Leakages
Measurements of water seepage through the upstream face of
the dam are performed automatically on a daily basis through
two weirs, located at the lowest portion of the inspection
gallery. They measure separately the water leakage on the Figure 4: Monitoring system Piezometers distribution.
right and left bank. A third weir device, located in the
inspection gallery at the dam toe, collects water from both The piezometric measurements since the beginning of 1979
sides, and the drainage area of the central concrete plug. generally showed a slightly decreasing trend for the uplift
Figure 3 shows the leakage evolution between the years 1979 pressure records. In the years 1985-87, the piezometers PZ06
and 2008. and PZ01 showed a significant reduction of the uplift
pressure. The measurements conducted after the year 2000
using the piezometers PZ02, PZ06, PZ08, PZ09, PZ12, PZ13
and PZ0A recorded the minimum uplift pressure values of the
period from 1979 to the present day. Figure 5 illustrates the
piezometric levels recorded from 2005 to 2008, compared
with the reservoir levels.
2420
2415
2410
PIEZOMETRIC MEASUREMENTS
RESERVOIR LEVEL (m asl)
2405
2400
2395
2390
2385
2380
2370
In the first period, until the year 1982, the water leakage 2365
2005 2006 2007 2008
reached 5.8 l/s. In the period 1983-1986 there was a PZ 01/02/0A PZ 05/12/12/17 PZ 06/08/09 Reservoir
significant reduction of the maximum leakage (up to 2 l/s). Figure 5: Monitoring system Piezometric measurements.
This was due to the effects of the maintenance executed in the
left and right bank during the summer seasons of 1983 and It must be mentioned that no correlation could be observed
1984. During the period 1986-1992 a further increase of between the storage elevation and the piezometers PZ05,
leakage up to 6 l/s was noticed. A new reduction occurred in PZ12, PZ13 and PZ17. The piezometers PZ01, PZ02 and
the years 1993 to 2001 (up to 3.2 l/s) as a result of a new PZ0A show a certain correlation of the pressure values if
compared to the water level variation in the reservoir. In In 2010 a new maintenance program was planned in the lower
order to reduce the uplift pressures that currently affect the part of the dam, below the elevation 2395 m asl up to the
dam in some sections, an integration of the grout curtain and foundation level, in the central section between joints G5 and
an extension of the drainage scheme were considered. G6. The total area affected corresponds to approx 1400 m2.
The general methodology consisted of removing and re-
Dam stability analysis grouting of the joints between the masonry blocks,
proceeding from bottom to the top sections. For the treatment
The dam stability analysis at Valsoera Dam was carried out of the vertical joints between the dam blocks, a two-
considering the maximum operating level in the reservoir component mortar with high adhesion and flexibility was
(2413 m asl). The safety factor (SF) was estimated for used. The grouting and the filling of the joints between the
different uplift pressures. masonry blocks have been made with a mix of cement-based
For the calculation the following values were considered: thixotropic and fiber-reinforced. For the grouting behind the
cohesion: c = 0 kPa; friction angle 48.5; safety factor SF = masonry blocks a ready-mix mortar was used.
1.5.
Re-engineering of the grout curtain
Re-grouting methodology
One of the key aspects of the maintenance works for the
Valsoera Dam was the re-grouting of the grout curtain using
the Grout Intensity Number technique (G.I.N.) [1]. The entire
section of the rock foundation below the elevation of 2'392 m Figure 10: G.I.N. curve for Valsoera maintenance works.
asl was consequently treated as illustrated in Figure 9. The
total area of rock foundation affected by the new grouting
works appeared to be greater than 2000 m2. The grouting The grouting process was stopped when one of the following
operation was carried out starting from the three conditions occurred: achieving the target G.I.N. = PxV
inspection/drainage gallery. Difficulties were encountered due (grout control curve); reaching the volume limit V = Vmax;
to restricted operation space. reaching of pressure limit P = Pmax. For the maintenance
works of the Valsoera Dam, the G.I.N. number was set to
1000 l/m x bar, limiting the maximum pressure to 25 bar
(static pressure, measured with the pump off). The maximum
volume was limited to 500 l/m. The grout hole pattern was
arranged into two rows (Figure 11). The first row is formed
by drilled holes, carried out from the inspection gallery and
inclined upstream at 10, with a variable length from 30 m in
the area of concrete plug to 15 m along the abutment. Those
perforations are distinguished, depending on the succession of
executions, in primary, secondary, and eventually tertiary
Figure 9: Extension and distribution of grouting works. holes. The second row includes the control drillings. They run
parallel to the centerline of the dam, 50 cm downstream of the
The G.I.N method limits the grouting pressure P, the volume first row, inclined upstream at 10 with inclinations variable
of grout V and the grouting intensity number G.I.N. (i.e. the in left and right directions. Their length varied between 20 to
product P x V). 40 m.
