SPORTS ARENA BASELINE REV.00 (8hrs Mon-Sat).m Split Project Summary Path Driving Predecessor Normal Task Baseline Progress Inactive Milestone Duration-only Start-only External Milestone
Milestone Path Driving Predecessor Milestone Task Critical Baseline Milestone Deadline Inactive Summary Manual Summary Rollup Finish-only Manual Progress

ENGR. ROBERT C. BULAN Sun 10/15/17


Project Manager Mon 3/23/20
2019
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
Shuttering works
Installation of rebars for beam & girders
Installation of rebar for slab
Concreting
Deshuttering works
Removal of Scaffoldings

Erecting Scaffoldings
Shuttering works
Installation of rebars for beam & girders
Installation of rebar fo

Ground Rod, 20mm x 3000mm Copper Clad

25 mm PVC, sch 40

Threaded Plug for Clean-out

Task Summary Path Driving Predecessor Summary Task Critical Split Baseline Summary Inactive Task Manual Task Manual Summary External Tasks Slippage

PASIG SPORTS ARENA BASELINE REV.00 (8hrs Mon-Sat).m Split Project Summary Path Driving Predecessor Normal Task Baseline Progress Inactive Milestone Duration-only Start-only External Milestone
Milestone Path Driving Predecessor Milestone Task Critical Baseline Milestone Deadline Inactive Summary Manual Summary Rollup Finish-only Manual Progress

ENGR. ROBERT C. BULAN Sun 10/15/17


Project Manager Mon 3/23/20
2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

Demobilization

Demolition of Ext'g Bldgs

Damp Proofing Polyethylene Sheet (6 mills)


Escombro

Task Summary Path Driving Predecessor Summary Task Critical Split Baseline Summary Inactive Task Manual Task Manual Summary External Tasks Slippage

PASIG SPORTS ARENA BASELINE REV.00 (8hrs Mon-Sat).m Split Project Summary Path Driving Predecessor Normal Task Baseline Progress Inactive Milestone Duration-only Start-only External Milestone
Milestone Path Driving Predecessor Milestone Task Critical Baseline Milestone Deadline Inactive Summary Manual Summary Rollup Finish-only Manual Progress

ENGR. ROBERT C. BULAN Sun 10/15/17


Project Manager Mon 3/23/20
2020
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov

n of rebars for beam & girders


Installation of rebar for slab
Concreting
Deshuttering works
Removal of Scaffoldings

Installation of rebars
Shuttering works
Concreting
Deshuttering works

Erecting Sccaffoldings
Installation of steel girder
Installation of steel deck
Removal of Sccaffoldings

15 mm PVC, Neltex or Atlanta, sch.40


15 mm IMC, MATSUSHITA, PANASONIC
65 mm PVC, Neltex or Atlanta, sch.40
110 mm PVC, Neltex or Atlanta, sch.40

Service Entrance Concrete Pedestal to DPG inside


Other accessories ( pulling compound, pull wires, h supports, electrical tape, Entrance caps, expansion junction box, utility box, etc.)

Bare wire 80mm2

Drainage Line & Collector Pipe (Catch Basin)


Collector of Perforated Pipe @ Mezzanine Area

Pipe Hangers
Sanitary Soil Stack
Water Supply

Task Summary Path Driving Predecessor Summary Task Critical Split Baseline Summary Inactive Task Manual Task Manual Summary External Tasks Slippage

PASIG SPORTS ARENA BASELINE REV.00 (8hrs Mon-Sat).m Split Project Summary Path Driving Predecessor Normal Task Baseline Progress Inactive Milestone Duration-only Start-only External Milestone
Milestone Path Driving Predecessor Milestone Task Critical Baseline Milestone Deadline Inactive Summary Manual Summary Rollup Finish-only Manual Progress

ENGR. ROBERT C. BULAN Sun 10/15/17


Project Manager Mon 3/23/20

Você também pode gostar