Avic-Mixed Development Project

Engineer: Supervision Consultant: Contractor:

AVIC Hotels Lanka Pvt Ltd. Central Engineering Consultancy Bureau CSCEC

SITE DIARY
Date: 2015.11.21 Name : S.M.J.M.T.Situge

Location Work Executed


Basement inspected accessive accumilated filling material in basement area due to
dumping of bay area filled in basement

Cappin beam demolishing North Air compresure wasrepaired around 11.00 am. It was noted in evening at 2.30
boundary pm.

Did you notice yes


any non approved
Materials used at site /
Material used but don't know the status ?

Drafted and sent defect notification in North boundary retaining wall


Defects Noted/ cracks
Verbal instruction given to contractor
regarding defects

Referred Method statements ,Drawings and


Engineer's comments.

Collected information

Plant & Labor Observations

General Comments:

Signature:.. Date:..
Avic-Mixed Development Project
Engineer: Supervision Consultant: Contractor:

AVIC Hotels Lanka Pvt Ltd. Central Engineering Consultancy Bureau CSCEC

SITE DIARY
Date: 15/11/2015 Name : W.C.M.T.M.Chandrasekara

Location Work Executed

Did you notice


any non approved
Materials used at site /
Material used but don't know the status ?

Defects Noted/
Verbal instruction given to contractor
regarding defects

1) WF-000550-Method statement of High and Large Formworks for


structural componets at transfer floor
Referred Method statements ,Drawings and
Engineer's comments.
Props to the floors shall remain as mention in work flow
Collected information

1).3 workers only to demolish the capping beam


Plant & Labor Observations

General Comments:
Heavy rain no any site work going on

Signature:.. Date:..
Avic-Mixed Development Project
Engineer: Supervision Consultant: Contractor:

AVIC Hotels Lanka Pvt Ltd. Central Engineering Consultancy Bureau CSCEC

SITE DIARY
Date: 14/11/2015 Name : W.C.M.T.M.Chandrasekara

Location Work Executed


1).Podium Level Grid A-D & 10 - Setting out work / attended but Not done
15

2). L2-Podium Grid line 16,19,21 14 Nos of columns Formwork Inspection Completed,A-21 and 19-C columns
and A-D formwork was not accepted

3).L2 to PL-Stair Case R/F & R/F and Form-work inspection has done.Found setting out has done without
Formwork inspection referance lines.

Did you notice


any non approved
Materials used at site /
Material used but don't know the status ?

21-A and 19-C column formwork was not properly vertically align
Defects Noted/ and plywood boards were not properly sheet to the 4"x2" timber
Verbal instruction given to contractor supports.CSCEC was Instructed verbaly to rectify and recall for
regarding defects inspection

1).Shop Drawings and Sketch List up to date

Referred Method statements ,Drawings and 2).Transfer Level Formwork Method Statement
Engineer's comments.

Collected information

1).3 workers only to demolish the capping beam


Plant & Labor Observations

General Comments:
# As informed by the CSCEC Zone A manager,Due to the sanken plant repair noway to take C50scc so no
any column concreting ca be proceed.

Signature:.. Date:..
Avic-Mixed Development Project
Engineer: Supervision Consultant: Contractor:

AVIC Hotels Lanka Pvt Ltd. Central Engineering Consultancy Bureau CSCEC

SITE DIARY
Date: 13/11/2015 Name : W.C.M.T.M.Chandrasekara

Location Work Executed


1) Podium Level Grid A-D & 10 - Slab & Beam concrete supervision
15

2)

Did you notice


any non approved
Materials used at site /
Material used but don't know the status ?

Defects Noted/ Cover for newly plased concrete was not enough then verbaly
Verbal instruction given to contractor informed to the concractor to provide
regarding defects

Shop Drawings Sketch List up to date

Referred Method statements ,Drawings and


Engineer's comments.

Collected information

Plant & Labour Observations

General Comments:

Signature:.. Date:..
Avic-Mixed Development Project
Engineer: Supervision Consultant: Contractor:

AVIC Hotels Lanka Pvt Ltd. Central Engineering Consultancy Bureau CSCEC

SITE DIARY
Date: 12/11/2015 Name : W.C.M.T.M.Chandrasekara

Location Work Executed


1) Podium Level Grid A-D & 10 - Slab & Beam Reinforcement Inspection
15

2)

Did you notice


any non approved
Materials used at site /
Material used but don't know the status ?

Crack on W1 walls and Lift core walls


Defects Noted/
Verbal instruction given to contractor
regarding defects

Shop Drawings PL

Referred Method statements ,Drawings and


Engineer's comments.

Collected information

Plant & Labour Observations

General Comments:

Signature:.. Date:..
Avic-Mixed Development Project
Engineer: Supervision Consultant: Contractor:

AVIC Hotels Lanka Pvt Ltd. Central Engineering Consultancy Bureau CSCEC

SITE DIARY
Date: 11/11/2015 Name : W.C.M.T.M.Chandrasekara

Location Work Executed


1) Cement Block Factory visit QAQC process Inspected,Block compressive Strength testing
-Weyangoda

2) PL reinforcement Inspection

Did you notice Water stagnated in the ramp construction joint


any non approved
Materials used at site /
Material used but don't know the status ?

Defects Noted/
Verbal instruction given to contractor
regarding defects

Shop Drawings of the PL and Structural Drawings of the PL studied

Referred Method statements ,Drawings and


Engineer's comments.

Collected information

Plant & Labour Observations

General Comments:

Signature:.. Date:..