The main features of the G.I.N. method are: use of a single
stable grout mix during the entire grouting process; a steady
low-to-medium rate grout pumping to avoid pressure peaks;
monitoring in real time of the parameters of pressure, flow,
grouted volume, and penetrability as a function of time, all by
means of graphs drawn directly on the site. The control of the
grouting process was carried out using of automatic
equipment which allows the programming and continuous
recording of the aforementioned parameters. The grouting
process is stopped when the function P = P (V), grouting Figure 11: Grout hole pattern.
pressure as a function of the total grouted volume (grouted
per linear meter), recorded in real time on the PV diagram, The grouting stable mix used corresponds to the following
intersects the chosen G.I.N. curve (Figure 10). characteristics: viscosity (standards Marsh cone diameter 4.5
mm): 38 45 seconds; cohesion: <1.5 mm (25 Pa); setting
time: <5% after 2 hours; Fine Portland cement type: CEM I
52.5; cement specific surface (Blaine): > 4300 cm2/gr; W/C
ratio (weight ratio between water and cement): 0.7. The
grouting perforations were performed by rotary destructive
30
percussive drilling machine with circulation of fluids. The
G.I.N. CURVE
control drillings were achieved by means of continuous PRIMARY HOLES
double core drillings equipment. The Lugeon permeability 25 SECONDARY HOLES
tests were performed measuring absorptions for at least 3 TERTIARY HOLES
values of pressure, increasing and decreasing trends (2-5-8-5-
20
PRESSURE P (bar)
2 bars).
15
Final controls
S10
P10
S12
P12
S14
P14
S16
P16
HOLE
of the graph (lower volumes and higher pressures). The
Figure 12: Total grouting volume absorbtion. overlapping of the values is explained by the fact that the
primary and secondary holes are positioned with a certain
spacing and thus may not interact. Additionally, this is
100 explained by the fact that the grouted rock mass was already
AVERAGE ABSORBED VOLUME (l/m)
90
treated during the construction of the dam and therefore the
80
main fissures of the rock (those which generally record
70
important absorption in primary holes) were already filled.
60
The tertiary holes performed close to the central dam concrete
50
plug showed absorptions between 250 and 330 l, and an
40
average cement take of 10-13 l/m, always reaching the upper
30
limit of the G.I.N. curve in terms of maximum pressures. The
20
tertiary holes, given the encouraging results obtained in the
10
area of the plug, have not been extended to the dam abutment.
0
The perforation control was limited to the central concrete
S9
P9
S7
P7
S5
P5
S3
P3
P1
S2
P2
S4
P4
S6
P6
S8
P8
P17
S15
P15
S13
P13
S11
P11
S10
P10
S12
P12
S14
P14
S16
P16
HOLE
plug area. The grouting revealed a grout take comparable to
Figure 13: Grouting absorption Average volume for meter the grouting performed in the tertiary holes. The volumes of
of hole. absorbed material are generally well distributed showing a
substantial uniform response of the rock mass. Passing from
Figure 14 shows the final values achieved in the grouting primary to secondary and tertiary holes, the absorbed volumes
works for primary, secondary and tertiary holes. decrease, and the final grouting pressure increase, in
accordance with the G.I.N. method. In order to check the
effectiveness of the grouting, some permeability tests were
performed within the control borehole. The diagram of Figure
15 summarizes the main grout take values at different depths.
The permeability recorded is always less than 1 UL.
PERMEABILITY U.L.
0.00 0.20 0.40 0.60 0.80
0.00
5.00
10.00
DEPTH (m)
15.00
20.00
C1
25.00
C2
C5
30.00
C6
35.00 C7
C10
40.00
Conclusion
Acknowledgements
References
[1] Lombardi G., Deere U. (1993). Grouting design and control using the
G.I.N. principle. Water Power & Dam Construction, June 1993, pp.
15-22.
[2] Turcotte G., Savard B., Lombardi G., Jobin H. (1994). The use of
stable grout and G.I.N. technique in grouting for dam rehabilitation.
Annual Meeting Canadian Dam Safety Conference CDSA and
CANCOLD, Winnipeg, Manitoba, Canada; October 1994, pp. 137-
161.
[3] Iride Energia, Lombardi Eng. Ltd, (2009). Progetto esecutivo dei
lavori di manutenzione straordinaria Technical Report 7004.4-R-1
(unpublished report).
[4] Lombardi G. (1996) Selecting the grouting intensity. The International
Jounal on Hydropower & Dams; Volume Three, Issue Four, pp. 62-66.