Escolar Documentos
Profissional Documentos
Cultura Documentos
of Safety Report
Schedule 4 -Part 2
SAFETY REPORTS Minimum Information to be included in a
Safety Report
1
Schedule 4 -Part 2
Minimum Information to be included in Existing Guidance
a Safety Report
2
Relationship between R2P2 and the ALARP Demonstration
ALARP Suite
"Reducing Risks, Protecting People"
ALARP Demonstration
HSE framework for the tolerability
of risk "Reducing Risks, Protecting People"
".... both individual risks and societal
concerns ....
.... must
must be
be taken
taken into
into account
account in
Unacceptable Region deciding whether a risk is unacceptable,
and societal concerns
Increasing Individual
3
ALARP Diagram
4
Case Specific ALARP Proportionate Risk Assessment
demonstration
The depth of the analysis in the
Also: operators report should be
proportionate to
"Why have I not done a) the nature and scale of the
it"? MAHs
b) the risks posed to
neighbouring populations
BLEVE
5
ALARP Demonstration
Risk estimation
Selection of a representative n But the higher the installation lies on the
societal concerns scale the greater the need
set of events to look for additional measures, over and
above the normal standards.
Estimation of consequences and frequency How to approach?
n 1. Identify risk reduction measures.
for each event n 2. Assess using Lines Of Defence analysis with
cost estimates
n 3. Possibly, in extreme cases, add a Cost Benefit
Ranking & screening (e.g risk matrix, fn Analysis.
curves)
6
`So what`
Sensitivity and uncertainty
analysis If all the risks are BA then
compliance with good practice
Would being more thorough be demonstrates ALARP
worthwhile?
Otherwise the events that
Uncertainties in models, data, contribute significantly to the
methodology.
risks need to be identified, risk
Cautious best-estimate basis.
basis. reduction options compiled,and
appropriate decision aids used
Adopt Precautionary Approach
p89
(eg LOPA for simple cases
p89 91R2P2
91R2P2
CBA for more difficult ones)
Purpose of SR is to demonstrate
ANMs (ALARP) from an activity
(`risk from what`) If AMNs are in place for each
major accident scenario then
Four combinations (`risk of what`
and `risk to what`):
there is nothing more that can be
done and professional judgement
1 IR to those on-site will suffice.
2 IR to those off-site
3 SR to those on-site
4 SR to those off-site
`Explicit` detailed quantification of
risks is not necessary unless the
proportionality is high